networ k a na l y s i s : p er t & c p m · 2020. 3. 20. · h e l p f ul to arm y f o r i ts m i...

41
Network Analysis : Pert & CPM MADE BY : RUCHIKA TYAGI (LECTURER) CIVIL DEPARTMENT GITAM

Upload: others

Post on 27-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Network Analysis : Pert & CPM

    MADE BY :RUCHIKA TYAGI(LECTURER)CIVIL DEPARTMENTGITAM

  • Introduction

    Network analysis is one of the important tools for projectmanagement. Whether major or minor a project has to be completed in a definitetime & at a definite cost.

    The necessary information of any particular data can berepresented as a project network. These techniques are very useful for planning, scheduling andexecuting large-time bound projects involving careful co-ordinationof variety of complex and interrelated activities

  • Objectives of network analysis

    Helpful in planningInter-relationship of various activitiesCost controlMinimisation of maintenance timeReduction of timeControl on idle resourcesAvoiding delays, interruptions

  • Applications of networkanalysis

    Planning, scheduling, monitoring and control oflarge and complex projects.Construction of factories, highways, building,bridges, cinemas etc.Helpful to army for its missile development.Assembly line schedulingInstallation of computers and high techmachineriesTo make marketing strategies

  • Methodology Involved in NetworkAnalysis

    Describing the Project

    Diagramming the network

    Estimating the time of completion

    Deterministicestimates

    Probabilisticestimates

    Monitoring the project progress

  • Key terminology

    Activity : All projects may be viewed as composed of activities. It isthe smallest unit of work consuming both time& resources thatproject manager should schedule & control. An activity is represented by an arrow in network diagram

    The head of the arrow shows sequence ofactivities.

  • Classification of activities

    Predecessor activity: Activities that must be completedimmediately prior to the start of another activity are calledpredecessor activities. Successor activity : activities that cannot be started until one ormore of other activities are completed but immediately succeedthem are called successor activities.

    Concurrent activities: activities that can be accomplished togetherare known as concurrent activities. Dummy activity: An activity which does not consume any resourcebut merely depicts the dependence of one activity on other is calleddummy activity. It is introduced in a network when two or moreparallel activities have the same start and finish nodes.

  • Event

    The beginning & end of an activities are called as events .Events are represented by numbered circles called nodes.

    i j

    Eventstart

    Event finish

  • Types of Events

    Merge event

    Burst event

    Merge & Burst Event

  • Path & Network

    An unbroken chain of activity arrows connecting the initial event tosome other event is called a path. A network is the graphical representation of logically & sequentiallyconnected arrows & nodes representing activities & events of aproject . It is a diagram depicting precedence relationships betweendifferent activities.

  • Errors in network logic

    Looping : looping is known as cycling error andcreates an impossible situation and it appearsthat none of the activities could ever becompleted. Dangling : sometimes a project network includesan activity which does not fit into the endobjective of the project and is carried out withoutany result related with completion of the project .Such an error in network is called dangling

  • Guidelines for NetworkConstruction

    A complete network diagram should have one stand point & onefinish point.The flow of the diagram should be from left to right.Arrows should not be crossed unless it is completely unavoidable.Arrows should be kept straight & not curved or bent.Angle between arrows should as large as possible.Each activity must have a tail or head event.. No two or moreactivities may have same tail & head events.Once the diagram is complete the nodes should be numbered fromleft to right. It should then be possible to address each activityuniquely by its tail & head event.

  • Stages for project management

    Project planning stages : in order tovisualize the sequencing or precedencerequirements of the activities in a project,it is helpful to draw a network diagram. Scheduling stage : once all work packageshave been identified and given uniquenames or identifiers, scheduling of theproject

  • Project control stage : project control refers to evaluating

    actual progress against the plan. Ifsignificant differences are observed, thenthe scheduling and resources allocationdecisions are changed to update andrevise the uncompleted part of the project

  • Advantages

    Planning & controlling projectsFlexibilityDesignation of responsibilitiesAchievement of objective with least costBetter managerial control

  • Limitations of PERT /CPM

    Network diagrams should have clear starting & ending points ,which are independent of each other which may not be possible inreal life. Another limitation is that it assumes that manager should focus oncritical activities. Resources will be available when needed for completion for an anactivity is again unreal.

  • Difficulties

    Difficulty in securing realistic time estimates.The planning & implementation of networks requires trained staff.Developing clear logical network is troublesome.

  • Example

    Activity

    Predecessoractivity

    A none

    B none

    C A

    D A

    E B

    F C

    G D & E

    1

    3

    2

    5

    4

    6

    A

    B

    C

    D

    E

    F

    G

  • Draw the network diagram for the following

    Activity

    Predecessoractivity

    A none

    B A

    C A

    D B

    E C

    F D ,E

  • 1 2

    3

    4

    5 6A

    B

    C

    D

    E

    F

  • Critical path

    Those activities which contribute directly to the overall duration ofthe project constitute critical activities, the critical activities form achain running through the network which is called critical path. Critical event : the slack of an event is the difference between thelatest & earliest events time. The events with zero slack time arecalled as critical events. Critical activities : The difference between latest start time &earliest start time of an activity will indicate amount of time bywhich the activity can be delayed without affecting the total projectduration. The difference is usually called total float. Activities with 0total float are called as critical activities

  • Critical path

    The critical path is the longest path in the network from the startingevent to ending event & defines the minimum time required tocomplete the project. The critical path is denoted by darker or double lines.

  • Difference between PERT & CPMPERT

    A probability model withuncertainty in activityduration . The duration ofeach activity is computedfrom multiple timeestimates with a view totake into account timeuncertainty.

    It is applied widely forplanning & schedulingresearch projects.

    PERT analysis does notusually consider costs.

    CPM

    A deterministic model with wellknown activity times based upon thepast experience.

    It is used for construction projects &business problems.

    CPM deals with cost of projectschedules & minimization.

  • Float : There are many activities where themaximum time available to finish the activity is morethan the time required to complete the activity. Thedifference between the two times is known as floatavailable for the activity. There are three types of float:

    Total float : It is the spare time available when allpreceding activities occur at earliest possible times &all success ding activities occur at latest possibletimes. Total float = Ls – Es or Lf – Ef

  • Free float : time available when all precedingactivities occur at the earliest possible time &allsucceeding activities also occur at the earliest possibletimes.

    Free float = total float - head event slackIndependent Float : it may be defined as theamount of time by which the start of an activity canbe delayed without affecting the earliest start timeof any successor activity , assuming that precedingactivity has finished at its latest finish time.Independent Float = free float – tail event slack

  • QUESTION :Activity

    Predece

    ssoractivity

    Optimistic (to)

    Mostlikely(tm)

    Pessimistic (tp)

    ABCDEFG

    --AABC

    D,E

    2214431

    3326541

    1043

    141257

  • CRITICAL PATH : 1-2-5-6 or A-D-G

    Activity Expected timeTe = to +4tm+tp 6

    A(1-2)B(1-3)C(2-4)D(2-5)E(3-5)F(4-6)G(5-6)

    4327642

  • activity

    te Es Ef = Es+te

    Lf LS=

    Lf -te

    Headslack

    Tailslack

    Total

    float

    Free

    float

    Independent

    float

    1-21-32-42-53-54-65-6

    4327642

    004436

    11

    436

    119

    1013

    459

    11111313

    027459

    11

    0230000

    0000230

    0230230

    0000230

    0000000

  • PERT

    1.

    2.

    3.

    4.

    PERT is designed for scheduling complex projects thatinvolve many inter-related tasks. it improves planningprocess because:

    It forms planner to define the projects variouscomponents activities.It provides a basis for normal time estimates & yetallows for some measure of optimism or pessimism inestimating the completion dates.It shows the effects of changes to overall plans theycontemplated.It provides built in means for ongoing evaluation of theplan.

  • ESTIMATING ACTIVITY TIMES

    Optimistic time ( t0 ) : is that time estimate of anactivity when everything is assumed to go as per plan.In other words it is the estimate of minimum possibletime which an activity takes in completion under idealconditions. Most likely time ( tm ) : the time which the activity willtake most frequently if repeated number of times. Pessimistic time ( tp) : the unlikely but possibleperformance time if whatever could go wrong , goeswrong in series. In other words it is the longest timethe can take.

  • EXPECTED TIME The times are combined statically to develop the

    expected time te . te = to + 4tm + tp 6 Standard deviation of the time of the time required to

    complete the project = tp - to 6

  • STEPS INVOLVED IN PERT

    Develop list of activities.A rough network for PERT is drawn.Events are numbered from left to right.Time estimates for each activity are obtained.Expected time for each activity is calculated : to+4tm+tp /6Using these expected times calculate earliest & latest finish& start times of activities.Estimate the critical path.Using this estimate compute the probability of meeting aspecified completion date by using the standard normalequation

    Z = Due date – expected date of completion standard deviation of critical path

  • QUESTION : The table showsactivities of project. Duration (days)

    JOB OPTIMISTIC

    MOSTLIKELY

    PESSIMISTIC

    1-21-32-42-63-43-54-55-6

    1531

    10252

    41034

    15455

    71537

    26658

  • 1.

    2.

    Draw the network &find expected projectcompletion time.What is the probability that it would becompleted in 41 days.

  • Variance of critical path

    Activity To Tp variance

    1-33-44-55-6

    51052

    152658

    2.777.1101Total=10.88

  • So, standard deviation = 3.30Probability for completing the job in 41 days.Z = DUE DATE – EXPECTED DATE OF COMPLETION S.D. OF CRITICAL PATH = 41 – 36 3.30 = 1.51The tabulated value of corresponding to calculated

    value i.e. 1.51 is .4345So probability is .5 + .4345 = .9345 i.e. 93.45% that

    project will be completed on 41 day.

  • QUESTION: Activity predecessor timeestimates (weeks)

    activity Preceding activity

    to tm tp

    ABCDEFG

    --AABC

    D,E

    2214431

    3326541

    1043

    141257

  • Find the expected duration andvariance of each activity.What is the expected projectlength?Calculate the variance &standarddeviation of the project length.

  • activity to Tm

    tp te variance

    ABCDEFG

    2214431

    3326542

    1043

    141257

    4327642

    16/91/91/9

    25/916/91/91

  • Various paths &expected project length A-C-F = 4+2+4 = 10 A-D-G = 4+7+2 = 13 CRITICAL

    PATH B-E-G = 3+6+2 = 11Thus critical path is A-D-G with an

    expected length of 13 days. Hencethe expected project length is 13days.

    Project variance = 16/9 + 25/9 + 1 =