    The Package DevelopmentProcess and the Effects on

    Product Packaging

    The Association for Rehabilitation Marketing & Sales2009 Annual Conference, Liverpool, NY

    Gus Castle - 6 / 9 / 09

  • 8/8/2019 Nestle - Zaka (2)

    2/20

    Technical Influence

    Market ability, performance, functionality,efficiency, economics, the environment, safetyand regulatory implications can influence any

    product / package design process.

    Involvement from many different departments isneeded to successfully launch a new product /package combination (Engineering, Marketing,

    Purchasing, Regulatory, Manufacturing, QualityControl, Safety etc.)

  • 8/8/2019 Nestle - Zaka (2)

    3/20

    Identifying the Product / Packaging

    Requirements

    An in depth review of the product / packagerequirements should be utilized to outline aproject time line to assure the combined product /package requirements will be met.

    A time line cannot be accurately identified withouta thorough review of all aspects.

    A major cause for time line extension is oversimplification during the project planning phase.

  • 8/8/2019 Nestle - Zaka (2)

    4/20

    Project Planning Considerations

    Meetings & Conference Calls: Project Start,Regular Updates and Summary

    The project start meeting takes place to introduce the

    team members, discuss the technical aspects andcreate a time line draft.

    Regular update meetings should occur at a frequencythat supports the complexity of the project.

    A summary meeting is held to identify any keylearnings that should be applied to the next project.

  • 8/8/2019 Nestle - Zaka (2)

    5/20

    Project Planning Considerations (con't) Sample Development: Samples are a very critical

    technical aspect associated with the PackageDevelopment Process. Samples of each componentas well as the overall configuration should betechnically developed, reviewed and approved.

    Prototype samples are needed to test ideas, showconcepts, confirm sizing, styles and materials. A finalapproved prototype sample is needed prior toreviewing the feasibility and financials of a project.

    Production sample runs are needed for qualification /validation purposes, sales samples, equipmenttesting, material testing, additional package testingand / or a combination of any of these.

  • 8/8/2019 Nestle - Zaka (2)

    6/20

    Project Planning Considerations (con't)

    Distribution Hazard Testing: Is completed toconfirm that the packaging has been designed andselected appropriately to protect the product in transit

    through the distribution cycle. Product / Package Compatibility Testing: Is

    completed to confirm that the packaging materials donot negatively effect the product in any way and viseversa.

    Packaging Clinical Studies: Are conducted to testthe effectiveness of an innovative packagingapplication from functionality and consumerpreference perspectives.

  • 8/8/2019 Nestle - Zaka (2)

    7/20

    Project Planning Considerations (con't)

    Equipment and Change Parts Development:Timing to support this aspect should always beadded to the time line if applicable, as it often is the

    longest period. Often other aspects such as artdevelopment can be completed in parallel.

    Art Development: Often a common reason for timeline extensions are the number of renditions createdleading up to the final approved version. Time should

    be alloted for graphic development, mock ups,approvals, revision, regulatory review and pre presswork.

  • 8/8/2019 Nestle - Zaka (2)

    8/20

    Project Planning Considerations (con't)

    Printing: The printing aspect can vary dramaticallydepending on the requirements. Typically, printingcan take anywhere from 2-8 weeks depending on the

    printer's schedule, as well as the size and complexityof the job.

    Material Procurement: Certain common materialscan be obtained readily and others may come fromother countries or be manufactured during a specific

    time frame. Timing of this aspect (and printing ifapplicable) are major influences on the typical leadtime scheduling and should always be considered.

  • 8/8/2019 Nestle - Zaka (2)

    9/20

    Project Planning Considerations (con't)

    Documentation: All documentation development,review and approval should be completed prior to thefirst production run of a new item. Documentation caninclude material specifications, process specifications,finished product specifications, technical drawings,regulatory documents, testing protocols and data, artproofs, etc..

  • 8/8/2019 Nestle - Zaka (2)

    10/20

    Project Planning Considerations (con't)

    Production Scheduling: This date can beidentified once the final production materialsdelivery information has been confirmed. A time

    buffer should be considered for the first run toaccommodate new learning curves.

    First Ship Date: Timing for the start shippingdate should be based upon the first lot availabilitytiming after inspection.

  • 8/8/2019 Nestle - Zaka (2)

    11/20

    Packaging Feasibility Analysis

    Utilized to identify the feasibility of a particularnew item and evaluate all pertinent aspects of thenew package / product combination launch.

    Is a report comprised of multiple sectionsgenerally including the project scope, requiredpackaging materials with costs, special producthandling requirements and / or regulatory

    aspects, change parts & tooling / equipment orcapital requirements, testing requirements,product availability, implementation time line andunit load pack out specifications.

  • 8/8/2019 Nestle - Zaka (2)

    12/20

    Suspension Packaging, Abbey Industriesand The Maco Bag Company (case study)

    Project Scope: To create a new packagesystem that can be utilized for shipping fragile

    items and electronics. Concept Development: Occurred over an 8

    month period. It could take 8 weeks to years todevelop and launch a new item. Pharmaceuticalcompanies may take 2-3 years to launch a newdrug when a food company may introduce newconcepts every quarter. Package developmentand product development are often completed inparallel.

  • 8/8/2019 Nestle - Zaka (2)

    13/20

    Case Study (con't)

    Sample Development: 4 prototype conceptswere developed prior to the final concept approval.All were designed with CAD and made by hand.

    Distribution Hazard Testing: The final conceptwas tested in a laboratory setting to confirm theproduct protection characteristics.

    Feasibility Analysis: Based upon the distribution

    hazard performance results, the cost analysis, theregulatory review and the production testing, itwas determined that the concept launch wasfeasible.

  • 8/8/2019 Nestle - Zaka (2)

    14/20

    Case Study (con't)

    Tooling and Capital: Special jigs were createdto assist the Abbey Group with the assembly ofthe Suspension Pack. Sealing and cutting dies

    were created for the pouch making portion of theproject. Adhesive transfer tape guns wereobtained to assist the Abbey Group with theassembly as well.

    Packaging Materials Procurement: Pouchmaterial, corrugated, case sealing glue andadhesive transfer tape were obtained a fewweeks prior to the first production run.

  • 8/8/2019 Nestle - Zaka (2)

    15/20

    Case Study (con't)

    Documentation: Finished packagingspecifications, assembly work instructions, a

    quality control protocol, technical drawings andcontractual documents were prepared for thisproject.

    First Production Run: The first run beganslowly and began to pick up after the first 3 hours.There was intense supervision during the startup.

  • 8/8/2019 Nestle - Zaka (2)

    16/20

    Case Study (con't)

    100% Quality Control Inspection: The firstproduction trial lot was inspected entirely suchthat the best possible product was sent to thecustomer.

    To notallow marginally produced productcreated during the learning curve to beshipped to the customer.

    To identify any key learning experiences thatcan be applied to the next production run orconcept design.

  • 8/8/2019 Nestle - Zaka (2)

    17/20

    The Effects Package Development can

    have on Product Quality and Perception The package / product system can be designed

    utilizing the most appropriate cost effective &functional materials for the application.

    All pertinent parties can be assured that theirneeds and level of involvement areaccommodated during the planning and designphase, therefore improving the end result andlevel of success.

    Through the utilization of a packaging feasibilityreport, price point determination can be mostaccurately identified to prevent margindegradation.

  • 8/8/2019 Nestle - Zaka (2)

    18/20

    The Effects Package Development can

    have on Product Quality and Perception(con't)

    A project time line provides validity to theestimated development and implementation

    timing. All critical aspects identified during theplanning phase should be included on the timeline.

    An accurately maintained time line serves as the

    single most important communication tool forlaunching a new or modified item smoothly andsuccessfully.

  • 8/8/2019 Nestle - Zaka (2)

    19/20

    Strengths, weaknesses and opportunities formargin improvement are identified during thedistribution hazard / product compatibility testing

    and clinical studies, as well as the first productiontrial.

    The various documentation generated during thedevelopment process maintains the historical,

    technical and legal information that is utilized forongoing production runs and continuousimprovement. Accurate documentation can helpfacilitate consistency and repeatability as well asshow validity and build customer confidence.

    The Effects Package Development can

    have on Product Quality and Perception(con't)

  • 8/8/2019 Nestle - Zaka (2)

    20/20

    Conclusion

    As many believe their ambition and ideas can movemountains (and in most cases they can), the oldsaying still goes, Rome wasn't built in a day

    With proper planning, time and resource allocation,it has been proven time and time again that greatthings are worth great effort.