nergy storage and iesel generator run time...

9
1 Energy Storage and Diesel Generator Run-Time Reduction Remote Area Power Supply (RAPS) Trial

Upload: others

Post on 25-Mar-2020

30 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

1

Energy Storage and Diesel Generator Run-Time

Reduction

Remote Area Power Supply (RAPS) Trial

Page 2: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

2

Summary

The aim of installing Remote Area Power Supply (RAPS) systems for the Energy Safe Victoria (ESV)

project was to determine if it is feasible to install backup power supplies to enable selective and

occasional de-energisation of high risk power lines on catastrophic fire risk days without

compromising power supplies to affected users.

In summary, this project has shown that it is technically feasible to take residential customers who

are currently connected to the grid and provide their electricity needs from an off-grid renewable

energy-based system. This allows parts of the electricity network to be de-energised and thus reduce

the risk of bush fires in remote areas.

Each of the ten households who participated in the trial were provided with a RedFlow RAPS system

that included a diesel generator, a 3.2kW or 4.8kW PV solar panel array and a RedFlow hybrid zinc-

bromide module (ZBM) flow battery and lead acid Power+BOS energy storage system (ESS). These

elements are shown below.

This report provides an overview of the proven use over this trial of RedFlow’s ZBM technology in

the significant reduction of diesel generator run-time in off-grid residential applications. It has been

shown that with the use of RedFlow’s hybrid ZBM and lead acid energy storage systems (ESS),

diesel generator run-time can be reduced to less than 33% of the time for each of the ten trial sites

of the ESV project, with the vast majority of sites operating their generators for approximately

15% of the time or less. This is a significant reduction compared to a system that does not utilize

energy storage, which would require diesel generators to run for the vast majority of the time to

ensure a steady and reliable supply of electricity to the loads.

Page 3: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

3

Background

As a result of the Victorian bushfires of Saturday 7th February 2009, the 2009 Victorian Bushfires

Royal Commission was established to investigate the causes and responses to the bushfires.

The Government, through Energy Safe Victoria (ESV), established a Powerline Bushfire Safety

Taskforce. The taskforce examined a range of options for reducing the risk of bushfires being caused

by electricity infrastructure. These included:

1. Targeted replacement of SWER and 22kV lines in highest bushfire risk areas with other

network and alternative technologies that deliver reduced bushfire risk, including aerial

bundled cable, underground cable and remote area power supplies;

2. Enhanced fault protection systems to minimise fire starts from fault currents;

3. Faster identification and location of faults to enable more rapid fire-fighting response;

4. Installation of backup power supplies to enable selective and occasional de-energisation of

high risk power lines on catastrophic fire risk days without compromising power supplies to

affected users.

RedFlow was selected to supply and install the backup power supplies (RAPS) required to trial the 4th

option. The energy storage component of the RAPS systems was aimed at reducing the diesel

generator run-time, thereby increasing diesel generator efficiency, saving costs on diesel fuel and

reducing the need for maintenance.

Ten households, each with one RAPS system, were selected as sites for the ESV trial. Five of these

systems were installed during late 2010, with the other five following in March 2011. All systems

were online by 28 March 2011. The trial officially ended on 31 December 2011, but many

households opted to keep their RAPS systems instead of connecting back to the grid. The RedFlow

RAPS were designed to the specification of an average daily load of 15kWh.

RedFlow Remote Area Power Supply (RAPS) installed at ESV 8

Page 4: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

4

Results

1. Energy Storage System

There was one RedFlow RAPS system installed at each trial household. These systems provided a

time-shifting capability to store energy generated by the solar panels for use at times of peak

demands (typically mornings and evenings). The energy storage also allowed the diesel generators to

operate at more efficient outputs by storing any energy not immediately used by the household

load. The image below shows the layout of the ESS which contains both lead-acid and zinc-bromine

batteries. Due to the nature of the SMA inverter, there is more data available for the LA batteries

than for the ZB batteries.

ESV 7

ESV 4 – LA Batteries ZB Battery

Page 5: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

5

The use of the ZB battery results in a smoothing in the LA state of charge (SOC) curve. This reduces

stress on the LA batteries, which do not react well to regular deep discharging. This is shown in the

graph below, which shows the effect of the ZB batteries over the month of July for ESV 10 as an

example. Also shown in the graph is the solar exposure for the ESV trial area over the course of the

month. The effect of high solar exposure over a period of more than one day shows a noticeable

reduction in diesel generator operation, a deeper charge of the ZB batteries and a smoothed LA

charge curve.

0

3

6

9

12

15

0

10

20

30

40

50

60

70

80

90

100

1 J

uly

2 J

uly

3 J

uly

4 J

uly

5 J

uly

6 J

uly

7 J

uly

8 J

uly

9 J

uly

10

Ju

ly

11

Ju

ly

12

Ju

ly

13

Ju

ly

14

Ju

ly

15

Ju

ly

16

Ju

ly

17

Ju

ly

18

Ju

ly

19

Ju

ly

20

Ju

ly

21

Ju

ly

22

Ju

ly

23

Ju

ly

24

Ju

ly

25

Ju

ly

26

Ju

ly

27

Ju

ly

28

Ju

ly

29

Ju

ly

30

Ju

ly

31

Ju

ly

MJ/

m2

% S

OC

LA SOC Smoothing due to ZB Use

LA SOC ZB SOC Diesel Generator Operation (High = On, Low = Off) Solar Exposure (MJ/m2)

Page 6: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

6

2. Diesel Generation

Each household’s RAPS system included a RedFlow-designed housing with a 7kVA diesel generator

unit to use as a back-up to the solar panels for the houses’ electricity generation. The diesel

generator was brought into operation when there was insufficient solar generation to power the

household, and the energy storage was also depleted.

The pictures below show the generator unit manufactured by RedFlow with a weatherproof

enclosure, a larger fuel tank with remote fuel level monitoring and a 7kVA Yanmar diesel generator.

There were large discrepancies between the percentages of time that the generators were

operating. As can be seen below, while the majority of generators were operating for under 15% of

the total trial time, ESV 1 and ESV 2 in particular had generators that ran for over one quarter of the

time. The reasons for this include high load usage and low solar generation, which is discussed in

further detail below.

ESV 9 ESV 3

Page 7: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

7

Ultimately, this meant that the energy storage in the RAPS system enabled a significant reduction in

diesel run time, compared to a system with no storage. Such a system would have required the

diesel generators to operate during most of the day, with the possible exception of times of the

highest solar exposure, when the solar panels produced an adequate output to power the household

load.

The weather also had a direct effect on the operation of the diesel generators. This can be seen in

the graph below, which shows the seasonal variation in the average generator run time for all ten

households (reduced to nine households once ESV 1 had withdrawn from the trial), compared to the

average monthly solar exposure (data taken from Bureau of Meteorology) for the area. There is a

clear inverse relationship displayed in the graph. The need for diesel generation increases during

the winter months due to the reduced solar exposure that limits the output of the solar panels.

From the data presented above, it is clear that there were great differences between the ten

households in terms of diesel generator operation. This is primarily due to significant variations in

individual household electricity use compared with the amount of electricity generated from the PV

solar array. However, the RAPS systems were still successful in reducing diesel generator run-time

to less than 33% in all cases.

0

5

10

15

20

25

30

35

ESV 1 ESV 2 ESV 3 ESV 4 ESV 5 ESV 6 ESV 7 ESV 8 ESV 9 ESV 10

%

Diesel Generator Run Time

0

5

10

15

20

25

0

5

10

15

20

25

30

35

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

MJ/

m2

ho

urs

/wee

k

week

Average Weekly Diesel Generator Run Time vs. Solar Exposure

Average Diesel Generator Run Time (hrs/week) Solar Exposure (MJ/m2)

Page 8: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

8

3. Solar As can be seen below, the average daily solar generation also varied greatly between trial

households. When compared to the diesel generator run-time, it can be seen that there is an

inverse correlation: high levels of solar generation generally resulted in low percentages of diesel

generator run-time.

The fluctuations in solar generator were not only due to the different sized panels installed at the

trial households, but were also influenced by the sub-optimum installation positions of many of the

panels. This included issues such as sub-optimum solar panel angles, installations behind hills and

installations behind fast-growing vegetation

In summary, increasing the size of the PV solar panels and installing them in the correct location and

orientation resulted in significantly higher solar panel outputs. This in turn resulted in reduced

diesel generator runtime, as shown above. It is important to note, however, that a generator will

always be required as a backup.

4. Household Usage The graph below shows the average daily load used by each household over the course of the trial.

As can be seen, there were significant variations between household loads. When compared to

diesel generator run-time, a correlation can be identified between high load diesel generator usages.

It is thus clear that most households remained at an average daily consumption of about 15kWh or

less, as the RAPS systems were designed for. However, ESV 2 significantly exceeded this figure,

contributing to its high diesel generation totals.

0

2

4

6

8

10

ESV 1 ESV 2 ESV 3 ESV 4 ESV 5 ESV 6 ESV 7 ESV 8 ESV 9 ESV 10

kWh

Average Daily Solar Generation and Losses by Household

0

5

10

15

20

25

ESV 1 ESV 2 ESV 3 ESV 4 ESV 5 ESV 6 ESV 7 ESV 8 ESV 9 ESV 10

kWh

Average Daily Load Usage by Household

Page 9: nergy Storage and iesel Generator Run Time Reductionredflow.com/wp-content/uploads/2012/10/ESV... · Generator Run-Time Reduction ... (RAPS) systems for the Energy Safe Victoria (ESV)

9

Conclusions

Overall, this project has shown that it is technically feasible to use an off-grid renewable energy-

based system to take residential customers off their normally-connected grid electricity supply. This

allows parts of the electricity network to be de-energised and thus reduce the risk of bush fires in

remote areas. In particular, it has been shown that RedFlow’s hybrid ZBM and lead acid ESS are

effective at reducing the diesel generator run-time of these RAPS systems.

Overall, RedFlow has learnt many valuable lessons over the course of the ESV trial, and will use these

to improve upon their technology for future RAPS applications. These have included:

The effectiveness of the RAPS system in greatly reducing the diesel runtime of each

generator.

o All households that kept true to the 15kWh per day load usage design specification

were able to limit their diesel generator run time to less than 15% of the time.

Furthermore, had the solar panels been installed in more favourable locations, and

their outputs been higher, this could have been reduced even further.

o In the most favourable circumstances, the RAPS system was successful in reducing

the generator run-time at ESV 9 to less than 4% of the trial time.

o Most households would have required diesel generators to run for almost 100% of

the time without the use of the RAPS system, and in particular, without the ESS.

This means that the RAPS systems were able to reduce diesel generator run-time by

approximately 95% in the case of ESV 9.

The significant effect that large household loads had on the reduction of diesel generator

run-time.

o Load profiles with higher usage during the middle of the day reduce the need to

start generators since this is the time of highest solar output. While the RAPS

system can time-shift this energy from the solar panels, there are losses associated

with storage and inverters etcetera. Large demand at peak times also increases the

need to operate diesel generators.

The significant effect that reduced solar exposure during winter, as well as poor locations of

solar panels during installation, can have on the reduction of diesel generator run-time.

o Diesel generators need to run more in winter than in summer due to the reduced

output from the solar panels during months of low solar exposure.

o Higher solar exposure reduces the need for diesel generators to operate to supply

loads when the energy storage is depleted.