TxDOT Environmental Affairs Division

NEPA ASSIGNMENT

22–Month Update

Carlos Swonke

Director, Environmental Affairs Division

Texas Department of Transportation

TxDOT Environmental Affairs Division

2013

May 2013 – Waiver of Sovereign Immunity Legislation signed by Governor

June 2013 – Begin preparing applications

August 2013 – NPRM for 327 Surface Transportation Project Delivery

Program Application Requirements

December 2013 – CE Assignment MOU executed (effective date 2/12/14)

2014

January 2014 – first draft of 327 MOU to FHWA

March 2014 – Draft Application Public Notice

May 2014 – Submittal of 327 NEPA Assignment Application

September 2014 – 327 Surface Transportation Project Deliver Program

Final Rule

October 2014 – Draft MOU Public Notice

December 16, 2014 - 327 NEPA Assignment MOU executed

History

2

TxDOT Environmental Affairs Division

The MOU – What is Assigned

TxDOT to assume NEPA decision responsibility for all projects on and off the state highway system

Specific exemptions

• Trinity Parkway EIS

• Harbor Bridge EIS

• South Padre Island 2nd Access Bridge EIS

Multi-state & international projects excluded

TxDOT to comprehensively assume responsibilities under other federal environmental laws, including

– Section 7 (Endangered Species Act)

– Section 106 (Historic Preservation Act)

– Section 4(f) (Department of Transportation Act)

– Section 404 (Clean Water Act)

Clean Air Act conformity remains with FHWA

3

TxDOT Environmental Affairs Division

Success

Reduced document review times

Expedited decision-making

Ownership

Cost of Implementation

– Program Adjustments

Audits

4

TxDOT Environmental Affairs Division

– Reduced Document Review Times

Environmental Assessments

Baseline (Preassignment / Start to FONSI)

• 30 months (median)

Since Assignment (only five EAs so far)

• 15 months (median)

Environmental Impact Statement

Baseline (Preassignment / Start to ROD)

• Eight years

– Expedited decision-making

– Ownership

5

TxDOT Environmental Affairs Division

Cost of Implementation

– Program Changes

• Guidance documents

• Organizational Structure

– Need for Expertise

– Project Documentation

• Electronic documentation system

6

TxDOT Environmental Affairs Division

Audits Three audits, so far (one of the three still pending completion)

7

TxDOT Environmental Affairs Division

Audit Focus Areas

Six main focus areas for FHWA audits

– Program Management

– Documentation and Records Management

– Quality Assurance/Quality Control

– Legal Sufficiency

– Performance Measures

– Training

FHWA will not evaluate specific project-related decisions, as these are the sole responsibility of the State

FHWA will review the processes/procedures used to reach project decisions

8

TxDOT Environmental Affairs Division

NEPA Assignment – It’s working!

Opportunity

– Streamline the delivery of transportation projects

Accountability

– Maintain consistency and compliance through self-assessments, external audits and

reporting

9

Conclusion