Measure TT Projects Update as approved by the Board of Trustees Nelson Cayabyab, Chief Facilities Officer

Completed Measure TT Projects

Facilities Department

Following is a partial list of significant Completed Project funded by Measure TT Bonds.

Our Children • Learning Today • Leading Tomorrow

Completed Measure TT Projects

Facilities Department

Our Children • Learning Today • Leading Tomorrow

Location ProjectAltadena ES ModernizationEliot MS AuditoriumField ES ModernizationMadison Student Drop-Off and Curb CutMarshall Fundamental New Sports ComplexMcKinley ES New Science Building, Cafeteria and GymRoosevelt ES Student Drop-OffSierra Madre MS New Campus

Return to projects list

Altadena ESModernization

Start Date: 07/08/2013NOC Date: 08/25/2015Contractor: Chalmers ConstructionArchitect: PBWS ArchitectsProject Inspector: SPAICTotal Cost: $8,140,887.79

• Start Date: December 6th, 2012• NOC Date: July 11th 2015• Contractor: The Nazerian Group• Architect: WLS • Project Inspector: SPAIC • Total Cost: $4,022,239.00

Return to projects list

Eliot MSModernization

• Start Date: 08/04/2014• NOC Date: 03/24/2016• Contractor: Mallcraft• Architect: Flewelling & Moody• Project Inspector: SPAIC• Total Cost: $1,902,782.36

Return to projects list

Field ESModernization

• Start Date: June 26, 2014• NOC Date: November 2015• Contractor: The Nazerian Group• Project Inspector: City

Inspection• Total Cost: $303,558.10

Return to projects list

Madison ESCurb cut

• Start Date: 05/01/2013• NOC Date: 07/15/2015• Contractor: G2K Construction• Architect: Flewelling & Moody• Project Inspector: SPAIC• Total Cost: $2,492,809.04

Return to projects list

Hamilton ESMPR Modernization

Return to projects list

Marshall FundamentalSport Complex

• Start Date: June 25, 2013 (Design)

• NOC Date: July 2017• Contractor: The Nazarian Group• Architect: MLA Architecture• Project Inspector: O’Neal

Construction Inspection• Total Cost: $ 9,995,949.00

• New State of the art Gym, with bleachers for 1200 seats, Teams rooms, coaches office, weight room

• New Restrooms, Concession Stand

• 4 New classrooms• New Tennis Courts (6)• Redesigned parking lot

Return to projects list

Marshall FundamentalSport Complex- Design Build

• Start Date: March 15th 2013• NOC Date: July 19th 2016• Contractor: Sinanian

Development Inc.• Architect: LPA• Project Inspector: SPAIC• Total Cost: $18,526,731.40

Return to projects list

McKinley

• Start Date: April 14, 2017• NOC Date: July 2017• Contractor: Amazing Electric• Architect: ONYX Architects• Project Inspector: Ned K. • Total Cost: $78,000

Return to projects list

Roosevelt ESCurb cut

• Start Date:07/01/205• NOC Date: March 2017• Contractor: Shenk Developers• Architect: LPA• Project Inspector: Knowland

Inspections• Total Cost:$10,416,716.51

Return to projects list

Washington MSLocker Room, Gym, Outdoor Basketball area.

• Start Date: July1, 2013• NOC Date: March 16th, 2017• Contractor: Sinanian Development

Inc.• Architect: PBWS• Project Inspector: All Area Corp.• Total Cost: $31,027,670.58

Return to projects list

Sierra Madre MSNew Campus

Notice of Completions recorded with the County Clerks office for completed projects from July 2016 up to date

School Name Project Name Date NOC was recorded

Total Cost includes soft cost and hard cost

McKinley McKinley K-8 Phase I New Construction Project

7/16/2016 $18,499,272.69

NOC cont…

Questions & Comments