Neighbourhood
Business
Forum
24 October 2018
• Current position
• Overall phasing
• Early works
• Traffic flows for first phase
• Introduction to J3
• Neighbourhood business forum membership and organisation
• Questions and answers
Agenda
Current position
• Acquire and demolish Kensington Place
properties
• Provide temporary/permanent plant zones
to maintain services to existing hospital
• Demolish existing energy centre
• Additional half deck and new access core
to refurbished Patriotic Street car park
• Construct Block A
• Construct Westaway Court
• Construct Temporary Link from 80s block
to Block A at level 02
• Decant all services (in Gwyneth Huelin
and central laboratory block) into Block A
and Westaway Court
Westaway Court
Sequencing – Stage 1
Main services to existing
hospital during construction of
block A.
• Temporary link from existing
80s Block to Block A
• Establishes safe buffer zone
and provides ongoing
access to interim hospital
• Demolish Gwyneth Huelin Wing, Peter
Crill House and central Laboratory Block
• Construct Block B
• Decant existing facilities from remainder
of existing hospital into Block B
• Provide temporary entrance to new
hospital
Sequencing – Stage 2
Westaway Court
• Demolish 80s and 60s
Blocks
• Construct Main Entrance
• Conclude refit of Granite
Block
Sequencing – Stage 3
Westaway Court
Transport
proposals
Westaway Court
N
People’s Park junction
Signalise junction to enable construction
traffic
Key
Location of highway/ junction works
Kensington Place
Acquisition of properties, surveys and soft strip
Removal of traffic calming measures prior to
demolition
Westaway Court
Asbestos survey
Soft strip
Patriotic Street MSCP
Modifications for additional staff car and
motorcycle parking
Service road, Westaway Court, Sunderland Court,
Kensington Place Properties
Ground Investigation
St Elmo
Soft strip and temporary propping
Demolition, including footway closure
All properties on construction route (dock to site)
Video condition survey
All highway works to be agreed with DfI
Streetworks and Highway Maintenance
Relevant highways and junctions - Topographical and
services survey
Esplanade/Kensington Place
Amend junction to enable construction
traffic
Early works
Traffic flow – Stage 1A
1
4
3
5
2
Jersey Future Hospital
Bruce Preston
Gary McGuire
Jersey Future Hospital
Where we’ve done this before
Royal Albert Hall London
Bristol Royal Infirmary
Bexley Wing St James’s Leeds
Combined University Hospital ManchesterPrincesshay Exeter
Milton Court London
Jersey Future Hospital
Potential vibration effect without mitigation• Identify risks to each specific department• Develop specific control and mitigation strategy• Communication and scheduling• Physical measures (primary and secondary)
Air quality, noise and vibration – control and mitigation
Jersey Future Hospital
Construction/EmergencyTraffic only
Open to traffic outside of
Working hours
Traffic management during works
Existing
Changed
Construction
Traffic Flow
Demolition traffic routes
• Starting point – how much do you already know?
• What level of detail would you like to know?
• How do you want to be involved in this forum?
• How would you like to be kept informed?
• Topics to be covered
Business forum – how shall we work?
Questions and answers?
Our contact details: [email protected] and 447862
Our website www.futurehospital.je
Construction impacts
Safe and continuous operation of the existing hospital
Modern Methods of Deconstruction (MMD)
Early risk identification, improving Health, Safety, Quality and the Environment
Modern Methods of Construction (MMC)
Building Information Modelling (BIM)
Modern Methods of Construction - prefabrication
Prefabrication and modular construction
Potential vibration effect without mitigation• Identify risks to each specific department• Develop specific control and mitigation strategy• Communication & scheduling• Physical measures (primary & Secondary)
Air quality, noise & vibration – control and mitigation
Existing hospital and Kensington Place properties
Environmental protection barrier
Early works - Key dates
Activity / Works RequiredAnticipated
start
Duration of
works
Ground Investigations
Service road, Westaway Court, Sunderland Court, Kensington Place propertiesOngoing 16 weeks
Drainage CCTV survey
General hospital site and surrounding roads Ongoing 2 weeks
St Elmo – Soft strip and temporary propping Ongoing 3 weeks
Topographical and service surveys
Relevant highways and junctions Winter‘18 4 weeks
Condition Surveys
All properties from the docks to the hospital including Kensington street,
Gloucester street and Newgate streetWinter ‘18 6 weeks
Westaway Court – asbestos surveys/soft strip Winter ‘19 8 weeks
Patriotic Street Car Park –staff car and motorcycle parking displaced from
Gloucester Street Staff Car ParkWinter‘19 4 weeks
St Elmo – Demolition Winter ‘19 4 weeks
People’s Park junction – amended signalised layout to allow large vehicles to
exist Kensington Street Winter’19 4 weeks