nedo 11 dec

Upload: mrhom

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 nedo 11 dec

    1/22

    NEDO-MEA Meeting

    11 December 2012

  • 7/30/2019 nedo 11 dec

    2/22

    MEA Background

    Bangkok, Nonthaburi and Samutprakan

    Service area : 3,192 km2

    Maximum Demand: 8,383 MW

    Substation no.: 149

    Number of customer : 3,115,695

    April , 2012Load

    Time

    2

  • 7/30/2019 nedo 11 dec

    3/22

    Distribution facilities

    Transformers Terminal station 230/69-115 kV ( 17 stations) 18,205.88 MVA

    Substation 69-115/12-24 kV ( 149 stations ) 18,405.00 MVA

    Distribution 12-24 kV/230-380 V 14,148.68 MVA

    TRANSMISSION LINES 230 kV ( 6 LINES ) 49.54 cct-km

    115 kV ( 38 LINES ) 722.75 cct-km

    69 kV ( 77 LINES ) 897.88 cct-km

    DISTRIBUTION LINES

    24 kV ( 1,156 LINES ) 12,829.52 cct-km

    12 kV ( 464 LINES ) 4,279.18 cct-km

    Low voltage 27,211.83 cct-km

    OPTICAL FIBER

    ADSS Structure Cable 10,000.00 cct-km

  • 7/30/2019 nedo 11 dec

    4/22

    Operation and maintenance

    No subsidiary company

    24 kV line maintenance by district office

    69 and 115 kV maintenance by Maintenancedepartment

    Substation equipment maintenance by

    Maintenance department

  • 7/30/2019 nedo 11 dec

    5/22

    MEA Quality of Electricity Supply for 69, 115

    and 230 kV System

    Frequency 50 0.5 Hz (normal operation) Data from EGAT

    Voltage supply 230 kV

    115 kV

    69 kV

    218.0 - 237.0 kV (normal)

    218.0 - 242.0 kV (emergency)

    106.4 - 117.6 kV (normal)

    96.0 - 123.0 kV (emergency)63.6 - 70.4 kV (normal)

    57.3 - 72.5 kV (emergency)

    Harmonic voltage THDv less than 3.0 % Refer to planning level in

    Engineering

    Recommendation G5/4

    table 4 and 5 which also

    include individual

    harmonic

    Voltage flicker Pst less than 0.8

    Plt less than 0.6

    Refer to planning level in

    IEC 61000-3-7

    Voltage unbalance Less than 1.4 % Refer to planning level in

    IEC 61000-3-13

    Temp. power frequency

    overvoltage

    Less than 173.2 % of nominal voltage Refer to EN 50160

  • 7/30/2019 nedo 11 dec

    6/22

    MEA Connection Regulation for 69, 115 and

    230 kV System

    Load size 230 kV not available

    115 kV larger than 15 MVA

    69 kV larger than 15 MVA

    Depend on specific area

    Maximum step voltage

    change

    Max. step voltage change at PCC due to

    customer load variation must less than 3.0

    % of nominal voltage

    Power factor Between 0.9 - 1.0 lagging

    Harmonic current Limit individual harmonic current up to order

    50th. The limits depend on load size, system

    capacity and fault level at PCC.

    Refer to planning level

    from Engineering

    Recommendation G5/4

    and assessment method

    from IEC 61000-3-6

    Voltage

    Flicker

    Limit Pst and Plt created by customer at

    PCC. The limits depend on load size and

    system capacity

    Refer to assessment

    method from IEC 61000-

    3-7

    Unbalanced current Limit negative sequence current. The limit

    depends on load size, system capacity and

    fault level at PCC.

    Refer to assessment

    method from IEC 61000-

    3-13

  • 7/30/2019 nedo 11 dec

    7/22

    MEA Quality of Electricity Supply for 12 and 24

    kV System

    Frequency 50 0.5 Hz (normal operation) Data from EGAT

    Voltage supply 12 kV

    24 kV

    10.9 - 11.8 kV (normal)

    10.8 - 12.0 kV (emergency) 21.8 -

    23.6 kV (normal)

    21.6 - 24.0 kV (emergency)

    Harmonic voltage THDv less than 4.0 % Refer to planning level in

    Engineering

    Recommendation G5/4

    table 3 which also include

    individual harmonic

    Voltage flicker Pst less than 0.9Plt less than 0.7

    Refer to planning level inIEC 61000-3-7

    Voltage unbalance Less than 1.8 % Refer to planning level in

    IEC 61000-3-13

    Temp. power frequency

    overvoltage

    Less than 173.2 % of nominal voltage Refer to EN 50160

  • 7/30/2019 nedo 11 dec

    8/22

    MEA Connection Regulation for 12 and 24

    kV System

    Load size larger than 300 kVA but less than 15 MVA Depend on specific area

    Maximum step voltage

    change

    Max. step voltage change at PCC due to

    customer load variation must less than 3.0

    % of nominal voltage

    Power factor Between 0.9 - 1.0 lagging

    Harmonic current Limit individual harmonic current up to order

    50th. The limits depend on load size, system

    capacity and fault level at PCC.

    Refer to planning level

    from Engineering

    Recommendation G5/4

    and assessment method

    from IEC 61000-3-6

    VoltageFlicker

    Limit Pst and Plt created by customer atPCC. The limits depend on load size and

    system capacity

    Refer to assessmentmethod from IEC 61000-

    3-7

    Unbalanced current Limit negative sequence current. The limit

    depends on load size, system capacity and

    fault level at PCC.

    Refer to assessment

    method from IEC 61000-

    3-13

  • 7/30/2019 nedo 11 dec

    9/22

    Adder

  • 7/30/2019 nedo 11 dec

    10/22

    Energy Regulatory Commission

    policy framework as to ensure the equality andfairness nested between consumers, producers,and other relevant interest groups.

    The primary functions and duties to oversee the regulations that deal with electricity

    systems of generation, transmission, distribution, andtheir system operator.

    monitoring energy market conditions by tariff review,

    licensing, approval of power purchase, disputesettlement and fulfilling its mandate, in order tocounterbalance each other, to ensure maximuminterests of the people and the country

  • 7/30/2019 nedo 11 dec

    11/22

    Tariff

    http://localhost/var/www/apps/conversion/tmp/scratch_4/tariff.docxhttp://localhost/var/www/apps/conversion/tmp/scratch_4/tariff.docx
  • 7/30/2019 nedo 11 dec

    12/22

    Challenge1. Power System

    Power Quality, Reliability, Security

    Loss Reduction, Economic

    2. Service

    Energy usage efficiency New Service

    3. Renewable Energy

    Manage and Support

    New Technology (EV, Energy Storage)

    4. IT Interoperability and Standard

    12

  • 7/30/2019 nedo 11 dec

    13/22

    13

    Smart Grid Roadmap

    Stage 12012 2016

    Laying the Foundations

    Stage 22017 2021

    Large Scale Implementation

    Power system

    40 automation substations Automation substation in all service area(170 stations)

    Manage and Control LBS in distributionnetwork cover 30% of service area. Manage and Control LBS in distributionnetwork cover all of service areaOutage area monitoring and managementsystem for HV and MV network Outage monitoring and managementsystem all networkAutomatic service restoration (Self-

    healing) in some area. Automatic service restoration (Self-healing) in all areaAsset management

  • 7/30/2019 nedo 11 dec

    14/22

    14

    Stage 1

    2012 2016

    Laying the Foundations

    Stage 2

    2017 2021

    Large Scale Implementation

    ServiceAutomatic meter reading (AMR) for commercial and industrial customerDaily load profile and power consumption monitoring for customer via internet andmobile phoneStreet light control

    Smart Grid Roadmap

  • 7/30/2019 nedo 11 dec

    15/22

    15

    Stage 1

    2012 2016Laying the Foundations

    Stage 2

    2017 2021Large Scale Implementation

    Energy

    conservation

    &

    Alternativeenergy

    Support integration of SPP/VSPP and

    renewable energy

    Monitoring and control SPP/VSPP and

    renewable energy in widely areaPilot project of 20 EV and 10 charging

    stations to study the effect to power

    system

    Support widely used of EV and charging

    station and electric vehicle to grid (V2G)

    Pilot project of energy storage Energy Storage for powersecurity

    Building Energy Management System(BEMS) Integration of BEMS and home energymanagement system

    Smart Grid Roadmap

  • 7/30/2019 nedo 11 dec

    16/22

    MEAs Smart Grid Projects

    objectiveProject

    EMS DMS SA BEMS EV ESS AMR

    Substation Automation

    According toIEC 61850p

    Remote control of distribution

    switch with Distribution

    Management System

    pOutage monitor in high

    voltage and medium voltage

    system

    p p p pself-healing in some area p p pAMR for Commercial and

    industrial customerp

    Ready for SPP/VSPP and

    Renewable Energy connectionp p p p

    Pilot use of EV and charging

    stationp

    Pilot use of Energy Storage pBuilding Energy ManagementSystem p

  • 7/30/2019 nedo 11 dec

    17/22

    MEAs Smart Grid Implementation Plan

    and BudgetBudget (MBaht)

    Project 2555 2556 2557 2558 2559 Total

    EMS - 40.0 311.1 - - 351.1

    DMS 360.3 561.8 475.84 121.80 121.80 1,641.54

    SA 150.0 165.0 180.0 200.0 220.0 915.0

    BEMS - 34.0 36.0 17.0 20.0 107.0

    EV 20.5 20.5 15.25 15.25 - 71.5

    ESS - 0.5 - 20 - 20.5

    AMR 328.172 - 360.85 - - 689.022Total 858.97 822 1379 374.1 362 3,795.66

  • 7/30/2019 nedo 11 dec

    18/22

    Pilot AMI

    http://localhost/var/www/apps/conversion/tmp/scratch_4/AMI%20for%20Smart%20Substation.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_4/AMI%20for%20Smart%20Substation.pdf
  • 7/30/2019 nedo 11 dec

    19/22

    VSPP

    VSPP or Very Small Power Producer is a powergenerator of a private sector , state agency , stateowned enterprise or individual who generate and

    sell electrical power less than 10 MW to MEA orPEA. Fuels which are used in a power generationprocess are solar energy , biogas and biomassenergy , hydropower , natural gas and etc. The

    objectives for purchasing electrical power fromVSPP are to support an efficient use of resourcesand reduce pollution effect to the environment

  • 7/30/2019 nedo 11 dec

    20/22

    Number of VSPP

  • 7/30/2019 nedo 11 dec

    21/22

    Condition or regulations to be

    authorized as VSPP

    Power Generation Using Renewable Energy (

    attached 1 )

    Power Generation Using Cogeneration Energy

    ( attached 2 )

    http://localhost/var/www/apps/conversion/tmp/scratch_4/Regulation%20-Renewable%20(attached%201).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_4/Regulation%20-Cogeneration%20(attached%202).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_4/Regulation%20-Cogeneration%20(attached%202).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_4/Regulation%20-Renewable%20(attached%201).pdf
  • 7/30/2019 nedo 11 dec

    22/22

    The procedure to be authorized as VSPP

    1. Procedures and criteria for consideration of

    power purchase from VSPPs.

    2. Conditions for purchasing electrical powerfrom VSPPs.

    3. Power purchasing point and connection point.

    4. Costs incurred for VSPPs.