Nebraska Data Center Market Update
David BartholomaiEconomic Development
Consultant
NEBRASKA’S OVERALL ECONOMY• Governor Commitment – Jobs and Education• Limited Hangover from Great Recession• Supportive Legislature• Modest Unemployment – 3.9% • Population Resurgence – Retention of Young People• Growing Technology and Export Base• Increasing Business and University Partnerships• Strong Populace Support for Business and Jobs• Talent and Innovation Success• Available Sites
Reliable Low Cost Power• Rates 20% to 40% Below National Average
– All Public Power Keeps Rates Consistently Low
• Reliability to 99.988• Up to 40% Non-Carbon Generation Mix
Credit: Paul Schlattman – ESD Global
Coal 51.4%
Nu-clear30.0%
Land-fill-
Gas0.4%
Natu-ral
Gas0.8%
Hy-dro, 3.2%
Wind14.2%
NPPD - 2012 OPPD - 2014
Generation Mix
Coal54.7%
Nuclear29.2%
Wind4.5%Hydro
2.6%Natural Gas/Oil
1.6%
Power Purchases 7.4%
Diverse & Redundant Fiber• Multiple Tier 1 and Tier 2 long-haul IXC carriers
with diverse routes• 10+ GIG bandwidth capacity on ICB basis• Long-Haul Providers Include:
360Networks
AT&T
CenturyLink
Cogent Communications
Cox Communications
Global Crossing
Iowa Network Services
Iowa Telecom
Level 3 Communications
MCI
NIPCO
Paetec
Pinpoint
SDN Communications
Sprint
Unite Private Network
Verizon
Windstream
XO Communications
• Physical/LogicalTopology Security
• Disaster Prevention
Low risk of threat from natural disasters.
Credit: Paul Schlattman – ESD Global
Major Data Center/IT Intensive CompaniesACI Worldwide
Cabela's (18,000 SF)
CenturyLink (300,000 SF)
ConAgra Foods (60,000 SF)
CoSentry (60,000 SF & 25,000 SF)
CSG Systems
Fidelity Investments (under construction)
First Data (250,000 SF & 50,000 SF)
First National Technology Solutions
(200,000 SF)
Google (200,000 SF)
Wipro / Infocrossing (80,000 SF)
InfoGroup
Interpublic Group
Mutual of Omaha (2)
PayPal
Pinpoint
Scott Data Center (80,000 SF)
Sprint
Union Pacific Headquarters and
Harriman Dispatching Center
USSTRATCOM
Verizon (180,000 SF)
West Corporation
Yahoo! (300,000 SF)
Red denotes data center operations
Data Center – Vendors & Suppliers(not comprehensive list)ADTAhern Fire SystemsAssociated Fire Protection CorpCarrierCiscoCEDCommonwealth ElectricContinental Fire and AlarmControl Management Inc.Dakota SecurityData Power TechnologyDennis Supply CoEaton/PowerwareEcho Electric Anixter - Emerson Network Power
FergusonGraybar - Emerson Network PowerGiestGraingerGreat Plains LocatingInnovative Electrical TechnologyInterstate Power SystemsJohnson Controls IncL3 CommunicationsMainelli MechanicalMcQuay InternationalMechanical SalesMGE UPS SystemsMiller Electric
Morrissey EngineeringNebraska Air FilterNebraska Iowa SupplyNMCPilbrico EngineeringPrairie MechanicalPrecision IndustriesPredictive TechnologyRuss Electric IncSapp BrothersSecurity Equipment Inc (Sei)Superior LightingWater EngineeringWesco
Training Programs
• Green Data Center Management Program• Mission Critical Facilities Program• On-Line Studies• Tailored Programs of Studies• Business Partnerships
Incentives for Data CentersNebraska Advantage Program
Nebraska Advantage ProgramTier 1: $1 million of new investment and 10 new jobs
Tier 2: $3 million of new investment and 30 new jobs
Large Data Center = $200 million of new investment and 30 new jobs
Tier 3: New job creation only - 30 new jobs
Tier 4: $12 million of new investment and 100 new jobs
Tier 5: New investment only - $37 million
Tier 6: $10 million investment with 75 new high paying jobs or $109 million investment and 50 new high paying jobs
Tier 2: $3 Million of New Investment and 30 New Jobs
• Sliding scale compensation tax credit each year for 7 years• 10% investment tax credit for 7 years• 100% sales & use tax refunds on capital purchases• Personal property tax exemption up to 10 years for the following:
– Computer systems and certain peripherals
Tier 2 Large Data Center: $200 Million and 30 New Jobs• All above plus• 10 year exemption on all personal property on site• Use credits for real property tax rebates from state• Sign sequential Tier 5 application at same time
Credit Use
Compensation Credit - Employee WithholdingIncome TaxSales TaxReal Property Tax (Tier 6 and Tier 2 LDC)
Investment Credits - Income TaxSales TaxReal Property Tax (Tier 6 and Tier 2 LDC)
Use of Credits
Tier 5: $37 Million of New Investment and Maintain Jobs
• 100% sales & use tax refunds on project’s capital purchases• Personal property tax exemption up to 10 years for the following:
– Computer systems and peripherals
Customized Job Training Program$500 to $4,000 per employee based on wages, fringe benefits and job quality
Fund reimburses the business up to 50% of the employee’s wages during the training time up to the allotted dollar amount
Positions must be maintained for two years after the training is complete
Site and Building Development FundAvailable to assist companies with infrastructure willing to make investment in Nebraska
Other Local Incentives Available
Nebraska Data Center Sites• Aurora• Fremont• Kearney• Omaha Metro• South Sioux City