nchrp 12-112 update of the aashto national movable ......national cooperative highway research...
TRANSCRIPT
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
NCHRP 12-112 Update of the AASHTO
Movable Highway Bridge Design
Specifications
June 24, 2019| Montgomery , AL
AASHTO T8 Committee Meeting
NCHRPNATIONAL
COOPERATIVE
HIGHWAY
RESEARCH
PROGRAM
Jeff Newman
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
Disclaimer
2
Phase I Research DiscussionScheduleWork PlanObjectives
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
Presentation Outline
Project Objectives
Phase I Work - Completed
Phase II Work - Ongoing
Updated Schedule
Discussion/Questions
3
Phase I Research DiscussionScheduleWork PlanObjectives
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
4
Firm POC Email
Modjeski and Masters, Inc. Jeffrey NewmanKevin JohnsThomas MurphyZolan PruczLance Borden
Hardesty & Hanover, LLC Jim PhillipsAlec NoblePaul Skelton
Auburn University Andrzej Nowak(Andy)
Independent Consultant Ian Buckle [email protected]
4
Research Team Introduction
Phase I Research DiscussionScheduleWork PlanObjectives
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
Develop and incorporate consistent reliability-based methodology into AASHTO Movable Highway Bridge Design Specifications (MHBDS)
Update MHBDS with special focus on Electrical, Hydraulic, and Mechanical sections.
555
Project Objectives
Phase I Research DiscussionScheduleWork PlanObjectives
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
6666
Phase I Planning - Completed
Phase I Research DiscussionScheduleWork PlanObjectives
Task
1 - Review Literature
2 – Discussion of Reliability-Based Methodology
3 – Proposed Methodology
4 – Outline Proposed Specification Modifications
5 – Interim Report No. 1
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
77777
Phase II Methodology Development - Ongoing
Phase I Research DiscussionScheduleWork PlanObjectives
Task Progress
6 – Development of the Approved Methodology 90%
7 – Develop Examples 20%
8 – Sample Section 0% (Anticipated to be Section 5 for Loads)
9 – Interim Report No. 2 0%
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
888888
Phase III Specification Revision and Update
Phase I Research DiscussionScheduleWork PlanObjectives
Task Status
10a – Complete Specification Development Pending Phase II Completion/Approval
10b – Fully Develop (Update) Examples Pending Phase II Completion/Approval
11 – Interim Report No. 3 Pending Phase II Completion/Approval
Phase IV Final Products
Task Status
12 – Revisions Based on Panel Input Pending Phase III Completion/Approval
13 – Final Deliverables Pending Phase III Completion/Approval
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
999999
Phase I Research DiscussionScheduleWork PlanObjectives
Phase I - Results
Summary of Phase I Research Findings
1. Meaningful Sample of Movables
8 Owners from diverse locations
267 movable bridges
44% Bascule
20% Vertical Lift
31% Swing
5% Retractable
92
22
2
52
83
15
Movable Bridge Type
Trunnion Bascule Rolling Lift Bascule Other Bascule
Vertical Lift Swing Retractable
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
101010101010
Phase I Research DiscussionScheduleWork PlanObjectives
Phase I - Results
Summary of Phase I Research Findings
2. Frequency of Operation
Min = 12 / yr
Max = 14,600 / yr
Average Min = 1,107 / yr (2.8 per day)
Average Max = 6,903 / yr (18.9 per day)
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
111111111111
Phase I Research DiscussionScheduleWork PlanObjectives
Phase I - Results
Summary of Phase I Research Findings
3. Waterway Categories & Wind Restrictions
21
129
105
12
PORT OF ENTRY COMMERCIAL MIXED USE RECREATIONAL
Waterway Categories
Average 39 mph
40
50
3530
40 4035
40
0
10
20
30
40
50
60
1 2 3 4 5 6 7 8
Operating Wind Restrictions (mph)
Sustained Wind Limit (mph) Wind Gust Limit (mph)
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
121212121212
Phase I Research DiscussionScheduleWork PlanObjectives
Phase I - Results
Summary of Phase I Research Findings
4. Reliability of Systems / Components
RATING SCALE:
5 = Excellent
4 = Good
3 = Satisfactory
2 = Fair
1 = Poor0
1
2
3
4
5
SupportMachinery
DriveMachinery
Locking / LiveLoad Transfer
Electrical Power/ Control
Traffic Control(gates / signals)
RoutineMaintenance
(over life)
Rel
iab
ility
Rat
ing
System / Component
Reliability - Routine Maintenance
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
131313131313
Phase I Research DiscussionScheduleWork PlanObjectives
Phase I - Results
Summary of Phase I Research Findings
5. Conclusions
Owner Surveys were very valuable:
Consistent Responses with widely varying Owners
Owners satisfied with existing code outcomes => calibrate to existing AASHTO Movable
Other than Dutch Code, design information is limited in applicability to movable bridges
We will utilize some of the Dutch code ideas such as targeted wind loading
Reliability indices correlate to Eurocode. We will calibrate to existing AASHTO code.
Reliability-Based Methods are best applied to Loads that are Resisted by Mechanical and Structural components
Electrical and Hydraulic design are subjected to NEC and NFPA, respectively
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
Sections 1 -4: General Updates
Section 5: Modify (Mechanical Design Loads and Power Requirements)
Add: Bridge Availability (Operational Requirements)
Add: Wind Loading During Operation
Add: Design Loads for Mechanical Subsystems and Components (Relocated from 6.5 & 7.4.1 and Updated)
Section 6: Update Resistance Factors
Section 7: Update Resistance Factors
Section 8: General Updates
1414141414141414141414
Phase I Research DiscussionScheduleWork PlanObjectives
Outline of Proposed Specification Modifications
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
Appx B: New “System Reliability”Objectives and Limitations
Failure Mode Analysis
• Acronyms and Definitions
• Methodology
Subsystem Development
• Reliability Block Diagram
• Mech / Elec (power) / Control / Hydraulic / Locking / Span Support / Traffic Control
Identifying Critical Failure Items
• Risk Assessment
Redundant Design
1515151515151515151515
Phase I Research DiscussionScheduleWork PlanObjectives
Outline of Proposed Specification Modifications
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
Survey 1: Bridge OwnersBridge Importance / Availability
Bridge Maintenance / Subsystem Malfunction
Component Reliability
Manufacturers / SuppliersStandard Product Reliability (limited data available such as L10)
Fabricated Product Reliability (no standardized data available)
Opportunities for future research (beyond this project)On-going input from:
• Bridge Owners / Manufacturers / Designers
16
Knowledge Gaps
1616161616
Phase I Research DiscussionScheduleWork PlanObjectives
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
1717171717171717171717
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Movable Bridge Limit States
Mechanical, Hydraulic, Electrical Design Limit States
Service
Fatigue
Overload
Extreme Event
Structural Limit StatesStrength
Service (not in current AASHTO)
Fatigue (not in current AASHTO)
Overload (not in current AASHTO)
Extreme Event
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
1818181818181818181818
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Service Limit StateDefinition: A state in which the function of the machinery, its performance,
durability, maintainability, and safety are preserved under normal use.
Objectives: Avoid elastic deformations in machinery components that may impair serviceability or produce localized stresses under normal operating loads that reduce the anticipated service life of components (i.e. premature or accelerated wear).
Load Cases:• Case 1a: 150% FLT of the motor (AASHTO Movable Ref: 5.7.1)
• Case 1b: Pump Pressure at Normal Pressure (relief valve setting) (AASHTO Movable Ref: 7.4.2)
• Case 1c: 1.0 FLT for Internal Combustion Engine (AASHTO Movable Ref: 5.7.1)
• Case 2: Motor or Machinery Brake Torque (AASHTO Movable Ref: 5.7.3) (Option 1)
Values in red are
from current
code and subject
to change
pending further
analysis
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
1919191919191919191919
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Fatigue Limit StateDefinition: A state in which crack development and growth in
machinery, due to repetitive loading, is prevented under normal use.
Objectives: Avoid development and growth of fatigue cracks in structural and mechanical components subject to tensile stress from repetitive loading due to bridge operation or truck loading.
Load Cases:• Case 2a: 100% FLT of the motor (AASHTO Movable Ref: 5.7.1)
• Case 2b: Pump Pressure at Normal Pressure (relief valve setting) (AASHTO Movable Ref: 7.4.2)
• Case 2c: Loading caused by movement of the movable span
Values in red are
from current
code and subject
to change
pending further
analysis
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2020202020202020202020
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Values in red are
from current
code and subject
to change
pending further
analysis
Overload Limit StateDefinition: A state in which the functionality of the operating machinery,
its ability to resist or transmit loads, is preserved under maximum operating or resisting loads.
Objectives: Avoid localized yielding that may permanently deform machinery components while allowing higher stresses for load cases of limited frequency.
Load Cases:• Case 3a: 1.5 ST or 1.5 BDT for uncontrolled AC motors (AASHTO Movable Ref: 5.7.1)
• Case 3b: 1.0 ST or 1.5 AT for controlled AC motors (AASHTO Movable Ref: 5.7.1)
• Case 3c: 3.0 FLT for controlled DC motors (AASHTO Movable Ref: 5.7.1)
• Case 3d: Hydraulic Pressure at Maximum Working Pressure (overriding pressure relief valve setting)
• Case 3e: 1.0 PT at Full Throttle for Internal Combustion Engine (AASHTO Movable Ref: 5.7.1)
• Case 4: Combined Motor or Machinery Brake Torque (Option 2)
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2121212121212121212121
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6Extreme Event Limit State
Definition: A state in which the capacity of the machinery to perform its functions related to maintaining stability of the movable span is preserved during an extreme event such as an earthquake or vessel allision.
Objectives: Avoid failure of machinery that participates in supporting or stabilizing the movable span during extreme events. Permanent plastic deformation that renders the machinery inoperable is acceptable provided the resulting displacements do not compromise the survivability of the movable span.
Load Cases:• Case 5a: Serviceability Earthquake bridge closed / Case 5b: Serviceability Earthquake bridge open
• Case 5c: Survivability Earthquake bridge closed / Case 5d: Survivability Earthquake bridge open
• Case 5e: Vessel Impact bridge closed / Case 5f: Vessel Impact bridge open
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2222222222222222222222
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Wind Loads
Maintain existing code correlation to operation up to Tropical Storm Force Winds (39mph / 10 psf)
Harmonize basis with AASHTO LRFD & ASCE 7-10 (3 second wind gust)
Correlate equivalent wind loadings for holding, structural design and temporary conditions (operating and holding)
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2323232323232323232323
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Wind Loads
Provide alternative method for bridges with outlying conditions
Traffic Importance
Waterway Importance
Limit minimum to 7.5 psf and recommend maximum of 12.5 psf
Provides basis for states like Michigan to use 50mph operating condition
Provides basis to adjust for critical bridge locations, e.g. port entrance / evacuation traffic
Provides options to lower cost of less critical bridges, e.g. seldom operated / low traffic bridges
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2424242424242424
Ph II Development DiscussionScheduleWork PlanObjectives
Task Submission Review completed Phase
5 – Interim Report No. 1 - Preliminary April 29, 2018 May 2018 I
5 – Interim Report No. 1 - Final August 31, 2018 September 2018 I
6 – Develop and Execute Methodology November 30, 2019 February 2020 II
7 – Develop Illustrative Examples December 31, 2019 February 2020 II
8 – Complete Sample Section of the Guide December 31, 2019 February 2020 II
9 – Interim Report No. 2 December 31, 2019 February 2020 II
10 & 11 – Complete Revised Specs & Examples / IR 3 August 31, 2020 September, 2020 III
12 & 13a – Revisions and Draft Final Report December 31, 2020 February, 2021 IV
13b – Final Report and End of project March 31, 2021 IV
Research Schedule
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
25252525252525252525
Ph II Development DiscussionScheduleWork PlanObjectives
- Open Discussion -
NCHRP 12-112 Update of the AASHTO LRFD
Movable Highway Bridge Design Specifications
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2626262626262626262626
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Proposed New Target Reliability IndicesβT ~ 1.0: Service LS
• Correlates to Pf = 0.15 = 15%
βT ~ 2.75: Overload LS• Correlates to Pf = 0.0049 = 0.49%
βT ~ 3.75: Extreme Event LS• Correlates to Pf = 0.0001 = 0.01%
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2727272727272727272727
Ph II Development DiscussionScheduleWork PlanObjectives
Execution of Methodology| Task 6
Service Limit Stateβ = 1.09: Reliability Index – Current MHBS
• Value as calculated by Auburn Team
βT ~ 1.0: Target Reliability Index – Proposed New• Correlates to Pf = 0.15 = 15%
β = 1.23 : Calculation Results with:• Recommended Load Factor: 𝛾 = 2.5
• Recommended Resistance Factor: 𝜙 = 0.8
NCHRP 12-112 - AASHTO T8 Committee Meeting - June 2019
2828282828282828282828
Ph II Development DiscussionScheduleWork PlanObjectives
Develop Illustrative Examples| Task 7
Service Limit State – Sample ProblemTorsion in a shaft
• Required Diameter = 1.402” Existing MHBS
• Required Diameter = 1.420” Proposed New LRFD Method
• Proposed New LRFD Method slightly more conservative by 1.3% for this example.
More samples will be run to verify consistency of results.