Navajo County Public Works. Navajo County Public Works. Major Capital Improvement Projects. Porter Mountain Road - $2.7 Million Realign, Replace and Reconstruct 1.7Miles of Existing Roadway to Apache County Line – under way Lone Pine Dam Road and Bridge - $ 5.0 Million - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Navajo County  Public Works

Navajo County Public Works

Page 2: Navajo County  Public Works

Navajo County Public Works

Major Capital Improvement Projects

Porter Mountain Road - $2.7 Million• Realign, Replace and Reconstruct 1.7Miles of Existing Roadway

to Apache County Line – under way

Lone Pine Dam Road and Bridge - $5.0 Million• Realign Existing Roadway• Construct New Bridge South of Dam • Hope to be out to construction this fall or next spring

Obed Bridge - $2.6 Million• Replace Bridge Truss System and Deck with new Bridge

Page 3: Navajo County  Public Works

Navajo County Public Works

Porter Mountain Road

Page 4: Navajo County  Public Works

Navajo County Public Works

Porter Mountain Road

Page 5: Navajo County  Public Works

Navajo County Public Works

Porter Mountain Road

Project Details•Upgrade Roadway & Existing Drainage System

•Coordinate with Local USFS District

•Federal Land Exchange Issues

•Selected Design-Build Team

•Plans and GMP completed at $2.27 M.

•Construction well underway, to be done in October, 2008

Page 6: Navajo County  Public Works

Navajo County Public Works

Lone Pine Dam Road and Bridge

Page 7: Navajo County  Public Works

Navajo County Public Works

Lone Pine Dam Road and Bridge

Roadway Alignment Study

Page 8: Navajo County  Public Works

Navajo County Public Works

Project Details

•1 Mile of Roadway Construction

•Realignment and Reconstruction

•440 ft Bridge Span

•100% Plans completed and submitted to ADOT in August, 2008

•Construction hopefully to bid in late 2008

Lone Pine Dam Road and Bridge

Page 9: Navajo County  Public Works

OBED BRIDGE

In final Design -Estimated cost $2.6 million

Page 10: Navajo County  Public Works

Navajo County Public Works

Roadway Maintenance

Surry Seal • Completed 20 miles this summer

AC Overlay

Double Chip Seal • Completed 5 miles near Taylor

• Rejected Bids, will re-bid in Spring 2009

Page 11: Navajo County  Public Works

Navajo County Public Works

Subdivisions

•Currently Processing 45 Subdivisions

•Lot Sizes from .5 to 10 acres

Page 12: Navajo County  Public Works

Navajo County Public Works

Transportation Study

Sub-Regional Study Completed in late 2007•Pinetop-Lakeside•Show Low•Snowflake•Taylor•Vernon•Concho

•Now Expanding study to include remainder of County, Winslow and Holbrook with ADOT support.

Page 13: Navajo County  Public Works

Navajo County Public Works

Transportation Study

Page 14: Navajo County  Public Works

Navajo County Public Works

Transportation Study

Page 15: Navajo County  Public Works

Navajo County Public Works

Transportation Study

Page 16: Navajo County  Public Works

Navajo County Public Works

Transportation Study

Summary:

•Study Completed July 2007 – Provides Traffic Impact Projected to 2030

•Additional Study Areas to be Incorporated (Holbrook, Heber/Overgaard, Winslow)

•Began additional study January 23, 2008

•Coordination with Statewide Study

•Interim Projection to 2015

Page 17: Navajo County  Public Works

Navajo County Public Works

Planning and Zoning

•Total New Roads added to Book of Maintained Roads: 15 Miles (2007)

•Propose Development Impact Fees; •Study on hold till new President elected•Implementation may be delayed due to economic concerns

Page 18: Navajo County  Public Works

Navajo County Public Works

Flood Control

•Preliminary DFIRM received Sep 2007•Digital GIS Format•Mapping Process - 27 miles of levees

oRuby WashoWinslowoHolbrookoMet with public in NovemberoAsked for additional time for review

•County Flood Control Audit – Feb 2007•Rating Improvement from Level 9 to 8•10% Discount in Flood Insurance Rates

•Revised Subdivision and Drainage Policy•Requires 100-year, 2-hour Detention•Complies with Applicable State Standards 

Page 19: Navajo County  Public Works

Navajo County Public Works

Current Vacancies

•Our positions are pretty well frozen for the time being, until the economy turns around.•Eliminated Deputy Planning Director position•Have position open for County Engineer (P.E.)

Page 20: Navajo County  Public Works

Current Projects

Navajo County Public Works

On-Call Engineering Services, 2007 - Retained four firms – kept them for 08-09

On-Call Soils Testing Services, 2007 - retained one firm – may expand in 09

Obed Road Bridge final Design - under contract (Transystems)

Selected one firm to perform Mountain View ID and one small ID (North Whistle Stop Loop)

Selected one firm to do Hilltop Lane ID Two new IDs in formation stage