national mission for clean ganga€¦ · national mission for clean ganga ministry of jal shakti,...
TRANSCRIPT
NATIONAL MISSION FOR CLEAN GANGA
Ministry of Jal Shakti,
Department of Water Resources, River Development & Ganga Rejuvenation, Government of India
LEA ASSOCIATES SOUTH ASIA PVT. LTD. New Delhi, India
Draft Environmental and Social Due Diligence Report
Interception and Diversion and STP Scheme in Saharanpur
January 2020
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | i
CONTENTS E. EXECUTIVE SUMMARY
1. INTRODUCTION ......................................................................................................... 1-1
1.1 NAMAMI GANGE PROGRAMME ............................................................................ 1-2
1.2 STRUCTURE OF THE REPORT .................................................................................. 1-2
2. PROJECT DESCRIPTION .............................................................................................. 2-1
2.1 CITY PROFILE .......................................................................................................... 2-1
2.2 EXISTING SCENARIO OF SEWERAGE FACILITIES IN SAHARANPUR CITY ................. 2-2
2.3 NECESSITY OF THIS PROJECT .................................................................................. 2-4
2.4 DESCRIPTION OF PROPOSED PROJECT ACTIVITIES ................................................ 2-5
2.5 Disposal of treated effluent ................................................................................. 2-12
2.6 SLUDGE STORAGE and disposal ........................................................................... 2-13
2.7 Cost Estimate ....................................................................................................... 2-13
3. APPROACH AND METHODOLOGY .............................................................................. 3-1
3.1 METHODOLOGY ..................................................................................................... 3-1
3.2 Review of available documents and data collation ............................................... 3-1
3.3 Describing the sub-project activities ..................................................................... 3-2
3.4 discussion with the key stakeholders .................................................................... 3-2
3.5 baseline environmental and social profile of project area .................................... 3-2
3.6 Screening Activities ................................................................................................ 3-2
3.7 Identification and assessment of impacts ............................................................. 3-2
3.8 Developing Management Action Plan ................................................................... 3-2
3.9 SCOPE OF WORK .................................................................................................... 3-3
4. ENVIRONMENTAL AND SOCIAL PROFILE OF PROJECT AREA ........................................ 4-1
4.1 Physiography .......................................................................................................... 4-1
4.2 Seismicity ............................................................................................................... 4-1
4.3 Climate and weather .............................................................................................. 4-2
4.4 Air Environment ..................................................................................................... 4-2
4.5 Water Environment ............................................................................................... 4-3
4.6 Water Quality ......................................................................................................... 4-4
4.7 Biological Environment .......................................................................................... 4-7
4.8 Noise Environment ................................................................................................ 4-8
4.9 Soil Environment .................................................................................................... 4-8
4.10 Forest area and land use ........................................................................................ 4-9
4.11 Ecological Sensitive area in the project area ......................................................... 4-9
4.12 Archaeological sites ............................................................................................... 4-9
4.13 Agro-climatic zones and soil condition ................................................................ 4-11
4.14 Socio-cultural environment ................................................................................. 4-11
4.15 Population ............................................................................................................ 4-11
4.16 Sex Ratio and Literacy rate .................................................................................. 4-12
4.17 Schedule Caste and Schedule Tribe Population .................................................. 4-12
4.18 Occupational Structure ........................................................................................ 4-12
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | i i
4.19 Slum areas in Project City .................................................................................... 4-13
4.20 Cityげs plaミミed aIti┗ities ....................................................................................... 4-13
5. ENVIRONMENTAL AND SOCIAL SAFEGUARD DUE DILIGENCE ...................................... 5-1
5.1 Policy, Legal and Regulatory Requirements .......................................................... 5-1
5.2 Key Applicable Laws and Regulations – Environmental & Social .......................... 5-1
5.3 Key Applicable Laws and Regulations – Social ....................................................... 5-4
5.4 Other Legislations applicable to Construction activities under the project .......... 5-4
5.5 Applicable World Bank Policies .............................................................................. 5-6
5.6 Compliance to Regulatory Requirements .............................................................. 5-6
5.7 Land Requirements ................................................................................................ 5-6
5.8 Stakeholder Consultations ................................................................................... 5-11
5.9 Environmental and Social Impact Assessment .................................................... 5-12
5.10 Environmental and Social Management Action Plan .......................................... 5-13
5.11 Construction & Occupational Health and Safety ................................................. 5-13
5.12 Implementation Arrangement ............................................................................. 5-13
5.13 Grievance Redress Mechanism ............................................................................ 5-14
5.14 Gender Assessment, Development ..................................................................... 5-14
5.15 Gender Based Violence (GBV) .............................................................................. 5-14
5.16 Integration of ESMAP with Project ...................................................................... 5-15
5.17 Requirements for preparation of ESHS Management Strategies and
Implementation Plans (ESHS-MSIP): .................................................................... 5-15
5.17.1 Requirements for the preparation of the Code of Conduct: ............................................ 5-15
5.17.2 Compliance with applicable laws, rules, and regulations of the jurisdiction .................. 5-16
6. FINDINGS OF GAP ANALYSIS ...................................................................................... 6-1
7. IMPLEMENTATION SCHEDULE AND RESPONSIBILITY .................................................. 7-1
8. RECOMMENDATIONS ................................................................................................ 8-1
8.1 Design and Planning Aspects ................................................................................. 8-1
8.2 Design and operational specific ............................................................................. 8-2
LIST OF TABLES
TABLE 2-1: SALIENT FEATURES OF EXISTING STP IN SAHARANPUR CITY ......................................................................................... 2-2
TABLE 2-2: SUMMARY OF EXISTING SEWERED AREAS - ZONE WISE IN SAHARANPUR CITY ............................................................ 2-4
TABLE 2-3: DETAILS OF EXISTING DRAINS IN SAHARANPUR ............................................................................................................ 2-4
TABLE 2-4: EFFLUENT DISCHARGE STANDARDS FOR SEWAGE TREATMENT PLANT (CPCB) ........................................................... 2-12
TABLE 2-5: CHARACTERISTICS OF TREATED SEWAGE EFFLUENT.................................................................................................... 2-12
TABLE 2-6: ABSTRACT OF COST ESTIMATION FOR PROPOSED SEWERAGE SCHEME FOR SAHARANPUR ....................................... 2-13
TABLE 4-1: RESULTS OF AMBIENT AIR QUALITY MONITORING CONDUCTED AT THE PROPOSED PROJECT LOCATION ................... 4-3
TABLE 4-2: PHYSICO-CHEMICAL & BIOLOGICAL CHARACTERISTICS OF SURFACE WATER SAMPLE OF DHAMOLA RIVER (UPSTREAM)
NEAR STP SITE
TABLE 4-3: PHYSICO-CHEMICAL & BIOLOGICAL CHARACTERISTICS OF SURFACE WATER SAMPLE OF DHAMOLA RIVER
(DOWNSTREAM) NEAR STP SITE ...................................................................................................................................................... 4-5
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | i i i
TABLE 4-4: ANALYSIS RESULT OF GROUND WATER SAMPLE ........................................................................................................... 4-6
TABLE 4-5: NOISE LEVEL IN PROJECT AREA: STP SITE RESIDENTIAL AREA ........................................................................................ 4-8
TABLE 4-6: NOISE LEVEL IN PROJECT AREA: COMMERCIAL AREAS .................................................................................................. 4-8
TABLE 5-1: ENVIRONMENTAL REGULATIONS AND LEGISLATIONS ................................................................................................... 5-1
TABLE 5-2: OPERATIONAL POLICIES OF WORLD BANK ..................................................................................................................... 5-6
TABLE 5-3: LAND REQUIREMENT DETAILS FOR THE PROPOSED IPS AND STP LOCATIONS .............................................................. 5-7
TABLE 5-4: PUBLIC CONSULTATION HELD DURING ESDDR PREPARATION .................................................................................... 5-11
TABLE 6-1: GAP ANALYSIS FINDINGS................................................................................................................................................ 6-1
TABLE 7-1: IMPLEMENTATION SCHEDULE AND ASSOCIATED RESPONSIBILITIES ............................................................................. 7-1
LIST OF FIGURES
FIGURE 2-1: REGIONAL SETTING OF SAHARANPUR DISTRICT AND SAHARANPUR CITY ................................................................... 2-1
FIGURE 2-2: EXISTING SEWERAGE PLAN OF SAHARANPUR CITY ..................................................................................................... 2-3
FIGURE 2-3: POPULATION GROWTH TREND OF SAHARANPUR CITY ............................................................................................... 2-5
FIGURE 3-1: FLOWCHART DESCRIBING STEPS ADOPTED FOR ESDDR PREPARATION ...................................................................... 3-1
FIGURE 4-1: SEISMIC MAP OF UTTAR PRADESH .............................................................................................................................. 4-1
FIGURE 4-2: LAST FIVE YEAR RAINFALL RECORD OF SAHARANPUR ............................................................................................... 4-2
FIGURE 4-3: AIR QUALITY IN SAHARANPUR CITY (2019) ................................................................................................................ 4-2
FIGURE 4-4: COMPARATIVE RECORD OF WATER QUALITY FOR THE YEAR 2018 AND 2019 ............................................................ 4-4
FIGURE 4-5: FOREST COVER MAP OF UTTAR PRADESH .................................................................................................................. 4-9
FIGURE 4-6: WILDLIFE PROTECTED AREAS IN UTTAR PRADESH ..................................................................................................... 4-9
FIGURE 4-7: MAP SHOWING THE DISTANCE OF RAJAJI NATIONAL PARK FROM THE PROPOSED STP SITE .................................... 4-10
FIGURE 4-8: AGRO-CLIMATIC AREAS IN UTTAR PRADESH.............................................................................................................. 4-11
FIGURE 4-9: POPULATION GROWTH IN THE REGION (FIGURES IN LAKHS) ................................................................................... 4-11
FIGURE 4-10: ST AND SC POPULATION OF SAHARANPUR M. CORP. .............................................................................................. 4-12
FIGURE 4-11: OCCUPATIONAL STRUCTURE OF SAHARANPUR MUNICIPAL CORPORATION ........................................................... 4-12
FIGURE 5-1: LAND IDENTIFIED FOR PROPOSED STP LOCATION AT BADSHAPUR VILLAGE ............................................................... 5-8
FIGURE 5-2: PROPOSED IPS LOCATION NEAR OLD POLICE CHOWKI (LAND IDENTIFIED) ................................................................. 5-9
FIGURE 5-3: PROPOSED IPS LOCATION NEAR PAPER MILL ROAD (LAND IDENTIFIED) ..................................................................... 5-9
FIGURE 5-4: REVENUE MAP FOR THE PROPOSED STP LOCATION .................................................................................................. 5-10
LIST OF ANNEXURES
ANNEXURE – 1: ENVIRONMENTAL AND SOCIAL SCREENING CHECKLIST
ANNEXURE – 2: MINUTES AND ATTENDANCE SHEETS OF STAKEHOLDER AND COMMUNITY CONSULTATIONS
ANNEXURE – 3: TEST REPORTS OF AIR QUALITY MONITORING CARRIED OUT AT PROJECT LOCATION
ANNEXURE – 4: TECHNICAL FEASIBILITY REPORT1 FOR SELECTED LAND FOR PROPOSED 90 MLD STP AND 2 IPS
ANNEXURE- 4.1: CONSENT/MOU BETWEEN LANDOWNERS AND JAL NIGAM, SAHARANPUR
ANNEXURE -4.2: MOU BETWEEN MUNICIPAL CORPORATION AND JAL NIGAM, SAHARANPUR ON LANDFILL SITE FOR SLUDGE
DISPOSAL
ANNEXURE –5: ENVIRONMENTAL AND SOCIAL MANAGEMENT ACTION PLAN (ESMAP)
ANNEXURE –6: GRIEVANCES REPORTING AND RECORDING FORMATS
.
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | iv
LIST OF ABBREVIATIONS
CBO --- Community-Based Organization
CPCB --- Central Pollution Control Board
CP GRAM --- Centralized Public Grievance Redress and Monitoring System
CTE --- Consent of Establish
CTO --- Consent of Operate
DM --- District Magistrate
DoE --- Department of Environment
DPR --- Detailed Project Report
EA --- Executing Agencies
EMP --- Environmental Management Plan
EPA --- Environment (Protection) Act
ESMF --- Environmental and Social Management Framework
ESAMP --- Environmental & Social Assessment and Management Plan
ESMAP --- Environmental & Social Management Action Plan
GAAP --- Governance and Accountability Action Plan
GoI --- Government of India
GBV --- Gender Based Violence
GRM --- Grievance Redressal Mechanism
GRO --- Grievance Redress Officer
ha. --- Hectare
I&D --- Interception & Diversion
ICC --- Internal Complaints Committee
IEC --- Information, Education and Communication
IMD --- Indian Metrological Department
INTACH --- Indian National Trust for Art and Culture Heritage
IPS --- Intermediate Pumping Station
LASA --- Lea Associates South Asia Private Limited
LPVA --- Land Price and Valuation Approval Committee
MC --- Municipal Corporation
MDA --- Meerut Development Authority
MFP --- Minor Forest Produce
MLD --- Million Liter per day
MoEFC&C --- Ministry of Environment, Forests and Climate Change
MoU --- Memorandum of Understanding
MPS --- Main Pumping Station
NCR --- National Capital Region
NGO --- Non-Government Organization
NGRBA --- National Ganga River Basin Authority
NGRBP --- National Ganga River Basin Projects
NH --- National Highways
NMCG --- National Mission for Clean Ganga
NOC --- No Objection Certificate
O&M --- Operation & Maintenance
OHS --- Occupational Health & Safety
OP --- Operational Policy
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page |v
PAFs --- Project Affected Families
SEIAA --- State Level Environment Impact Assessment Authority
SPCB --- State Pollution Control Board
SMCG --- State Mission for Clean Ganga
SPS --- Sewage Pumping Station
ST --- Scheduled Tribe
STP --- Sewage Treatment Plant
ToR --- Terms Of Reference
ULBs --- Urban Local Bodies
UPJN --- Uttar Pradesh Jal Nigam
UPPCB --- Uttar Pradesh Pollution Control Board
WB --- World Bank
YAP --- Yamuna Action Plan
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | E -1
E- EXECUTIVE SUMMARY
INTRODUCTION
1. The Go┗eヴミマeミt of Iミdia has gi┗eミ Gaミga the status of a さNatioミal ‘i┗eヴざ aミd iミ exercise of the powers
conferred by sub-sections (1) and (3) of Section 3 of the Environment (Protection) Act, 1986, the Central
Government constituted the National Ganga River Basin Authority (NGRBA) on 20th
February 2009, as a planning,
financing, monitoring and coordinating authority for strengthening the collective efforts of the Central and State
Governments for effective abatement of pollution and conservation of the Ganga river by adopting a river basin
approach with comprehensive planning and management. In regards to this initiative, under pollution abatement
pヴogヴaママe NG‘BA pヴoposes さIミteヴIeptioミ & Di┗eヴsioミ aミd “TP sIheマe iミ “ahaヴaミpuヴざ.
2. Fuヴtheヴ, iミ the yeaヴ ヲヰヱヴ the Go┗eヴミマeミt of Iミdia lauミIhed さNaマaマi Gaミgeざ pヴogヴaママe, ┘hiIh Io┗eヴs the previously sanctioned ongoing projects as well as the projects in new components with multi sector mandate to
address both water quality and water quantity issues. The programme aims at integrating previous & currently
ongoing initiatives by enhancing efficiency, extracting synergies and supplementing them with more comprehensive
& better coordinated interventions. Namami Gange Programme has been segregated into two different
components:
► Component A: Pertains to ongoing projects of cleaning of river Ganga & its tributaries, including World Bank
Assisted NGRBA programme having remaining central liabilities.
► Component B: Pertains to new initiatives to be undertaken in 5 major sectors i.e. Infrastructure Development
(Sewage Treatment, River Front Development, and Industrial Wastewater Treatment & Solid Waste
Management), Institutional Development, Ecological Sustainability, Research & Development and
Communication & Public Outreach.
PROJECT AREA
3. The project city is located in Saharanpur District of Uttar Pradesh and is the administrative head quarter of
the Saharanpur Division. The city is situated close to the borders of the States of Haryana and Uttarakhand and
located about 550 km from the capital city of Lucknow, 164 km from Delhi and 70 km from Dehradun, the capital of
the state of Uttarakhand.
4. Saharanpur city is situated in the upper doab region and is the land laying between two converging or
confluent Rivers Yamuna and Ganga. The city grew in a region named after a Sufi Saint Shah Haroon Chishti. The
city has been selected for developing infrastructure under both the 'Smart City' and AMRUT missions, which are to
be funded by the central government of India.
PROJECT DESCRIPTION
5. The Project area lies between latitude 290 ヰヰげ aミd ンヰ0
ヲヴげ ミoヴth aミd loミgitude ΑΑ0 Αヰげ aミd ΑΒ0
ヱヲげ east iミ the upper Ganga doab
2 in the Indo-Gangetic plains of India. The State of Uttar Pradesh is classified into three
distinct regions: (i) the northern sub-mountain region called Tarai, (ii) the Gangetic Plains and (iii) the Southern
Plateau. Additionally, for the purpose of development planning, Bundelkhand region is separated from Southern
Plateau. Geographically, Saharanpur city is located in northwestern Gangetic plains and Tarai, Bhahbar zones of
Uttar Pradesh State, India. The area is flat alluvial plain with a gentle slope from north to south direction.
6. The municipal corporation of Saharanpur (as of 2011) is 46.74 Km2 and the other census town covering
6.29Km2. The entire Saharanpur district is divided into 5 tehsils namely, Saharanpur, Behat, Nakur, Deoband and
2 Doab is a term used in South Asia for the "tongue," or tract of land lying between two converging, or confluent, rivers. It is
similar to an interfluve.
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page |E -2
Rampur Maniharan. According to the 2011 census, Saharanpur city (Municipal Corporation3) has population of
705,478 and the number of households4 is 129,856.
7. As per the Environmental and Social Management Framework (NGRBA, 2011)5, the implementation of such
river pollution mitigation projects under the NGRBP is anticipated to encounter a variety of environmental and
social issues/problems. Therefore, the study of the environment and social sector is required for analyzing the
impacts of the proposed project and suggesting the management plans to handle any negative impacts. In this
regard, the Environmental and Social Due Diligence Report (ESDDR) has been prepared.
8. The ESDDR will provide a clear understanding of the prevailing and expected environmental and social
impacts as well as their probable causes, which have to be considered while preparing and implementing the
proposed interventions for strengthening the existing and proposed sewerage infrastructure of Saharanpur.
EXISTING SCENARIO OF SEWERAGE FACILITIES
9. Sewerage system in Saharanpur was partially implemented and the entire sewage and sullage is carried by
the existing system of open nalas and discharge into rivers of Dhamola or Pandhoi, resulting in deterioration of
water quality of these rivers.
10. In the year 1998, under Yamuna Action Plan-1 (YAP1) interception and diversion works and STP had been
provided in the city. The total length of the sewerage network in Saharanpur Nagar Nigam is about 111 Km. out of
which 27.37 Km. is trunk sewer and 84.15 km of Brach sewers. The entire piped sewerage system is divided into 4
zones and encompassing 30 wards and 157 colonies. There are 3 Intermediate Pumping Stations (IPS) and 1 Main
Pumping Station (MPS) and 1 STP (38 MLD).
11. The sewer flow from Intermediate Pumping Stations (IPS) is pumped to manholes located on the trunk
sewers and is carried by gravity to Main Pumping Station (MPS) located at Praduman Nagar STP.
12. Presently, in Saharanpur city total 51 drains were trapped during YAP-1 and connected with sewerage
system to divert flow to the STP of 38 MLD at Praduman Nagar through 3 intermediate Pumping Stations (IPS).
Saharanpur city does not have a proper sewerage system and all houses have individual septic tanks that discharge
into the open drains causing pollution.
NECESSITY OF THIS PROJECT
13. Saharanpur city, unlike other Indian cities, does not have a centralized existing sewer system for collection,
transportation, treatment and disposal of domestic and institutional wastewater. Due to tremendous population
growth and increased areas of habitation, different sections of existing main and branch sewers network are
partially and/or fully chocked. The untreated sewerage disposal is also a critical area; most of the wastewater of
town and from un-sewered areas is discharged directly into the drains creating an unhygienic environment.
Likewise, the effluents from industries, slaughterhouses etc. are also discharged directly into the drains without any
treatment. In addition to the above, during monsoon the wastewater from the nalas (which are small open drains),
overflows into the nearby roads and by-lanes resulting in waterlogging and ponding at various locations in the city.
This creates nuisance and unhygienic conditions and eventually leads to serious health hazards. Further, individual
septic tanks are not properly maintained in the city and are one of the major sources of pollution. Hence, it is of
utmost importance to develop proper septate management in Saharanpur city.
3 District Census Handbook, Saharanpur, 2011. 4
Detail Project Report for I&D & STP Works in Saharanpur City under Namami Gange Programm, 2018. 5 For the Environmental and Social Management Framework (ESMF) document please refer
https://www.nmcg.nic.in/writereaddata/fileupload/25_Namami_Gange_ESMF__August_17_2017__1___1_.pdf
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page |E -3
14. Therefore, in order to reduce pollution load of major drains of Saharanpur, the existing sewerage network
necessities renovation, strengthening and establishment of new STP along with intermediate pumping stations, so
that the wastewater would be treated before its discharge to Pandhoi and Dhamola Rivers, which finally joins with
the Ganga River at downstream.
PROPOSED PROJECT ACTIVITIES
15. The proposed project involves strengthening of existing sewerage infrastructure of the Saharanpur district
by intercepting and diverting the wastewater flowing through existing nalas, newly proposed sewage treatment
plant of capacity 85 MLD to treat the wastewater before its discharge to Dhamola and Pandhoi rivers, which finally
joins with the Ganga River at downstream.
16. According to the Detailed Project Report (DPR), the マajoヴ Ioマpoミeミts of the pヴoposed さIミteヴIeptioミ & Diversion with STP at Saharanpur, Uttaヴ Pヴadeshざ uミdeヴ Naマaマi Gaミge Pヴogヴaマ iミIlude:
► Interception & Diversion structures (9 Nos.)
► Raising main and I&D network.
► New MPS (1 No.)
► Construction of new Sewage Treatment Plant (STP) of capacity 85 MLD.
► Operation & maintenance (O&M) for 15 years.
► Installation of trash arresting rack and its regular O&M at the mouth of all drains.
► Adequate provision for handling septage in the STP.
APPROACH AND METHODOLOGY
17. The Environmental and Social Due Diligence Report (ESDDR) is prepared by LEA Associates South Asia
Private Limited, New Delhi, on the basis of Detailed Project Report that has been prepared by UP Jal Nigam. The
Environmental and Social Management Framework (ESMF of NGRBA, 2011) is intended to identify and assess the
several environment and social impacts (both positive and negative) that may results for the proposed river
pollution mitigation project of Rivers Dhamola and Pandhoi at Saharanpur, under NGRBP, as well as to provide a
corresponding management plan to handle any adverse/negative impacts. The methodology adopted for
conducting Environmental and Social Due Diligence for the proposed interventions includes –
► Review of available documents and data collection,
► Describing the sub-project activities,
► Describing the baseline profile of project area,
► Survey and interactions / discussions with the key stakeholders,
► Discussions with the host population,
► Screening Activities,
► Identification and analysis of impacts,
► Formulation of Management Action Plan,
► Preparation of ESDDR
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page |E -4
PROJECT SCREENING
18. The project screening was carried out to understand the nature, scale and magnitude of environmental and
social issues associated with the project. The screening activity was conducted as per the guidelines provided in
Environmental and Social Management Framework (ESMF of NGRBA, 2011) and on the secondary data analysis,
field assessments and stakeholder interactions/consultations. Thereafter, based on the aforementioned, the
environmental and social impacts were identified and analyzed to develop an Environmental and Social
Management Action Plan (ESMAP) outlining suitable mitigation measures to be adopted by the relevant
implementing actions associated with the present project.
19. Based on the Environmental and Social Screening carried out as part of this due diligence exercise using the
screening matrix of the Environmental and Social Management Framework of NGRBA, the present project of
Interception and Diversion and STP iミ “ahaヴaミpuヴ, falls uミdeヴ けLow IマpaItげ Iategoヴy. Project requires purchase of
7.81 ha. of private land, however does not envisage any displacement of landowners. Project follows Uttar Pradesh
Negotiation (Mutual Consent) Policy, 2015 to purchase the required land. This project has an overall positive impact
by tapping the wastewater and preventing its flow into the river Ganga.
BASELINE ENVIRONMENTAL AND SOCIAL FEATURES OF SAHARANPUR
20. The baseline information forms the basis to analyze the probable impacts of the proposed project vis-à-vis
the present background environmental and social quality of the study area. The baseline information of existing
environmental quality and social features related to the physio-chemical aspects, ecological aspects, socio-
economic and cultural aspects of the project area has been collected and collated from various secondary sources
and from available literature. The information on the baseline environmental and social conditions were gathered
through primary surveys at strategic locations considering various project components like laying of sewer line,
construction of IPS, STP etc.
ENVIRONMENTAL AND SOCIAL IMPACTS AND THEIR MITIGATION MEASURES
21. The project envisages few environmental and social impacts that can be mitigated with proper
implementation of safeguard measures. For establishing various proposed project components (i.e. one STP – 85
MLD, 9 Pumping Stations, Staff quarters, etc.) about 8.22 hectare of land is required. Out of the total land
requirement, about 0.41 hectare of government land is available for 7 IPS locations. However, government land is
not available for remaining 2 IPS and the proposed STP and about 7.81 hectare of land will be required. In this
regard, Jal Nigam, Saharanpur is acquiring the private land in accordance with the UP Negotiation (Mutual Consent)
Policy, 2015. The purchase of private land affects 75 landowners. Project authorities have consulted the affected
landowners and obtained requisite consent.
22. The project is expected to benefit the Saharanpur city, as the wastewater that currently flows untreated
into the Dhamola and Pandhoi Rivers and finally to the River Ganga will be captured, treated and the remainder of
the treated effluent will be allowed to flow into the river.
INSTITUTIONAL ARRANGEMENT FOR IMPLEMENTING ESDDR
23. In general, the Uttar Pradesh Jal Nigam (UPJN), Saharanpur (with assistance from Concessionaire and
Independent Engineer / Supervision Consultant) is the responsible entity for ensuring the implementation of
mitigation measures as suggested in the ESDDR.
COST ESTIMATE
24. Indicative cost estimated for proposed sewerage scheme in Saharanpur city is Rs.547.86 crore
(429.41+118.45 O&M Cost) including Environmental and Social Management Action Plan (ESMAP), public awareness
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.1
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page |E -5
and Environmental Monitoring for construction and operation phases has been worked out as Rs. 0.48 crore and the
cost of land purchase is estimated as 30 crore.
IMPLEMENTATION SCHEDULE
25. It is anticipated that entire work will be completed within 24 months from the date of start. The contract
for implementing the Sewerage and STP Scheme at Saharanpur is based on Hybrid Annuity Model.
AGENCY RESPONSIBLE FOR EXECUTION AND O&M WORKS
26. Agency responsible for execution and O&M works is U.P. Jal Nigam, Saharanpur Zone which is headed by
the Chief Engineer, U.P. Jal Nigam, Saharanpur and assisted by the Project Manager, Urban Works Unit-II, U.P. Jal
Nigam, Saharanpur.
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 1-1
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1. INTRODUCTION
1. River Ganga, along with her many tributaries, has been the source of physical and spiritual sustenance of
Indian civilization for millennia, and consequently, her well-being is of prime national concern. It is the largest river
basin in India in terms of catchment area aミd Ioミstitutes alマost ヲヶ peヴIeミt of the Iouミtヴyげs laミd マass, ミeaヴ aHout ンヰ peヴIeミt of Iouミtヴyげs ┘ateヴ ヴesouヴIes aミd suppoヴts マoヴe thaミ ヴヰ peヴIeミt of Iouミtヴyげs populatioミ6
. The delta of
the Ganga basin is one of the largest in the world, which is known by Sundarbans. It is the 20th
longest river in Asia.
Drainage of the River traverses through 11 states of the country (Uttar Pradesh, Madhya Pradesh, Rajasthan, Bihar,
West Bengal, Uttarakhand, Jharkhand, Haryana, Chhattisgarh, Himachal Pradesh and Delhi), where largely covered
states are Uttar Pradesh (28.02%), Bihar (10.86%), West Bengal (8.3%), Uttarakhand (6.15 %) and Jharkhand
(5.85%). In addition to the physical resource value, the economic, environmental and cultural value of river Ganga is
enormous iミ Iミdia. The Gaミga also seヴ┗es as oミe of Iミdiaげs holiest ヴi┗eヴs ┘hose Iultuヴal aミd spiヴitual sigミifiIaミIe is widely known.
2. Despite this iconic status and religious heritage, the Ganga River today is facing formidable pollution
pressures, along with the attendant threats to its biodiversity and environmental sustainability. An ever-growing
population, together with inadequately planned urbanization and industrialization, has affected the quality of the
ヴi┗eヴげs ┘ateヴs. Today, the Gaミgaげs ┘ateヴs aヴe sullied Hy the incessant outpouring of sewage, as well as by the large
┗oluマes of solid aミd iミdustヴial ┘aste that aヴe Ihuヴミed out Hy huマaミ aミd eIoミoマiI aIti┗ity aloミg the ヴi┗eヴげs Haミks. According to the reports, the main causes of extreme pollution pressures in river Ganga includes (i) inadequacy of
municipal wastewater infrastructure and services, (ii) inadequacy of industrial effluent management, (iii) solid waste
and non-point pollution sources, and (iv) inadequate in-stream flows.
3. The World Bank recognizes that the pollution in River Ganga is primarily a result of inadequate
infrastructure, the weak capacity of local water and wastewater utilities in the basin, and the poor state of
environmental monitoring and regulation. The Government of India (GoI) has received loan assistance from the
World Bank for the Mission Clean Ganga related activities under NGRBA Program (later which is included as one of
the component of the Namami Gange Programme) at the level of institutional development, operational and
implementation support and in four sectors, namely, wastewater collection and treatment, industrial pollution
control, solid waste management and riverfront development.
4. At the Central level, the National Mission for Clean Ganga (NMCG) registered as a society on 12th
August
2011 under the Societies Registration Act, 1860, was constituted as an authority to ensure implementation of
Namami Gange Programme. At State level, State Mission for Clean Ganga (SMCGs) were set-up as registered
societies in the respective states, namely Uttarakhand, Uttar Pradesh, Bihar and West Bengal while Jharkhand has a
dedicated nodal cell within the Department of Urban Development was set up.
5. NMCG acted as implementation arm of National Ganga River Basin Authority (NGRBA) which was
constituted under the provisions of the Environment (Protection) Act (EPA), 1986. NGRBA has since been dissolved
with effect from the 07th
October 2016, consequent to the constitution of National Council for Rejuvenation,
Protection and Management of River Ganga (referred as National Ganga Council) vide Notification No. S.O. 3187(E),
dated 07th
October 2016 under EPA 1986 and subsequent amendments vide Notification No. S.O. 1793(E), dated the
21st
May, 2019 and Notification No. S.O. 3163(E), dated 02nd
September, 2019.
6. The current focus of World Bank funded National Ganga River Basin Projects (NGRBP) under National
Mission for Clean Ganga (NMCG) is on six participating states namely Uttarakhand, Uttar Pradesh, Bihar, Jharkhand,
6 Source: Environmental and Social Management Framework (ESMF) for the Namami Ganga Programme, Ministry of Water
Resources, River Development & Ganga Rejuvenation, Government of India, 2011 (Revised August 2017).
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.2
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 1-2
West Bengal and Madhya Pradesh. The National Mission for Clean Ganga (NMCG), the implementing wing of
Namami Gange Programme has appointed LEA Associates South Asia Private Limited, New Delhi, as a Consulting
agency for the preparation of Environmental and Social Due Diligence Report (ESDDR) for さInterception & Diversion and STP Scheme in “aharanpurざ in the state of Uttar Pradesh, under National Mission for Clean Ganga (NMCG),
following the principles of ESMF of NGRBA.
1.1 NAMAMI GANGE PROGRAMME
7. The Go┗eヴミマeミt of Iミdia has lauミIhed さNaマaマi Gaミgeざ as aミ Iミtegヴated Coミseヴ┗ati┗e Missioミ Programme in the year 2014. The Namami Gange programme is an umbrella programme which covers the
previously sanctioned ongoing projects as well as the projects in new components with multi sector mandate to
address both water quality and water quantity issues. The programme aims at integrating previous and currently
ongoing initiatives by enhancing efficiency, extracting synergies and supplementing them with more comprehensive
and better coordinated interventions. Namami Gange Programme has been segregated into two different
components:
► Component A: Pertains to ongoing projects of cleaning of river Ganga & its tributaries, including World Bank
Assisted NGRBA programme having remaining central liabilities.
► Component B: Pertains to new initiatives to be undertaken in 5 major sectors i.e. Infrastructure Development
(Sewage Treatment, River Front Development, and Industrial Wastewater Treatment & Solid Waste
Management), Institutional Development, Ecological Sustainability, Research & Development and
Communication & Public Outreach.
8. The Namami Gange Programme will be implemented in the Ganga Basin in India. The overall technical
assistance and program development under the proposed project will focus on the entire Ganga Basin; however
specific sub-project investments under this project will focus on critical stretches of six basin states of Uttarakhand,
Uttar Pradesh, Bihar, Jharkhand, West Bengal and Madhya Pradesh in India.
9. A comprehensive, basin-level, and multi-sectoral approach has been adopted, with support for investments
in wastewater, solid waste and river front management, industrial effluent management, address non-point source
of pollution and maintaining ecological flows and assessment of biodiversity and afforestation and public
participation. The portfolio of investments under the NGRBA program includes the following:
► Sewerage and sanitation systems/sewage treatment plants (new/up gradation)
► Solid Waste Management
► Industrial Pollution Control Initiatives
► River front Management initiatives
1.2 STRUCTURE OF THE REPORT
10. This ヴepoヴt deals ┘ith the Eミ┗iヴoミマeミtal aミd “oIial Due DiligeミIe foヴ the pヴoposed さIミteヴIeptioミ & Diversion and STP Scheme iミ “ahaヴaミpuヴざ as peヴ the ヴeケuiヴeマeミt of Eミ┗iヴoミマeミt aミd “oIial Maミageマeミt Framework (ESMF) of NGRBA. In line with the requisite of ToR, the present ESDDR has been arranged in following
chapters:
Chapter 1 Introduction
This chapter describes briefly the project and its background and Portfolios of Investments.
Chapter 2
Project Description
This chapter presents a brief profile of the Saharanpur city and provides description of the proposed
Interception & Diversion and STP Scheme in Saharanpur. It also describes the scenario of existing
sewerage infrastructure of the project area, need of the proposed project, and outlines the various
Draft Report
Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.2
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 1-3
components and/or interventions proposed under the work.
Chapter 3
Approach and Methodology
This chapter presents the different steps followed during the process of environmental & social Due
Diligence and scope of the present study.
Chapter 4
Environmental and Social Profile of the Project Area
Description of the baseline environmental and social condition including the baseline physical
environment, biological environment and socio-cultural conditions of the project area are briefly
described in this chapter.
Chapter 5
Environmental and Social Safeguard Due Diligence
This chapter captures the policy and legal framework of government of India as well the policies of
World Bank applicable to the project followed by its compliance, consultation processes carried out
with the various sections of community and stakeholder groups, potential environmental and social
impacts associated with the proposed project, institutional arrangement for implementation of
ESMAP and Grievance Redress Mechanism.
Chapter 6
Findings of Gap Analysis
This chapter provides the major observations of Gap Analysis with respect to major environment and
social attributes of the project.
Chapter 7
Implementation Schedule and Responsibilities
This chapter envisages the implementation schedule, responsibilities and respective time frame for
implementation of ESMAP.
Chapter 8
Recommendations
This chapter provides the necessary recommendations to ensure compliance with the ESMF towards
improving the environmental and social performance of the project.
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-1
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
2. PROJECT DE“CRIPTION
2.1 CITY PROFILE
11. The Saharanpur city is situated close to the borders of the States of Haryana and Uttarakhand and is
located about 550 km. from the capital city of Lucknow, 164 km from Delhi and 70 km from Dehradun, the capital of
the State of Uttarakhand. It is a place of historical, cultural and administrative importance since the time
immemorial.
12. The city is governed by Municipal Corporation in Saharanpur district of Uttar Pradesh, India. The sub-
project area falls in Saharanpur tehsil of Saharanpur district. The project tehsil exists with Saharanpur Municipal
Corporation and Malhipur, Kailashpur, Gagalhedi Must. Census towns and adjoining 128 villages.
13. The municipal corporation of Saharanpur (as of 2011) is 46.74 Km2 and the other census town covering
6.29Km2. The entire Saharanpur district is divided into 5 tehsils namely Saharanpur, Behat, Nakur, Deoband and
Rampur Maniharan. According to the 2011 census, Saharanpur city (Municipal Corporation) has a population of
705,478 and the No. of Households is 129,856.
14. Saharanpur district is one of the prosperous and a great exporting district in Uttar Pradesh due to its,
improved agriculture and sound industrial base and increases the volume of commerce. The food grains of the
export items from the district are wheat, oil-seeds, sugar and forest products etc. Woodwork industry is more
famous in the decoration by wood carving, of the door, doorways and carving consists of light floral designs such as
lotus, rose, tress and fruits etc. There are several large scale industries located in Saharanpur which includes Paper
mill, dairy, textiles and Sugar Mill etc.
Figure 2-1: Regional setting of Saharanpur District and Saharanpur City
Source: https://www.mapsofindia.com/maps/uttarpradesh/districts/Saharanpur.htm
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-2
15. The city plays a major role in contribution towards overall economic development of the region. By road,
Saharanpur city is well-connected to major cities like Delhi, Noida, Faridabad, Ghaziabad, Haridwar and other cities.
2.2 EXISTING SCENARIO OF SEWERAGE FACILITIES IN SAHARANPUR CITY
16. Sewerage system in Saharanpur was partially developed and mainly interception and diversion and STP
works were provided in the city under Yamuna Action Plan-1 in the year 1998. The total length of sewerage network
in Saharanpur Nagar Nigam is about 111km. out of which 27.37km. is trunk sewer and 84.15km is branch sewers.
There are 3 Intermediate Pumping Stations (IPS) and 1 Main Pumping Station (MPS). The Intermediate Pumping
Stations (IPS) pumps the sewage to Main Pumping Station (MPS) and from there; it is pumped to sewage form at
treatment plant located at Praduman Nagar STP.
17. Presently, in Saharanpur city one Sewage Treatment Plant (STP) of 38 MLD located at Praduman Nagar is
maintained by the Saharanpur Nagar Nigam through Uttar Pradesh Jal Nigam (UPJN).
Table 2-1: Salient Features of existing STP in Saharanpur city
No. Features Details
1
Population
Year 1998
402400
(-) 61930 (Zone-E population)
= 340470
(Zone E comprises of area between
Railway line and Dhamola River which is not covered with
sewerage system and not considered)
Year 2023 535500
2 Design Base Year (STP) 1998
Design year (I& D) 2023
3
Rate of Water Supply
Year 1998
Year 2023
150 MLD
150 MLD
4 Flow in MLD
Year 2023 38 MLD
5 STP Capacity in MLD 38 MLD
6
Sewage Quality
BOD (mg/l)
TSS (mg/l)
200 influent/30 after treatment
400 influent/50 after treatment
7
Collection pump/sump
Pump
Capacity
Discharge
5 nos.
75 H.P
14850 L.P.S
8 Disposal of treated effluent Treated effluent is disposed in River Dhamola
Source: Detail Project Report for I&D & STP Works in Saharanpur City under Namami Gange Program, 2019.
27. Saharanpur city does not have a proper sewerage system and all houses have individual septic tanks that
discharge in to open drains causing pollution. Individual septic tanks are not properly maintained in the city and are
major source of pollution. Hence, it is of utmost importance to develop proper septate management in Saharanpur
city.
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-3
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
Figure 2-2: Existing sewerage plan of Saharanpur city
Source: DPR, Uttar Pradesh Jal Nigam, Saharanpur
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-4
18. On the basis of topographical and geographical features the city has been divided into four sewerage
zones. The sewer zone wise status is tabulated below:
Table 2-2: Summary of Existing Sewered Areas - zone wise in Saharanpur City
Sl.
No. Sewerage Zone No.
No. of
Wards
No. of
Colonies
Trunk
Sewer
Length (km)
Branch
Sewer
Length
(km)
No. of
Manholes
Operation at Sewer
Lines (km)
Chocked Sewer
Lines (km)
1 Zone - 1 6 19 3.80 8.20 900 9.80 2.20
2 Zone - 2 11 90 9.45 20.95 2240 20.50 9.90
3 Zone - 3 6 20 6.00 27.00 1985 32.40 0.60
4 Zone - 4 7 28 8.19 28.00 1786 35.10 1.02
TOTAL 30 157 27.37 84.15 6911 97.80 13.72
19. are a total of fifty one (51) drains were taped during YAP-1 in Saharanpur that connected with sewerage
system to divert the flow to the STP of 38 MLD at Praduman Nagar through 3 numbers of Intermediate Pumping
Stations (IPS). The details of these drains are summarized as under:
Table 2-3: Details of existing drains in Saharanpur
Source: Detail Project Report for I&D & STP Works in Saharanpur City under Namami Gange Program, 2019.
2.3 NECESSITY OF THIS PROJECT
20. Saharanpur city unlike other Indian cities does not have a centralized sewer system for collection,
transportation, treatment and disposal of domestic and institutional wastewater. Due to tremendous population
growth and increased areas of habitation, different sections of existing sewers network are partially and/or fully
chocked, carries reduced flow and the STPs are not receiving designed flow.
No. Name of IPS/MPS No. of Nalas/Drains tapped Nearest Location Capacity of IPS (MLD)
1 IPS-Dalmandi 8 Nalas/Drains Eastern side of River Pandhoi 6.9 MLD
2 IPS-Rakesh Theatre 14 Nalas/Drains Left and Right side of River Dhamola,
Pandhoi 12.6 MLD
3 IPS-Govindnagar 17 Nalas/Drains Right side of Pandhoi river and between
Rakesh theatre 24 MLD
4 MPS-Paduman
Nagar 12 Nalas/Drains
Khalasi road, west river of Dhamola
River. 38 MLD
Total 51 Nalas/Drains
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-5
Figure 2-3: Population Growth Trend of Saharanpur City
21. As per DPR, the water requirement for the city in the year 2020 is 112.48 MLD, if considered for the year
2023 the estimated water requirement will be as 118.22 MLD. The sewage generation in 2023 is considered as 80%
of total water supplied (according to the DPR) which works out 108 lpcd, therefore the estimated sewage
generation in the year 2023 will be 95 MLD. (existing STP is 38 MLD and proposed STP is for 85 MLD, total 123 MLD
of Sewerage Treatment capacities will be available in 2023).
Year Projected
Population
Water Supply
requirement (lpcd)
Water Supply
requirement (MLD)
Total Sewage
generation (lpcd)
Total Sewage Generation
(MLD)
2020 833168 135 112.48 108 85
2023 875704 135 118.22 108 95
2035 1105878 135 149.30 108 120
2050 1471865 135 198.70 108 159
Source: DPR, Saharanpur-Jal Nigam
22. The untreated sewerage disposal is a critical area; most of the wastewater of town and from un-sewered
areas is discharged directly into the drains creating unhygienic environment. The census data on decadal population
of Saharanpur (Municipal Corporation) City since year 1991 and up to 2023 is presented in Figure 2-3.
23. Likewise, the effluents of industries, effluent of different slaughter houses are also discharged directly into
the drains without any treatment. In order to reduce pollution load of major drains of Saharanpur, the existing
sewerage network necessities renovation and strengthening, so that the wastewater would be treated before its
discharge to Pandhoi and Dhamola rivers, which finally joins with the Ganga River at downstream near Kannauj
district of Uttar Pradesh.
2.4 DESCRIPTION OF PROPOSED PROJECT ACTIVITIES
24. The proposed project involves strengthening of existing sewerage infrastructure of the Saharanpur district
by intercepting and diverting the wastewater flowing through proposed 9 IPS to newly proposed sewage treatment
plant of capacity 85 MLD to treat the wastewater before its discharge to Pandhoi and Dhamola rivers, which finally
joins with the Ganga River at downstream. Figure 2.4 (I&D alignment) and 2.5 (with land use) shows the location
map of existing and proposed STPs and IPS locations.
0
1
2
3
4
5
6
7
8
9
1991 2001 2011 2020 2023
3.74
4.55
7.05
8.34 8.76
Po
pu
lati
on
(in
la
kh
s)
Years
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-6
25. As per the DPR, the マajoヴ Ioマpoミeミts of the pヴoposed さIミteヴIeptioミ & Di┗eヴsioミ ┘ith “TP Scheme at
Saharanpur Uttar Pradesh under Namami Gange Program includes:
► Interception & Diversion structures (9 Nos.)
► Raising main and I&D network.
► New MPS (1 No.)
► Construction of new Sewage Treatment Plant (STP) of capacity 85 MLD.
► Operation & maintenance (O&M) for 15 years.
► Installation of trash arresting rack and its regular O&M at the mouth of all drains.
► Adequate provision for handling septage in the STP.
26. As per DPR, it is proposed to repair and renovate the existing I&D and STP to utilize its full design capacity
of 38 MLD. Further proposed to commission Interception & Diversion works of the drains remaining (including
some of already tapped under YAP-1) and construction of additional IPS, MPS and STP to cater for the complete
projected drain discharge.
27. The proposed Interception and Diversion for each Nala in different stretch of River Pandhoi and Dhamola is
discussed in the following tables below.
Table 2-4: Details of Proposed I&D Schemes in Saharanpur
Source: Detail Project Report for I &D & STP Works in Saharanpur City under Namami Gange Programm, 2019.
28. The proposed I&D System with STP in Saharanpur will not impact trees and any natural environment
(except for few bushes), since the sewers are planned to be laid along the road or center of the road where ROW is
not sufficient. Probable impact in terms of increase in the dust level while excavating the land material, cutting and
back filling may be seen. There may be temporary impacts like a minor inconvenience to the people to access their
No. Name of IPS/MPS No. of Nalas/Drains tapped Capacity (MLD)
1 IPS-1 Near Numaish Camp Janata Colony Drain,
Numaish Camp-V shape Drain
1.57 MLD
2 IPS-2 Near Toilet block, Shakti
Nagar 4 Nalas/Drains
3.77 MLD
3 IPS-3 Near Sapna Talkies 10 Nalas/Drains 9.31 MLD
4 IPS-4 Old Police Chowki 5 Nalas/Drains 2.86 MLD
5 IPS-5 Near Pahalwan Pulia 5 Nalas/Drains 6.43 MLD
6 IPS-6 Near Taj Nala 14 Nalas/Drains 95.30 MLD
7 IPS-7 Paper Mill Road 4 Nalas/Drains 11.50 MLD
8 IPS-8 Near Kanshi Ram Colony 6 Nalas/Drains 19.41 MLD
9 IPS-9 near Govindnagar 1 Nala/Drain (Hati Gate) 22.18 MLD
10 MPS-(Inside the STP site) Drains/Nalas of IPS-6, 8 and 9 136.89 MLD
11 STP- Badshapur - 85 MLD
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-7
premises and temporary blockage of drains/ water logging by unmanaged excavated material while laying the sewer
lines. The table below (Table 2.5) provides the land use details of I&D structure and anticipated impacts.
Table 2-5: Profile of Proposed I&D Structure in Saharanpur
No. Name of
IPS/MPS
Details of I&D Structure
Land Use
Anticipated Impacts
1
IPS-1 Near
Numaish
Camp
This proposed I&D structure will be
tapped with drains from Janata Colony,
Numaish Camp, from this IPS-1 the
wastewater pumped to MH-111 on link
road through a rising main of 250 mm dia
and length of 355m.
Residential and nearby
water body (near Dhamola
River)
Since the proposed I&D
system of IPS -1 location is
situated near to the
Dhamola River,
contamination of water
body by unmanaged
excavated and construction
materials is envisaged and
there may be temporary
blockage of drains/
waterlogging and temporary
flooding during monsoon.
2
IPS-2 Near
Toilet block,
Shantii Nagar
This will be tapped with 4 drains in Shanti
Nagar and pumped to MH-138 near jail
Chungi through rising main of 300 mm dia
and length 316m.
Commercial/Market area
The proposed I&D structure
situated in the commercial
and market area, probable
increase in the dust level
while excavating the land
material and cutting and
backfilling activities. There
may be temporary blockage
of drains/ waterlogging by
unmanaged excavated
material while laying the
sewer lines.
During construction, a minor
inconvenience to the people
to access their premises is
envisaged.
3 IPS-3 Near
Sapna Talkies
The IPS-3 will be tapped with 10 drains and
this will be pumped to proposed sewer line
of 800mm dia starting at MH-179 near
Khan Alampura through a rising main of
dia 450mm and 206m length.
4 IPS-4 Old
Police Chowki
Proposed IPS-4 will be tapped with 5
drains and pumped through proposed
sewer line of 500mm dia starting at MH-55
near Vadafone shop through a DI rising
main of dia 300mm and length 311m.I
Commercial area and nearby
Water body (Near Dhamola
River)
Since the proposed I&D
system is situated near to
another side of Dhamola
River, contamination of
water body by unmanaged
excavated and construction
materials is envisaged and
there may be temporary
blockage of drains/ water
logging and temporary
flooding during monsoon.
Probable increase in the
dust level while excavating
the land material, cutting
and backfilling.
5
IPS-5 Near
Pahalwan
Pulia
Proposed IPS-5 will be tapped with 5
drains and pumped through proposed
sewer line of 500mm dia starting at MH-85
near Krishi Prasar Bhawan through a DI
rising main of dia 400mm and length
525m.
Commercial and Market area
This is situated in the
commercial and built-up area
and it is envisaged temporary
traffic inconvenience
(including fuel emissions,
congestions, longer travel
times and blockage of access)
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-8
and safety hazards to labours
and road users.
During construction, a minor
inconvenience to the people
to access their premises is
envisaged.
6 IPS-6 Near Taj
Nala
Proposed IPS-6 will be tapped with 14
drains and pumped through proposed
sewer line of 500mm dia starting at MH-85
near Krishi Prasar Bhawan through a DI
rising main of dia 400mm and length
525m.
Residential and Water body
Probable increase in the dust
level while excavating the
land material and cutting and
back filling activities. There
may be temporary blockage
of drains/ waterlogging by
unmanaged excavated
material while laying the
sewer lines.
7 IPS-7 Paper
Mill Road
Proposed IPS-7 will be tapped with 4
drains and pumped through proposed
sewer line of 800mm dia starting at MH-
210 opposite dairy through a DI raising
main of dia 500mm and length 714m.
Commercial and Industrial
Area
This is situated in the
commercial, built-up area and
it is envisaged temporary
traffic inconvenience
(including fuel emissions,
congestions, longer travel
times and blockage of access)
and safety hazards to labours
and road users.
During construction, a minor
inconvenience to the people
to access their premises is
envisaged.
8
IPS-8 Near
Kanshi Ram
Colony
Proposed IPS-8 will be tapped with 6
drains and pumped through existing STP of
38 MLD through a DI rising main of dia
600mm and length 1250m.
Residential area
This is situated in the
residential area There may be
temporary blockage of drains/
water logging by unmanaged
excavated material while
laying the sewer lines. During
construction, a minor
inconvenience to the people
to access their premises is
envisaged.
Bad odour, Health hazard and
public nuisance.
9 IPS-9 near
Govind Nagar
Proposed IPS-9 will be tapped with 1 drain
and pumped to junction near railway
bridge through a DI rising main of dia
600mm and length 360m.
10 MPS-(Inside
the STP site)
Proposed MPS will be tapped with IPS-6,
IPS-8 and IPS-9 and other sewered areas
of Saharanpur
Residential and Agriculture
Area
This proposed I&D System is
situated in the agriculture
area and connecting to IPS
6, 8 and 9, which comprises
residential and agriculture.
There may be temporary
impacts like a minor
inconvenience to the people
to access their premises and
temporary blockage of
drains/ waterlogging by
unmanaged excavated
material while laying the
sewer lines.
Probable increase in the
dust level while excavating
the land material, cutting
and backfilling.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-9
29. During the assessment of project sites of I & D scheme, the vicinity of the sub-project component area is
mostly built up and agricultural area, and envisaged that the impacts associated with I&D alignment are temporary
during the construction stage, no tree cutting is envisaged. Construction of 85 MLD STP at village Badshahpur near
Dhamola River attracts Private Land purchase of 7.8083 ha. This will be purchased through UP Negotiation (Mutual
Consent) Policy, 2015. 75 landowners are getting impacted due to land purchase and there is no displacement of
households from the acquiring land, hence the overall impact category falls in low category. However, necessary
care shall be taken by the potential Concessionaire / Concessionaire to avoid disturbance to neighborhood area
under supervision of concerned authority of UPJN, Saharanpur Zone. In order to address the E&S issues, site
specific EMP has to be prepared by the Concessionaire and get it approved from competent authority of UPJN.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-10
Figure 2.4 Proposed I&D Alignment with STP in Saharanpur
Source: Jal Nigam, Saharanpur Division
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-11
Figure 2.5: Location Map Showing Existing and Proposed IPS and STP Locations
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-12
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
30. According to the DPR, It is proposed to provide new STP with capacity of 85 MLD is based on population
projection over a period of time internal sewers in the city shall be laid and discharge in drains shall decrease
consequently; the estimated sewage generation in the year 2035 is 119 MLD. Existing capacity of STP is 38 MLD and
required further STP with 81 MLD, hence the proposed STP has been considered for the capacity of 85 MLD. The
contract for implementing the Sewerage and STP Scheme at Saharanpur is based on Hybrid Annuity Model. It is
anticipated that entire work will be completed within 24 months from the date of start.
31. The key objective of the proposed project is to prevent untreated wastewater by intercepting and diverting
it to the newly proposed STP of capacity 85 MLD before its discharge to Dhamola and Pandhoi rivers in Saharanpur
city, and also to achieve the sewage effluent standards as prescribed by the CPCB, MoEF&CC, Government of India,
and recommended by the CPHEEO in its latest manual and by the NGT vide its order dated 30th April 2019.
32. The IhaヴaIteヴistiIs of tヴeated se┘age efflueミt of pヴoposed “TPげs as pヴesIヴiHed Hy the aHo┗e-mentioned
statutory authorities are given below:
Table 2-6: Effluent Discharge Standards for Sewage Treatment Plant (CPCB)
Sl. No. Parameters Parameters Limit (Standards for New STPs Design after notification date)*
1 pH 6.5 – 9.0
2 Biochemical Oxygen Demand BOD (mg/l) 10
3 Chemical Oxygen Demand (COD) (mg/l) 50
4 Total Suspended Solids TSS (mg/l) 20
5 Ammonical Nitrogen (NH4-N) [mg/l] 5
6 Total Nitrogen (N-total) [mg/l] 10
7 Faecal Coliform (MPN/100 ml) <100
Note:
(i) These standards will be applicable for discharge in water resources as well as for land disposal. The standards for Faecal Coliform may not be applied for use of treated sewage in industrial purposes.
(ii) * Achievements of Standards for existing STPs within 05 years from the date of notification.
Source : MoEFC&C Draft Notification; dated 24th November 2015.
Table 2-7: Characteristics of treated sewage effluent
Parameters Standards for treated sewage effluent for disposal into water bodies
Biochemical Oxygen Demand BOD (mg/l) <10
Chemical Oxygen Demand (COD) (mg/l) 50
Total Suspended Solids TSS (mg/l) <20
Total Nitrogen (mg/l) <10
Ammonical Nitrogen (mg/l) <5
Total Phosphorus (mg/l) 1.0
Faecal Coliform MPN/100 ml : Desirable,
Permissible <100, 230
Source: Hon’ble NGT Order dated 30th
April 2019.
2.5 DISPOSAL OF TREATED EFFLUENT
33. The treated wastewater of STP will be preferably reused for agriculture & industrial purposes and is being
discharged into the River Dhamola. The other alternative measure to reuse the water shall be explored.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-13
2.6 SLUDGE STORAGE AND DISPOSAL
34. The dewatered sludge shall be disposed of suitably at identified landfill site and will be used as manure
(after necessary laboratory analysis of biological and chemical testing including heavy metal contamination), if
found suitable shall be distributed/handed over to the local farmers for horticulture/agriculture purposes. In case, if
the laboratory analysis are not found within the suitable range for usage in horticulture purpose, shall be disposed
in the adequate land fill site authorized by Municipal Corporation and Jal Nigam. The location identified for the
sludge disposal is at Maheshwari Khurd and Ghunna on Saharanpur Behat Road which is located away from the
habitation and nearby water bodies. The landfill site was identified by the Municipal Corporation and for entire
Saharanpur area. At present from the existing STP, the sludge is disposed in the same landfill site at Maheshwari
Khurd and most of the sludge is being used for agriculture/horticulture purposes. The MoU between Saharanpur
Municipal Corporation and Jal Nigam, Saharanpur Division on sludge disposal and storage is attached as an
Annexure 4.2.
35. Appropriate Sludge Management Plan shall be prepared by the Concessionaire. Suitable site for disposal
has been identified by the Jal Nigam, Saharanpur and mutual agreement between Municipal Corporation and Jal
Nigam, Saharanpur division was completed for the safe disposal of sludge generated at the STP. The necessary
safeguard measures associated with the storage and disposal of sludge are provided in the ESMAP (under sludge
management component in Annexure-5).
2.7 COST ESTIMATE
36. Indicative cost estimated for proposed sewerage scheme in Saharanpur city is Rs. 547.86 crore
(429.41+118.45 O&M cost) including Environmental and Social Management Action Plan (ESMAP), public awareness
and environmental monitoring for construction and operation phases has been worked out as Rs. 0.48 crore and the
cost of land purchase is estimated as 30 crore.
Table 2-4: Abstract of Cost Estimation for Proposed Sewerage Scheme for Saharanpur
S.No Item Cost (Rs. Lakhs)
A
I&D Works of Nala tapping arrangement with necessary carrier
sewer lines from nala tapping to collection Tank at
STP site
9405.73
B Intermediate Pumping Stations-(Civil ,Electrical &
Mechanical Works [email protected]/mld )
3485.80
C Rising Mains 2082.08
D Sewage Treatment Plant with MPS- 85 MLD (Civil works & E&M
works)
11475.00
E Repair and Renovation of existing STP and IPS 1738.88
F Open Channel for disposal of treated water 19.23
Sub Total (A to F) + price escalation 10%, Centage charges of
subtotal , GST 12% and labour cess1%- Total
39875.09
G Cost of Work on which no Charges will be Admissible (including
Communication and public outreach, GAAP, ESAMP)
17.54
H Electricity Connection Charges for IPS, 48.00
I Cost of Land Purchase 3000.00
J Operation and Maintenance Cost Duration for 15 years+ One
year DLP
11845.00
K Grand Total (A to J) 54786.00
Source: DPR- Saharanpur 2019
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2-14
37. In addition to the total cost, implementation of Environmental and social aspects is worked out for Rs.
31.0Lakh for the cost of public awareness, monitoring of environmental parameters and purchase of noise meter
other than the cost of implementation of ESAMP mentioned in the above table (G). Hence, the total cost for
implementation of Environmental and Social safeguards is estimated for Rs. 0.48 crores (0.31+0.17=0.48).
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 3-1
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
3. APPROACH AND METHODOLOGY
3.1 METHODOLOGY
38. The Environmental and Social Management Framework (ESMF of NGRBA, 2011)7 is intended to identify and
assess several environment and social impacts (both positive and negative) that may result for the proposed river
pollution mitigation project of Dhamola River at Saharanpur, under NGRBP, as well as to provide a corresponding
management plan to handle any adverse/negative impacts. The methodology adopted for conducting
Environmental and Social Due Diligence for the proposed interventions is given in Figure 3-1 below.
Figure 3-1: Flowchart describing steps adopted for ESDDR preparation
39. The Environmental and Social Due Diligence Report (ESDDR) has been prepared by LEA Associates South
Asia Private Limited, New Delhi, on the basis of Detailed Project Report that has been prepared by UP Jal Nigam.
3.2 REVIEW OF AVAILABLE DOCUMENTS AND DATA COLLATION
40. Review of available documents and collating information from various documents to assess the possible
environmental and social impacts of the proposed project. All the available information and data (quantitative,
qualitative) regarding the proposed project has been collected mainly from the Detailed Project Report (DPR),
7 For the Environmental and Social Management Framework (ESMF) document please refer
https://www.nmcg.nic.in/writereaddata/fileupload/25_Namami_Gange_ESMF__August_17_2017__1___1_.pdf
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 3-2
consultation with stake-holders and other secondary sources including the water/air/noise monitoring data of UP
Pollution Control Board, UP Jal Nigam and from the reports of tests conducted at site.
3.3 DESCRIBING THE SUB-PROJECT ACTIVITIES
41. With the help of information and data received mainly from the Detailed Project Report (DPR) and
consultations with stake-holders, a brief description and analysis of the project activities has been established.
Based on initial understanding, the list of required information has been drafted before conducting the field survey.
3.4 DISCUSSION WITH THE KEY STAKEHOLDERS
42. The key stakeholders including the UP Jal Nigam, Saharanpur were interacted (both formally and
informally) during the field visits while preparing the ESDDR. Associated government departments were visited to
collect the relevant data and their feedback on the proposed project activities. Also they were asked about the
mitigation plans they have adopted or are planning to adopt, suggestions for improvement and any public
grievances.
3.5 BASELINE ENVIRONMENTAL AND SOCIAL PROFILE OF PROJECT AREA
43. With the help of secondary information/data received from the available documents and from the
discussions/interactions with key stakeholders and host population, a brief description of the baseline
environmental and social profile of the project area has been established.
3.6 SCREENING ACTIVITIES
44. The project screening has also been carried out to understand the nature, scale and magnitude of potential
environmental and social impacts associated with the proposed project. The screening activities have been
conducted as per the guidelines provided in Environmental and Social Management Framework of NGRBA (NGRBA,
2011) and on the basis of secondary data analysis, field assessments and stakeholder interactions/consultations.
45. The screening checklist included criteria that detailed out the impact level of various activities during the
construction and operation phases. The criteria included environmental factors such as the presence of eco-
sensitive region in and around the project area, clearance of tree cover, improper storage of excavation spoils,
flooding of adjacent areas, elevated noise and dust levels, damage to existing utilities, etc. Social criteria included
factors such as requirement of land purchase, displacement of tribes, loss of livelihood and gender issues.
3.7 IDENTIFICATION AND ASSESSMENT OF IMPACTS
46. Based on the analysis of the data collected from field surveys, stakeholder interactions/ consultations and
secondary sources, issues related to the environmental and social sectors were identified. The impacts so identified
were compared with the existing baseline environmental and social condition of the study region. The impacts of
the activities are mostly positive with few adverse impacts.
3.8 DEVELOPING MANAGEMENT ACTION PLAN
47. Based on the identified and assessed potential environmental and social impacts, an appropriate mitigation
/ management action plan has been developed recommending suitable measures needed to prevent, minimize,
mitigate, or compensate for adverse impacts (if any) and to improve the environmental and social performance.
The mitigation plans is suggested for different stages of the project, as applicable: designing phase, construction
phase and, operation and maintenance phase.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 3-3
3.9 SCOPE OF WORK
48. Based on the Environmental and Social Screening carried out as part of this due diligence exercise using the
screening matrix provided in the Environmental and Social Management Framework of NGRBA (refer Annexure-1),
concludes that the present project of pollution abatement works at Saharanpur under Saharanpur Municipal
Coヴpoヴatioミ, is Iategoヴized as けLow IマpaItげ Iategoヴy. The pヴojeIt Ioマpoミeミts ha┗e liマited eミ┗iヴoミマeミt aミd soIial impacts, which can be mitigated with the adoption of suitable mitigation measures. The scope of the ESDDR that
has been finalized on the basis of project screening and categorization are given below:
► Describe the sub-project and its components;
► Describe the baseline environmental and social conditions of the sub-project areas and the proposed project
facilities;
► Identification and analysis of key environmental issues viz. presence of any ecologically sensitive areas in the
vicinity of the project site, as well as social issues (if any) associated with the project;
► Interactions / discussions with the key stakeholders;
► Environmental and Social Screening and categorization of the sub-project as per the requirements of ESMF of
NGRBA / Namami Gange Program;
► Develop Environmental and Social Management Action Plan (ESMAP) outlining suitable mitigation measures to
be adopted by the relevant implementing actor;
► Outline the requirements of specific permissions / clearances / approvals that may be applicable to the
proposed project and the requirements of any detailed study [e.g. preparation of Environmental and Social
Impact Assessment (ESIA), Resettlement Action Plan (RAP).
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-1
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
4. ENVIRONMENTAL AND “OCIAL PROFILE OF PROJECT AREA
49. This section briefly describes the baseline environmental and social profile of the study area. Saharanpur
city is the head quarter of Saharanpur District. The project city is situated on the upper doab region and the land
lying between two converging or confluent Rivers Yamuna and Ganga and is located at about 170 km. from Delhi,
capital city of India and 68 km. from south west of Dehradun. The city grew in a region named after a Sufi Saint
Shah Haroon Chishti.
50. The project tehsil exists with Saharanpur Municipal Corporation and Malhipur, Kailashpur, Gagalhedi Must,
Census towns and adjoining 128 villages. The project location adjoins 128 villages/settlements with a population of
6.38 lakh and the population of the city and other census towns is 7.31 lakh as per census 2011.
4.1 PHYSIOGRAPHY
51. The project area lies between latitude 290 ヰヰげ aミd ンヰ0
ヲヴげ ミoヴth aミd loミgitude ΑΑ0 Αヰげ aミd ΑΒ0
ヱヲげ east iミ the upper Ganga doab
8. Geographically, the city is located in western region of Gangetic plain in the State of Uttar
Pradesh. The state has classified into three distinct regions; the northern sub-mountain region called Tarai, the
Gangetic Plains and the Southern Plateau. Additionally for the purpose of development planning, Bundelkhand
region is separated from Southern Plateau. Saharanpur city is located in north western Gangetic plains and Tarai,
Bhahbar zones of Uttar Pradesh in India. The area is almost flat alluvial plain with gentle slope from north to south
direction.
4.2 SEISMICITY
52. As per the seismic
hazard map of India,
Saharanpur falls in Seismically
Active zone IV (Severe
Intensity Zone9). In
consideration of this, due
measures have been
incorporated in designing of
water / waste-water retaining
structures considering the
earthquake load for seismic
zone V. (viz. Sewage Lifting
Station or Sewage Treatment
Plants, as per provision of the
Code).
8 Doab is a term used in South Asia for the "tongue," or tract of land lying between two converging, or confluent, rivers. It is
similar to an interfluve. 9 Ministry of Earth Sciences, Govt. of India published in 2017 for the earthquake-prone State/area in the country based on BIS [IS-1893
(part1):2002, grouped the country into four seismic zones i.e Zone –II to Zone V; of these, Zone five is most seismically active zone while zone II is
least active zone. Zone IV covers parts of Jammu & Kashmir and Himachal Pradesh, Union Territory of Delhi, Sikkim, northern parts of Uttar
Pradesh, Bihar and West Bengal, parts of Gujarat and small portions of Maharashtra near the west coast and Rajasthan.
Figure 4-1: Seismic Map of Uttar Pradesh Source: Uttar Pradesh State Disaster Management Plan-2016-17
Saharanpur
Saharanpur
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-2
4.3 CLIMATE AND WEATHER
53. The project area has climate variations of extreme conditions, exceptionally hot in summer and extremely
cold in winters. The temperature reaches up to 45oC in certain places of the project region, in winters it falls up to
6.6oC. The annual average
temperature is 23.30C. During the
summer season (from April to June),
hot winds blow in the region.
Summers last from early April to
late June and are extremely hot. The
average annual temperature is
24.7°C in Saharanpur.
54. Saharanpur has a monsoon
influenced sub-tropical climate due
to its proximity to the Himalayan
region. The annual average
precipitation received in the city is
1204 mm. As per IMD data, the
rainfall of the last 5 years (Figure 4-
2) displays that the month of July
has recorded the maximum annual rainfall during the year.
4.4 AIR ENVIRONMENT
55. Figure 4-3 shows the
graphic representation of Ambient
Air Quality data being recorded by
the Uttar Pradesh State Pollution
Control Board (UPPCB) in year
2019, the monitoring stations
located at Clock tower and near IIT
of Saharanpur city. The
concentration of PM10 varies from
68.37 µg/m3 to 248.79 µg/m
3
during the year January, October
and November the concentration
levels of PM10 values are much
higher than the National Ambient
Air Quality standard of 100 µg/m3.
The concentration of SO2 and NO2
is within the CPCB standard.
56. The monitoring stations of a Clock tower and near IIT, Saharanpur are situated in the northern and eastern
side of the city. The monitored PM10 levels published by SPCB show the higher values due to anthropogenic
Figure 4-2: Last Five Year Rainfall Record of Saharanpur
Source: Website of Customized Rainfall Information System (CRIS), Hydromet Division, India
Meteorological Department, Ministry of Earth Science, New Delhi
Figure 4-3: Air quality in Saharanpur City (2019)
Source: Uttar Pradesh Pollution Control Board (http://www.uppcb.com)
Ra
infa
ll (m
m)
Months
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-3
activities near Clock tower and near IIT Saharanpur. This monitoring location of SPCB is located in the market area
and nearby Saharanpur Railway junction.
57. The higher level of ambient air quality considering the proposed project site forms the baseline information
(Secondary Source). The city has various sources of air pollution in the region such as dust rising from unpaved
roads, domestic fuel burning, vehicular traffic, agricultural and industrial activities essentially due to paper mills and
textile industries etc., resulting into severe health hazards and respiratory problems in the city. It was assessed
during the site visit and according to the discussions with the official of Jal Nigam, Saharanpur Division that I&D
alignment will be placed along the road within the available land width and also placed at the center of the road
where the RoW is restricted. Hence, there will not be any major impact due to laying of I&D structure in the city,
only minimal/temporary impacts such as temporary inconveniences to the local community and traffic congestion
are envisaged.
58. The prime objective of baseline air quality monitoring is to assess existing air quality of the area. This will
also be useful in assessing the conformity to standards of the ambient air quality during the construction and
operation phases. Proper safeguard measures to be followed according to the recommendations provided in the
report under Section 8 and site specific EMP to be prepared after analysing the local situation and to be followed
suitable mitigation measures to address any such anticipated issue.
59. Ambient air quality monitoring at the proposed project location was carried out from 13th
January 2020 to
18th January 2020 to assess the ambient air quality. Major air pollutants viz. Particulate Matter (PM2.5 & PM10),
Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2), and Carbon Monoxide (CO) representing the basic air quality in the
proposed project were identified for Ambient Air Quality Monitoring (AAQM). The results of ambient air quality
monitoring carried out at the proposed project location are given in Table 4-1 below:
Table 4-1: Results of Ambient Air Quality Monitoring conducted at the proposed project location
Ambient Air Monitoring Result at Project STP site
S. No. Monitoring Dates
Geographic Location PM2.5 PM10 SO2 NO2 CO
Latitude Longitude (µg/m 3) (µg/m 3) (µg/m 3) (µg/m 3) (µg/m 3)
1 13.01.2020 to 18.01.2020 29°55'5.79"N
77°33'8.02"E 53.2 78.6 8.3 12.5 530.2
Permissible Limit (as per CPCB Guidelines) 60.0 100.0 80.0 80.0 4000
60. Ambient Air Quality Monitoring reveals that the concentrations of PM2.5 and PM10 are lower than the
National Ambient Air Quality standard of 60 µg/m3 and 100 µg/m3 respectively. The gaseous pollutants SO2, NO2,
CO are concerned, the concentrations were found within the prescribed limit of CPCB. Detailed Air Monitoring Lab
reports are attached as Annexure-3. The standards of Ambient Air Quality in India are available online at
http://cpcbenvis.nic.in.
4.5 WATER ENVIRONMENT
61. The project area has a principle river Yamuna and Pandhoi and Dhamola are tributaries of Yamuna River.
These tributaries are non-perennial in nature. The River Dhamola is a tributary of Hindon River which is the tributary
of Yamuna, flowing during the monsoon season. It originates in Saharanpur districts (Uttar Pradesh), from upper
Shivalik in lower Himalayan Range. The Hindon River receives considerable amount of wastewater every day from
the industries and municipal area of Saharanpur city and it discharged in river Hindon through rivers of Pandhoi and
Dhamola, which leads to deterioration of water quality.
62. As per information available from Central Ground Water Authority, the Saharanpur city falls under
overexploited zone. The level of ground water ranges from 10-20 meter below ground level (mbgl).
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-4
4.6 WATER QUALITY
63. The organic parameters of BOD have been studied for River Hindon downstream station at Saharanpur.
Consecutively two years data have been studied for the assessment. All the secondary data have been sourced from
the website of Uttar Pradesh Pollution Control Board, Lucknow. As per the available data from SPCB for the year
2018 and 2019, an illustrative record of the water quality record has been shown in the below in figures. The
concentration of BOD data for consecutive two years shows concentration much higher than what is permissible for
various uses, i.e. 30mg/l. The Total coliform and DO values have not been recorded/not available in the website of
Uttar Pradesh Pollution Control Board.
64. The sampling was done both for surface water and underground water. The samples were taken from the
identified monitoring locations around the proposed project area. Total of 3 samples were taken, 2 samples for
surface water at both the Upstream & Downstream of Dhamola River near STP Site, Saharanpur and 1 sample for
ground water from the STP located at Tarapur, Saharanpur. The water quality analysis results are given in Table 4-2,
Table 4-3 and Table 4-4 below:
Table 4-2: Physico-chemical & Biological Characteristics of Surface Water sample of Dhamola River (Upstream) near STP Site
S. No.
Parameters Unit IS: 2296 -1992(Class C)
Results Test method Tolerance Limit
1 pH - 6.5 - 8.5 7.12 IS: 3025(Pt-11)1983, RA. 2002
2 Temperature °C - 21.6 APHA 23rd Edn.2017-2550 B
3 D.O mg/l Minimum -4 0.9 IS 3025(Part-38): 2006.
4 BOD mg/l 30 92 IS 3025(Part-44):1993, RA 2009
5 Color Hazen 300 10 IS: 3025 (Pt-4) 1983, RA 2017
6 Odour - - Dis-
Agreeable IS: 3025(Pt-5)
7 TDS mg/l 1500 480 IS 3025(Part-16): 1984, RA 2006
8 TSS mg/l - 43.7 IS 3025(Part-17)
9 TKN mg/l 14.7 IS: 3025(Pt-34)1988, RA. 2003
10 Ammonical Nitrogen mg/l 1.78 IS: 3025(Pt-34)1988, RA. 2003
11 Nitrate(as NO3) mg/l 50 4.9 IS: 3025(Pt-34)1988, RA. 2003
12 Free Ammonia mg/l <0.1 IS: 3025(Pt-34)1988, RA. 2003
13 Chlorides (as Cl) mg/l 600 64 IS 3025(Part-32): 1988
14 Sulphates (as SO4) mg/l 400 33.8 IS 3025(Part-24):1986, RA 2003
15 Fluoride (as F) mg/l 1.5 0.61 APHA 21st Ed., 4500F(D)
Figure 4-4: Comparative record of Water quality for the year 2018 and 2019
48 44
40 40 38
54 50 52
40 44 43
0
20
40
60
Jan Feb Mar Apr May Jun Jul Aug Sep Oct NovCo
nce
ntr
ati
on
of
BO
D i
n m
g/l
Trend of BOD (mg/l) of Hindon River-
Saharanpur, 2018
43 44 40
52 50 54
38 40 40 44
48
0
20
40
60
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Trend of BOD (mg/l) of Hindon River-
Saharanpur, 2019
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-5
S. No.
Parameters Unit IS: 2296 -1992(Class C)
Results Test method Tolerance Limit
16 Oil & Grease mg/l 0.1 <0.1 IS 3025(Part-39):1991, RA 2009
17 Phenolic Compound (as C6H5OH) mg/l 0.005 <0.001 5530-B,C&E,APHA 23rd 2017
18 Arsenic mg/l 0.2 <0.1 3110- B, APHA 23rd Ed. 2017 (AAS)
19 Mercury( as Hg) mg/l - <0.001 3110- B, APHA 23rd Ed.2017
20 Lead ( as Pb) mg/l 0.1 0.02 3110- B, APHA 23rd Ed. 2017 (AAS)
21 Cadmium (as Cd) mg/l 0.01 0.006 3110- B, APHA 23rd Ed. 2017 (AAS)
22 Chromium (as Cr+6
) mg/l 0.05 0.02 IS 3025(Part-52): 200
23 Copper (as Cu) mg/l 1.5 0.19 3110- B, APHA 23rd Ed. 2017 (AAS)
24 Zinc (as Zn) mg/l 15 0.69 3110- B, APHA 23rd Ed. 2017 (AAS)
25 Selenium (as Se) mg/l - <0.1 IS: 3025 (P- 56)
26 Anionic detergents (as MBAS) mg/l 1.0 <0.1 Annexure K Of IS 13428
27 Iron (as Fe) mg/l 50 0.45 3500-Fe- B, APHA 23rd Ed. 2017
28 Sulphide(as H2S) mg/l - 0.18 IS-3025 (P-29)
29 Phosphate (as PO4) mg/l - 0.43 APHA 22nd
Edn.2012-4500-P C
30 Cyanide (as CN) mg/l 0.05 <0.1 4500-CN-B,C & E, APHA 23rd Ed.2017
31 Manganese (as Mn) mg/l 0.22 3110- B, APHA 23rd Ed.2017
32 COD mg/l - 424 IS 3025(Part-58): 2006
Microbiological Parameters
33 Total Coli form MPN/100ml 5000 380000 IS : 1622-1981
Table 4-3: Physico-chemical & Biological Characteristics of Surface Water sample of Dhamola River (Downstream) near STP
Site
S. No.
Parameters Unit IS: 2296 -1992(Class C)
Results Test method Tolerance Limit
1 pH - 6.5 - 8.5 6.82 IS: 3025(Pt-11)1983, RA. 2002
2 Temperature °C - 21.2 APHA 23rd Edn.2017-2550 B
3 D.O mg/l Minimum -4 0.6 IS 3025(Part-38): 2006.
4 BOD mg/l 30 102 IS 3025(Part-44):1993, RA 2009
5 Color Hazen 300 20 IS: 3025 (Pt-4) 1983, RA 2017
6 Odour - - Dis-
Agreeable IS: 3025(Pt-5)
7 TDS mg/l 1500 466 IS 3025(Part-16): 1984, RA 2006
8 TSS mg/l - 54.4 IS 3025(Part-17)
9 TKN mg/l 18.5 IS: 3025(Pt-34)1988, RA. 2003
10 Ammonical Nitrogen mg/l 1.87 IS: 3025(Pt-34)1988, RA. 2003
11 Nitrate(as NO3) mg/l 50 5.6 IS: 3025(Pt-34)1988, RA. 2003
12 Free Ammonia mg/l <0.1 IS: 3025(Pt-34)1988, RA. 2003
13 Chlorides (as Cl) mg/l 600 52 IS 3025(Part-32): 1988
14 Sulphates (as SO4) mg/l 400 27.7 IS 3025(Part-24):1986, RA 2003
15 Fluoride (as F) mg/l 1.5 0.64 APHA 21st Ed., 4500F(D)
16 Oil & Grease mg/l 0.1 <0.1 IS 3025(Part-39):1991, RA 2009
17 Phenolic Compound (as C6H5OH) mg/l 0.005 <0.001 5530-B,C&E,APHA 23rd 2017
18 Arsenic mg/l 0.2 <0.1 3110- B, APHA 23rd Ed. 2017 (AAS)
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-6
S. No.
Parameters Unit IS: 2296 -1992(Class C)
Results Test method Tolerance Limit
19 Mercury( as Hg) mg/l - <0.001 3110- B, APHA 23rd Ed.2017
20 Lead ( as Pb) mg/l 0.1 0.02 3110- B, APHA 23rd Ed. 2017 (AAS)
21 Cadmium (as Cd) mg/l 0.01 0.004 3110- B, APHA 23rd Ed. 2017 (AAS)
22 Chromium (as Cr+6
) mg/l 0.05 0.01 IS 3025(Part-52): 200
23 Copper (as Cu) mg/l 1.5 0.15 3110- B, APHA 23rd Ed. 2017 (AAS)
24 Zinc (as Zn) mg/l 15 0.62 3110- B, APHA 23rd Ed. 2017 (AAS)
25 Selenium (as Se) mg/l - <0.1 IS: 3025 (P- 56)
26 Anionic detergents (as MBAS) mg/l 1.0 <0.1 Annexure K Of IS 13428
27 Iron (as Fe) mg/l 50 0.42 3500-Fe- B, APHA 23rd Ed. 2017
28 Sulphide(as H2S) mg/l - 0.13 IS-3025 (P-29)
29 Phosphate (as PO4) mg/l - 0.41 APHA 22nd
Edn.2012-4500-P C
30 Cyanide (as CN) mg/l 0.05 <0.1 4500-CN-B,C & E, APHA 23
rd
Ed.2017
31 Manganese (as Mn) mg/l 0.21 3110- B, APHA 23rd Ed.2017
32 COD mg/l - 460 IS 3025(Part-58): 2006
Microbiological Parameters
33 Total Coli form MPN/100ml 5000 420000 IS : 1622-1981
Table 4-4: Analysis Result of Ground Water Sample
S. No. Parameters Unit
Limit (IS-10500:2012)
Results Test method Desirable
Limit Permissible
Limit
1 Color Hazen 5 15 <5 IS: 3025(Pt-4)
2 Odour - Agreeable Agreeable Agreeable IS: 3025(Pt-5)
3 Taste - Agreeable Agreeable Agreeable IS: 3025(Pt-8)
4 Turbidity NTU 1 5 <1 IS 3025(Part-10)
5 pH - 6.5-8.5 No Relaxation 7.34 IS: 3025(Pt-11)
6 Total Hardness (as CaCO3) mg/l 200 600 250.0 IS 3025(Part-21)
7 Iron (as Fe) mg/l 1.0 No Relaxation 0.24 3500-Fe- B, APHA 23rd Ed.2017
8 Chlorides (as Cl) mg/l 250 1000 102.0 IS 3025(Part-32)
9 Fluoride (as F ) mg/l 1 1.5 0.56 4500-F-(D),APHA 23rd Ed. 2017
10 TDS mg/l 500 2000 638 IS 3025(Part-16)
11 Calcium (as Ca2+
) mg/l 75 200 60.0 IS 3025(Part-40)
12 Magnesium (as Mg2+
) mg/l 30 100 24.3 3500-Mg B, APHA 23rd Ed 2017
13 Sulphate (as SO4) mg/l 200 400 42.5 IS 3025(Part-24)
14 Nitrate (as NO3) mg/l 45 No Relaxation 6.6 IS: 3025(Pt-34)
15 Total Chromium (as Cr) mg/l 0.05 No Relaxation <0.01 3110 - B, APHA 23rd Ed.2017
16 Alkalinity as CaCO3 mg/l 200 600 480.0 IS 3025(Part-23)
17 Aluminum (as Al) mg/l 0.03 0.2 <0.01 IS 3025(Part-55)
18 Total Arsenic(as As) mg/l 0.01 No Relaxation <0.01 3110- B, APHA 23rd Ed2017
19 Copper (as Cu) mg/l 0.05 1.5 <0.05 3110- B, APHA 23rd Ed2017
20 Manganese (as Mn) mg/l 0.1 0.3 <0.01 3110- B, APHA 23rd Ed2017
21 Zinc (as Zn) mg/l 5 15 0.18 3110- B, APHA 23rd Ed2017
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-7
S. No. Parameters Unit
Limit (IS-10500:2012)
Results Test method Desirable
Limit Permissible
Limit
22 Ammonia (as NH3-N) mg/l 0.5 No Relaxation <0.1 4500-NH3-B &C, APHA 23rd ED2017
23 Anionic Detergents (as MBAS)
mg/l 0.2 1 <0.1 Annexure K of IS-13428
24 Boron (as B) mg/l 0.5 1 0.05 IS: 3025(Pt-57)
25 Mineral Oil mg/l 0.5 No Relaxation <0.1 IS 3025(Part-39)
26 Phenolic Compound (as C6H5OH)
mg/l 0.001 0.002 <0.001 IS 3025(Part-44)
27 Cadmium (as Cd) mg/l 0.003 No Relaxation <0.002 3110- B, APHA 23rd Ed2017
28 Cyanide (as CN) mg/l 0.05 No Relaxation <0.1 4500- CN-B,C &E, APHA 23rd Ed2017
29 Lead mg/l 0.01 No Relaxation <0.01 3110- B, APHA 23rd Ed2017
30 Mercury (as Hg) mg/l 0.001 No Relaxation <0.001 3110- B, APHA 23rd Ed2017
31 Nickel (as Ni) mg/l 0.02 No Relaxation <0.02 3110- B, APHA 23rd Ed2017
32 Residual Free Chlorine mg/l 0.2 1.0 <0.2 4500-Cl-B, APHA 23nd Ed2017
33 Molybdenum (Mo) mg/l <0.05 0.07 No Relaxation 3110- B, APHA 23rd Ed.2017
34 Polynuclear Aromatic Hydro Carbons
mg/l <0.0001 0.0001 No Relaxation APHA 6440,23rd Ed.2017
35 Poly chlorinated biphenyl mg/l <0.0001 0.0005 No Relaxation APHA 6430,23rd Ed.2017
Microbiological Parameters
36 Total Coli form MPN/100ml Shall not be detectable in
any 100 ml of sample <1 IS : 1622-1981
37 E.coli E.coli/100ml Shall not be detectable in
any 100 ml of sample Absent IS : 1622-1981
65. A review of the above chemical analysis reveals that there is some variation in chemical composition of
surface water samples collected from upstream and downstream of Dhamola River but the ground water collected
from the existing STP located at Tarapur remains suitable for drinking purposes as all the constituents are within the
limits prescribed for drinking water standards promulgated by Indian Standards (IS: 10500). This high concentration
of BOD in water samples collected from Dhamola River possibly due to the discharge of untreated waste water from
the households and various industries particularly sugar and paper mill industries exist in nearby. Water Quality
data is attached as Annexure-3 and Indian standard Drinking water Specification, IS 10500:2012 for water quality is
available online at http://cgwb.gov.in/Documents/WQ-standards.pdf.
4.7 BIOLOGICAL ENVIRONMENT
66. The Botanical Garden (named it as Company Garden) located in center of the Saharanpur city and it is
considered second only to the Kolkata Botanical Garden in terms of contributing research and science and the study
of flora and fauna. It is one of the oldest existing gardens in India and dates back to before 1750. In 1817, it was
acquired by the British East India Company and placed under the authority of the District Surgeon.
67. A research study explains on botanical garden under the Botanical survey of India that there are 235
dendroid species including 173 trees, 59 shrubs and 3 species of climbers are exists. The dominant species in this
garden are Sterculia alata, Sweteinia mahogni, Tectona grandis, Shorea robusta, Bischofia javanica, Albizia sp., Ficus
spp. Acacia sp. etc. Some species like Haematoxylon campechianum, Drypetes sepiarea, Sterculia acerifolia,
Santalum album, Dillenia indica, Encephalortos humulis, Taxodium macronatum etc are represented by one or two
specimen.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-8
68. The woody climber species is endemic to Saharanpur. Many of the exotic species were introduced during
last few centuries for commercial, experimental and ornamental exploitations. Few fine specimen of this plant along
with other exotics can be seen in the Garden which needs proper conservation and protection Thuja sp, Juniperus
sp., Cycas spp, Agathis sp., Pinus sp., Encephalortos sp., Taxodium sp., Araucaria sp., etc are some of the
gymnospermic representatives in this garden.
4.8 NOISE ENVIRONMENT
69. The environmental impact of noise can have several effects varying from annoyance to hearing loss
depending on loudness of noise levels. The main objective of the noise level monitoring is to assess the background
noise levels in different zones viz. industrial, commercial, residential, and silence zones within the vicinity of the
project site.
70. Ambient noise levels were measured around the proposed project site. The noise levels recorded during
the day and night time respectively. The noise levels near the residential area of the proposed project location were
found within the prescribed limits. However, in commercial areas (i.e. near Swapna Theatre and Shantinagar) it was
above the prescribed standards of noise quality during the day time. Noise Quality data attached as Annexure-3 and
Ambient Air Quality Standards in respect of Noise is available online at http://cpcbenvis.nic.in.
Table 4-5: Noise level in project area: STP site Residential area
Table 4-6: Noise level in project area: Commercial Areas
4.9 SOIL ENVIRONMENT
71. Assessment of soil quality is an important aspect with reference to tree plantations, percolation of water,
ground water impact etc. The information on soils has been collected from various secondary sources and also
through primary soil sampling analysis of which is described in this section.
72. Randomly a soil sample was collected from proposed STP site near Tarapur, up to depth of 15 cm and then
sent to the laboratory for analyzing various physical and chemical characteristics of the soil of the project location.
The analysis result show that soil is basic in nature as pH value is 7.34 with organic matter 1.11%. The concentration
of Nitrogen (878.90 Kg/Ha), Phosphorus (65.5 Kg/Ha) and Potassium (122.3 Kg/Ha) has been found to be in good
amount in the soil samples. Soil texture is Sandy to Clay Loam. Soil Quality data is attached as Annexure-3.
S. No. Date
Sampling Location
Geographic Locations Equivalent Noise
Level, Leq (Day)
Equivalent Noise
Level, Leq (Night) Test Method Latitude Longitude dB (A) dB (A)
1 09.01.2020 STP Site-Residential Area 29°55'7.61"N 77°33'7.97"E
49.5 40.0
IS 9989 : 1981
(RA 2008) Limit for Residential Zone As Per the Noise Pollution (Regulation and Control)
Rules, 2000 55 45
S. No. Date Sampling Location
Geographic Locations Equivalent Noise Level,
Leq (Day)
Equivalent Noise Level,
Leq (Night) Test Method Latitude Longitude dB (A) dB (A)
1 02.02.2020 Near Swapna Theatre 29°57'44.58"N 29°57'44.59"N
69.3 53.6
IS 9989 : 1981
(RA 2008)
2 02.02.2020 Shantinagar, Saharanpur 29°57'59.78"N 77°33'45.71"E
68.6 51.3
Limit for Commercial Zone As Per the Noise Pollution (Regulation and
Control) Rules, 2000 65 55
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-9
Table 4-7: Soil sample details in the project area
4.10 FOREST AREA AND LAND USE
73. The project region
located in Gangetic plains
having highly fertile alluvial soil
and became an important place
in the field of agriculture in the
State. Roughly 70% of the land
is under agricultural use. The
significance of commercial
crops have increased manifold
as an importance of sugar cane
production. Saharanpur is well
known for its agriculture
produce such as sugar,
mangoes and rice.
74. District forest cover as
per India State of Forest Report-
2011, 175 km2 moderate dense forest and 200km
2 is open forest area is situated in Saharanpur District in northern
part which is a hilly trac and most of the forests are there. Other than that no forest area is envisaged in the
District.
4.11 ECOLOGICAL SENSITIVE AREA IN THE PROJECT AREA
75. During the site assessment,
it was observed that the project area
is not located in the vicinity of any
forest or wild life sanctuary and eco-
sensitive area. Rajaji National park is
situated near Haridwar, Uttarankand
and is located from the project city is
around 40 Km. (approx.).
4.12 ARCHAEOLOGICAL SITES
76. During the site assessment,
the proposed STP site is not located
within regulatory zone of ASI
structure (300 m). There is 1protected monuments namely Mound and Sahaspal ka Killa located in the city and 1.5
km away from the proposed IPS location. Therefore, no prior permission is required under ASI.
S. No. Date Sampling Location Geographical Location
Distance from the
Proposed Site Remarks
Latitude Longitude
1 09.01.2020 STP Site- near Tarapur,
Saharanpur 29°55'4.70"N 77°33'10.52"E At project site-STP Agriculture Land
Figure 4-5: Forest cover Map of Uttar Pradesh
Figure 4-6: Wildlife Protected Areas in Uttar Pradesh
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-10
Figure 4-7: Map showing the distance of Rajaji National Park from the proposed STP site
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-11
4.13 AGRO-CLIMATIC ZONES AND SOIL CONDITION
77. State of Uttar Pradesh has categorized into 9 zones based on their agro-climatic conditions. The city of
Saharanpur is comes under western plain zone and some portion in Tarai zone and having alluvial soil (pH value from
normal to alkaline) and Organic matter minimum to medium quantity. The soil is highly fertile and rich. Major crops in
this area are Paddy, wheat and sugarcane.
Figure 4-8: Agro-climatic Areas in Uttar Pradesh
4.14 SOCIO-CULTURAL ENVIRONMENT
78. The town is a prominent tourist destination and is famous for its cottage industries including wood carving.
The Botanical Gardens, established by the British East India Company in the city are also quite famous and serve as a
center for botanical research. It leads to increase the visitor ratio and the traffic congestion for the future perspective,
proper mitigations measures to be taken while laying the sever network in order to avoid or minimize the disturbance
to local and outside visitors in the City.
79. Hindus are prominent in Saharanpur city with 50.92 percent and followed by Muslim community is the
second most popular religion in the city with approximately 45.89 per cent. In addition, half of its population has their
livelihood in the wood handicrafts industry.
4.15 POPULATION
80. Project tehsil population is 13.69 lakh in 2011 which was 10.94 lakh in 2001. Population of the tehsil grew at
an Average Annual Growth Rate (AAGR) of 2.52
percent during the period 2001 to 2011. The total
urban population residing in the project tehsil during
2001 was 4.65 lakh which increased to 7.31 lakh in
2011 with an AAGR of 5.71 percent, which covers
almost 96% Saharanpur City population of 7.05 lakhs.
81. Total population of Saharanpur city is 7.05
lakh, which is almost 51 percent to the Tehsil
population of which 3.71 lakhs are males while 3.33
lakhs are females as per Census 2011. The City
population as per census 2001 and 1991 it was 4.55 Figure 4-9: Population growth in the Region (Figures in Lakhs)
and 3.74 lakhs respectively.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-12
4.16 SEX RATIO AND LITERACY RATE
82. Project city revealed the sex ratio of 898 females per thousand males. The literacy rate of Saharanpur city as
per 2011 census is 76.32 percent, higher than the Tehsil average (73.13%); this constitutes 80.37 percent male
literates and 71.82 percent female literates.
4.17 SCHEDULE CASTE AND SCHEDULE TRIBE POPULATION
83. Analysis of social groups for the project city
has been done on the basis of concentration of
Schedule Caste (SC) and Schedule Tribe (ST)
population in Tehsil and project city. As per census
2011, the total SC and ST population of tehsil is 2.95
lakh, which shares 21.51 per cent SC and only 0.06
per cent ST to the total population.
84. As per Census 2011, SC and ST population
for Saharanpur city accounts for the figure of 1,
00,989. Of this the share of ST community is only
0.12 percent to the total population.
4.18 OCCUPATIONAL STRUCTURE
85. The total workers in project city are 2.19 lakhs (31.05%), in which main workers consist of 26.65 percent,
marginal workers are exist 4.41 percent and non-workers contribution is 68.95 percent as per census 2011. Workers
composition for the city shows highest share of workers in other sectors10 (89.47 percent) followed by Household
Industry workers (5.97 percent).
Figure 4-11: Occupational Structure of Saharanpur Municipal Corporation
10 Other Workers: all those workers other than cultivators or agricultural labourers or household industry workers are 'Other
Workers'. The type of workers that come under this category of 'OW' include all government servants, municipal employees,
teachers, factory workers, plantation workers, those engaged in trade, commerce, business, transport banking, mining,
construction, political or social work, priests, entertainment artists, etc. In effect, all those workers other than cultivators or
agricultural labourers or household industry workers are 'Other Workers'.
Figure 4-10: ST and SC Population of Saharanpur M. Corp.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4-13
4.19 SLUM AREAS IN PROJECT CITY
86. The city has only one slum (Mandi Basti) with 33.6 percent of population to the total population and 32,000
households (approximately) located in Saharanpur Municipal Corporation area with the basic facilities of tap water
connection and paved roads.
4.20 CITY’“ PLANNED ACTIVITIES
87. The city has divided into 86 wards and total over 1.29 lakhs of houses to which it supplies basic amenities like
water and sewerage. It also authorizes to build roads within Municipal Corporation limits and impose taxes on
properties coming under its jurisdiction.
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-1
5. ENVIRONMENTAL AND “OCIAL “AFEGUARD DUE DILIGENCE
88. The process of environmental and social due diligence was accomplished through the review of available
documents viz. Detailed Project Reports (DPR) and other literatures related to environmental and social aspects of the
project area. Several site visits / field surveys, detailed interactions with key stakeholders and consultations with host
communities at site wherever feasible are also conducted to identify and assess the anticipated environmental and
social impacts associated with the proposed project, as well as to develop an Environmental and Social Management
Action Plan (ESMAP) recommending suitable mitigation measures.
5.1 POLICY, LEGAL AND REGULATORY REQUIREMENTS
89. The policy, legal and regulatory requirements that are applicable to the environmental and social aspects of
the investments implemented under the programme are as follows:
► Policy and Regulatory Framework of Government of India (GoI)
► Environmental Policy and Regulations of the respective State Governments
► Legislations applicable to construction activities
5.2 KEY APPLICABLE LAWS AND REGULATIONS – ENVIRONMENTAL & SOCIAL
90. The key environmental and social laws and regulations as relevant to the projects under the NGRBP are
tabulated below. The key environmental regulations can also be accessed at www.moef.nic.in/rules-and-regulations.
Table 5-1: Environmental Regulations and Legislations
S.
No. Act / Rules Purpose
Applicable
(Yes / No) Reason for Applicability Authority
1 Environment
Protection Act, 1986
To protect and improve
overall environment.
This is an umbrella Act.
Yes
As all environmental
notifications, rules and
schedules are issued
under this act.
MoEFC&C, CPCB,
SPCB
2
Environmental
Impact Assessment
NotifiIatioミ ヱヴth “epげ 2006 and its
amendments
To ensure and regulate
all new development
work which is listed in
EIA Schedule
No
The project is only for
sewerage network and
STP Project, hence as per
the notification including
its amendments does not
attract requirement of
environmental clearance.
MoEFC&C, SEAA,
GOI
3
Solid Waste
Management Rules,
2016
To manage collection,
transportation,
Segregation,
Treatment, and
disposal of solid wastes
(other than Hazardous
water, plastic Waste ,
BIO Medical waste)
Yes
Applicable for Waste
generated from the
camp, offices, STPs.
MoEFC&C, CPCB,
SPCB
4
UP Negotiation
(Mutual Consent)
Policy, 2015 GO No ‐ヲ/ヲヰヱヵ/ヲヱヵ/ Ek‐ヱン‐ヲヰヱヵ‐ ヲヰふヴΒぶ/ヲヰヱヱ Rajaswa Anubhag-13
The provisions of this
Act relating to land
purchase
compensation,
rehabilitation and
resettlement, shall
Yes
2 proposed IPS and 85
MLD STP have no
government land and for
that private land
purchase of around 7.8
ha area will be required.
District
Magistrate,
Municipal
Corporation and
Revenue
Department, State
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-2
S.
No. Act / Rules Purpose
Applicable
(Yes / No) Reason for Applicability Authority
dt 19.03.2015 and
subsequent
amendments
thereof.
apply, when the
appropriate
Government acquires
land for its own use,
hold and control,
including for Public
Sector Undertakings
and for public purpose
Government
5
The Right to Fair
Compensation and
Transparency in Land
Acquisition,
Rehabilitation and
Resettlement Act,
2013
The provisions of this
Act relating to land
acquisition
compensation,
rehabilitation and
resettlement
assistance.
No
Right now the Act is not
applicable, in case Uttar
Pradesh Negotiation
(Mutual Consent) Policy,
2015 fails, this act shall
prevail
District
Magistrate,
Municipal
Corporation and
Revenue
Department, State
Government
6
The Forest
(Conservation) Act,
1980
To regulate the non-
forest activity and
conservation of Forest
of India.
No
No forest land diversion
and tree felling is
required in the project.
State Forest
Department & GOI
MOEF &CC
7 National Forest
Policy, 1988
To maintain ecological
stability through
preservation and
restoration of
biological diversity.
No
This policy will be
applicable if any eco
sensitive feature exists in
and around the
investments.
Forest Dept., State
Gov. and
MoEFC&C, GoI
8 Wild Life Protection
Act, 1972
To protect wildlife
through certain of
National Parks and
Sanctuaries
No
None of project location
and activities is located
near to any National Park
/ Sanctuary / Eco
sensitive zones and nor
fall within 10 Km. radius
of such protected areas.
Chief Conservator
Wildlife, Wildlife
Wing, State Forest
Dept. and
MoEFC&C, GoI
9
Air (Prevention and
Control of Pollution)
Act, 1981
To control air pollution
by controlling emission
of air pollutants as per
the prescribed
standards.
Yes
Consent to establish and
consent to operate is
required to be obtained
from SPCB under section
21 of Air (Prevention and
control of Pollution) Act
1981.
State Pollution
Control Board,
Uttar Pradesh
10
Water Prevention
and Control of
Pollution) Act, 1974
To control water
pollution by controlling
discharge of pollutants
as per the prescribed
standards
Yes
Consent to establish
(CTE) and consent to
operate (CTO) is required
to be obtained from SPCB
under section 25 of this
Act.
State Pollution
Control Board,
Uttar Pradesh
11
The Noise Pollution
(Regulation and
Control) Rules, 2000
& amendments
The standards for noise
for day and night have
been promulgated by
the MoEFC&C for
various activities.
Yes
This act will be
applicable for all
construction equipment
deployed at worksite and
in operation.
State Pollution
Control Board,
Uttar Pradesh
12 Ancient Monuments
and Archaeological
Conservation of
cultural and historical No
None of the new
construction of STP, MPS,
Archaeological
Department Gol,
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-3
S.
No. Act / Rules Purpose
Applicable
(Yes / No) Reason for Applicability Authority
Sites and Remains
Act, 1958
remains found in India. IPS are located near to
regulated zone of any ASI
structure
Indian Heritage
Society and Indian
National Trust for
Art and Culture
Heritage (INTACH).
13 Public Liability and
Insurance Act, 1991
Protection form
hazardous materials
and accidents.
No
This act will be applicable
for providing immediate
relief to the persons
affected by accident
occurring while handling
any hazardous
substances / chemicals
viz. chlorine (to be used
for Chlorination System)
as detailed in the
Schedule to this act
State Pollution
Control Board,
Uttar Pradesh
14 Explosive Act 1984
Safe transportation,
storage and use of
explosive material.
Yes
This act will be applicable
during construction by
the Concessionaire for
the storing diesel,
lubricants, etc.
Chief Controller of
Explosives
15 Minor Mineral
Concession Rules
For opening new
quarry. Yes
This act will be applicable
during construction by
the Concessionaire for
the use of minor minerals
like stone, soil, river
sand; etc.
SEIAA, District
Collector
16 The Mines Act
The mining act has
been notified for safe
and sound mining
activity.
No
The construction
activities for investments
will require aggregates.
These will be procured
through mining from
approved quarries.
Dept. of mining,
State Government
17 Central Motor
Vehicle Act 1988
To check vehicular air
and noise pollution. Yes
This rule will be
applicable to vehicles
deployed for
construction activities
and construction
Machinery.
Motor Vehicle
Department
18
Demolition and
Construction Waste
Management Rules
2016
The rules shall apply to
every waste resulting
from construction,
remodeling, repair and
demolition of any civil
structure of individual
or organization or
authority who
generates construction
and demolition waste
Yes
This rule is applicable for
demolition and
construction waste
generated while laying of
I&D structure
State Pollution
Control Board,
Uttar Pradesh and
EA/
Concessionaire
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-4
S.
No. Act / Rules Purpose
Applicable
(Yes / No) Reason for Applicability Authority
such as materials,
debris etc.,
19
Hazardous waste
management,
handling and
transboundary rules,
2016
For making effective
procedure for
inventory, control,
handling and disposal
hazardous wastes.
Yes
This rule is applicable in
the storage, use and
disposal of hazardous
substances viz. chlorine
to be used for
Chlorination System,
waste oils, emulsions,
colour, spent chemicals
and metal finishing
wastes emanating during
construction
State Pollution
Control Board,
Uttar Pradesh and
EA/
Concessionaire
20
The Plastic Waste
Management Rules,
2016
For the storage and
disposal of plastic
wastes through
authorized vendors.
Yes
This act will be applicable
for the storage and
disposal of all the plastic
wastes viz. plastic bags /
cement bags generate
during the construction.
State Pollution
Control Board ,
Uttar Pradesh
5.3 KEY APPLICABLE LAWS AND REGULATIONS – SOCIAL
► Environmental and Social Management Framework for NGRBA
► UP Negotiation (Mutual Consent) Policy, 2015GO No ‐ヲ/ヲヰヱヵ/ヲヱヵ/ Ek‐ヱン‐ヲヰヱヵ‐ ヲヰふヴΒぶ/ヲヰヱヱ ‘ajas┘a AミuHhag-13
dt 19.03.2015 and subsequent amendments thereof.
► 73rd
Constitution Amendment Act, 1992 (The Act enables participation of Panchayat level institutions in decision
making by broadening the village level functions, supporting implementation of development Schemes. The Act
provides for involvement of the PRIs especially, the Gram Sabha/Panchayat during project preparation and
implementation. The Panchayat at the village level will be involved for preparation and implementation of the
project)
5.4 OTHER LEGISLATIONS APPLICABLE TO CONSTRUCTION ACTIVITIES UNDER THE PROJECT
► Workmen's Compensation Act 1923 (the Act provides for compensation in case of injury by accident arising out
of and during the course of employment);
► Payment of Gratuity Act, 1972 (gratuity is payable to an employee under the Act on satisfaction of certain
conditions on separation if an employee has completed 5 years);
► Employees PF and Miscellaneous Provision Act 1952 (the Act provides for monthly contributions by the employer
plus workers);
► Maternity Benefit Act, 1951 (the Act provides for leave and some other benefits to women employees in case of
confinement or miscarriage, etc.);
► Contract Labor (Regulation and Abolition) Act, 1970 (the Act provides for certain welfare measures to be
provided by the Concessionaire to contract labour);
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-5
► Minimum Wages Act, 1948 (the employer is supposed to pay not less than the Minimum Wages fixed by the
Government as per provisions of the Act);
► Payment of Wages Act, 1936 (it lays down as to by what date the wages are to be paid, when it will be paid and
what deductions can be made from the wages of the workers);
► Equal Remuneration Act, 1979 (the Act provides for payment of equal wages for work of equal nature to Male
and Female workers and not for making discrimination against Female employees);
► Payment of Bonus Act, 1965 (the Act provides for payments of annual bonus subject to a minimum of 83.3% of
wages and maximum of 20% of wages);
► Industrial Disputes Act, 1947 (the Act lays down the machinery and procedure for resolution of industrial
disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or
retrenching the employees or closing down the establishment);
► Industrial Employment (Standing Orders) Act; 1946 (the Act provides for laying down rules governing the
conditions of employment);
► Trade Unions Act, 1926 (the Act lays down the procedure for registration of trade unions of workers and
employers. The trade unions registered under the Act have been given certain immunities from civil and criminal
liabilities);
► Child Labour (Prohibition and Regulation) Act, 1986 (the Act prohibits employment of children below 14 years of
age in certain occupations and processes and provides for regulation of employment of children in all other
occupations and processes. Employment of child labour is prohibited in Building and Construction Industry);
► Inter-“tate Migヴaミt Woヴkマeミげs ふ‘egulatioミ of Eマployマeミt aミd Coミditioミs of “eヴ┗iIeぶ AIt, ヱΓΑΓ ふthe iミteヴ-state
migrant workers, in an establishment to which this Act becomes applicable, are required to be provided certain
facilities such as housing, medical aid, travelling expenses from home to the establishment and back, etc.);
► The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996
and the Cess Act of 1996 (all the establishments who carry on any building or other construction work and
employs 10 or more workers are covered under this Act; the employer of the establishment is required to
provide safety measures at the building or construction work and other welfare measures, such as canteens, first-
aid facilities, ambulance, housing accommodation for Workers near the workplace, etc.);
► The Factories Act, 1948 (the Act lays down the procedure for approval of plans before setting up a factory, health
and safety provisions, welfare provisions, working hours and rendering information-regarding accidents or
dangerous occurrences to designated authorities);
► Sexual Harassment of Women at the Workplace (Prevention, Prohibition and Redressal) Act, 2013 ( The Act
defines Sexual Harassment in the Workplace, provides for an enquiry procedure in case of complaints and
mandates the setting up of an Internal Complaints Committee)- This is a legislative Act that seeks to protect
women from sexual harassment in the construction camp/ any work place.
► Hazardous Wastes (Management, Handling and Trans-boundary Movement) Rules, 2008 (the Rules govern
handling, movement and disposal of hazardous waste);
► Manufacture, Storage and Import of Hazardous Chemicals Rules 1989, amended 1994 and 2000 (the Rules
provide indicative criteria for hazardous chemicals and require occupiers to identify major accident hazards and
prepare on-site and off-site emergency plans).
► All the laws and regulations set by different authorities (MoEF, NGRBA, CPCB, etc.) have been reviewed to
understand the applicable laws in the context of this proposed sub-project in Saharanpur. All the applicable laws
enlist the responsible authority and reasons for its applicability. It is therefore proposed that during the
implementation of this project responsible authorities should be contacted acted by the implementing agency for
monitoring the law and regulation.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-6
5.5 APPLICABLE WORLD BANK POLICIES
91. The Operational Policies of World Bank applicable to the project under Namami Gange programme are as
follows:
Table 5-2: Operational Policies of World Bank
Applicable World Bank Policies
Environmental Assessment (OP 4.01) – Umbrella Policy applicable for all infrastructural projects- Applicable in all
Investments. Operational Policy 4.01 (OP 4.01) is one of the ten safeguard policies of the World Bank, which provides
the Environmental Assessment (EA) guidance for the lending operations. The OP 4.01 requires the borrower to screen
projects upstream in the project cycle for potential impacts. Thereafter, an appropriate EA approach to assess,
minimize / enhance and mitigate potentially adverse impacts is selected depending on nature and scale of project. The
EA needs to be integrated in the project development process such that timely measures can be applied to address
identified impacts. The policy requires consultation with affected groups and NGOs to recognize community concerns
and the need to address the same as part of EA.
Natural Habitats (OP 4.04) – To protect natural habitat including forest & wildlife areas- Not Applicable, no Forest and
Wild Life are impacted due to project. OP ヴ.ヰヴ sets out the Woヴld Baミkげs poliIy on supporting and emphasizing the
precautionary approach to natural resource management and ensuring opportunities for environmentally sustainable
development. As per this policy, the Bank does not support projects that involve significant conversion or degradation
of critical natural habitats. Projects involving non-critical habitats are supported if no alternatives are available and if
acceptable mitigation measures are in place.
5.6 COMPLIANCE TO REGULATORY REQUIREMENTS
► The project does not require any environmental clearance, or forest clearance. At the same time, the project
requires to obtain required consents and permissions from competent authorities. The specific requirements are
mentioned as under, for which the Concessionaire should comply with before initiating the construction:
► Consent to Establish (CTE) and Consent to Operate (CTO) for the establishment and operation of STP is
mandatory to obtain under Water (Prevention and Control of Pollution) Act 1972 of Government of India.
► Permission for use of water for construction purpose from irrigation department/CGWA (for Surface or Ground
Water) respectively.
► Labour license requires to be obtained by the Concessionaire prior to construction.
5.7 LAND REQUIREMENTS
92. As per the discussions held with the officials of UP Jal Nigam, Saharanpur, it is assessed that for establishing
various proposed project components (i.e. One STP – 85 MLD, 9 Pumping Stations, Staff quarters, etc.) about 8.22
Hectares of land is required. Out of the total land requirement, about 0.41 Hectares of government land is available
for 7 IPS locations. However, government land is not available for remaining 2 IPS and the proposed STP and about
7.81 hectares of land will be required. In this regard, Jal Nigam, Saharanpur is acquiring the private land in accordance
with the UP Negotiation (Mutual Consent) PoliIy GO No ‐ヲ/ヲヰヱヵ/ヲヱヵ/ Ek‐ヱン‐ヲヰヱヵ‐ ヲヰふヴΒぶ/ヲヰヱヱ sub-section-13 dated
19.03.2015.
93. The land purchase pヴoposal has Heeミ suHマitted to the Coママittee Ioミstituted uミdeヴ suH seItioミ けkhaげ foヴ the approval and finalization of land rates. Affidavits from the landowners to sell in favor of the IPS and STP have been
obtained. UP Governments Negotiation (Mutual Consent) policy covers all the assistance provisions of RFCTLARR Act
2013. However the provisions of Rights to Fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 and subsequent supplements shall prevail in case negotiation purchase fails.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-7
94. The technical feasibility report11
for selected land under Namami Gange project for 85 MLD STP and 2 IPS has
been issued. For the available Government, NOC has obtained from Municipal Corporation, Saharanpur and Irrigation
Departments. Copy of the feasibility report on private land and Consent/MOU between landowner and project
authority is provided at Annexure-4 and 4.1.
Table 5-3: Land Requirement Details for the Proposed IPS and STP locations
Sl.
No. IPS No. Name of Location
Total
Land
required
(ha)
Available Govt.
Land (ha)
Land to be
Purchased (ha) Details of proposed land
Land Details of proposed IPS Locations
1 1 Near Numaish Camp
Bridge 0.0200 0.0200
0.00
Municipal Corporation
Land identified as barren land
bearing survey no 271. NOC has
been issued vide letter no. 730
dt. 04.10.2019.
2 2 Shanti Nagar 0.0300 0.0300
0.00
Municipal Corporation,
Abandoned toilets block
existed, which need to be
demolished and NOC has been
issued vide letter no. 704 dt.
13.09.2019.
3 3 Near Sapna Cinema 0.0300 0.0300
0.00
Irrigation Department,
It is in the name of irrigation
department in RoR and NOC has
been issued vide letter no.
3224/ flafuf[kl / dt.30.10.2019
13.09.2019.
4 4 Near Old Police Chowki 0.0300 0.00
0.0300
Private Land,
No MC Land is available; hence
land will be purchased from
private person.
5 5 Near Peer Pahalwan
Pulia 0.0300 0.0300
0.00
DRRO (District R&R Officer)
Land,
Near this IPS the village name is
Dara Rajpura bearing khasra no
513, for obtaining NOC,
necessary correspondence has
been done with District
Magistrate.
6 6 Near Rakesh Cinema 0.0800 0.0800
0.00
Municipal Corporation,
Land is available and finalized.
NOC has been issued vide letter
no. 705 dt. 13.09.2019.
7 7 Near confluence
Dhamola and Pandhoi 0.1200 0.1200
0.00
Irrigation Department,
It is in the name of irrigation
department in RoR and NOC has
been issued vide letter no.
3224/ flafuf[kl / dt.30.10.2019
13.09.2019.
8 8 Near Bijali Ghar, paper
Mill road 0.0800 0.00
0.0800
Private Land,
No MC Land is available; hence
land will be purchased from
11 A complete detailed report on the availability of land and the requirement of private land for the IPS and STP
construction which is jointly prepared by DPR Consultant, Project Manager, UP Jal Nigam, Concerned Departments
and revenue authority Saharanpur.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-8
Sl.
No. IPS No. Name of Location
Total
Land
required
(ha)
Available Govt.
Land (ha)
Land to be
Purchased (ha) Details of proposed land
private person.
9 9 Kanshiram colony near
overhead water tank 0.1000 0.1000
0.00
Municipal Corporation,
NOC has been issued vide letter
no. 730 dt. 04.10.2019.
Sub-total 0.5200 0.4100
0.1100
Government land is not
available for 2 IPS locations
Land Details of Proposed STP location
1 Villages
Badshapur 7.0113 0.00 7.0113 As per UP Negotiation (Mutual
Consent) Policy, 2015. GO No ‐ヲ/ヲヰヱヵ/ヲヱヵ/ Ek‐ヱン‐ヲヰヱヵ‐ 20(48)/2011 Rajaswa Anubhag-
13 dated 19.03.2015 sub section
kha, the Committee for the total
land to be purchased and land
finalization of land rate has
been constituted. Affidavits
from the landowners have been
obtained.
2 Shekhpur Kadim 0.687 0.00 0.687
Sub-total 7.6983 0 7.6983
Grand Total 8.2183 0.4100
7.8083
95. The total area of land required for the project, as estimated by the UP Jal Nigam, Saharanpur is 7.81 ha.
Altogether 75 landowners will be affected due to the land purchase. Revenue map showing the boundary of the
proposed STP has been provided in Figure 5-4.
Figure 5-1: Land Identified for proposed STP location at Badshapur village
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-9
Figure 5-2: Proposed IPS Location Near Old Police Chowki
(Land identified)
Figure 5-3: Proposed IPS location Near Paper Mill Road (Land
identified)
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-10
Figure 5-4: Revenue Map for the Proposed STP location
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-11
5.8 STAKEHOLDER CONSULTATIONS
96. Stakeholder consultations were carried out while preparing the ESDDR. Officials of various departments
including the UP Jal Nigam, Saharanpur and Mayor of Municipal Corporation were consulted. Different sections of the
local community including landowners, residents of households, shop keepers, etc. were also consulted during the
preparation of ESDDR. The details of the consultation and issues discussed have been summarized in the table below
and minutes of the meeting along with attendance sheets included as an Annexure 2.
Table 5-4: Public Consultation held during ESDDR preparation
Sl
.
N
o.
Date
of
Consul
tation
Locatio
n
Name of the
Officials/Per
son met
Discussion Outcomes Photos
1 7th
Januar
y 2020
Office
of the
Project
Manag
er, UP
Jal
Nigam,
Sahara
npur
Er. Rajendra
Singh,
Executive
Engineer
cum Project
Manager, Er.
Abhay
Kumar,
Assist.
Project
Engineer, Er.
Prashant
Kumar,
Deputy
Project
Engineer, Mr
Janeshwar
Pandey, Naib
Tehsildar, Mr
Mahendra
Pal, Lekhpal
and Mr
Pradeep
Upadhyay,
ward
councillor,
ward no.-39,
MC
Saharanpur
Draft DPR has been prepared by
WAPCOS.
All the 9 IPS locations have been
marked, project description board is
presented at the site and proper
fencing is done.
Location and required area of
proposed STP has also been
identified and marked on the
revenue map (Figure 5-4). Related
documents have been collected
from office of the Project Manager.
A total of 75 landowners have given
their consent for land purchase to
Jal Nigam for construction of STP
and pumping houses.
The land will be purchased through
Negotiation (Mutual Consent)
Policy, 2015 as peヴ GO No ‐ヲ/ヲヰヱヵ/ヲヱヵ/ Ek‐ヱン‐ヲヰヱヵ‐ 20(48)/2011 Rajaswa Anubhag-13
dt 19.03.2015 and subsequent
amendments thereof.
2 7th
Januar
y 2020
Lando
wner
near
85
MLD
STP,
Badsha
hpur
Md.
Meharban Ali
s/o Md Iliyas
(9456895254
)
During consultation the participant
intimated that the landowners have
given their voluntary consent for
land purchase to UP Jal Nigam.
Compensation for trees will also be
paid as per the policy.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-12
Sl
.
N
o.
Date
of
Consul
tation
Locatio
n
Name of the
Officials/Per
son met
Discussion Outcomes Photos
3 7th
Januar
y 2020
Local
Party
Leader
and
comm
unity
people
near
Pahalw
an
Peer
(IPS)
Shri Jiten
Sachdeva,
Shankar and
others
The proposed site identified by
UPJN is free of encumbrances.
Community people have expressed
their satisfaction for the proposed
project.
4 7th
Januar
y 2020
Mayor,
Sahara
npur
Munici
pal
Corpor
ation
Shri Sanjeev
Walia,
Mahapaur
(Mayor),
Saharanpur,
Er. Vedpal
Khewria,
Project
Engineer,
UPJN
Sh. Walia, Mayor assured
administrative support to the
project authority in this connection.
97. The project specific EMP to be prepared by the Concessionaire shall address respective suggestions provided
by the local community during the preparatory stage. :
► Access must be provided to shop owners/residential houses/schools and other users of community
► Excavation works on roads should be done with proper planning in order to avoid or minimize the disturbance to
local residents.
► Restoration of excavated roads/sites should be carried out on priority basis.
► Excessive amount of noise while during excavation works should be avoided.
► Appropriate measures should be adopted for dust suppression during construction works.
► Construction works should be regulated according to school timings, especially in adjacent areas of educational
institutions.
► The Concessionaire has to make sure that consultation/intimation to the respective gram panchayat before
initiating the construction activities at the STP site.
5.9 ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT
98. Based on the Environmental and Social Screening carried out as part of this due diligence exercise using the
screening matrix of the Environmental and Social Management Framework (ESMF of NGRBA, 2011)12
, the present
12 For the Environmental and Social Management Framework (ESMF) document please refer
https://www.nmcg.nic.in/writereaddata/fileupload/25_Namami_Gange_ESMF__August_17_2017__1___1_.pdf
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-13
project of I&D and STP scheme in Saharanpur have minimal temporary impacts and falls uミdeヴ けlow IマpaItげ Iategoヴy
(please refer Annexure-1 for the screening checklist). The major outcomes of the screening are given under:
► The proposed project for establishing various project components (i.e. STP, Pumping Stations, Staff quarters, etc.)
is neither located in any eco-sensitive area nor in any adjoining eco-sensitive area.
► There are about 7.8083 ha of private land purchase envisaged in the project. The identified land for the proposed
project belongs to 75 landowners.
► The screening also reiterates that the project does not involve loss of livelihood.
► The project will not have any impact on the tribal population.
► The project components have limited environment and social impacts, which can be mitigated with the adoption
of suitable mitigation measures by way of project specific Environmental Management Plan (EMP).
5.10 ENVIRONMENTAL AND SOCIAL MANAGEMENT ACTION PLAN
99. The Environmental and Social Management Action Plan (ESMAP) has been prepared to provide information
about the potential environmental and social impacts, proposed mitigation measures towards minimizing the impacts
and responsible agencies for implementation and monitoring. This ESMAP will also be included in the bid documents
and will be further reviewed and updated during implementation. The ESMAP will be made binding on all
Concessionaires operating on the site and will be included in the contractual clauses. Non-compliance with, or any
deviation from, the conditions set out in this document constitutes a failure in compliance. The major components of
the ESMAP are provided in Annexure-5.
5.11 CONSTRUCTION & OCCUPATIONAL HEALTH AND SAFETY
100. The Concessionaire who will be procured for the project on Hybrid Annuity Model, is liable to develop a
project specific EMP. The Concessionaire shall ensure that the following aspects are included and implemented on
site, complying with the provisions given in ESMF:
► Concessionaire shall adopt appropriate implementation mechanism for restoration of topsoil (to control soil
disturbance), dust suppression, use of DG sets in acoustic enclosure with proper stack height (for betterment of
Air), restoration of construction sites, etc.
► Appropriate training to be imparted to construction labourers regarding health and safety aspects.
Concessionaire shall provide the workers with PPEs and they shall be encouraged to consistently use the PPEs.
► Proper civil work schedule shall be in place and be included as part of EMP.
► Properly insulated electrical works shall be provided at respective STPs and in construction sites elsewhere.
► Integration of adequate safely aspects (Protection rails along walk ways at height) in STP.
► Adhering to the monitoring and reporting of the environment Management Measure applicable to the
construction stage wise.
5.12 IMPLEMENTATION ARRANGEMENT
101. State Mission for Clean Ganga-Uttar Pradesh (SMCG-UP) in an extended arm of National Mission for Clean
Ganga (NMCG) for the state of Uttar Pradesh and implementing the Namami Gange and other programmes through
various executing agencies. At state level it is implementing arm of State Ganga Committee constituted vide S.O. 3187
E dated 07th
October, 2016 under Environment protection act 1986. The Uttar Pradesh Jal Nigam (UPJN), Government
of Uttar Pradesh is functioning as the State Mission for Clean Ganga (SMCG) for the implementation of NBRGA
projects. The Uttar Pradesh Jal Nigam (UPJN), Saharanpur Zone which is headed by the Chief Engineer, U.P. Jal Nigam,
Ghaziabad and assisted by the Project Manager, U.P. Jal Nigam, Saharanpur; with assistance from Concessionaire and
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-14
Independent Engineer / Supervision Consultant is the responsible entity for ensuring the implementation of
mitigation measures as suggested in the ESMAP of the ESDDR.
5.13 GRIEVANCE REDRESS MECHANISM
102. Currently, NMCG has one GRM officer, who addresses all queries registered on the Centralized Public
Grievance Redress and Monitoring System (CP GRAM) portal of NMCG. The GRM officer is supported by one social
expert who helps to coordinate with all the state the SMCGs.
103. At SMCG level, reporting of grievances are being monitored by Environmental and Social experts. All
Executing Agencies have a GRM mechanism at each project site. The project manager and deputy project managers
are in-charge of these GRMs. To register grievances, a register has been kept at all project site offices and in some
sites sometime field team received grievances over mobile phones as well as on Whats App massages. The grievances
should be resolved by conducting monthly review meetings and if site team is unable to resolve the issue on its own,
the complaint/matter is brought up to Senior Management of EA.
104. ESDDR suggest establishing the similar grievance redress mechanism in Saharanpur site as well. Further, it is
also recommended to constitute a GRC in the PIU to record and redress public grievances. A dedicated team under
the supervision of the Project Engineer at UP Jal Nigam, Saharanpur could be appointed for recording the grievances.
The name and contact information of Grievance Redressal Officers (GROs) should be displayed at the
project/construction site, labour camps, in communities where construction work is taking place and in the websites
of ULB, EA and SMCG. Also, a toll free number should be generated and displayed in work sites for registering
grievances. A grievance reporting format is attached at Annexure-6.
5.14 GENDER ASSESSMENT, DEVELOPMENT
105. According to ESMF, the objective of Gender Assessment and Development is to analyse gender issues during
the preparation stage of sub projects, design interventions and primary data collection. The gender analysis shall be
carried out based on findings from gender specific queries and requirements during data collection and community
consultation process. The quantitative and qualitative analysis shall include sex disaggregated data, issues related to
gender disparity, needs, constraints, priorities and understanding of gender based inequitable risks, benefits and
opportunities as well as gender relevant indicators.
5.15 GENDER BASED VIOLENCE (GBV)
28. GBV is aミ uマHヴella teヴマ foヴ aミy haヴマful aIt that is peヴpetヴated agaiミst a peヴsoミげs ┘ill aミd that is Hased oミ socially ascribed gender differences. GBV includes acts that inflict physical, mental, sexual harm or suffering; threats
of such acts; and coercion and other deprivations of liberty, whether occurring in public or in private life. The project
site includes both the actual locations where civil works are conducted and also the associated areas such as the
loIatioミs of ┘oヴkeヴsげ Iaマps, ケuaヴヴies, etI. These GBV ヴisks ミeed to He assessed thヴoughout the pヴojeItげs life Hy monitoring the situation, assessing the effectiveness of risk mitigation measures, and adapting them.
29. Since a sub project involves construction work that will demand a constant supply of labourers, the influx of
migrant workforce can be a potential risk for the host population. The influx of labour force can lead to the risk of
Gender-Based Violence.
106. ESDDR in ESMAP suggests key actions and responsibilities of project partners. The interventions will be at
three levels, that of SPMG, EA and of the Contractor. According to guidelines of ESMAP on GBV prevention has been
prepared clearly defining the roles and responsibilities at all levels. Robust measures shall be prepared and
implemented to address the risk of gender based violence in the project and adjoining communities.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-15
5.16 INTEGRATION OF ESMAP WITH PROJECT
107. To ensure the implementation of safeguard measures by the Concessionaire, the ESMAP including the
preparation of project specific detailed ESAMP and necessary recommendation of ESSDDR will be included in the bid
document. The ESMAP clearly outlines the responsibility for various safeguard management actions associated with
the project activities related to Labour Management, Assessment of Gender Based Violence and Grievance Redress
Mechanism to ensure compliance of the same by follwing the safeguard requirements of the ESMF.
5.17 REQUIREMENTS FOR PREPARATION OF ESHS MANAGEMENT STRATEGIES AND IMPLEMENTATION
PLANS (ESHS-MSIP):
108. The Concessionaire shall submit comprehensive and concise Environmental, Social, Health and Safety
Management Strategies and Implementation Plans (ESHS-MSIP). These strategies and plans shall describe in detail the
actions, materials, equipment, management processes etc. that will be implemented by the Concessionaire, and its
subcontractors.
109. In developing these strategies and plans, the Concessionaire shall have regard to the ESHS provisions of the
Concession Agreement including those as may be more fully described in the following:
a. Works Requirements described in Concession Agreement;
b. Environmental and Social Impact Assessment (ESIA);
c. Environmental and Social Management Plan (ESMP);
d. Consent Conditions (regulatory authority conditions attached to any permits or approvals for the
project).
5.17.1 Requirements for the preparation of the Code of Conduct:
110. The Concessionaire shall submit the Code of Conduct that will apply to the Concessionaireげs employees and
Sub-contractors. The Code of Conduct shall ensure compliance with the ESHS provisions of the Concession
agreement, including those as may be more fully described in the following:
a. Works Requirements described in Concession Agreement;
b. Environmental and Social Impact Assessment (ESIA);
c. Environmental Management Plan (EMP);
d. Consent Conditions (regulatory authority conditions attached to any permits or approvals for the project).
Minimum requirements for the code of conduct
111. A minimum requirement for the Code of Conduct should be set out, taking into consideration the issues,
impacts, and mitigation measures identified in:
a. Project reports e.g. ESIA/ESMP
b. consent/permit conditions
c. required standards including World Bank Group EHS Guidelines and Performance Standards
d. national legal and/or regulatory requirements and standards (where these represent higher standards than
the WBG EHS Guidelines and PS)
e. relevant standards e.g. Workers Accommodation: Process and Standards (Indian Standards, and in
f. the absence of such Indian Standards those of IFC and EBRD)
g. relevant sector standards e.g. workers accommodation
h. grievances redress mechanisms
112. The types of issues identified could include risks associated with: labor influx, spread of communicable
diseases, sexual harassment, gender based violence, illicit behavior and crime, and maintaining a safe environment
etc. A satisfactory code of conduct will contain obligations on all project staff (including sub-contractors and day
workers) that are suitable to address the following issues, as a minimum.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5-16
5.17.2 Compliance with applicable laws, rules, and regulations of the jurisdiction
Compliance with applicable health and safety requirements (including wearing prescribed personal
protective equipment, preventing avoidable accidents and a duty to report conditions or practices
that pose a safety hazard or threaten the environment)
The use of illegal substances
Non-Discrimination (for example on the basis of family status, ethnicity, race, gender, religion,
language, marital status, birth, age, disability, or political conviction)
Interactions with community members (for example to convey an attitude of respect and nondiscrimination)
Sexual harassment (for example to prohibit use of language or behavior, in particular towards
women or children, that is inappropriate, harassing, abusive, sexually provocative, demeaning or
culturally inappropriate)
Violence or exploitation (for example the prohibition of the exchange of money, employment,
goods, or services for sex, including sexual favors or other forms of humiliating, degrading or
exploitative behavior)
Protection of children (including prohibitions against abuse, defilement, or otherwise unacceptable
behavior with children, limiting interactions with children, and ensuring their safety in project areas)
Sanitation requirements (for example, to ensure workers use specified sanitary facilities provided
by their employer and not open areas)
Avoidance of conflicts of interest (such that benefits, Concession Agreement, or employment, or
any sort of preferential treatment or favors, are not provided to any person with whom there is a
financial, family, or personal connection)
Respecting reasonable work instructions (including regarding environmental and social norms)
Protection and proper use of property (for example, to prohibit theft, carelessness or waste)
Duty to report violations of this Code
Non retaliation against workers who report violations of the Code, if that report is made in good
faith.
The Code of Conduct should be written in plain language and signed by each worker to indicate that they have:
received a copy of the code;
had the code explained to them;
acknowledged that adherence to this Code of Conduct is a condition of employment; and
understood that violations of the Code can result in serious consequences, up to and including dismissal, or
referral to legal authorities
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 6-1
6. FINDING“ OF GAP ANALY“I“
113. As prescribed in the ESMF, a Gap Analysis with respect to major environment and social attributes has been
done and the major observations are presented in Table 6-1 below :
Table 6-1: GAP Analysis Findings
Sl.
No.
Key Principles and Attributes GAP Remarks
1
Assessment of environmental
and social Impacts
To be complied
by
Concessionairing
authority
through their
Concessionaire
As per ESDDR study and screening checklist, the
present project is Iategoヴized as ha┗iミg けlow
IマpaItげ. The project does not trigger EIA notification
2006.
Construction of 85 MLD STP at village
Badshahpur near Dhamola River attracts Private
Land purchase of 7.8083 ha. And will be
purchased through UP Negotiation (Mutual
Consent) Policy, 2015 GO No ‐ヲ/ヲヰヱヵ/ヲヱヵ/ Ek‐ヱン‐ヲヰヱヵ‐ ヲヰふヴΒぶ/ヲヰヱヱ ‘ajas┘a AミuHhag-13 dt
19.03.2015. However the provisions of rights to
Fair compensation and transparency in land
acquisition, rehabilitation and resettlement act,
2013 and subsequent supplements by GoUP
shall prevail in case negotiation purchase fails.
The duration of associated impact shall be
during construction phase. This can be
mitigated through proper project specific
Environmental Management Plan (EMP)
prepared and implemented by the
Concessionaire under the supervision of UPJN,
Saharanpur Zone.
2
Implementation of Mitigation
and Management Measures
To be complied
during
construction and
operation stages
The Concessionaire to be procured on Hybrid
Annuity Model is mandated to prepare the project
specific EMP and get approval of NMCG / World
Bank.
3
Principle of Avoidance Complied To avoid the disturbance to local public as per the
procedure of GoI, 7 IPSs are proposed on available
vacant government land.
4
Linkages with other projects Not Applicable The proposed I&D and sewerage scheme of
Saharanpur is a fresh development project. There
is no linkage of projects.
5
Involuntary restriction of access
to legally designated parks and
protected areas
Not Applicable All the project components are planned within
government land; there is no involvement of any
designated parks and protected areas.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 6-2
Sl.
No.
Key Principles and Attributes GAP Remarks
6
Recognition of untitled persons
such as squatters and
encroachers including customary
rights
To be complied
by
Implementation
authority
Necessary care shall be taken care of by the
potential Concessionaire / Concessionaire to
avoid disturbance to neighborhood area under
supervision of concerned authority of UPJN,
Saharanpur Zone.
In order to address the E&S issues, site specific
EMP has to be prepared by Concessionaire and
get approved from competent authority of
UPJN.
7 Avoiding displacement of
Indigenous People
Not Applicable The project will neither displace nor have any
temporary disturbance on the indigenous people.
Planning
1
Threshold for Resettlement
Action Plan (RP)
Not Applicable Project purchases 7.81ha of private land.
Altogether, 75 private landowners are affected due
to the project. The project purchases private land
following Uttar Pradesh Negotiation (Mutual
Consent) Policy, 2015. All the affected landowners
have given the requisite consent for acquiring their
land.
Since the land is purchased through UP Negotiation
(Mutual Consent) Policy 2015, Resettlement Action
Plan is not required.
2 Need to replace / restore CPRs Not Applicable The project does not have any impact on CPRs.
3
Consultation and participation of
PAPs during project planning
Complied Consultation with local residents and various
stakeholder groups are conducted during
planning stage.
Temporary disturbances to public are envisaged
during excavation works, which will be
mitigated through appropriate measures in
ESMAP.
4
Participation of NGOs in project
planning
To be complied
by
Implementation
authority
NGOs are recognized as a major stakeholder group
in the project implementation stage, for awareness
creation about project activities and for ensuring
community participation. Consultation Framework
provided as part of Social Management Plan (in
ESMAP) suggests for conducting meetings with
NGOs to solicit feedback from local community.
5 Cut-off date Not Applicable Preliminary information has already been collected
by the Jal Nigam, Saharanpur
6
Definition of a family for R&R
assistance
Not Applicable Land Purchase through the Mutual Consent of UP
Govt. – seItioミ ミo. けKha, seヴial ミo. ヱヲ, マeミtioミs that as the rate of land has been decided taking
into consideration all previous and present
provisions, acts etc. Therefore, no R&R will be
applicable separately.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 6-3
Sl.
No.
Key Principles and Attributes GAP Remarks
7 Need and scope of census and
socio-economic surveys
Not Applicable Preliminary information has already been collected
by the Jal Nigam, Saharanpur.
8 Compensation Applicable Land compensation will be paid according to
through the Mutual Consent of UP Govt.
9 Primary Authority for Land
Purchase
Applicable Involvement of Revenue Department, Govt. of
Uttar Pradesh.
10 Principle to restore/improve
living standards
Not Applicable -
11 Compensation for land at
replacement value
Applicable Land compensation will be paid according to
through the Mutual Consent of UP Govt.
12 Treatment of depreciation and
Salvage
Not Applicable
13 Transaction and transition fee Not Applicable
14 Land for Land as an option for
compensation
Not Applicable
Resettlement Assistance
1 Cash assistance over and above
compensation Not Applicable
-
2 Assistance to poorest of the poor
or vulnerable category of people Not Applicable
Preliminary information has already been collected
by the Jal Nigam, Saharanpur
3
Provision of infrastructure and
public services at resettlement
sites
Not Applicable
Implementation
1 Implementation of RAP Not Applicable
Since the land is purchased through UP Negotiation
(Mutual Consent) Policy 2015, Resettlement Action
Plan is not required, hence preparation and
implementation of Resettlement Action Plan is not
required.
2 Participation of civil society in
implementation of RP Not Applicable
-
3
Opportunity for PAPs to
participate in planning, design
and implementation
Applicable
Project has already taken a participatory approach
in which the landowners were informed about the
project details (including benefits and impacts).
4 Disclosure of RAP Not Applicable
Since the land is purchased through UP Negotiation
(Mutual Consent) Policy 2015, Resettlement Action
Plan is not required, hence preparation and
disclosure of Resettlement Action Plan is not
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 6-4
Sl.
No.
Key Principles and Attributes GAP Remarks
required.
Grievance Redressal Mechanism
1 Procedure for dispute resolution
and appeals
To be complied by
Implementation
authority
GRM Cell already exists in SMCG level with
specific officer-in-charge. As practiced, a
Register should be consistently maintained at all
project site offices to report the grievances. The
grievances should be resolved by conducting
monthly review meetings and if site team is
unable to resolve the issue on its own, the
complaint/matter is brought up to Senior
Management of EA.
Further, it is recommended to constitute a GRC
in the PIU to record and redress public
grievances. A dedicated team under the
supervision of the Project Manager could be
appointed for recording the grievances. The
name and contact information of Grievance
Redressal Officers (GROs) should be displayed at
the project site, labour camps, in communities
where construction work is taking place and in
the websites of ULB, EA and SMCG. A toll free
number should be generated and displayed in
work sites for registering grievances.
A Grievance Register must be maintained in
Project offices and at each Construction site
followed by the Status of GBV Complaints -
Total Register, Resolved, Pending, and Type of
action taken.
2 Composition of Grievance
Redress Committee
3 Participation of representative of
PAPs and civil society
Monitoring
1 Independent monitoring
To be Complied
by
Implementation
Authority
ESMF provides for independent environment
and social compliance monitoring / audit by
third party inspection agency for each of the sub
projects. ESMAP should be accordingly
amended for implementation.
Independent Environment and
Social/Compliance Monitoring Audit by the third
party independent inspection agency shall be
carried out annual audits on basis of the
concessionaire monthly reports and Executive
Summary, as per the ESMF requirements of
NGRBA program.
The Audit process will check the environmental
and social categorization of subprojects,
adequacy of the project specific detailed
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 6-5
Sl.
No.
Key Principles and Attributes GAP Remarks
ESAMP, conformity to the requirements of
ESMF during project planning and
implementation as well as recommend specific
measures to include/improve the environment
and social management measures during
implementation
The safeguard monitoring and reporting
mechanisms of the project including the
Monthly Reports (MRs) and other status reports
on the implementation of environmental and
social safeguard measures shall also be audited
during the Independent Environment & Social
compliance Monitoring Audit, as well as provide
recommendations to improve the quality and
contents of these reports.
2 Periodic evaluation and
monitoring
To be Complied
by
Implementation
Authority
Internal Monitoring framework provided in ESMAP
should be updated to include parameters such as,
formation of GRC, site specific restoration of
excavated roads/construction sites, dust pollution,
greenery maintenance along the periphery of
project site, environmental monitoring (air, noise,
soil, water) and inclusion of project specific EMP in
the Bid / Contract Document.
Institutional Capacity
1
Provision of Environmental and
Social Experts in Executing
Agencies
To be Complied
by
Implementation
Authority
The proposed interventions involve numerous
construction activities. Accordingly, the
available Project Staffs of UP Jal Nigam,
Saharanpur Division; shall be trained and
assigned for monitoring as well as ensure
compliance of environmental and social
safeguard measures associated with the day to
day construction activities of the proposed
project.
At state level arrangement / deployment /
engagement one Environmental Expert and one
Social Expert at the UP Jal Nigam, Lucknow shall
be considered.
The Environmental Social Experts deployed at
the UP Jal Nigam, Lucknow; can provide
necessary guidance/training to the designated
Project Staffs of Executing Agencies, as and
when required, related to the implementation
of environmental and social safeguard
measures.
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 7-1
7. IMPLEMENTATION “CHEDULE AND RE“PON“IBILITY
114. The implementation schedule, responsibilities and respective time frame is tabulated below:
Table 7-1: Implementation Schedule and Associated Responsibilities
Sl.
No. Action Responsibility Timeframe
ENVIRONMENT SAFEGUARD
1
Prepare EMP & incorporate suitable
conditions in Contract to prepare and
implement ESMP by the
Concessionaire.
UP Jal Nigam /
SMCG
Detailed EMP shall be prepared by
Concessionaire before execution of the
project.
2
OHtaiミ けCoミseミtげ fヴoマ “tate Pollutioミ control Board for establishment and
operation of STPs.
UP Jal Nigam /
SMCG /
Concessionaire
Immediate and ensure that the works shall
be initiated after receiving the Consents.
3
Initiate implementation of the
recommended measures (presented
in Sect. 8.1.1 and 8.1.2).
UP Jal Nigam /
SMCG Throughout the project period.
DETAILED ENVIRONMENTAL MANAGEMENT PLAN
4
Preparation of detailed EMP (as per
the Contract) and obtain the approval
of the NMCG / Word Bank.
Concessionaire Within 3 months of the commencement of
Contract.
SOCIAL SAFEGUARDS
5
Purchase of additional 7.8083 ha. of
land for construction of 85 MLD-STP
and 2 IPS at Purani Police Chowki and
Paper mill road.
UP Jal Nigam /
SMCG /
Concessionaire
Encumbrance-free of land should be
handed over prior to the award of the
project / or start of civil works
6 Hiring of NGO/CBO for information
dissemination
UP Jal Nigam /
SMCG
Immediate/ Prior to disbursement of
retroactive claim under the project
7 Prepare IEC material UP Jal Nigam /
SMCG/NGO One Month after Action No. 6.
8 Establish GRC UP Jal Nigam /
SMCG Immediate
9 Designate Grievance Officer
UP Jal Nigam /
SMCG/
Concessionaire
Immediate
10 Information dissemination UP Jal Nigam /
SMCG/NGO Continuous after Action No. 7.
11 In- Country disclosure of this ESDDR UP Jal Nigam /
SMCG / NMCG
Immediate (Prior to initiation of Bidding
process)
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 8-1
8. RECOMMENDATION“
115. The Environmental and Social Due Diligence Report (ESDDR) is prepared by LEA Associates South Asia Private
Limited, New Delhi, on the basis of Detailed Project Report that has been prepared by UP Jal Nigam. Based on the
Environmental and Social Screening carried out as part of this due diligence exercise using the screening matrix of the
Environmental and Social Management Framework (ESMF of NGRBA, 2011)13
, the present project of I&D and STP
works iミ “ahaヴaミpuヴ, falls uミdeヴ けLow IマpaItげ Iategoヴy.
116. The project does not trigger EIA notification 2006 and its amendments. The project components have limited
environmental and social impacts during construction phase. These associated impacts can be mitigated through the
adoption of suitable mitigation measures in the form of project specific Environmental Management Plan (EMP)
prepared and implemented by the Concessionaire under the supervision of UP Jal Nigam.
117. The project requires 7.81 ha of private land and the land is being secured following Uttar Pradesh
Negotiation (Mutual Consent) Policy, 2015. The purchase of private land affects 75 landowners. Project authorities
have consulted the affected landowners and obtained requisite consent.
118. Based on the findings of due diligence exercise, the following recommendations are provided with an
objective to ensure compliance with the ESMF:
8.1 DESIGN AND PLANNING ASPECTS
► Suitable conditions shall be incorporated in the Bid/Contract documents to prepare and implement ESAMP by
the Concessionaire during the execution/operation stages.
► A detailed project specific ESAMP requires to be prepared by the Concessionaire before execution of the project
and shall obtain approval from the NMCG / World Bank
► Consent to Establish (CTE) for the establishment and Consent to Operate (CTO) for operation of STPs are
mandatory to obtain under Water (Prevention and Control of Pollution) Act 1972 and & Air (prevention and
Control of pollution) Act 1981 of Government of India; shall be obtained for the establishment of Sewage
Treatment Plant (STP), as this needs to be obtained prior to start of construction work.
► Consent conditions shall be complied with and compliance report shall be submitted periodically to the Uttar
Pradesh State Pollution Control Board (UPPCB).
► A detailed project specific EMP requires to be prepared by the Concessionaire during the project
execution/operation stages and shall obtain approval from the NMCG and the World Bank.
► The EMP once approved by the NMCG and World Bank shall be incorporated in the Bid/Contract documents, with
necessary amendments (if necessary) or agreements with the Concessionaire, and shall be fully complied during
the execution/operation stages.
► Appropriate measures should be taken to control/channelize the discharge of untreated effluent directly into the
river.
► Tree plantation along with landscaping around the STP is advised in order to improve the aesthetic value and also
to control bad odour.
► Permission for tree felling (if any) shall be obtained from the Forest Department.
► Permission shall be obtained for the use of water for construction purpose from irrigation department/CGWA
(for Surface or Ground Water) respectively.
13 For the Environmental and Social Management Framework (ESMF) document please refer
https://www.nmcg.nic.in/writereaddata/fileupload/25_Namami_Gange_ESMF__August_17_2017__1___1_.pdf
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 8-2
► Labour license requires to be obtained by Concessionaire prior to construction.
► Pollution under Control Certificate should be obtained for Construction Vehicles.
► Earth materials shall be procured from approved / licensed quarries.
► Higher capacity DG sets shall be complied with CPCB norms, adequate Stack Height and Acoustic Measure shall
be mandated.
► Formal Intimation to line department to be given regarding excavation works in order to avoid or minimize the
damages to existing utilities in the construction site.
► The Sewerage lines are planned beneath the existing road, so an alternative traffic management plan, diversion
plan or avoidance to traffic congestion plan shall be in place.
► A Gender Action Plan to be prepared to address the risk of gender based violence in the project and adjoining
communities.
► Orientation and sensitization training needs to be provided for all project staff and contractors, in particular,
safety supervisors and engineers on GBV at all levels.
► ICC committees addressing GBV need to be constituted at EA, SPMG and NMCG level.
► GBV needs to be integrated with GRM with special provisions, so, confidentiality/personal information can be
controlled /maintained.
► Periodic progress reporting (monthly, quarterly and yearly) requires to be done by the Concessionaire, and the
frequency of submission to EA/SMCG shall be revealed in the EMP.
► Independent Environment and Social/Compliance Monitoring Audit by the third party independent inspection
agency shall be carried out annually, as per the ESMF requirements of NGRBA program
8.2 DESIGN AND OPERATIONAL SPECIFIC
► Appropriate Sludge Management Plan shall be in place. Sludge generated from the STPs shall be disposed in
designated places without causing difficulty to public life.
► Concessionaire shall sign a Memorandum of Understanding (MoU) with the concerned competent authority prior
to the disposal of sludge at available landfill site authorized by MC/ULB
► Specific site needs to be identified for intermittent storage of waste from SPS and STP sites. A preliminary site for
intermittent storage of waste from SPS and STP has to be planned at available landfill site authorized by MC/ULB.
Concessionaire should also explore an alternate site before commencing the construction works.
► In coordination with the local agriculture / horticulture department, awareness programme shall be organized for
the local farmers for information dissemination related to the advantage of usage of sludge as manure for
agriculture purpose.
► Accumulated sludge and solid waste to be cleared within 24 hours and spraying of suitable herbicides on
accumulated sludge/solid waste to reduce odour.
► Ensure proper functioning of STP for digestion of sludge and ensure adequate functioning of dewatering units for
efficient functioning of system
► Periodic disposal of accumulated sludge/solid waste to designated land fill sites of the city
► Consideration shall be given for constructing garland drain around the site with small opening intermittently in
the boundary wall allowing rainwater to drain-off without accumulating in the adjacent residential areas.
► Excavated materials should be used for backfilling of the trench area, low lying areas of the site.
► Efficient site restoration measure shall be developed and checked regularly by assigned engineer to avoid the
public and traffic inconvenience.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 8-3
► Maintenance of site health (Air, water, Noise, Soil Quality) and safety of worker (OHS) shall be checked on regular
basis.
► To avoid inconvenience advance notice shall be circulated / given to the local residents, shop owners, vendors
and squatters.
► UP Jal Nigam shall adopt the public relation activities to disseminate the necessary information about the project
like (i) announcement on FM radio, (II) space in local newspaper, (III) printing and distributing pamphlets through
local newspaper vendors, and (IV) putting up information boards at construction site.
► UP Jal Nigam through the Concessionaire shall ensure (i) adequate safety measures during construction, (ii)
ensure uninterrupted access to residences and shops, (iii) sprinkle water to control dust, and (iv) restoration of
sites without delay.
► Local community shall be consulted before commencement of works at respective locations; this shall be
organized through awareness campaigns and disclosure of information related to the project components.
► EA (UP Jal Nigam) is advised to hire services of local NGOs/CBOs for information dissemination and public
consultations.
► Options shall be explored for biogas generation and energy recovery methods such as to prevent the excess
biogas from escaping into the atmosphere, an automatic biogas flaring system shall be provided which burns the
biogas that can convert into the electricity and reduces the emission of GHGs.
► Independent Environment and Social/Compliance Monitoring Audit by the third party independent inspection
agency shall be carried out annual audits on basis of the concessionaire monthly reports and Executive Summary,
as per the ESMF requirements of NGRBA program.
► The audit process will check the conformity of environmental and social categorization of investments, Audit the
adequacy of the ESMP and recommend practicable measures to include/improve the management measures and
Auditing the compliance of the Approved Investments.
► GRM cell already exists in SMCG level with specific officer-in-charge. As practiced, a register should be
consistently maintained at all project site offices to report the grievances. The grievances should be resolved by
conducting monthly review meetings and if site team is unable to resolve the issue on its own, the
complaint/matter is brought up to Senior Management of EA.
► Apart from that, a separate register shall be maintained by the Concessionaire in weekly meetings to address the
grievances (if any discussed and resolved). If the matter will not be resolved in weekly meeting, it will be
forwarded to higher level for decision
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | i
Annexures
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 1
ANNEXURE – 1: ENVIRONMENTAL AND SOCIAL SCREENING CHECKLIST
Project Title: Interception & Diversion with STP in Saharanpur
Implementing Agency: Uttar Pradesh Jal Nigam, Saharanpur
Project Cost: 547.8563 Crore
Project Components: Intermediate Pumping Stations (IPS) 9 Nos.
Construction of new Sewage Treatment Plant (STP) of capacity 85 MLD.
Operation & maintenance (O&M) for 15 years.
Installation of trash arresting rack and its regular O&M at the mouth of all drains.
Adequate provision for handling septage in the STP.
Project Location (Area / District): Saharanpur
Sl. No. Screening Criteria
Assessment of
Category
(High/ low)
Remarks / Explanatory note for categorisation
1
Is the project in an eco-sensitive area or
adjoining an eco-sensitive area? (Yes/No) If
Yes, which is the area? Elaborate impact
accordingly.
No impact
The various components of the proposed project at
Saharanpur is not located nearby any eco-sensitive
area and there is no such area within 10 Km.
2
Will the project create significant/ limited/
no social impacts? High Impact
Majorly project location is planned in the private land.
An option of acquiring additional 7.81 hectare of land
at Bhadshahpur and Shekpur Villages for STP and 2 IPS
locations in Saharanpur. The land purchase procedure
is in advanced stage as per Negotiation (Mutual
Consent) Policy, 2015 GO No -2/2015/215/Ek-13‐2015‐ 20(48)/2011 sub-section-13 dated 19.03.2015 and
subsequent amendments thereof.
Involuntary land taking resulting in loss of
income from agricultural land, plantation
or other existing land-use.
High Impact
Construction of 85 MLD STP at Bashadpur and Shekpur
villages, and it attracts Private Land purchase of 7.81
ha. and the impacted areas are agricultural land. The
land purchase procedure is in advanced stage as per
Negotiation (Mutual Consent) Policy, 2015 GO No -
2/2015/215/Ek-13‐2015‐ 20(48)/2011 Rajaswa
Anubhag-13 dated 19.03.2015 and subsequent
amendments thereof.
Involuntary land taking resulting in
relocation of title holder or non-titleholder
households.
No Impact
Land selected for proposed interventions is agriculture
land. Therefore it will not involve any relocation of
households.
Any reduction of access to traditional and
river dependent communities (to river and
areas where they earn for their primary or
substantial livelihood).
No Impact No displacement of river dependent communities is
envisaged.
Any displacement or adverse impact on
tribal settlement(s). No Impact
Not envisaged any displacement or adverse impact on
tribal settlement(s).
Any specific gender issues. No Impact
No gender specific issue directly related to the project
is envisaged. However, better sanitation facility will
improve health status of women in the area. Women
labourer will also get an employment during
construction.
3 Will the project create significant / limited
/ no environmental impacts during the
Low and short term
Impact The STP is proposed to be constructed in open and
vacant land at the existing STP site. Therefore, there
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 2
Sl. No. Screening Criteria
Assessment of
Category
(High/ low)
Remarks / Explanatory note for categorisation
construction stage? (significant / limited /
no impacts)
will be only short term / limited environmental impact.
The proposed lifting stations will be constructed in
govt. land, which are open areas. Therefore, it will
minimise the impact.
The proposed sewer line will be under the road with
minimum 3m or more road width.
Clearance of vegetation / tree-cover Low Impact No tree cutting is required.
Direct discharge of construction run-off,
improper storage and disposal of
excavation spoils, wastes and other
construction materials adversely affecting
water quality and flow regimes.
Low and short term
impact
The STP will be SBR type prefabricated units with
minimal civil works. The STP to be developed on fresh
land will have construction specific impact during civil
construction activity. With due care and management
direct discharge, improper storage of wastes shall be
taken care of.
The laying of sewer lines is not much in the proposed
project; however laying will cause some traffic
disruption of temporary nature.
Sensitive locations like schools, hospitals will have
special problems which will be taken care of during
construction.
Flooding of adjacent areas Low Impact
Construction of project will not obstruct any of natural
drain /channel near the site. The level of STPs and SPS
will be made with due care of high flood level record.
Dewatering for construction will not generate any
significant amount of water to flood adjacent areas.
Proposed STP and MPS will have garland drain to avoid
further flooding in premises and neighbourhood area
in case of storm water during monsoon.
Improper storage and handling of
substances leading to contamination of soil
and water
Low and short term
impact
Civil Construction material like cement, sand, earth
etc. will be prevalent in use, while contaminated
material such fuel, used oil shall be taken care of
properly for storage and handling properly at site.
Further the EMP shall be framed with inclusion of site
specific environmental issues to address the safety
health related issues·
Elevated noise and dust emission Low and short term
impact
Proper measure will be taken during sewer laying to
minimise the noise and dust emissions. Concessionaire
should ensure the proper acoustic measure for noise
generating unit like DG set as per CPCB norm, etc.
The Concessionaire has to submit the method
statement to comply with Air Act, 1981 and Noise
Rules as per EP Act, 1986 before construction.
Disruption to traffic movements Low and short term
Impact
No much sewer laying work are envisaged, but
construction of rising main and I&D network work will
need proper traffic management at the site.
Proper diversion of traffic will ensure less disruption
during construction. Concessionaire shall ensure the
proper traffic management in place prior to
construction activities.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 3
Sl. No. Screening Criteria
Assessment of
Category
(High/ low)
Remarks / Explanatory note for categorisation
Damage to existing infrastructure, public
utilities, amenities, etc.
Low and short term
Impact
Utility mapping of the existing infrastructure and
relocation of the same if required will minimise the
damage on existing infrastructure.
No much Sewer laying work is envisaged however
shifting of other utilities like telephone lines, electric
poles or street lights etc. if required shall be shifted
temporarily or relocated (only if needed) after taking
due permission from the concerned department.
Failure to restore temporary construction
sites
Low and short term
Impact
The roads will be reinstated to its original conditions
after laying of sewer line.
Mitigation measures towards restoration of temporary
construction sites will be part of ESMP of
Concessionaireげs Hid document.
Possible conflicts with and/or disruption to
local community No impact
The local community will be made aware of the
temporary nature of disruption.
All possible disputes during construction work shall be
avoided by hiring of local labour as much as possible.
In case of migrant labour hiring, the fundamental
facility in labour camp shall be ensured by
Concessionaire to avoid further disputes.
Health risks due to unhygienic conditions
at workers camps Low Impact
Adequate sanitation facilities and safety arrangement
will be provided to the workers to tackle on-site
hazards in construction camp. A site specific ESAMP
shall be having Health and hygiene maintenance plan
for project construction site, which will be part of BID
document for its completed implementation at sites.
Safety hazards during construction Low and short term
Impact
Proper health and safety statement will be submitted
by the Concessionaire and approved by The Engineer
prior to the construction. This will be included in
ESAMP and be part of Bid document.
4
Will the project create significant / limited
/ no environmental impacts during the
operational stage? (Significant / limited /
no impacts)
Limited
STP will have minimal odour and noise pollution.
Moreover, provision of green belt, landscaping within
the STP and SPS premised will reduce the negative
impact of odour.
The proposed projects of establishment of STP are
based on advance technologies of sewerage
wastewater treatment plan.
Flooding of adjacent areas Low Impact
Proposed STP and MPS will have garland drain to avoid
further flooding in premises and neighbourhood area
in case of storm water during monsoon.
Impacts to water quality due to effluent
discharge Low Impact
The characteristics of the treated wastewater from
SBR reactor will be within limit set by latest NGT /CPCB
guideline 2019.
Gas emissions Low Impact SBR or other Aerobic reactor is a compact system and
the possibility of the gas emission is very less.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 4
Sl. No. Screening Criteria
Assessment of
Category
(High/ low)
Remarks / Explanatory note for categorisation
Safety hazards Low Impact
Mechanised system and trained people will be
deployed to run the Pumping Stations and STPs will
reduce the risk of safety hazards.
Proper PPEs shall be ensured by the Concessionaire for
Concessionaire and Staff of STP/ MPS. First Aid
Measures shall be adhered as part of safety
management.
Emergency Site management plan shall be adhered to
the deputed STP area to avoid unsafe hazard like fire,
electricity etc.
5
Do projects of this nature / type require
prior environmental clearance either from
the MOEF&CC or from a relevant state
Government department?
(MOEF&CC/relevant State Government
department/ No clearance at all)
No clearance
required
The project is not an environmental sensitive project
and does not require clearance as per Environmental
Impact Assessment Notification 14th
“epteマHeヴげ ヲヰヰヶ. However, the proposed project needs Consent to
Establish (CTE) prior to start of construction of STP and
Consent to Operate (CTO) prior to start operation of
STP. These permissions are required from State
Pollution Control Board (UPPCB) under Air and Water
Act.
6
Does the project involve any prior
clearance from the MOEF&CC or State
Forest department for either the
conversion of forest land or for tree-
cutting? (Yes/ No). If yes, which?
No clearance
required
Overall Assessment Low
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 5
ANNEXURE – 2: MINUTES AND ATTENDANCE SHEETS OF STAKEHOLDER
AND COMMUNITY CONSULTATIONS
MINUTES OF MEETINGS
1. Discussion held with the officials of Nagar Nigam, Saharanpur
Date: 7th
January 2020 Time: 11 am
Venue: Office of the Project Manager, UP Jal Nigam, Saharanpur
Number of participants: 6
Attended by:
Sh. Rajendra Singh, Executive Engineer cum Project Manager, Sh. Abhay Kumar, Assist. Project Engineer, Sh. Prashant Kumar, Deputy Project Engineer, Sh. Janeshwar Pandey, Naib Tehsildar, Sh. Mahendra Pal, Lekhpal Sh. Pradeep Upadhyay, Ward Councillor, ward no.-39, MC Saharanpur
Shri Pradeep Upadhyay, Municipal Councillor, expressed his satisfaction and understands all the technical
features of the IPS.
Two proposed site i.e. (i) Mill Road and (ii) Kathiram Colony were visited by the officials and a sample video
of IPS process was shown to them.
The Ward Councillor intimated that the proposed project site located in the Kashiram Colony which is
within the Municipal limits.
The participants intimated that the proposed pumping station would make noise. Thus mitigation
measures should be adopted to reduce the impact of noise.
The participants thanked and assured all the cooperation during planning and implementation phases.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 6
Attendance Sheet of the Consultation conducted with officials of Nagar Nigam, Saharanpur
2. Discussion held with the Local Party Leader and community people near Peer Pahalwan IPS
Date: 7th
January 2020 Time: 3 pm
Venue: Pahalwan Peer (IPS)
Number of participants: 6
Attended by:
Sh. Jiten Sachdeva, Local Party Leader Sh. Shankar Sh. Vinod Sh. Vivek Sh. Aman Sh. Pankaj
Discussion was held in length about the purpose of the project and how it is beneficial for the State as well
as the nearby communities.
The laws and regulations as well as World Bank Safeguard policies applicable to the project were discussed.
Safety and precautionary measures were discussed to avoid any accidents during the construction phase of
the projects.
Community people welcomed the initiative of the proposed project to cater the pollution of the River
Yamuna.
The meeting was concluded with vote of thanks given by Sh. Jiten Sachdeva.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 7
Attendance Sheet of the Consultation conducted with Local Party Leader and community people near Peer
Pahalwan IPS
3. Discussion held with the Shri Sanjeev Walia, Mahapaur (Mayor), Saharanpur
Date: 7th
January 2020 Time: 5 pm
Venue: Office of the Mayor, Mahapaur, Saharanpur
Number of participants: 2
Attended by:
Sh. Sanjeev Walia, Mayor Sh. Vedpal Khewria, Project Engineer, UPJN
The meeting was held with Sh. Sanjeev Walia, Mayor regarding the proposed project of 9 pumping stations
and one STP.
The laws and regulations as well as World Bank Safeguard policies applicable to the project were discussed.
He intimated that for the required land, consent of landowners as per the Uttar Pradesh Negotiation
(Mutual Consent) Policy, 2015 has been taken.
He further thanked and assured all the cooperation during planning and implementation phases.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 8
Letter received from Sh. Sanjeev Walia, Mayor of Mahapaur, Saharanpur
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 9
ANNEXURE – 3: TEST REPORTS OF AIR QUALITY MONITORING CARRIED
OUT AT PROJECT LOCATION
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 10
Test Reports of Surface Water Quality Monitoring carried out at project location
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 11
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 12
Test Reports of Ground Water Quality Monitoring carried out at project location
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 13
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 14
Test Reports of Noise Quality Monitoring carried out at project location
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 15
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 16
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 17
Test Reports of Soil Quality Monitoring carried out at project location
Capture the photographs during sample collection-Saharanpur City
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 18
Surface Water –Downstream of Dhamola Noise testing at near Sapna Theatre, Saharanpur
Groundwater sample (Hand pump) near STP Ambient Air quality near STP, Tarapur
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 19
ANNEXURE – 4: TECHNICAL FEASIBILITY REPORT14 FOR SELECTED LAND FOR
PROPOSED 90 MLD STP AND 2 IPS
.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 20
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 21
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 22
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 23
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 24
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 25
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 26
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 27
ANNEXURE 4.1: CONSENT/MOU BETWEEN LANDOWNERS AND JAL NIGAM, SAHARANPUR
(This consent is for two survey numbers 174 and 175 and remaining surveys numbers are
also received in a similar line from the landowners)
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 28
ANNEXURE 4.2: MOU BETWEEN MUNICIPAL CORPORATION AND JAL NIGAM, SAHARANPUR ON
LANDFILL SITE FOR SLUDGE DISPOSAL
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 29
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 30
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
C A N A D A | I N D I A | A F R I C A | M I D D L E E A S T Page | 31
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 32
ANNEXURE – 5: ENVIRONMENTAL AND SOCIAL MANAGEMENT ACTION PLAN (ESMAP)
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
Pre-construction Stage
Statutory clearances (i.e. Environmental Clearances, Forest Land diversion, NOCs, Permits, etc.)
All statutory clearances required for Environmental
and Social aspects during construction shall be
ensured and made available prior to award of civil
works and/or before start of civil works.
Ensure that all necessary approvals for construction
to be obtained by Concessionaire are in place before
start of construction activities.
Acknowledge in writing and provide report on
compliance all obtained consents, permits, clearance,
NOCs, etc.
Include in detailed design drawings and documents all
conditions and provisions if necessary.
The Environment (Protection), Act, 1986
The Forest
(Conservation) Act, 1980
UP Jal Nigam / SMCG / Prospective Concessionaire
NMCG / UP Jal Nigam / SMCG
Before Construction
Consent to Establish (CTE) / Consent to Operate (CTO)
Consent to Establish (CTE) need to be obtained
prior to the start of STP construction work from the
State Pollution Control Board
Under the Air (Prevention and Control of Pollution) Act, 1981.
The Water (Prevention
and Control of Pollution) Act, 1974
HAM Concessioner NMCG/SMCG/Jal
Nigam Before start of construction work.
Tree Felling permission & transportation permission
The implementing agency prior to start of felling of
trees, should take tree felling permission from district
regulatory office like Divisional Forest Officer/ District
Collector Officer/Tree Officer.
Try to save the trees by adjusting the plant layout or
the alignment of sewage intake structures, sewer
mains, pumping stations, etc.
Provide adequate protection to the trees to be
retained with tree guards (e.g. Masonry tree guards,
low level RCC tree guards, circular iron tree guard
with Bars) as required.
The Indian Forest Act, 1927
HAM Concessionaire NMCG / UP Jal Nigam / SMCG
Pre-construction & Construction phase
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 33
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
Identify the number of trees that will be affected with
girth size & species type along the sewer mains,
pumping / lifting station sites and sewerage
treatment plant site. The details to be indicated on
map to scale and / or a strip map as may be
appropriate. Prepare tree cutting schedule to
facilitate clearance requirements.
Trees identified for felling shall be removed from the
construction sites before commencement of
construction with prior permission from the concerned
department.
Undertake tree plantation (not less than three rows
inside and along the boundary of STP, and
compensatory plantation as per the tree felling
clearances).
Compensatory plantation by way of re-plantation of at
least thrice / ten times as mention in the permission/
clearance letter and in line with competent authority
guidelines.
Utility Relocation
Identify the common utilities to be affected such as:
telephone cables, electric cables, electric poles, water
pipelines, public tabs, etc.
Identify and include list of affected utilities and
Concessionaire of these utilities in the detailed design
documents to prevent unnecessary disruption of
services during construction phase.
Affected utilities shall be relocated with prior approval
of the concerned agencies before construction starts.
Provide advance notice (not less than 10 working
days) to affected parties. The advance notice shall be
in the form of written notice and a grievance redressal
cell shall be established for timely addressing of
Prospective Concessionaire in collaboration and
approval of concerned department / UP Jal Nigam /
SMCG
Concerned department / UP
Jal Nigam / SMCG
Pre-construction & Construction phase
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 34
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
grievances.
Bid document to include requirement for a
Contingency Plan for service interruptions (For
example provision of water if disruption is more than
24 hours).
Concessionaire is required to prepare a contingency
plan to include actions to be taken in case of
unintentional interruption of services.
Labor Camps/ Stacking yard
The identification of locations of labor camps should
be finalized prior to the start of construction work.
The raw material stacking area should be identified
and get approved by the implementing agency prior
to start of construction work.
Concessionaire
SMCG / NMCG / Other
implementing agency
Disposal of treated wastewater
The construction activities at STP shall be initiated
only after Consent to Establish (CTE) certificate is
secured from the UPPCB.
The treated water quality shall comply with the
prescribed standards of the State Pollution Control
Board and NGT before let out into the
stream/nala/drain/open land/irrigation purposes.
Prospective Concessionaire
/ Concessionaires UP Jal Nigam /
SMCG
Pre-construction, Construction and Post Construction phase
Construction Stage
Natural sources of construction materials
Prioritize sites already permitted by the Department of
Mines and Geology.
Concessionaire to prepare list of approved quarry
sites and sources of materials with the approval of UP
Jal Nigam / SMCG.
Bid document to include requirement for verification of
suitability of sources and permit for additional quarry
sites if necessary.
The Concessionaire has to procure aggregate from
the identified authorized vendor who has all the
Vendor/Supplier should have prior approval for sand/ quarry material
mining under Amended EIA notification dated 15
th January, 2016.
Prospective Concessionaire / Concessionaires to finalize quarry sites and sources of
materials in consultation and approval of UP Jal
Nigam / SMCG
UP Jal Nigam / SMCG
Upon submission of work plan by the Concessionaire / Concessionaire.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 35
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
necessary approvals.
Storage of construction materials
The construction materials shall be stockpiled in
designated areas only.
The Concessionaire shall identify the site for
temporary use of land for construction sites / storage
of construction materials, etc. These sites shall be
operated only after prior approval of the engineer.
Prioritize areas within or nearest possible vacant
space in the project location.
Construction materials shall be stored on the high
laying areas and storing near to storm water run-off
channels or any low lying areas to be avoided.
If it is deemed necessary to locate elsewhere,
consider sites that will not promote instability and
result in destruction of property, vegetation,
irrigation, and drinking water supply systems.
Prospective Concessionaire
/ Concessionaires UP Jal Nigam /
SMCG
Pre-construction, Construction and Post Construction phase
Disposal of construction debris and excavated materials
Suitable site should be identified for safe disposal of
construction debris and excavated materials, in
relatively low lying areas, away from the water
bodies, residential and agricultural fields, etc., and
got approved by the engineer.
Ensure the site shall be selected preferably from
barren, infertile lands. In case agricultural land needs
to be selected, written consent from landowners (not
lessees) will be obtained for reuse of excess spoils.
Care should be taken that dumped material does not
affect natural drainage system.
Excavated soil and construction debris shall be
suitably stored to filling back the excavated areas
after placing the sewer lines.
Top soil generated during various construction
activities shall be used for agricultural purpose,
The Construction & Demolition Waste
Management Rules, 2016.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During construction
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 36
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
planned land filling and landscaping.
All the construction and demolition waste should be
disposed off at suitable location, complying with the
norms of government regulation.
All the plastic/ cement bags should be stored
properly and should be disposed through authorized
vendor.
The Plastic Waste Management Rules,
2016.
Pollution from fuel and lubricants
Care to be taken to store fuel and oil (if required) at a
place away from any drainage channel/nala
preferably to be stored in drums mounted on a
concrete paved platform.
The Concessionaire shall ensure that all
constructions vehicle parking location, fuel /
lubricants storage sites, vehicle machinery and
equipment. Maintenance and refueling sites will be
located at least 500m from rivers and irrigation
canal/ponds.
All location and layout plans of such sites submitted
by the Concessionaire prior to their establishment
and will be approved by the engineer.
Concessionaire shall ensure that all
vehicle/machinery and equipment operation.
Maintenance and refueling will be carried out in such
a fashion that spillage of fuels and lubricants does
not contaminate the ground.
Concessionaire will arrange for collection, storing
and disposal of oily wastes to the pre-identified
disposal sites (list to be submitted to Engineer) and
approved by the engineer. All spills and collected
petroleum products will be disposed off in
accordance with MoEF&CC and state PCB
guidelines.
Engineer will certify that all arrangements comply
Hazardous and Other Wastes
(Management and Transboundary
Movement) Rules, 2016
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 37
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
with the guidelines of PCB/MoEF&CC or any other
relevant laws.
Air pollution for emissions from the construction vehicles, equipment and machinery
Damp down exposed soil and any stockpiled
material on site by water sprinkling necessary during
dry weather.
Tarpaulins shall be to cover sand and other loose
material when transported by trucks.
All heavy equipment and machinery shall be fitted
with air pollution control devices.
Maintain construction vehicles and obtain “Pollution under Control” certificate from concerned Authority.
Ambient Air Quality monitoring has to be performed
as per the Environmental Monitoring Program.
The Concessionaire has to submit the method
statement to comply with Air Act, 1981 before
construction.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Decline of ground water quality
Ground water quality may get contaminated due to
leaching of wastewater. So, the treated water quality
shall comply with the standards laid down by the
CPCB for disposal onto land, water body or for
irrigation use.
Regular monitoring is required for the treated sewage
quality and also the ground water quality in the nearby
areas and ensures compliance with CPCB standards.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Water pollution from construction
The Concessionaire shall take all precautionary
measures to prevent the wastewater generated during
construction from entering into streams, water bodies
or the irrigation system. All waste arising from the
project is to be disposed off in the manner that is
acceptable by the Engineer.
STP operations shall take place only after Consent to
Operate (CTO) certificate is accorded by the UPPCB
and treated water quality shall comply with the
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 38
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
consent conditions stipulated by UPPCB or at
minimum shall meet the discharge standards
depending on the type of receiving water body
(stream / nala / drain / open land / irrigation purpose,
etc.).
Performance standards shall always be maintained,
ensuring efficient working condition of treatment plant.
Extraction of Ground Water
The extraction of ground water for construction work
should not be anticipated. If required, prior permission
from the SGWB is required.
The Concessionaire can utilize STP treated water, if
water quality meets the water quality requirement for
construction work.
He can use surface water, only after prior permission
form the regulatory authority.
The Environment (Protection) Act, 1986
Prospective Concessionaire / Concessionaires
SMCG/NMCG/Jal Nigam
During Construction Phase
Portable Water
Sufficient supply of portable water at all the
construction camp, active site, etc. should be
provided and maintained.
The water Quality should comply with
IS:10500 (2012) norms
Prospective Concessionaire / Concessionaires
MNCG/SMCG /Implementing
agency
During Construction phase/ Operation Phase
Flooding of adjacent areas
Garland drain shall be constructed within the
premises of proposed STP and MPS to avoid flooding
in premises and neighborhood area in case of storm
water during monsoon.
Stockpiled areas shall be bordered by berms.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation phases
Increased noise level due to construction activities
Provide curtains or sound barriers (poly sheets /
sheets) all around the construction site.
Proper maintenance of construction equipment and
vehicles.
The Concessionaire has to submit the method
statement to comply with Noise Rules as per EP Act,
1986 before construction.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation phases
Noise pollution due to operation of pumps and machineries
DG sets will be provided with acoustic enclosures.
No night time construction work should be anticipated
Green belt / tree plantation and landscaping will be
The Noise Pollution
(Regulation and Control) Rules, 2000
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation phases
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 39
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
developed along the periphery of the STP and SPS
which will attenuate noise.
Pump station in STP shall ensure minimum noise
generation by locating within a noise reducing
structure or in an enclosed space (such as
concrete/brick structure).
DG sets will be provided with acoustic enclosures.
Equipment’s need to meet the noise standards as prescribed by CPCB
15.
Ambient Air Quality monitoring with respect to Noise
should be carried out at all the construction site,
stacking yard, loading and unloading area, etc. as
per the general and specific condition of CTE.
Impact of surrounding areas
To avoid the problems of foul smell polluted air,
insects, noise pollution and other problems buffer
zones to be provided in the form of green belt
around the STP site, this has to be strictly ensured.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Protection of soil and Environmental enhancing
The 15 cm top soil should be stored at designated
location within the site. It should be stabilized using
seeding and mulching as preventive measures. It
can also be used for gardening purposes at STP site
as an environmental enhancing measure.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During construction
Settlement of backfilled area after construction
The backfilling material shall be free from petroleum
products, slag, cinders, ash or other material.
Backfilling activity should strictly follow the
construction schedule.
Proper compaction as per the soil condition and retain
the original level/ alignment.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
15 http://moef.gov.in/citizen/specinfo/noise.html
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 40
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
Information signs and hoardings
The Concessionaire shall provide, erect and maintain
informatory /safety signs, hoardings written in English
and local languages, whatever required or as
suggested by the Engineer.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Planning temporary traffic
Alternate traffic routing to be adopted in consultation
with traffic police authorities.
Temporary diversion will be provided with the
approval of the engineer. Detailed traffic control plans
will be prepared and submitted to the engineers for
approval, at least two weeks prior to commencement
of works.
Construction activities at commercial / business and
market areas must be completed on war footing basis
to minimize business loss.
The traffic control and plans shall contain details of
temporary diversion, details of traffic arrangements
after cessation of work each day, SIGNAGES, safety
measures for transport of hazardous materials and
arrangements of flagmen.
Any accidents and/or risk of inconveniences caused
to the community shall be borne by the
Concessionaire.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
Pre-construction, Construction and Post Construction phase
Disposal of treated wastewater
The treated water quality shall comply with the
prescribed standards of the State Pollution Control
Board and NGT before let out into the
stream/nala/drain/open land/irrigation purposes, and
necessary permission to be obtained from the
concerned department.
Ensure efficient working condition or treatment plant.
Prevent the pollution of stream water and other water
bodies receiving STP discharge.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
Pre-construction, Construction and Operation phase
Disposal of sludge Instead of disposing digested sludge it shall be CPHEEO; Manual on Prospective Concessionaire UP Jal Nigam / During
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 41
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
provided to the local farmers for agriculture purpose,
and/or to the local authorities to use as manure for
landscaping purposes in city level / district level.
Suitable site should be identified for the safe disposal
of sludge generated at the STP and got approved by
the Engineer. Prepare a Sludge Disposal Plan and
adheres to the same.
Concessionaire shall sign a Memorandum of
Understanding (MoU) with the concerned competent
authority prior to the disposal of sludge at available
landfill site authorized by MC/ULB.
Regular clearance of accumulated sludge and solid
waste will minimize odor nuisance.
A logbook for sludge disposal shall be maintained at
STP sites.
In coordination with the local agriculture / horticulture
department, awareness programme shall be
organized for the local farmers for information
dissemination related to the advantage of usage of
sludge as manure for agriculture purpose.
Sewerage and Sewage Treatment Systems -
2013
/ Concessionaires SMCG Construction and Operation
Compensatory plantation of trees
Compensatory plantation by way of re-plantation of
at least thrice / ten times as mention in the
permission/ clearance letter and in line with
competent authority guidelines.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
Pre-construction, Construction and Post Construction phase
Construction of labour camps
Concessionaire/Concessionaire shall follow all
relevant provisions of the Factories Act, 1948 and the
Building and the other Construction Workers
(Regulation of Employment and Conditions of
Service) Act, 1996 for construction and maintenance
of labour camp.
The location, layout and basic facility provision of
each labour camp will be submitted to Engineer prior
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During the Construction
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 42
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
to their construction.
The construction will commence only upon the written
approval of the Engineer.
The Concessionaire shall maintain necessary living
accommodation and ancillary facilities in functional
and hygienic manner and as approved by the
engineer.
All temporary accommodation must be constructed
and maintained in such a fashion that uncontaminated
water is available for drinking, cooking and washing.
The sewage system for the camp must be planned.
Adequate health care is to be provided for the work
force. The layout of the construction camp and details
of the facilities provided should be prepared shall be
approved by the engineer. The construction camp
shall not be located within 1000m from the nearest
water stream, residential areas and / or any sensitive
land uses like schools, hospitals, etc.
Labour camp & facilities
Settling up of labour camps needs to be done as per the procedures. Adequate potable water facilities, sanitation and drainage etc., in conformity with the Indian labour laws shall be ensured. The Concessionaire shall also guarantee the following: The location, layout and basic facility provision of
each labour camp will be submitted to Engineer prior
to their construction.
The construction will commence only upon the written
approval of the Engineer.
The Concessionaire shall construct and maintain all
labour accommodation in such a fashion that
uncontaminated water is available for drinking,
cooking and washing.
Supply of sufficient quantity of potable water (as per
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Pre-construction and Construction phase
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 43
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
IS) in every workplace/labour camp site at suitable
and easily accessible places and regular maintenance
of such facilities.
Separate Washrooms for female labour must be
constructed at the labour camps and each
construction sites.
The sewage system for the camp are designed, built
and operated in such fashion that no health hazards
occurs and no pollution to the air, ground water or
adjacent water courses take place. Ensure adequate
water supply is to be provided in all toilets and urinals.
Risk from Electrical Equipment
The Concessionaire shall take all required precautions to prevent danger from electrical equipment and ensure that – No material shall be stacked or placed as to cause
danger or inconvenience to any person or the public.
All necessary fencing and lights will be provided to
protect the public in construction zones.
All machines to be used in the construction will
conform to the relevant Indian Standards (IS) codes,
will be free from patent defect, will be kept in good
working order, will be regularly inspected and properly
maintained as per IS provision and to satisfaction of
the Engineer.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Safety aspects
Adequate precautions shall be taken to prevent the
accidents and from the machineries. All machines
used shall confirm to the relevant Indian standards
code and shall be regularly inspected.
The excavation and loose soil shall be maintained
with the provisions of shoring trench sides by placing
sheeting, timber shores, trench jacks, bracing, piles,
etc. to avoid collapse of soil.
Exposed surface shall be resurfaced and stabilized on
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During construction
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 44
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
priority basis.
Protective footwear and protective goggles to all
workers employed on mixing of materials like cement,
concrete etc.
Welder’s protective eye shields shall be provided to workers who are engaged in welding works.
Earplugs shall be provided to workers exposed to
loud noise, and workers working in crushing,
compaction, or concrete mixing operation.
The Concessionaire shall supply all necessary safety
appliances such as safety goggles, helmets, safety
belts, ear plugs, mask etc. to workers and staffs.
The Concessionaire will comply with all the
precautions as required for ensuring the safety of the
workmen as per the International Labour Organization
(ILO) convention No. 62 as far as those are applicable
to this contract. The Concessionaire will make sure
that during the construction work all relevant
provisions of the factories act, 1948 and Building and
other Conditions of Services) Act, 1996 are adhered
to.
The Concessionaire will not employ any person below
the age 14 years for any work and no woman will be
employed on the work of painting with products
containing lead in any form.
First Aid
The Concessionaire shall arrange for: Readily available first aid units including an adequate
supply of sterilized dressing materials and appliances
as per the Factories Rules I every work zone.
Availability of suitable transport at all times to take
injured or sick persons to the nearest hospital.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction
Livelihood If any impacts on livelihood of any permanent shop owners, licensed kiosks noticed during construction,
UP Jal Nigam / SMCG / Prospective Concessionaire
NMCG / UP Jal Nigam / SMCG
Pre-construction & Construction phase
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 45
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
then should be compensated according to the Entitlement Matrix of ESMF.
Impact on Community
If any temporary/Permanent impact on residential structures, land and assets and/or CPR will be occurred during construction, then should be compensated according to the Entitlement Matrix of ESMF.
UP Jal Nigam / SMCG /
Prospective Concessionaire NMCG / UP Jal Nigam / SMCG
Pre-construction & Construction phase
Possible conflicts with and/or disruption to local community
The local community will be made aware well in
advance of the temporary nature of disruption.
Community Consultations shall be conducted at all
the project locations prior to the initiation of
construction activities.
All possible disputes during construction work shall be
avoided by hiring of local labour as much as possible.
In case of migrant labour hiring, the fundamental
facilities in labour camp shall be ensured by
Concessionaire to avoid further disputes.
UP Jal Nigam / SMCG / Prospective Concessionaire
NMCG / UP Jal Nigam / SMCG
Pre-construction & Construction phase
Community Consultations
Consultations with community shall be conducted at
all the project locations and in nearby residential and
market area.
Information and awareness regarding GBV and GRM
should be disseminated in consultation
Minor grievances can be resolved through
consultation at the construction sites and
communities.
UP Jal Nigam / SMCG / Prospective Concessionaire
NMCG / UP Jal Nigam / SMCG
Pre-construction & Construction and Operation phase.
Grievance Redressal
The name and contact information of Grievance
Redressal Officers (GROs) should be displayed at the
project/construction site, labour camps, in
communities where construction work is taking place
and in the websites of ULB, EA and SMCG.
A grievance Register must be maintained and
monitored at each of the construction site.
Also, a toll free number should be generated and
displayed in work sites and websites of ULB, EA and
UP Jal Nigam / SMCG / Prospective Concessionaire
NMCG / UP Jal Nigam / SMCG
During Construction and Operation
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 46
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
SMCG for registering grievances.
Mandatory training’s for the workforce on the GBV grievance redressal mechanism for reporting and
response of GBV incidents
Training should be imparted to the stakeholders,
Implementing Agencies and Concessionaire
regarding identification, reporting, recording and
resolving the GBV cases.
Gender Assessment and Development
Employ female in construction and other project related activities.
A gender disaggregated details of labourers shall be maintained in register at all the projects sites.
Female participation in O&M, Monitoring & Evaluation processes
Training & Capacity Building of project staff focusing on Labour Standards
Orientation of project staff, contractors and other stakeholders regarding Gender Sensitive issues and Gender development indicators.
Subproject design should be Gender responsive.
Preparation and development of IEC (Information,
Education and Communication) material in the local
language on gender equality.
UP Jal Nigam / SMCG / Prospective
Concessionaire/Concessionaire
NMCG / UP Jal Nigam / SMCG
Pre-construction, During Construction and Operation phase
Gender Based Violence (GBV)
Mandatory and repeated training and awareness raising for the workforce about refraining from unacceptable conduct toward local community members, specifically women Informing workers about national laws that make sexual harassment and gender-based violence a punishable offence which is prosecuted; Introducing a Worker Code of Conduct as part of the employment contract and including sanctions for non-compliance (e.g., termination), Contractors adopting a policy to cooperate with law enforcement agencies in investigating complaints
Sexual Harassment of Women at Work Place (Prevention, Prohibition
and Redressal) Act, 2013
UP Jal Nigam / SMCG / Prospective
Concessionaire/Concessionaire
NMCG / UP Jal Nigam / SMCG
Pre-construction, During Construction and Operation phase
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 47
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
about gender-based violence. A small transport allowance, ideally allowing workers to regularly return for brief visits to their families, spouses, and friends, ICC committees addressing GBV and GRM need to be constituted at EA, SPMG and NMCG level. Prepare IEC material in the local language for policy against Sexual harassment at workplace and display in strategic locations Capacity Building of Social and Environment Specialists and project officials and project staff on GBV to be organized at regular intervals. Inclusion of consequences of GBV in safety induction. A Grievance Register must be maintained in Project offices and at each Construction site followed by the Status of GBV Complaints - Total cases, Resolved, Pending, and Type of action taken.
Operation Stage
Leakages, blockages and overflow issues in sewers
Bid document to include requirement for an effective
action plan to avoid and/or immediate clearance of
such leakages, blockages and overflow.
Implementation of regular O&M schedules.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Operation
Odour control
Adequate green belt / tree plantation and landscaping
will be developed along the periphery of the STP and
SPS will reduce the negative impact of odour.
Spraying of water will be done on the odour creating
units.
Spraying of herbicides like Maple and Gtech on
accumulated sludge/solid waste will reduce the
negative impact of odour.
Monitoring will be done on Ambient Air Quality around
STP site.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Operation
Septage Sludge Handling
The operator should encourage and considered fecal
sludge generated from the individual septic tank at the
Operator UP Jal Nigam /
SMCG During Operation
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 48
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
SPS and at the screening point of STP.
Care should be taken that the fecal sludge are diluted
as per the CPHEEO norms before discharging the
fecal sludge into pumping stations or at the screening
point of the STP.
Jal Nigam should identify a certain number of
pumping stations which would accept the fecal sludge
for final discharge into the STP network for treatment.
Each such location should be locality based up on the
distance and economic considerations
DPR, Saharanpur (Chapter 6)
Disposal of sludge
Instead of disposing digested sludge it shall be
provided to the local farmers for agriculture purpose,
and/or to the local authorities to use as manure for
landscaping purposes in city level / district level.
Suitable site should be identified for the safe disposal
of sludge generated at the STP and got approved by
the Engineer. Prepare a Sludge Disposal Plan and
adheres to the same.
Concessionaire shall sign a Memorandum of
Understanding (MoU) with the concerned competent
authority prior to the disposal of sludge at available
landfill site authorized by MC/ULB.
Regular clearance of accumulated sludge and solid
waste will minimize odor nuisance.
A logbook for sludge disposal shall be maintained at
STP sites.
In coordination with the local agriculture / horticulture
department, awareness programme shall be
organized for the local farmers for information
dissemination related to the advantage of usage of
sludge as manure for agriculture purpose.
CPHEEO; Manual on Sewerage and Sewage Treatment Systems -
2013
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and Operation
Noise pollution due to operation of pumps
DG sets will be provided with acoustic enclosures.
Green belt / tree plantation and landscaping will be
The Noise Pollution (Regulation and
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Construction and
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 49
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
and machineries developed along the periphery of the STP and SPS
which will attenuate noise.
Pump station in STP shall ensure minimum noise
generation by locating within a noise reducing
structure or in an enclosed space (such as
concrete/brick structure).
DG sets will be provided with acoustic enclosures.
Control) Rules, 2000 Operation phases
Protective Equipment’s
For Chlorination System the following mitigation measures will be in place to arrest/ identify any leakage of chlorine Neutralization System.
Leak Detection System.
Ventilation System
Appropriate personal protection equipment (PPE) including oxygen masks will be provided for personnel working in plants where there is a risk due to harmful gaseous emissions [Hydrogen sulphide (H2S), Carbon Monoxide (CO), Methane (CH4), etc.].
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Operation
Safety measures
Mechanised system and trained people shall be
deployed to run the Pumping Stations and STPs to
reduce the risk of safety hazards.
Handrails on both sides of walkways close to deeper
tanks and STPs needs to be ensured.
Smaller on and off switches at STP units to be
installed with protection from rain water to minimize
electrical short circuit
All personnel engaged in plant will be provided safety
clothing and Personal Protective Equipment’s (PPE) and also trained to implement Occupational Health
and Safety (OHS).
During storage and use of Hazardous Materials like
Chlorine etc. it will be ensured that chemicals and fuel
handling and storage is safe and materials do not
causing any damage.
Prospective Concessionaire / Concessionaires
UP Jal Nigam / SMCG
During Operation
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 50
Potential Impacts Mitigation Measures Reference Responsible for Implementation
Responsible for Monitoring
Time Frame
Chlorine will be stored in accordance with safety
standards and regulations in force.
Operating staff will be provided induction training on
safe handling, storage and precautions in use of
hazardous materials. Also directions will be given
regarding Chlorine emergency repair kits, and other
emergency procedures.
Leak detecting arrangements will be properly
provided in the plant.
Storage of large quantity of Chlorine will be avoided
and only procured based on need and accurate
inventory will be maintained.
Only approved instruments should be used for lifting
and opening cylinders.
Appropriate personal protection equipment (PPE)
including oxygen masks will be provided for personnel
cleaning underground sewers where there is a risk
due to oxygen deficiency and harmful gaseous
emissions [Hydrogen sulphide (H2S), Carbon
Monoxide (CO), Methane (CH4), etc.].
The contact details of police station, ambulance
services and fire stations nearby to the site shall be
displayed.
Draft Report Environmental and Social Due Diligence Report (ESDDR) for Interception
& Diversion and STP Scheme in Saharanpur
1.3
CANADA | ASIA | INDIA | AFRICA | MIDDLE EAST Page | 51
ANNEXURE – 6: GRIEVANCES REPORTING AND RECORDING FORMATS
Grievance Redress Mechanism
Format for recording grievances at investment level
Sl. No.
Name of the investment District Unique ID Date of
receipt
Name of the aggrieved person (if agreed by the
aggrieved person)
Details of the
complaint
Action taken
Date of action taken
Whether resolved/
Date
if not, reason thereof
Whether escalated
If yes, to whom
Date of escalation
Number of court cases
Number of court case resolved
(i) SMCG
(ii) NMCG
1
2
3
4
5
6
7
8
9
10