National Grid Carbon / DNV-GL Carbon Capture & Storage Upscaling Capital Cost Estimate Date: July 2015 Rev: B2 B2 10/07/2015 Updated with Revised Design Basis CRM BRM BRM B1 02/07/2015 Draft Issue for Client Comment CRM BRM BRM Rev No. Date Description Issued By Checked By Approved By Client Approval 1 Ref. Ares(2015)4291175 - 14/10/2015

Upload: trinhhanh

Post on 20-Mar-2018

243 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

 

National Grid Carbon / DNV-GL Carbon Capture & Storage Upscaling

Capital Cost Estimate

Date: July 2015 Rev: B2

B2 10/07/2015 Updated with Revised

Design Basis CRM BRM BRM

B1 02/07/2015 Draft Issue for Client

Comment CRM BRM BRM

Rev No.

Date Description Issued ByChecked

By Approved

By Client

Approval

1

Ref. Ares(2015)4291175 - 14/10/2015

Page 2: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Comments and Qualifications                 

2

Page 3: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV-GL

09/07/2015

Estimate Comments & Qualifications ‐ Rev B2 

 

1. Introduction 

 PCP Ltd was commissioned by DNV‐GL in June 2015 to prepare high‐level capital cost estimates for various carbon dioxide transpiration options as part of a feasibility study on behalf of National Grid Carbon for up‐scaling proposed carbon capture and storage facilities.  Option 1 proposes to transport CO2  from Rotterdam to the  injection  facility offshore North Sea  (Pipeline Option) whilst  Option  2  proposes  to  transport  CO2  by  ship  from  Rotterdam  to  a  facility  on  the  River Humber, from where a pipeline will connect into the proposed CCS Cross Country pipeline at Camblesforth multi‐junction (Shipping Option).  Three different cases have been considered for the study, each with a different CO2 flow rate as shown in 

Table 1. 

Table 1 CO2 Flow Rates 

Case CO2 Flow Rate 

(MTPA)  (m3/h) 

1  2  722 

2  5  1805 

3  7.32  2643 

 For the purpose of cost estimation, the following nomenclature will apply:  

Case 1A ‐ Pipeline Option, 2 MTPA (722 m3/h) 

Case 1B ‐ Pipeline Option, 5 MTPA (1805 m3/h) 

Case 1C ‐ Pipeline Option, 7.32 MTPA (2643 m3/h)  

Case 2A ‐ Shipping Option, 2 MTPA (722 m3/h) 

Case 2B ‐ Shipping Option, 5 MTPA (1805 m3/h) 

Case 2C ‐ Shipping Option, 7.32 MTPA (2643 m3/h)   

2. Cost Estimate Basis 

2.1. General Notes 

The  basis  of  this  estimate was  to  use  Level  1  estimating  techniques  from  PCP’s  Conceptual  Estimating manual. This manual  is  intended to enable the user to prepare a conceptual estimate with only a  limited amount of engineering information.    

2.2. Estimate Location Cost Factor 

Our  cost  estimating  system  is  based  on  construction  in  Northern  Europe  so  no  further  adjustment  is required.  

2.3. Estimate Date Basis 

The estimate has been prepared on a 2Q 2015 basis and no forward escalation is included. 

3

Page 4: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV-GL

09/07/2015

2.4. Exchange Rates 

 The estimate has been prepared in British Pounds. This estimate reflects the following exchange rates:   £1.00 GBP  = $1.55 USD £1.00 GBP  = €1.38 EUR  

2.5. Accuracy of Estimate 

This estimate was prepared using a Level 1 estimating methodology basis and should be considered to have an accuracy of +/‐40%   

3. Cost Estimating Methodology 

3.1. Process Equipment Pricing 

Major  process  equipment  items were  estimated  using  in‐house  proprietary  software  based  on  the  key technical  parameters.  For  the  purposes  of  the  estimate  it  has  been  assumed  that  the  large  scale  CO2 storage will be in LTCS spheres with a maximum diameter of 27m.  Offsites & Utility Units have been priced based analysis of the historical relationship between these units and the total process units cost based on data from the analysis of other production facility projects. It  is assumed the sites will be standalone with imported power supply. 

3.2. Process Plant ‐ Other Direct Costs 

The cost of bulk materials, such as piping, instrumentation, electrical materials, civil works, structural steel and their  field erection have been pro‐rated  from the equipment cost using  factors  from the Conceptual Estimating  manual.    These  factors  have  been  developed  from  an  extensive  analysis  of  the  historical construction costs of similar units.   

3.3. Shipping, Customs Clearance and Land Transport 

It is assumed that the majority of materials will be purchased from European suppliers. Shipping & customs clearance has been estimated using rates developed from historical analysis of similar projects.  

3.4. Construction Management 

It  is assumed that the field erection will be performed by a series of specialist subcontractors for each of the main disciplines such as civil works, piping etc and the EPC contractor will verify the quality of the work, co‐ordinate the contractors & generally to manage the construction effort.  These construction management costs have been  taken as a percentage of  the  total  field erection costs based on experience from other similar projects.  This  includes for the managing contractors construction staff, quantity surveyors, secretaries, clerks, staff accommodation  and  travel.    It  also  includes  the  temporary  offices, warehouses,  lay  down  areas,  office supplies  and  reproduction  costs,  general  support  (e.g.  drivers,  cleaners,  warehousemen,  material offloading gang, etc), electricity, fuel and maintenance, catering and communications. 

4

Page 5: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV-GL

09/07/2015

3.5. Design & Engineering, Procurement and Project Management  

The  engineering  design,  procurement  and  project management  hours  have  been  developed  using  data from the Conceptual Estimating Manual as a ratio to total construction manhours.  These  engineering  hours were  priced  at GBP  £80  per  hour;  this  rate  assumes  that  all  the  engineering activities will be carried out in Europe.  

3.6. Offshore Pipelines 

Pipeline material costs have been developed  from our proprietary estimating systems and cross‐checked against recent quotations obtained for other projects.  It should be noted that the lengths used as the basis of the estimate  include an allowance for route deviation and ‘overage’ developed from analysis of similar historical projects.    Weights  for  the anodes were generated using calculations  from  the PCP Subsea Estimating Systems and priced using in‐house data from recent projects.  The types,  lengths and thicknesses of corrosion coatings were generated using our proprietary estimating system.   The quantities and  lengths of the Tie‐In Spools were developed from the PCP Subsea Estimating Systems priced  at  current  average  costs  per  tonne  from  recent  projects  in  the  region.    Tie‐in  spool  installation durations were developed based upon the spool dimensions and weights and norms from the PCP Subsea Estimating Systems.    Route  and  Geophysical  Survey  durations  and  costs  have  been  taken  from  the  PCP  Subsea  Estimating Systems.    Pipeline  installation durations and costs have been developed using  the PCP Estimating Systems and are based on previous lay experience in the region.  Pipeline  installation  consumables  are  the  items  used  during  the  pipeline  installation  including welding materials, spacers, etc.  They have been included in the estimate based on a cost per pipeline joint for the PCP Subsea Estimating Systems which varies depends upon the line size etc. Pre/Post Lay Survey durations have been based on  continuous monitoring of  the pipeline  installation  and  rock dumping  activities  and priced at current project actual rates from recent project analysis.  It has been assumed that Pipeline trenching and backfill will not be required.  Quantities  for  gravel  dumping  has  been  taken  from  the  PCP  Subsea  Estimating  Systems  and  costs developed based upon the pipeline  lengths, diameters and criteria  in the PCP Pipeline Estimating System, including typical span  lengths and berm profiles.    It  is assumed that gravel dumping will only be required for span protection and limited lengths of pipeline protection.  It has been assumed  that  the entire  length of each of  the  tie‐in  spools will be protected with  concrete mattresses; quantities of mattresses  required  for  spool protection have been  calculated  from  the  spool dimensions using a typical mattress size of 6m x 3m.   Installation durations and mattress costs have been developed from a recent similar project in the region.  Hydrotesting and commissioning durations and costs have been developed based upon criteria  from  the PCP Subsea Estimating System.   

5

Page 6: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV-GL

09/07/2015

3.7. Owner’s Costs 

Owner’s  management  costs  cover  salaries,  departmental  overhead  costs,  travel  costs  and  outside consultants employed by the owner to control and manage the work.    Allowance  is also  included for  insurance and 3rd party verification which would normally come under the Owner’s scope.  

3.8. Contingency 

Contingency  is normally  applied  to  an  estimate  to provide  a  reasonable  level of  confidence of  avoiding project  overruns.    Owners’  contingency  is  normally  applied  to  cover  project  scope  changes  and  other unforeseen items.  It is not to cover items that could be reasonably anticipated, such as piping clashes, for which an allowance has been included in the base estimate.  Contingency has been added at 15% of the total EPC Cost.  

3.9. Operating Costs 

The  figures  for maintenance, operating personnel and  insurance costs have been calculated based upon the Capital Costs, using percentages developed from recent project experience.  Maintenance costs include for regular inspection, repair and replacement where necessary for all project elements.    Property overhead  costs  can  vary  very dramatically between different projects and  locations depending upon local authorities and government policy.  They have therefore been excluded from this operating cost estimate.  Imported Power has been based on a historical  cost per kwh. Fuel Gas  for  the Gas Heaters  is  currently excluded.   

4. Exclusions 

  Land Purchase Values and Pipeline ROW 

Major Site Preparation works such as large scale cut & fill, land reclamation etc. 

Operating & Capital Spares 

Import Duties and Local Taxes. 

License Fees. 

Finance Charges. 

Forward Escalation 

 

 

6

Page 7: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Overall Summary 

7

Page 8: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : All Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Option Comparison

CAPEX

Grand Total

(£UK)

PIPELINE OPTIONS

Pipeline Option ‐ Case 1A 617,534,311

Pipeline Option ‐ Case 1B 865,932,416

Pipeline Option ‐ Case 1C 1,130,502,292

SHIPPING OPTIONS

Shipping Option ‐ Case 2A 153,401,203

Shipping Option ‐ Case 2B 229,266,723

Shipping Option ‐ Case 2C 292,335,648

Description

8

Page 9: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : All Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Option Comparison

OPEX

Grand Total

(£UK)

PIPELINE OPTIONS

Pipeline Option ‐ Case 1A 6,891,872

Pipeline Option ‐ Case 1B 11,549,499

Pipeline Option ‐ Case 1C 14,674,548

SHIPPING OPTIONS

Shipping Option ‐ Case 2A 6,090,072

Shipping Option ‐ Case 2B 10,466,893

Shipping Option ‐ Case 2C 14,164,723

Description

9

Page 10: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1A                 

10

Page 11: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1A 

Summary 

11

Page 12: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ Overall Summary

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Onshore Facilities EPC Cost 23,807,776

Pipeline EPC Cost 441,238,064

Offshore Facilities EPC Cost 2,900,000

Total EPC Cost 467,945,840

Owner's Management 52,547,270

Third Party Inspection & Certification 9,459,985

CAR Insurance 9,507,249

Owner's Contingency 78,073,967

Forward Escalation Excluded

Total Pipeline Option ‐ Case 1A 617,534,311

Description

12

Page 13: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1A 

Onshore Facilities EPC Cost                

13

Page 14: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ Onshore Facilities

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

PROCESS UNITS

Pumping Station 5,873,187 1,858,770 3,568,839 11,300,797

Total Process & Storage 5,873,187 1,858,770 3,568,839 11,300,797

UTILITIES & INFRASTRUCTURE

Power Import 1,996,966 246,783 453,422 2,697,170

Firewater System 271,219 169,512 237,317 678,048

Service & Potable Water 226,016 141,260 197,764 565,040

Instrument Air 90,406 56,504 79,106 226,016

Open & Closed Drains 99,447 62,154 87,016 248,618

Vent System 226,016 141,260 197,764 565,040

Control System 625,000 78,125 703,125

Roads, Paving, Fences 463,710 463,710

Buildings 915,704 915,704

Sub‐Total Utilities & Infrast. 3,535,070 2,196,887 1,330,513 7,062,470

Total Direct Cost 9,408,257 4,055,657 4,899,353 18,363,267

Design & Engineering 3,127,245 3,127,245

Construction Management 2,317,265 2,317,265

Sub‐Total Indirects 5,444,510 5,444,510

Total EPC Cost 9,408,257 4,055,657 4,899,353 5,444,510 23,807,776

Description

14

Page 15: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ Pumping Station

Centrifugal Pumps, Metering Skid, Pressure Control Valves

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 3,507,114 3,507,114

Piping Material 1,332,703 1,332,703

Instruments 672,711 672,711

Electrical Material 245,498 245,498

Bulks Sub‐Total 2,250,912 2,250,912

Equipment Erection 280,569 280,569

Pipe Fabrication & Erection 1,753,557 1,753,557

Instrument Erection 420,854 420,854

Electrical Erection 350,711 350,711

Founds, Trenching & U/G Piping 1,157,348 1,157,348

Steelwork 420,854 420,854

Insulation 175,356 175,356

Paint 105,213 105,213

Scaffolding 561,138 561,138

Pre‐Commissioning / Commissioning 202,010 202,010

Labour Sub‐Total 1,858,770 3,568,839 5,427,610

Shipping and Freight 115,161 115,161

Direct Sub‐Total 5,873,187 1,858,770 3,568,839 11,300,797

Description

15

Page 16: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Metering Costing Program Report

Pipeline Option - Case 1A

by PCP Ltd

Metering Skids

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1A-1

Metering SkidMetering Description

Total SkidCost 1,531,190

Currency Basis UK

£

LiquidFluid Measured :

Turbine MeterMeter Type :

total flow capacity 722 m3/hr

Fiscal Meter

Comments

2 x 100%Meter Configuration :

18Line Size :

6Meter Size :

Inch

Inch

Each meter stream includes inlet and outlet isolation valves, strainer, pressure & temp instrumentation. Cost is for complete skid including interconnecting pipework, cabling, junction boxes, prefab shelter, flow computer and supervisory computer system.Also includes bi-directional prover with interconnecting pipework, valves & instrumentation

Total Skid Weight 36.3 Te

Item No.

THE PROJECT CONTROL PARTNERSHIP Metering Costing Program Version 15.10

16

Page 17: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pig Launchers and Receivers Costing Program Report

Pipeline Option - Case 1APig Launchers / Receivers

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1A-PL-1

Pig Launcher /RecieverDescription

Total Cost 134,704

Currency Basis UK

£

18Line Size (")

2500#Pressure Rating

Comments

Bi-Directional (Launcher/Type: Carbon SteelMaterial

Total Weight 8.4 Te

Item No.

PCP Ltd Pig Launcher / Receiver Costing Program Version 15.10

17

Page 18: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Pipeline Option - Case 1APumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

361.00Flowrate

112.00Differential Pressure

1A-1

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.31Specific Gravity

3682.88Head m

1500.00Motor Size KW

78.72Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

613,740

Total Pump Weight 14 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

361.00Flowrate

112.00Differential Pressure

1A-2

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.31Specific Gravity

3682.88Head m

1500.00Motor Size KW

78.72Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

613,740

Total Pump Weight 14 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

18

Page 19: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Pipeline Option - Case 1APumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

361.00Flowrate

112.00Differential Pressure

1A-3

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.31Specific Gravity

3682.88Head m

1500.00Motor Size KW

78.72Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

613,740

Total Pump Weight 14 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

19

Page 20: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ Power Import

4MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 1,645,218 1,645,218

Piping Material

Instruments

Electrical Material 312,591 312,591

Bulks Sub‐Total 312,591 312,591

Equipment Erection 82,261 82,261

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 345,496 345,496

Founds, Trenching & U/G Piping 115,165 115,165

Steelwork 82,261 82,261

Insulation

Paint 49,357 49,357

Scaffolding

Pre‐Commissioning / Commissioning 25,665 25,665

Labour Sub‐Total 246,783 453,422 700,205

Shipping and Freight 39,156 39,156

Direct Sub‐Total 1,996,966 246,783 453,422 2,697,170

Description

20

Page 21: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1A Checked by :  BRM

Currency Basis:  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 271,219 169,512 237,317 678,048

Service & Potable Water 226,016 141,260 197,764 565,040

Instrument Air 90,406 56,504 79,106 226,016

Open & Closed Drains 99,447 62,154 87,016 248,618

Vent System 226,016 141,260 197,764 565,040

Total Utilities & Infrastructure 913,104 570,690 798,966 2,282,761

Description

21

Page 22: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1A 

Pipeline EPC Cost                

22

Page 23: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate Summary Sheet

PREPARED BY PCP LTD

Project: Carbon Capture & Storage Date: July 2015

Location: Central North Sea Estimated by: CRM

Discipline: Pipeline Option ‐ Case 1A Checked by: BRM

Currency Basis: GBP Revision No: B2

Pipeline Option ‐ Case 1A ‐ Offshore Pipeline475 km, 18" N.B. 20.6 mm WT, 240 barg, X65

IndirectCosts

(£UK) (£UK) (£UK) (£UK) (£UK)

Offshore Pipelines

Linepipe & Misc. Materials Procurement 168,844,042 168,844,042

External Coating and Overweighting 14,984,140 14,984,140

Tie‐In Spools Fabrication and Installation 491,214 2,090,000 2,581,214

Pipeline Surveys & Installation 140,296,370 140,296,370

Pipeline Stabilisation and Protection 20,625 7,492,878 7,513,503

Pipeline Crossings 57,750 4,179,000 4,236,750

Risers & J‐Tubes 305,090 4,062,000 4,367,090

Hydrotesting and Commissioning 2,153,402 2,153,402

Transportation and Logistics 13,678,292 13,678,292

Total Offshore Pipelines 198,381,152 160,273,649 358,654,802

SSIV Structures

Procurement & Fabrication 4,962,817 1,901,792 6,864,609

SSIV Installation 2,280,000 2,280,000

Total SSIV Structures 4,962,817 1,901,792 2,280,000 9,144,609

Landfall

Shore Approach Pull & Tie In 10,600,000 10,600,000

Total Landfall 10,600,000 10,600,000

Detailed Design and Engineering 37,839,941 37,839,941

Purchasing, Expediting & Inspection 7,366,141 7,366,141

Project Management 17,632,572 17,632,572

Total EPC Pipeline Option ‐ Case 1A 203,343,969 1,901,792 173,153,649 62,838,654 441,238,064

DescriptionMaterial Fabrication Installation Total

23

Page 24: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15

Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2

Item : Pipeline Option ‐ Case 1A Currency Basis :  UK£

Pipeline Option ‐ Case 1A

Unit Cost Installation Material Fab. Installation Indirect Total

Item No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

Pipeline Option ‐ Case 1A

Length Width

1. Linepipe & Misc. Materials Procurement 1           Lot 168,844,042 168,844,042

2. External Coating and Overweighting 1           Lot 14,984,140 14,984,140

3. Tie‐In & Expansion Spools Fabrication & Installation 1           Lot 21.25 491,214 2,090,000 2,581,214

4. Pipeline Surveys & Installation 1           Lot 891.77 140,296,370 140,296,370

5. Pipeline Stabilisation and Protection 1           Lot 150.25 20,625 7,492,878 7,513,503

6. Pipeline Crossings & Guard Boats 1           Lot 147.0 57,750 4,179,000 4,236,750

8. Risers & J‐Tubes 1           Lot 115.0 305,090 4,062,000 4,367,090

7. Hydrotesting and Commissioning 1           Lot 2,153,402 2,153,402

8. Transportation and Logistics 1           Lot 13,678,292 13,678,292

9. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ Pipeline Option ‐ Case 1A 1,325.27 198,381,152 160,273,649 358,654,802

Item and Description

24

Page 25: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2Item : SSIV Structures Currency Basis :  UK£

SSIV Structures

Unit Cost Installation Material Fab. Installation Indirect TotalItem No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

SSIV Structures

Length Width1. Procurement & Fabrication 1           Lot 4,962,817 1,901,792 6,864,6092. SSIV Installation 1           Lot 12.0 2,280,000 2,280,000

3. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ SSIV Structures 12 4,962,817 1,901,792 2,280,000 9,144,609

Item and Description

25

Page 26: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2Item : Landfall Construction Currency Basis :  UK£

Landfall Construction

Unit Cost Installation Material Fab. Installation Indirect TotalItem No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

Landfall ConstructionLength Width

1. Pipeline Shore Approach Pull‐In & Tie‐In 1           Lot 10,600,000 10,600,0002. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ Landfall Construction 10,600,000 10,600,000

Item and Description

26

Page 27: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1A 

Offshore Facilities EPC Cost                

27

Page 28: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1A Checked by :  BRM

Currency Basis:  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ Offshore  Facilities

Scope:

Pig Reciever, Flow Control Valve, 50m of Piping to Tie‐in to existing injection header

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Offshore Facilities 883,599 300,722 605,085 1,110,594 2,900,000

Total Offshore Facilities 883,599 300,722 605,085 1,110,594 2,900,000

Description

28

Page 29: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1A 

OPEX                

29

Page 30: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

GL Noble Denton

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1A ‐ OPEXp p

Category Qty Unit Unit Cost (£) OPEX Cost (£)

ONSHORE

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 285,693 285,693

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 309,501 309,501

Insurance

Insurance to cover material damage 1 Lot 238,078 238,078

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 33,600,000 KWH 0.07 2,419,200

PIPELINE

Maintenance & Operating Costs

Annual Maintenance, Inspections and Remedial Works 1 Lot 1,346,209 1,346,209

Insurance

Insurance to cover material damage 1 Lot 2,293,190 2,293,190

Property Overheads

Property Taxes and Overheads ExcludedProperty Taxes and Overheads xcluded

Utilities, Catalysts & Chemicals

Corrosion Inhibitor and Other Chemicals 0 Lot Not Required

Total Annual Operating Cost 6,891,872

30

Page 31: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1B 

31

Page 32: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1B 

Summary                

32

Page 33: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ Overall Summary

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Onshore Facilities EPC Cost 39,889,478

Pipeline EPC Cost 613,693,596

Offshore Facilities EPC Cost 3,250,000

Total EPC Cost 656,833,074

Owner's Management 72,769,463

Third Party Inspection & Certification 13,158,149

CAR Insurance 13,731,349

Owner's Contingency 109,440,381

Forward Escalation Excluded

Total Pipeline Option ‐ Case 1B 865,932,416

Description

33

Page 34: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1B 

Onshore Facilities EPC Cost                

34

Page 35: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ Onshore Facilities

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

PROCESS UNITS

Pumping Station 10,294,363 3,312,716 6,360,414 19,967,493

Total Process & Storage 10,294,363 3,312,716 6,360,414 19,967,493

UTILITIES & INFRASTRUCTURE

Power Import 3,394,842 419,531 770,818 4,585,190

Firewater System 479,220 299,512 419,317 1,198,050

Service & Potable Water 399,350 249,594 349,431 998,375

Instrument Air 159,740 99,837 139,772 399,350

Open & Closed Drains 175,714 109,821 153,750 439,285

Vent System 399,350 249,594 349,431 998,375

Control System 625,000 78,125 703,125

Roads, Paving, Fences 814,255 814,255

Buildings 1,571,112 1,571,112

Sub‐Total Utilities & Infrast. 5,633,215 3,813,256 2,260,644 11,707,116

Total Direct Cost 15,927,578 7,125,972 8,621,059 31,674,609

Design & Engineering 4,125,596 4,125,596

Construction Management 4,089,273 4,089,273

Sub‐Total Indirects 8,214,869 8,214,869

Total EPC Cost 15,927,578 7,125,972 8,621,059 8,214,869 39,889,478

Description

35

Page 36: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ Pumping Station

Centrifugal Pumps, Metering Skid, Pressure Control Valves

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 6,250,407 6,250,407

Piping Material 2,375,155 2,375,155

Instruments 1,029,423 1,029,423

Electrical Material 437,528 437,528

Bulks Sub‐Total 3,842,106 3,842,106

Equipment Erection 500,033 500,033

Pipe Fabrication & Erection 3,125,204 3,125,204

Instrument Erection 750,049 750,049

Electrical Erection 625,041 625,041

Founds, Trenching & U/G Piping 2,062,634 2,062,634

Steelwork 750,049 750,049

Insulation 312,520 312,520

Paint 187,512 187,512

Scaffolding 1,000,065 1,000,065

Pre‐Commissioning / Commissioning 360,023 360,023

Labour Sub‐Total 3,312,716 6,360,414 9,673,130

Shipping and Freight 201,850 201,850

Direct Sub‐Total 10,294,363 3,312,716 6,360,414 19,967,493

Description

36

Page 37: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Metering Costing Program Report

Pipeline Option - Case 1B

by PCP Ltd

Metering Skids

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1B-1

Metering SkidMetering Description

Total SkidCost 1,939,553

Currency Basis UK

£

LiquidFluid Measured :

Turbine MeterMeter Type :

total flow capacity 1806 m3/hr

Fiscal Meter

Comments

2 x 100%Meter Configuration :

26Line Size :

10Meter Size :

Inch

Inch

Each meter stream includes inlet and outlet isolation valves, strainer, pressure & temp instrumentation. Cost is for complete skid including interconnecting pipework, cabling, junction boxes, prefab shelter, flow computer and supervisory computer system.Also includes bi-directional prover with interconnecting pipework, valves & instrumentation

Total Skid Weight 49.3 Te

Item No.

THE PROJECT CONTROL PARTNERSHIP Metering Costing Program Version 15.10

37

Page 38: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pig Launchers and Receivers Costing Program Report

Pipeline Option - Case 1BPig Launchers / Receivers

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1B-PL-1

Pig Launcher /RecieverDescription

Total Cost 208,567

Currency Basis UK

£

28Line Size (")

2500#Pressure Rating

Comments

Bi-Directional (Launcher/Type: Carbon SteelMaterial

Total Weight 12.9 Te

Item No.

PCP Ltd Pig Launcher / Receiver Costing Program Version 15.10

38

Page 39: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Pipeline Option - Case 1BPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

903.00Flowrate

123.00Differential Pressure

1B-1

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.32Specific Gravity

3918.20Head m

4100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

1,367,429

Total Pump Weight 28 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

903.00Flowrate

123.00Differential Pressure

1B-2

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.32Specific Gravity

3918.20Head m

4100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

1,367,429

Total Pump Weight 28 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

39

Page 40: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Pipeline Option - Case 1BPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

903.00Flowrate

123.00Differential Pressure

1B-3

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.32Specific Gravity

3918.20Head m

4100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

1,367,429

Total Pump Weight 28 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

40

Page 41: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ Power Import

9 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 2,796,871 2,796,871

Piping Material

Instruments

Electrical Material 531,405 531,405

Bulks Sub‐Total 531,405 531,405

Equipment Erection 139,844 139,844

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 587,343 587,343

Founds, Trenching & U/G Piping 195,781 195,781

Steelwork 139,844 139,844

Insulation

Paint 83,906 83,906

Scaffolding

Pre‐Commissioning / Commissioning 43,631 43,631

Labour Sub‐Total 419,531 770,818 1,190,348

Shipping and Freight 66,566 66,566

Direct Sub‐Total 3,394,842 419,531 770,818 4,585,190

Description

41

Page 42: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipleine Option Case 1B Checked by :  BRM

Currency Basis:  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 479,220 299,512 419,317 1,198,050

Service & Potable Water 399,350 249,594 349,431 998,375

Instrument Air 159,740 99,837 139,772 399,350

Open & Closed Drains 175,714 109,821 153,750 439,285

Vent System 399,350 249,594 349,431 998,375

Total Utilities & Infrastructure 1,613,373 1,008,358 1,411,702 4,033,434

Description

42

Page 43: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1B 

Pipeline EPC Cost                

43

Page 44: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate Summary Sheet

Prepared by PCP LTD

Project: Carbon Capture & Storage Date: July 2015

Location: Central North Sea Estimated by: CRM

Discipline: Pipeline Option ‐ Case 1B Checked by: BRM

Currency Basis: GBP Revision No: B2

Pipeline Option ‐ Case 1B ‐ Offshore Pipeline475 km, 24" N.B. 27.0 mm WT, 250 barg, X65

IndirectCosts

(£UK) (£UK) (£UK) (£UK) (£UK)

Offshore Pipelines

Linepipe & Misc. Materials Procurement 261,043,014 261,043,014

External Coating and Overweighting 19,504,308 19,504,308

Tie‐In Spools Fabrication and Installation 774,509 2,470,000 3,244,509

Pipeline Surveys & Installation 175,086,370 175,086,370

Pipeline Stabilisation and Protection 20,625 9,207,416 9,228,041

Pipeline Crossings 57,750 4,179,000 4,236,750

Risers & J‐Tubes 444,539 4,870,000 5,314,539

Hydrotesting and Commissioning 2,974,464 2,974,464

Transportation and Logistics 23,917,802 23,917,802

Total Offshore Pipelines 305,762,546 198,787,249 504,549,795

SSIV Structures

Procurement & Fabrication 5,474,377 1,901,792 7,376,169

SSIV Installation 3,800,000 3,800,000

Total SSIV Structures 5,474,377 1,901,792 3,800,000 11,176,169

Landfall

Shore Approach Pull & Tie In 10,600,000 10,600,000

Total Landfall 10,600,000 10,600,000

Detailed Design and Engineering 52,632,596 52,632,596

Purchasing, Expediting & Inspection 10,314,441 10,314,441

Project Management 24,420,595 24,420,595

Total EPC Pipeline Option ‐ Case 1B 311,236,923 1,901,792 213,187,249 87,367,632 613,693,596

DescriptionMaterial Fabrication Installation Total

44

Page 45: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15

Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2

Item : Pipeline Option ‐ Case 1B Currency Basis :  UK£

Pipeline Option ‐ Case 1B

Unit Cost Installation Material Fab. Installation Indirect Total

Item No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

Pipeline Option ‐ Case 1B

Length Width

1. Linepipe & Misc. Materials Procurement 1              Lot 261,043,014 261,043,014

2. External Coating and Overweighting 1              Lot 19,504,308 19,504,308

3. Tie‐In & Expansion Spools Fabrication & Installation 1              Lot 25.50 774,509 2,470,000 3,244,509

4. Pipeline Surveys & Installation 1              Lot 1,084.06 175,086,370 175,086,370

5. Pipeline Stabilisation and Protection 1              Lot 184.75 20,625 9,207,416 9,228,041

6. Pipeline Crossings & Guard Boats 1              Lot 147.0 57,750 4,179,000 4,236,750

8. Risers & J‐Tubes 1              Lot 131.0 444,539 4,870,000 5,314,539

7. Hydrotesting and Commissioning 1              Lot 2,974,464 2,974,464

8. Transportation and Logistics 1              Lot 23,917,802 23,917,802

9. Design, Engineering & Project Management 1              Lot

Total ‐ Offshore Pipelines ‐ Pipeline Option ‐ Case 1B 1,572.31 305,762,546 198,787,249 504,549,795

Item and Description

45

Page 46: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2Item : SSIV Structures Currency Basis :  UK£

SSIV Structures

Unit Cost Installation Material Fab. Installation Indirect TotalItem No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

SSIV Structures

Length Width1. Procurement & Fabrication 1           Lot 5,474,377 1,901,792 7,376,1692. SSIV Installation 1           Lot 20.0 3,800,000 3,800,000

3. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ SSIV Structures 20 5,474,377 1,901,792 3,800,000 11,176,169

Item and Description

46

Page 47: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2Item : Landfall Construction Currency Basis :  UK£

Landfall Construction

Unit Cost Installation Material Fab. Installation Indirect TotalItem No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

Landfall ConstructionLength Width

1. Pipeline Shore Approach Pull‐In & Tie‐In 1           Lot 10,600,000 10,600,0002. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ Landfall Construction 10,600,000 10,600,000

Item and Description

47

Page 48: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1B 

Offshore Facilities EPC Cost                

48

Page 49: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1B Checked by :  BRM

Currency Basis:  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ Offshore  Facilities

Scope:

Pig Reciever, Flow Control Valve, 50m of Piping to Tie‐in to existing injection header

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Offshore Facilities 1,087,142 310,693 653,221 1,198,945 3,250,000

Total Offshore Facilities 1,087,142 310,693 653,221 1,198,945 3,250,000

Description

49

Page 50: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1B 

OPEX                

50

Page 51: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

GL Noble Denton

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1B ‐ OPEXp p

Category Qty Unit Unit Cost (£) OPEX Cost (£)

ONSHORE

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 478,674 478,674

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 518,563 518,563

Insurance

Insurance to cover material damage 1 Lot 398,895 398,895

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 75,600,000 KWH 0.07 5,443,200

PIPELINE

Maintenance & Operating Costs

Annual Maintenance, Inspections and Remedial Works 1 Lot 1,544,200 1,544,200

Insurance

Insurance to cover material damage 1 Lot 3,165,968 3,165,968

Property Overheads

Property Taxes and Overheads ExcludedProperty Taxes and Overheads xcluded

Utilities, Catalysts & Chemicals

Corrosion Inhibitor and Other Chemicals 0 Lot Not Required

Total Annual Operating Cost 11,549,499

51

Page 52: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1C                 

52

Page 53: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1C 

Summary                

53

Page 54: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ Overall Summary

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Onshore Facilities EPC Cost 48,283,653

Pipeline EPC Cost 805,720,533

Offshore Facilities EPC Cost 3,625,000

Total EPC Cost 857,629,185

Owner's Management 94,985,206

Third Party Inspection & Certification 17,274,358

CAR Insurance 17,721,383

Owner's Contingency 142,892,159

Forward Escalation Excluded

Total Pipeline Option ‐ Case 1C 1,130,502,292

Description

54

Page 55: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1C 

Onshore Facilities EPC Cost                

55

Page 56: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ Onshore Facilities

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

PROCESS UNITS

Pumping Station 12,817,401 4,136,123 7,941,357 24,894,880

Total Process & Storage 12,817,401 4,136,123 7,941,357 24,894,880

UTILITIES & INFRASTRUCTURE

Power Import 3,847,487 475,468 873,593 5,196,549

Firewater System 597,477 373,423 522,792 1,493,693

Service & Potable Water 497,898 311,186 435,660 1,244,744

Instrument Air 199,159 124,474 174,264 497,898

Open & Closed Drains 219,075 136,922 191,691 547,687

Vent System 497,898 311,186 435,660 1,244,744

Control System 625,000 78,125 703,125

Roads, Paving, Fences 987,641 987,641

Buildings 1,816,604 1,816,604

Sub‐Total Utilities & Infrast. 6,483,994 4,536,905 2,711,786 13,732,685

Total Direct Cost 19,301,395 8,673,029 10,653,143 38,627,566

Design & Engineering 4,647,067 4,647,067

Construction Management 5,009,019 5,009,019

Sub‐Total Indirects 9,656,087 9,656,087

Total EPC Cost 19,301,395 8,673,029 10,653,143 9,656,087 48,283,653

Description

56

Page 57: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ Pumping Station

Centrifugal Pumps, Metering Skid, Pressure Control Valves

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 7,804,006 7,804,006

Piping Material 2,965,522 2,965,522

Instruments 1,250,270 1,250,270

Electrical Material 546,280 546,280

Bulks Sub‐Total 4,762,073 4,762,073

Equipment Erection 624,320 624,320

Pipe Fabrication & Erection 3,902,003 3,902,003

Instrument Erection 936,481 936,481

Electrical Erection 780,401 780,401

Founds, Trenching & U/G Piping 2,575,322 2,575,322

Steelwork 936,481 936,481

Insulation 390,200 390,200

Paint 234,120 234,120

Scaffolding 1,248,641 1,248,641

Pre‐Commissioning / Commissioning 449,511 449,511

Labour Sub‐Total 4,136,123 7,941,357 12,077,480

Shipping and Freight 251,322 251,322

Direct Sub‐Total 12,817,401 4,136,123 7,941,357 24,894,880

Description

57

Page 58: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Metering Costing Program Report

Pipeline Option - Case 1C

by PCP Ltd

Metering Skids

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1C-1

Metering SkidMetering Description

Total SkidCost 2,109,426

Currency Basis UK

£

LiquidFluid Measured :

Turbine MeterMeter Type :

total flow capacity 2644 m3/hr

Fiscal Meter

Comments

2 x 100%Meter Configuration :

28Line Size :

12Meter Size :

Inch

Inch

Each meter stream includes inlet and outlet isolation valves, strainer, pressure & temp instrumentation. Cost is for complete skid including interconnecting pipework, cabling, junction boxes, prefab shelter, flow computer and supervisory computer system.Also includes bi-directional prover with interconnecting pipework, valves & instrumentation

Total Skid Weight 55.0 Te

Item No.

THE PROJECT CONTROL PARTNERSHIP Metering Costing Program Version 15.10

58

Page 59: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pig Launchers and Receivers Costing Program Report

Pipeline Option - Case 1CPig Launchers / Receivers

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1C-PL-1

Pig Launcher /RecieverDescription

Total Cost 223,417

Currency Basis UK

£

30Line Size (")

2500#Pressure Rating

Comments

Bi-Directional (Launcher/Type: Carbon SteelMaterial

Total Weight 13.8 Te

Item No.

PCP Ltd Pig Launcher / Receiver Costing Program Version 15.10

59

Page 60: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Pipeline Option - Case 1CPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1322.00Flowrate

110.00Differential Pressure

1C-1

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.32Specific Gravity

3559.70Head m

5500.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

1,823,721

Total Pump Weight 36 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

1322.00Flowrate

110.00Differential Pressure

1C-2

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.32Specific Gravity

3559.70Head m

5500.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

1,823,721

Total Pump Weight 36 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

60

Page 61: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Pipeline Option - Case 1CPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1322.00Flowrate

110.00Differential Pressure

1C-3

PumpPump Description

Total Pump Cost

Carbon SteelCasing:

m³/hr

Bar

Comments

To API

0.32Specific Gravity

3559.70Head m

5500.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

1,823,721

Total Pump Weight 36 Te

MATERIALS

Carbon SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

61

Page 62: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ Power Import

12 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 3,169,787 3,169,787

Piping Material

Instruments

Electrical Material 602,260 602,260

Bulks Sub‐Total 602,260 602,260

Equipment Erection 158,489 158,489

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 665,655 665,655

Founds, Trenching & U/G Piping 221,885 221,885

Steelwork 158,489 158,489

Insulation

Paint 95,094 95,094

Scaffolding

Pre‐Commissioning / Commissioning 49,449 49,449

Labour Sub‐Total 475,468 873,593 1,349,061

Shipping and Freight 75,441 75,441

Direct Sub‐Total 3,847,487 475,468 873,593 5,196,549

Description

62

Page 63: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option Case 1C Checked by :  BRM

Currency Basis:  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 597,477 373,423 522,792 1,493,693

Service & Potable Water 497,898 311,186 435,660 1,244,744

Instrument Air 199,159 124,474 174,264 497,898

Open & Closed Drains 219,075 136,922 191,691 547,687

Vent System 497,898 311,186 435,660 1,244,744

Total Utilities & Infrastructure 2,011,506 1,257,191 1,760,068 5,028,766

Description

63

Page 64: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1C 

Pipeline EPC Cost                

64

Page 65: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate Summary Sheet

Prepared by PCP LTD

Project: Carbon Capture & Storage Date: July 2015

Location: Central North Sea Estimated by: CRM

Discipline: Pipeline Option ‐ Case 1C Checked by: BRM

Currency Basis: GBP Revision No: B2

Pipeline Option ‐ Case 1C ‐ Offshore Pipeline475 km, 30" N.B. 31.8 mm WT, 240 barg, X65

IndirectCosts

(£UK) (£UK) (£UK) (£UK) (£UK)

Offshore Pipelines

Linepipe & Misc. Materials Procurement 375,172,866 375,172,866

External Coating and Overweighting 24,088,257 24,088,257

Tie‐In Spools Fabrication and Installation 1,046,844 2,470,000 3,516,844

Pipeline Surveys & Installation 205,716,370 205,716,370

Pipeline Stabilisation and Protection 20,625 10,853,587 10,874,212

Pipeline Crossings 57,750 4,179,000 4,236,750

Risers & J‐Tubes 611,257 4,870,000 5,481,257

Hydrotesting and Commissioning 3,785,210 3,785,210

Transportation and Logistics 35,303,271 35,303,271

Total Offshore Pipelines 436,300,870 231,874,167 668,175,037

SSIV Structures

Procurement & Fabrication 6,497,497 1,901,792 8,399,289

SSIV Installation 3,800,000 3,800,000

Total SSIV Structures 6,497,497 1,901,792 3,800,000 12,199,289

Landfall

Shore Approach Pull & Tie In 10,600,000 10,600,000

Total Landfall 10,600,000 10,600,000

Detailed Design and Engineering 69,097,433 69,097,433

Purchasing, Expediting & Inspection 13,586,946 13,586,946

Project Management 32,061,829 32,061,829

Total EPC Pipeline Option ‐ Case 1C 442,798,367 1,901,792 246,274,167 114,746,207 805,720,533

DescriptionMaterial Fabrication Installation Total

65

Page 66: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15

Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2

Item : Pipeline Option ‐ Case 1C Currency Basis :  UK£

Pipeline Option ‐ Case 1C

Unit Cost Installation Material Fab. Installation Indirect Total

Item No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

Pipeline Option ‐ Case 1C

Length Width

1. Linepipe & Misc. Materials Procurement 1              Lot 375,172,866 375,172,866

2. External Coating and Overweighting 1              Lot 24,088,257 24,088,257

3. Tie‐In & Expansion Spools Fabrication & Installation 1              Lot 25.50 1,046,844 2,470,000 3,516,844

4. Pipeline Surveys & Installation 1              Lot 1,252.78 205,716,370 205,716,370

5. Pipeline Stabilisation and Protection 1              Lot 216.75 20,625 10,853,587 10,874,212

6. Pipeline Crossings & Guard Boats 1              Lot 147.0 57,750 4,179,000 4,236,750

8. Risers & J‐Tubes 1              Lot 131.0 611,257 4,870,000 5,481,257

7. Hydrotesting and Commissioning 1              Lot 3,785,210 3,785,210

8. Transportation and Logistics 1              Lot 35,303,271 35,303,271

9. Design, Engineering & Project Management 1              Lot

Total ‐ Offshore Pipelines ‐ Pipeline Option ‐ Case 1C 1,773.03 436,300,870 231,874,167 668,175,037

Item and Description

66

Page 67: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2Item : SSIV Structures Currency Basis :  UK£

SSIV Structures

Unit Cost Installation Material Fab. Installation Indirect TotalItem No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

SSIV Structures

Length Width1. Procurement & Fabrication 1           Lot 6,497,497 1,901,792 8,399,2892. SSIV Installation 1           Lot 20.0 3,800,000 3,800,000

3. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ SSIV Structures 20 6,497,497 1,901,792 3,800,000 12,199,289

Item and Description

67

Page 68: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Carbon Capture & Storage

Offshore Pipelines ‐ Detail Sheets

Prepared by The Project Control Partnership

Client : National Grid Carbon / DNV GL Date :  Jul 15Location : Central North Sea Estimated by :  CRM

Project Title : Carbon Capture & Storage Checked by :  BRM

Discipline : Offshore Pipelines Revision N° :  B2Item : Landfall Construction Currency Basis :  UK£

Landfall Construction

Unit Cost Installation Material Fab. Installation Indirect TotalItem No. Qty Unit Material  Fab. Vessel Unit NPT & Total Costs Costs Costs Costs Costs

(UK£) (UK£) (UK£/Day) Days WoW Days (UK£) (UK£) (UK£) (UK£) (UK£)

Landfall ConstructionLength Width

1. Pipeline Shore Approach Pull‐In & Tie‐In 1           Lot 10,600,000 10,600,0002. Design, Engineering & Project Management 1           Lot

Total ‐ Offshore Pipelines ‐ Landfall Construction 10,600,000 10,600,000

Item and Description

68

Page 69: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1C 

Offshore Facilities EPC Cost                

69

Page 70: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1C Checked by :  BRM

Currency Basis:  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ Offshore  Facilities

Scope:

Pig Reciever, Flow Control Valve, 50m of Piping to Tie‐in to existing injection header

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Offshore Facilities 1,232,764 378,170 710,320 1,303,746 3,625,000

Total Offshore Facilities 1,232,764 378,170 710,320 1,303,746 3,625,000

Description

70

Page 71: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Pipeline Option Case 1C 

OPEX                

71

Page 72: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

GL Noble Denton

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Pipeline Option ‐ Case 1C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Pipeline Option ‐ Case 1C ‐ OPEXp p

Category Qty Unit Unit Cost (£) OPEX Cost (£)

ONSHORE

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 579,404 579,404

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 627,687 627,687

Insurance

Insurance to cover material damage 1 Lot 482,837 482,837

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 100,800,000 KWH 0.07 7,257,600

PIPELINE

Maintenance & Operating Costs

Annual Maintenance, Inspections and Remedial Works 1 Lot 1,589,668 1,589,668

Insurance

Insurance to cover material damage 1 Lot 4,137,353 4,137,353

Property Overheads

Property Taxes and Overheads ExcludedProperty Taxes and Overheads xcluded

Utilities, Catalysts & Chemicals

Corrosion Inhibitor and Other Chemicals 0 Lot Not Required

Total Annual Operating Cost 14,674,548

72

Page 73: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2A

73

Page 74: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2A 

Summary                

74

Page 75: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Overall Summary

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Port of Rotterdam EPC Cost 69,914,382

Onshore UK EPC Cost 48,947,456

Total EPC Cost 118,861,838

Owner's Management 12,399,135

Third Party Inspection & Certification 1,239,914

CAR Insurance 891,464

Owner's Contingency 20,008,853

Forward Escalation Excluded

Total Shipping Option ‐ Case 2A 153,401,203

Description

75

Page 76: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2A 

Port of Rotterdam                

76

Page 77: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Port of Rotterdam EPC

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

ONSHORE FACILITIES

Pumping Station 21,072,052 11,004,012 14,065,983 46,142,046

Total Process & Storage 21,072,052 11,004,012 14,065,983 46,142,046

UTILITIES & INFRASTRUCTURE

Power Import 772,160 95,423 175,323 1,042,906

Firewater System 553,705 346,065 484,491 1,384,261

Service & Potable Water 461,420 288,388 403,743 1,153,551

Instrument Air 184,568 115,355 161,497 461,420

Open & Closed Drains 203,025 126,891 177,647 507,563

Vent System 461,420 288,388 403,743 1,153,551

Control System 1,200,000 150,000 1,350,000

Roads, Paving, Fences 1,239,711 1,239,711

Buildings 943,189 943,189

Sub‐Total Utilities & Infrast. 3,836,299 3,443,408 1,956,445 9,236,152

Total Direct Cost 24,908,351 14,447,420 16,022,427 55,378,198

Design & Engineering 7,513,365 7,513,365

Construction Management 7,022,819 7,022,819

Sub‐Total Indirects 14,536,184 14,536,184

Total EPC Cost 24,908,351 14,447,420 16,022,427 14,536,184 69,914,382

Description

77

Page 78: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Port of Rotterdam Pumping Station

Centrifugal Pumps, Loading Arms, Storage Spheres

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 13,526,119 13,526,119

Piping Material 5,741,486 5,741,486

Instruments 990,673 990,673

Electrical Material 788,305 788,305

Bulks Sub‐Total 7,520,463 7,520,463

Equipment Erection 1,051,073 1,051,073

Pipe Fabrication & Erection 7,226,126 7,226,126

Instrument Erection 1,576,609 1,576,609

Electrical Erection 1,313,841 1,313,841

Founds, Trenching & U/G Piping 4,335,676 4,335,676

Steelwork 1,576,609 1,576,609

Insulation 4,697,574 4,697,574

Paint 394,152 394,152

Scaffolding 2,102,146 2,102,146

Pre‐Commissioning / Commissioning 796,188 796,188

Labour Sub‐Total 11,004,012 14,065,983 25,069,994

Shipping and Freight 413,177 413,177

Direct Sub‐Total 21,072,052 11,004,012 14,065,983 46,529,754

Description

78

Page 79: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2A RotterdamStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

26.75Diameter

2A1-1

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

26.75Diameter

2A1-2

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

79

Page 80: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2A RotterdamPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1048.00Flowrate

3.00Differential Pressure

2A1-1

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.05Specific Gravity

29.12Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

1048.00Flowrate

3.00Differential Pressure

2A1-2

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.05Specific Gravity

29.12Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

80

Page 81: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2A RotterdamPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1048.00Flowrate

3.00Differential Pressure

2A1-3

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.05Specific Gravity

29.12Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

81

Page 82: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2A RotterdamLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2A1-1Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

2A1-2Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

82

Page 83: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2A RotterdamLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2A1-3Item No.

Vapour ReturnDescription

Total Equip Cost

Carbon SteelMaterial

Comments

Marine Loading ArmType:

224,556

Currency Basis UK

£

Total Equip Weight 17.9 Te

6Diameter: Inches

LPGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

83

Page 84: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Port of Rotterdam Power Import

0.3 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 636,151 636,151

Piping Material

Instruments

Electrical Material 120,869 120,869

Bulks Sub‐Total 120,869 120,869

Equipment Erection 31,808 31,808

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 133,592 133,592

Founds, Trenching & U/G Piping 44,531 44,531

Steelwork 31,808 31,808

Insulation

Paint 19,085 19,085

Scaffolding

Pre‐Commissioning / Commissioning 9,924 9,924

Labour Sub‐Total 95,423 175,323 270,746

Shipping and Freight 15,140 15,140

Direct Sub‐Total 772,160 95,423 175,323 1,042,906

Description

84

Page 85: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Port of Rotterdam Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 553,705 346,065 484,491 1,384,261

Service & Potable Water 461,420 288,388 403,743 1,153,551

Instrument Air 184,568 115,355 161,497 461,420

Open & Closed Drains 203,025 126,891 177,647 507,563

Vent System 461,420 288,388 403,743 1,153,551

Total Utilities & Infrastructure 1,864,139 1,165,087 1,631,121 4,660,347

Description

85

Page 86: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2A 

Onshore UK                

86

Page 87: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Onshore UK EPC

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

ONSHORE FACILITIES

Pumping Station 15,111,823 8,466,954 7,522,989 31,101,767

Total Process & Storage 15,111,823 8,466,954 7,522,989 31,101,767

UTILITIES & INFRASTRUCTURE

Power Import 1,198,180 148,070 272,053 1,618,303

Firewater System 373,221 233,263 326,569 933,053

Service & Potable Water 311,018 194,386 272,140 777,544

Instrument Air 124,407 77,754 108,856 311,018

Open & Closed Drains 136,848 85,530 119,742 342,119

Vent System 311,018 194,386 272,140 777,544

Fuel Gas System 93,305 58,316 81,642 233,263

Control System 1,200,000 150,000 1,350,000

Roads, Paving, Fences 823,876 823,876

Buildings 444,209 444,209

Sub‐Total Utilities & Infrast. 3,747,996 2,259,790 1,603,143 7,610,929

Total Direct Cost 18,859,820 10,726,744 9,126,132 38,712,695

Design & Engineering 6,263,452 6,263,452

Construction Management 3,971,308 3,971,308

Sub‐Total Indirects 10,234,760 10,234,760

Total EPC Cost 18,859,820 10,726,744 9,126,132 10,234,760 48,947,456

Description

87

Page 88: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Onshore UK Pumping Station

Centrifugal Pumps, Loading Arms, Storage Spheres, Gas Fired Vaporizer

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 8,308,555 8,308,555

Piping Material 4,977,812 4,977,812

Instruments 282,262 282,262

Electrical Material 1,388,397 1,388,397

Bulks Sub‐Total 6,648,471 6,648,471

Equipment Erection 81,670 81,670

Pipe Fabrication & Erection 4,402,036 4,402,036

Instrument Erection 490,023 490,023

Electrical Erection 980,045 980,045

Founds, Trenching & U/G Piping 1,470,068 1,470,068

Steelwork 980,045 980,045

Insulation 5,608,490 5,608,490

Paint 408,352 408,352

Scaffolding 1,143,386 1,143,386

Pre‐Commissioning / Commissioning 425,830 425,830

Labour Sub‐Total 8,466,954 7,522,989 15,989,943

Shipping and Freight 296,310 296,310

Direct Sub‐Total 15,111,823 8,466,954 7,522,989 31,243,280

Description

88

Page 89: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2A Onshore UKStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

26.75Diameter

2A2-1

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

89

Page 90: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Fired Heater Costing Program Report

Shipping Option - Case 2A Onshore UKHeaters

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2A2-1

Vaporizer (Gas Fired)Description

Total Heater Cost 908,622

Currency Basis UK

£

6.10Duty

146.00Pressure

MW

Bar

Comments

Indirect Fired Heater Carbon SteelMaterial

Includes independent stack

Cost based on Low NOx Burners

Total Heater Weight 65 Te

Item No.

PCP Ltd Heater Costing Program Version 15.10

90

Page 91: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2A Onshore UKPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

102.00Flowrate

139.00Differential Pressure

2A2-1

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1232.11Head m

500.00Motor Size KW

62.44Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

253,458

Total Pump Weight 5 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

102.00Flowrate

139.00Differential Pressure

2A2-2

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1232.11Head m

500.00Motor Size KW

62.44Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

253,458

Total Pump Weight 5 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

91

Page 92: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2A Onshore UKPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

102.00Flowrate

139.00Differential Pressure

2A2-3

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1232.11Head m

500.00Motor Size KW

62.44Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

253,458

Total Pump Weight 5 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

92

Page 93: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2A Onshore UKLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2A2-1Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

2A2-2Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

93

Page 94: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2A Onshore UKLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2A2-3Item No.

Vapour ReturnDescription

Total Equip Cost

Carbon SteelMaterial

Comments

Marine Loading ArmType:

224,556

Currency Basis UK

£

Total Equip Weight 17.9 Te

6Diameter: Inches

LPGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

94

Page 95: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Onshore UK Power Import

1.5 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 987,131 987,131

Piping Material

Instruments

Electrical Material 187,555 187,555

Bulks Sub‐Total 187,555 187,555

Equipment Erection 49,357 49,357

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 207,298 207,298

Founds, Trenching & U/G Piping 69,099 69,099

Steelwork 49,357 49,357

Insulation

Paint 29,614 29,614

Scaffolding

Pre‐Commissioning / Commissioning 15,399 15,399

Labour Sub‐Total 148,070 272,053 420,123

Shipping and Freight 23,494 23,494

Direct Sub‐Total 1,198,180 148,070 272,053 1,618,303

Description

95

Page 96: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ Onshore UK Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 373,221 233,263 326,569 933,053

Service & Potable Water 311,018 194,386 272,140 777,544

Instrument Air 124,407 77,754 108,856 311,018

Open & Closed Drains 136,848 85,530 119,742 342,119

Vent System 311,018 194,386 272,140 777,544

Fuel Gas System 93,305 58,316 81,642 233,263

Total Utilities & Infrastructure 1,349,817 843,635 1,181,090 3,374,542

Description

96

Page 97: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2A 

OPEX 

97

Page 98: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

GL Noble Denton

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2A Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2A ‐ OPEX

Category Qty Unit Unit Cost (£) OPEX Cost (£)

PORT OF ROTTERDAM

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 838,973 838,973

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 908,887 908,887

Insurance

Insurance to cover material damage 1 Lot 699,144 699,144

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 2,520,000 KWH 0.07 181,440

ONSHORE UK

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 587,369 587,369

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 636,317 636,317

Insurance

Insurance to cover material damage 1 Lot 489,475 489,475

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 1,500kW x 8000 Hrs 12,000,000 KWH 0.07 864,000

Imported Fuel Gas 594.4 KG / hr x 8000 Hrs 4,755,200 KG 0.19 884,467

Total Annual Operating Cost 6,090,072

98

Page 99: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2B

99

Page 100: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2B 

Summary                

100

Page 101: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Overall Summary

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Port of Rotterdam EPC Cost 103,801,699

Onshore UK EPC Cost 76,483,368

Total EPC Cost 180,285,068

Owner's Management 16,113,784

Third Party Inspection & Certification 1,611,378

CAR Insurance 1,352,138

Owner's Contingency 29,904,355

Forward Escalation Excluded

Total Shipping Option ‐ Case 2B 229,266,723

Description

101

Page 102: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2B 

Port of Rotterdam                

102

Page 103: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Port of Rotterdam EPC

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

ONSHORE FACILITIES

Pumping Station 32,161,227 17,174,281 21,391,968 70,727,475

Total Process & Storage 32,161,227 17,174,281 21,391,968 70,727,475

UTILITIES & INFRASTRUCTURE

Power Import 772,160 95,423 175,323 1,042,906

Firewater System 848,730 530,456 742,638 2,121,824

Service & Potable Water 707,275 442,047 618,865 1,768,187

Instrument Air 282,910 176,819 247,546 707,275

Open & Closed Drains 311,201 194,501 272,301 778,002

Vent System 707,275 442,047 618,865 1,768,187

Control System 1,250,000 156,250 1,406,250

Roads, Paving, Fences 1,855,570 1,855,570

Buildings 1,285,332 1,285,332

Sub‐Total Utilities & Infrast. 4,879,550 5,022,193 2,831,789 12,733,533

Total Direct Cost 37,040,777 22,196,474 24,223,757 83,461,008

Design & Engineering 9,759,576 9,759,576

Construction Management 10,581,116 10,581,116

Sub‐Total Indirects 20,340,691 20,340,691

Total EPC Cost 37,040,777 22,196,474 24,223,757 20,340,691 103,801,699

Description

103

Page 104: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Port of Rotterdam Pumping Station

Centrifugal Pumps, Loading Arms, Storage Spheres

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 20,368,997 20,368,997

Piping Material 8,731,823 8,731,823

Instruments 1,618,625 1,618,625

Electrical Material 1,198,877 1,198,877

Bulks Sub‐Total 11,549,325 11,549,325

Equipment Erection 1,598,503 1,598,503

Pipe Fabrication & Erection 10,989,709 10,989,709

Instrument Erection 2,397,755 2,397,755

Electrical Erection 1,998,129 1,998,129

Founds, Trenching & U/G Piping 6,593,825 6,593,825

Steelwork 2,397,755 2,397,755

Insulation 7,583,262 7,583,262

Paint 599,439 599,439

Scaffolding 3,197,006 3,197,006

Pre‐Commissioning / Commissioning 1,210,866 1,210,866

Labour Sub‐Total 17,174,281 21,391,968 38,566,249

Shipping and Freight 630,612 630,612

Direct Sub‐Total 32,161,227 17,174,281 21,391,968 71,115,183

Description

104

Page 105: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2B RotterdamStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

24.90Diameter

2B1-1

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

24.90Diameter

2B1-2

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

105

Page 106: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2B RotterdamStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

24.90Diameter

2B1-3

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

24.90Diameter

2B1-4

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

106

Page 107: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2B RotterdamPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1048.00Flowrate

3.00Differential Pressure

2B1-1

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

26.59Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

1048.00Flowrate

3.00Differential Pressure

2B1-2

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

26.59Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

107

Page 108: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2B RotterdamPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1048.00Flowrate

3.00Differential Pressure

2B1-3

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

26.59Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

108

Page 109: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2B RotterdamLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2B1-1Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

2B1-2Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

109

Page 110: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2B RotterdamLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2B1-3Item No.

Vapour ReturnDescription

Total Equip Cost

Carbon SteelMaterial

Comments

Marine Loading ArmType:

224,556

Currency Basis UK

£

Total Equip Weight 17.9 Te

6Diameter: Inches

LPGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

110

Page 111: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Port of Rotterdam Power Import

0.3 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 636,151 636,151

Piping Material

Instruments

Electrical Material 120,869 120,869

Bulks Sub‐Total 120,869 120,869

Equipment Erection 31,808 31,808

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 133,592 133,592

Founds, Trenching & U/G Piping 44,531 44,531

Steelwork 31,808 31,808

Insulation

Paint 19,085 19,085

Scaffolding

Pre‐Commissioning / Commissioning 9,924 9,924

Labour Sub‐Total 95,423 175,323 270,746

Shipping and Freight 15,140 15,140

Direct Sub‐Total 772,160 95,423 175,323 1,042,906

Description

111

Page 112: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Port of Rotterdam Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 848,730 530,456 742,638 2,121,824

Service & Potable Water 707,275 442,047 618,865 1,768,187

Instrument Air 282,910 176,819 247,546 707,275

Open & Closed Drains 311,201 194,501 272,301 778,002

Vent System 707,275 442,047 618,865 1,768,187

Total Utilities & Infrastructure 2,857,390 1,785,869 2,500,216 7,143,475

Description

112

Page 113: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2B 

Onshore UK                

113

Page 114: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Onshore UK EPC

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

ONSHORE FACILITIES

Pumping Station 24,711,178 13,891,651 12,246,251 50,849,081

Total Process & Storage 24,711,178 13,891,651 12,246,251 50,849,081

UTILITIES & INFRASTRUCTURE

Power Import 1,730,704 213,878 392,966 2,337,548

Firewater System 610,189 381,368 533,915 1,525,472

Service & Potable Water 508,491 317,807 444,929 1,271,227

Instrument Air 203,396 127,123 177,972 508,491

Open & Closed Drains 223,736 139,835 195,769 559,340

Vent System 508,491 317,807 444,929 1,271,227

Fuel Gas System 93,305 58,316 81,642 233,263

Control System 1,250,000 156,250 1,406,250

Roads, Paving, Fences 1,324,847 1,324,847

Buildings 641,635 641,635

Sub‐Total Utilities & Infrast. 5,128,312 3,522,616 2,428,373 11,079,301

Total Direct Cost 29,839,491 17,414,267 14,674,624 61,928,382

Design & Engineering 8,144,629 8,144,629

Construction Management 6,410,358 6,410,358

Sub‐Total Indirects 14,554,986 14,554,986

Total EPC Cost 29,839,491 17,414,267 14,674,624 14,554,986 76,483,368

Description

114

Page 115: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Onshore UK Pumping Station

Centrifugal Pumps, Loading Arms, Storage Spheres, Gas Fired Vaporizer

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 13,559,899 13,559,899

Piping Material 8,103,101 8,103,101

Instruments 568,782 568,782

Electrical Material 2,260,094 2,260,094

Bulks Sub‐Total 10,931,977 10,931,977

Equipment Erection 132,947 132,947

Pipe Fabrication & Erection 7,165,827 7,165,827

Instrument Erection 797,680 797,680

Electrical Erection 1,595,360 1,595,360

Founds, Trenching & U/G Piping 2,393,040 2,393,040

Steelwork 1,595,360 1,595,360

Insulation 9,238,517 9,238,517

Paint 664,733 664,733

Scaffolding 1,861,254 1,861,254

Pre‐Commissioning / Commissioning 693,184 693,184

Labour Sub‐Total 13,891,651 12,246,251 26,137,902

Shipping and Freight 484,533 484,533

Direct Sub‐Total 24,711,178 13,891,651 12,246,251 51,114,311

Description

115

Page 116: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2B Onshore UKStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

24.90Diameter

2B2-1

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

24.90Diameter

2B2-2

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

116

Page 117: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Fired Heater Costing Program Report

Shipping Option - Case 2B Onshore UKHeaters

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2B2-1

Vaporizer (Gas Fired)Description

Total Heater Cost 1,031,382

Currency Basis UK

£

7.50Duty

145.00Pressure

MW

Bar

Comments

Indirect Fired Heater Carbon SteelMaterial

Includes independent stack

Cost based on Low NOx Burners

Total Heater Weight 77 Te

Item No.

2B2-2

Vaporizer (Gas Fired)Description

Total Heater Cost 1,073,077

Currency Basis UK

£

8.00Duty

145.00Pressure

MW

Bar

Comments

Indirect Fired Heater Carbon SteelMaterial

Includes independent stack

Cost based on Low NOx Burners

Total Heater Weight 81 Te

Item No.

PCP Ltd Heater Costing Program Version 15.10

117

Page 118: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2B Onshore UKPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

255.00Flowrate

138.00Differential Pressure

2B2-1

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1223.24Head m

1300.00Motor Size KW

74.24Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

464,814

Total Pump Weight 11 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

255.00Flowrate

138.00Differential Pressure

2B2-2

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1223.24Head m

1300.00Motor Size KW

74.24Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

464,814

Total Pump Weight 11 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

118

Page 119: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2B Onshore UKPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

255.00Flowrate

138.00Differential Pressure

2B2-3

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1223.24Head m

1300.00Motor Size KW

74.24Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

464,814

Total Pump Weight 11 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

119

Page 120: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2B Onshore UKLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2B2-1Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

2B2-2Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

120

Page 121: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2B Onshore UKLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2B2-3Item No.

Vapour ReturnDescription

Total Equip Cost

Carbon SteelMaterial

Comments

Marine Loading ArmType:

224,556

Currency Basis UK

£

Total Equip Weight 17.9 Te

6Diameter: Inches

LPGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

121

Page 122: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Onshore UK Power Import

3 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 1,425,856 1,425,856

Piping Material

Instruments

Electrical Material 270,913 270,913

Bulks Sub‐Total 270,913 270,913

Equipment Erection 71,293 71,293

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 299,430 299,430

Founds, Trenching & U/G Piping 99,810 99,810

Steelwork 71,293 71,293

Insulation

Paint 42,776 42,776

Scaffolding

Pre‐Commissioning / Commissioning 22,243 22,243

Labour Sub‐Total 213,878 392,966 606,844

Shipping and Freight 33,935 33,935

Direct Sub‐Total 1,730,704 213,878 392,966 2,337,548

Description

122

Page 123: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ Onshore UK Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 610,189 381,368 533,915 1,525,472

Service & Potable Water 508,491 317,807 444,929 1,271,227

Instrument Air 203,396 127,123 177,972 508,491

Open & Closed Drains 223,736 139,835 195,769 559,340

Vent System 508,491 317,807 444,929 1,271,227

Fuel Gas System 152,547 95,342 133,479 381,368

Total Utilities & Infrastructure 2,206,850 1,379,281 1,930,994 5,517,125

Description

123

Page 124: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2B 

OPEX 

124

Page 125: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

GL Noble Denton

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2B Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2B ‐ OPEX

Category Qty Unit Unit Cost (£) OPEX Cost (£)

PORT OF ROTTERDAM

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 1,245,620 1,245,620

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 1,349,422 1,349,422

Insurance

Insurance to cover material damage 1 Lot 1,038,017 1,038,017

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 2,520,000 KWH 0.07 181,440

ONSHORE UK

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 917,800 917,800

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 994,284 994,284

Insurance

Insurance to cover material damage 1 Lot 764,834 764,834

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 3,000kW x 8000 Hrs 24,000,000 KWH 0.07 1,728,000

Imported Fuel Gas 1510.4 KG / hr x 8000 Hrs 12,083,200 KG 0.19 2,247,475

Total Annual Operating Cost 10,466,893

125

Page 126: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2C

126

Page 127: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2C 

Summary                

127

Page 128: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Capital Cost Estimate

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Overall Summary

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Port of Rotterdam EPC Cost 123,913,606

Onshore UK EPC Cost 107,510,019

Total EPC Cost 231,423,625

Owner's Management 19,132,372

Third Party Inspection & Certification 1,913,237

CAR Insurance 1,735,677

Owner's Contingency 38,130,737

Forward Escalation Excluded

Total Shipping Option ‐ Case 2C 292,335,648

Description

128

Page 129: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2C 

Port of Rotterdam                

129

Page 130: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Port of Rotterdam EPC

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

ONSHORE FACILITIES

Pumping Station 38,881,020 20,579,568 25,882,988 85,343,576

Total Process & Storage 38,881,020 20,579,568 25,882,988 85,343,576

UTILITIES & INFRASTRUCTURE

Power Import 772,160 95,423 175,323 1,042,906

Firewater System 1,024,123 640,077 896,108 2,560,307

Service & Potable Water 853,436 533,397 746,756 2,133,589

Instrument Air 341,374 213,359 298,703 853,436

Open & Closed Drains 375,512 234,695 328,573 938,779

Vent System 853,436 533,397 746,756 2,133,589

Control System 1,250,000 156,250 1,406,250

Roads, Paving, Fences 2,233,107 2,233,107

Buildings 1,495,076 1,495,076

Sub‐Total Utilities & Infrast. 5,470,041 5,978,531 3,348,469 14,797,040

Total Direct Cost 44,351,060 26,558,098 29,231,457 100,140,615

Design & Engineering 11,010,546 11,010,546

Construction Management 12,762,444 12,762,444

Sub‐Total Indirects 23,772,990 23,772,990

Total EPC Cost 44,351,060 26,558,098 29,231,457 23,772,990 123,913,606

Description

130

Page 131: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Port of Rotterdam Pumping Station

Centrifugal Pumps, Loading Arms, Storage Spheres

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 24,606,937 24,606,937

Piping Material 10,564,978 10,564,978

Instruments 1,926,947 1,926,947

Electrical Material 1,450,569 1,450,569

Bulks Sub‐Total 13,942,495 13,942,495

Equipment Erection 1,934,092 1,934,092

Pipe Fabrication & Erection 13,296,884 13,296,884

Instrument Erection 2,901,138 2,901,138

Electrical Erection 2,417,615 2,417,615

Founds, Trenching & U/G Piping 7,978,130 7,978,130

Steelwork 2,901,138 2,901,138

Insulation 8,975,015 8,975,015

Paint 725,285 725,285

Scaffolding 3,868,184 3,868,184

Pre‐Commissioning / Commissioning 1,465,075 1,465,075

Labour Sub‐Total 20,579,568 25,882,988 46,462,556

Shipping and Freight 762,373 762,373

Direct Sub‐Total 38,881,020 20,579,568 25,882,988 85,774,361

Description

131

Page 132: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2C RotterdamStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

26.75Diameter

2C1-1

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

26.75Diameter

2C1-2

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

132

Page 133: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2C RotterdamStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

26.75Diameter

2C1-3

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

26.75Diameter

2C1-4

Storage SphereSphere Description

10,022Capacity:

62,940Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 5,540,409

Total Sphere Weight 720.0 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

133

Page 134: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2C RotterdamPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1048.00Flowrate

3.00Differential Pressure

2C1-1

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

26.59Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

1048.00Flowrate

3.00Differential Pressure

2C1-2

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

26.59Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

134

Page 135: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2C RotterdamPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

1048.00Flowrate

3.00Differential Pressure

2C1-3

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

26.59Head m

100.00Motor Size KW

80.00Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

448,717

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

135

Page 136: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2C RotterdamLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2C1-1Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

2C1-2Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

136

Page 137: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2C RotterdamLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2C1-3Item No.

Vapour ReturnDescription

Total Equip Cost

Carbon SteelMaterial

Comments

Marine Loading ArmType:

224,556

Currency Basis UK

£

Total Equip Weight 17.9 Te

6Diameter: Inches

LPGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

137

Page 138: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Port of Rotterdam Power Station

0.3 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 636,151 636,151

Piping Material

Instruments

Electrical Material 120,869 120,869

Bulks Sub‐Total 120,869 120,869

Equipment Erection 31,808 31,808

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 133,592 133,592

Founds, Trenching & U/G Piping 44,531 44,531

Steelwork 31,808 31,808

Insulation

Paint 19,085 19,085

Scaffolding

Pre‐Commissioning / Commissioning 9,924 9,924

Labour Sub‐Total 95,423 175,323 270,746

Shipping and Freight 15,140 15,140

Direct Sub‐Total 772,160 95,423 175,323 1,042,906

Description

138

Page 139: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Port of Rotterdam Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 1,024,123 640,077 896,108 2,560,307

Service & Potable Water 853,436 533,397 746,756 2,133,589

Instrument Air 341,374 213,359 298,703 853,436

Open & Closed Drains 375,512 234,695 328,573 938,779

Vent System 853,436 533,397 746,756 2,133,589

Total Utilities & Infrastructure 3,447,880 2,154,925 3,016,895 8,619,701

Description

139

Page 140: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2C 

Onshore UK  

140

Page 141: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Onshore UK EPC

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

ONSHORE FACILITIES

Pumping Station 35,598,478 20,136,761 17,660,084 73,395,323

Total Process & Storage 35,598,478 20,136,761 17,660,084 73,395,323

UTILITIES & INFRASTRUCTURE

Power Import 2,156,724 266,525 489,696 2,912,945

Firewater System 880,744 550,465 770,651 2,201,860

Service & Potable Water 733,953 458,721 642,209 1,834,883

Instrument Air 293,581 183,488 256,884 733,953

Open & Closed Drains 322,939 201,837 282,572 807,349

Vent System 733,953 458,721 642,209 1,834,883

Fuel Gas System 93,305 58,316 81,642 233,263

Control System 1,300,000 162,500 1,462,500

Roads, Paving, Fences 1,885,394 1,885,394

Buildings 799,576 799,576

Sub‐Total Utilities & Infrast. 6,515,200 4,863,043 3,328,363 14,706,606

Total Direct Cost 42,113,678 24,999,805 20,988,447 88,101,929

Design & Engineering 10,247,645 10,247,645

Construction Management 9,160,445 9,160,445

Sub‐Total Indirects 19,408,090 19,408,090

Total EPC Cost 42,113,678 24,999,805 20,988,447 19,408,090 107,510,019

Description

141

Page 142: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Onshore UK Pumping Station

Centrifugal Pumps, Loading Arms, Storage Spheres, Gas Fired Vaporizer

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 19,528,321 19,528,321

Piping Material 11,685,326 11,685,326

Instruments 783,918 783,918

Electrical Material 3,259,238 3,259,238

Bulks Sub‐Total 15,728,481 15,728,481

Equipment Erection 191,720 191,720

Pipe Fabrication & Erection 10,333,701 10,333,701

Instrument Erection 1,150,319 1,150,319

Electrical Erection 2,300,638 2,300,638

Founds, Trenching & U/G Piping 3,450,958 3,450,958

Steelwork 2,300,638 2,300,638

Insulation 13,426,566 13,426,566

Paint 958,599 958,599

Scaffolding 2,684,078 2,684,078

Pre‐Commissioning / Commissioning 999,627 999,627

Labour Sub‐Total 20,136,761 17,660,084 37,796,845

Shipping and Freight 698,009 698,009

Direct Sub‐Total 35,598,478 20,136,761 17,660,084 73,751,657

Description

142

Page 143: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2C Onshore UKStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

24.90Diameter

2C2-1

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

24.90Diameter

2C2-2

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

143

Page 144: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Sphere Costing Program Report

Shipping Option - Case 2C Onshore UKStorage Spheres

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

24.90Diameter

2C2-3

Storage SphereSphere Description

8,083Capacity:

50,764Capacity:

M3

Barrels

Total Sphere Cost

Low Temp CSMaterial:

m

Comments

Currency Basis UK

£ 4,480,924

Total Sphere Weight 582.3 Te

7.00Pressure Bar

Item No.

PCP Ltd Sphere Costing Program Version 15.10

144

Page 145: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Fired Heater Costing Program Report

Shipping Option - Case 2C Onshore UKHeaters

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2C2-1

Vaporizer (Gas Fired)Description

Total Heater Cost 1,039,803

Currency Basis UK

£

7.60Duty

147.00Pressure

MW

Bar

Comments

Indirect Fired Heater Carbon SteelMaterial

Includes independent stack

Cost based on Low NOx Burners

Total Heater Weight 78 Te

Item No.

2C2-2

Vaporizer (Gas Fired)Description

Total Heater Cost 1,039,803

Currency Basis UK

£

7.60Duty

147.00Pressure

MW

Bar

Comments

Indirect Fired Heater Carbon SteelMaterial

Includes independent stack

Cost based on Low NOx Burners

Total Heater Weight 78 Te

Item No.

PCP Ltd Heater Costing Program Version 15.10

145

Page 146: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Fired Heater Costing Program Report

Shipping Option - Case 2C Onshore UKHeaters

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2C2-3

Vaporizer (Gas Fired)Description

Total Heater Cost 1,039,803

Currency Basis UK

£

7.60Duty

147.00Pressure

MW

Bar

Comments

Indirect Fired Heater Carbon SteelMaterial

Includes independent stack

Cost based on Low NOx Burners

Total Heater Weight 78 Te

Item No.

PCP Ltd Heater Costing Program Version 15.10

146

Page 147: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2C Onshore UKPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

373.00Flowrate

140.00Differential Pressure

2C2-1

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1240.97Head m

1900.00Motor Size KW

79.14Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

622,330

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

373.00Flowrate

140.00Differential Pressure

2C2-2

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1240.97Head m

1900.00Motor Size KW

79.14Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

622,330

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

147

Page 148: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Pump Costing Program Report

Shipping Option - Case 2C Onshore UKPumps

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

373.00Flowrate

140.00Differential Pressure

2C2-3

Cryogenic PumpPump Description

Total Pump Cost

Stainless SteelCasing:

m³/hr

Bar

Comments

To API

1.15Specific Gravity

1240.97Head m

1900.00Motor Size KW

79.14Efficiency %

CentrifugalPump:

Electric MotorDriver:

£

UKCurrency Basis

622,330

Total Pump Weight 16 Te

MATERIALS

Stainless SteelImpellor / Internals:

TYPE

Item No.

PCP Ltd Pump Costing Program Version 15.10

148

Page 149: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2C Onshore UKLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2C2-1Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

2C2-2Item No.

Loading ArmDescription

Total Equip Cost

Stainless SteelMaterial

Comments

Marine Loading ArmType:

437,297

Currency Basis UK

£

Total Equip Weight 21.8 Te

8Diameter: Inches

LNGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

149

Page 150: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

Loading Arms Costing Program Report

Shipping Option - Case 2C Onshore UKLoading Arms

by PCP Ltd

National Grid Carbon / DNV GLClient:Central North SeaLocation:

Project ID N°Carbon Capture & StorageProject Title:

July 2015Date:B2Revision No:

UKCurrency Basis:CRMEstimated by:

2C2-3Item No.

Vapour ReturnDescription

Total Equip Cost

Carbon SteelMaterial

Comments

Marine Loading ArmType:

224,556

Currency Basis UK

£

Total Equip Weight 17.9 Te

6Diameter: Inches

LPGProduct:

THE PROJECT CONTROL PARTNERSHIP Water Treatment Costing Program Version 15.10

150

Page 151: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Onshore UK Power Station

4.5 MW Substation

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Total Equipment Cost 1,776,836 1,776,836

Piping Material

Instruments

Electrical Material 337,599 337,599

Bulks Sub‐Total 337,599 337,599

Equipment Erection 88,842 88,842

Pipe Fabrication & Erection

Instrument Erection

Electrical Erection 373,136 373,136

Founds, Trenching & U/G Piping 124,379 124,379

Steelwork 88,842 88,842

Insulation

Paint 53,305 53,305

Scaffolding

Pre‐Commissioning / Commissioning 27,719 27,719

Labour Sub‐Total 266,525 489,696 756,221

Shipping and Freight 42,289 42,289

Direct Sub‐Total 2,156,724 266,525 489,696 2,912,945

Description

151

Page 152: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV GL

Carbon Capture & Storage

Estimate Summary by Area

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ Onshore UK Utilities & Infrastructure

MaterialsMaterial & 

Labour S/CLabour Indirects Grand Total

(£UK) (£UK) (£UK) (£UK) (£UK)

Firewater System 880,744 550,465 770,651 2,201,860

Service & Potable Water 733,953 458,721 642,209 1,834,883

Instrument Air 293,581 183,488 256,884 733,953

Open & Closed Drains 322,939 201,837 282,572 807,349

Vent System 733,953 458,721 642,209 1,834,883

Fuel Gas System 220,186 137,616 192,663 550,465

Total Utilities & Infrastructure 3,185,357 1,990,848 2,787,187 7,963,393

Description

152

Page 153: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

National Grid Carbon / DNV‐GL CARBON CAPTURE & STORAGE UPSCALING 

Shipping Option Case 2C 

OPEX  

153

Page 154: National Grid Carbon / DNV-GL Carbon Capture & Storage ...hub.globalccsinstitute.com/sites/default/files/publications/198303... · National Grid Carbon / DNV-GL Carbon Capture & Storage

GL Noble Denton

Carbon Capture & Storage

Cost Estimate by Discipline

Prepared by PCP LTD

Location : Central North Sea Date :  July 2015

Project Title : Carbon Capture & Storage Estimated by :  CRM

Case : Shipping Option ‐ Case 2C Checked by :  BRM

Currency Basis :  GBP Revision N° :  B2

Shipping Option ‐ Case 2C ‐ OPEX

Category Qty Unit Unit Cost (£) OPEX Cost (£)

PORT OF ROTTERDAM

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 1,486,963 1,486,963

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 1,610,877 1,610,877

Insurance

Insurance to cover material damage 1 Lot 1,239,136 1,239,136

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 2,520,000 KWH 0.07 181,440

ONSHORE UK

Maintenance & Operating Costs

Maintenance Staff, Outside Contractors and Materials 1 Lot 1,290,120 1,290,120

Operating Personnel Costs, Excluding Maintenance Staff 1 Lot 1,397,630 1,397,630

Insurance

Insurance to cover material damage 1 Lot 1,075,100 1,075,100

Property Overheads

Property Taxes and Overheads Excluded

Utilities, Catalysts & Chemicals

Imported Electricity 4,500kW x 8000 Hrs 36,000,000 KWH 0.07 2,592,000

Imported Fuel Gas 2212 KG / hr x 8000 Hrs 17,696,000 KG 0.19 3,291,456

Total Annual Operating Cost 14,164,723