nassau expressway operational & resiliency … · 2017-12-20 · nassau expressway operational...

87
NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY IMPROVEMENTS PIN 0072.14, Contract D900042 DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS Final December 20, 2017

Upload: others

Post on 07-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

NASSAU EXPRESSWAY OPERATIONAL& RESILIENCY IMPROVEMENTS

PIN 0072.14, Contract D900042

DB CONTRACT DOCUMENTS

PART 3PROJECT REQUIREMENTS

Final December 20, 2017

Page 2: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

This Page is intentionally left blank

Page 3: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway i Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

Table of Contents

SECTION 1 GENERAL .................................................................................................................. 1

1.1 PURPOSE .................................................................................................................................. 11.2 SCOPE ...................................................................................................................................... 11.3 SCOPE OF WORK – MAJOR ITEMS ................................................................................................ 11.4 COORDINATION WITH OTHER PROJECTS ....................................................................................... 21.5 THIRD PARTY AGREEMENTS (NON-UTILITY) .................................................................................. 21.6 DESIGN CODES AND MANUALS..................................................................................................... 21.7 REQUIREMENTS ......................................................................................................................... 61.8 DELIVERABLES ........................................................................................................................... 61.9 INDICATIVE PLANS ...................................................................................................................... 71.10 DIRECTIVE PLANS ....................................................................................................................... 71.11 CADD ...................................................................................................................................... 71.12 SCHEDULE OF PROJECT COMPLETION .......................................................................................... 71.13 WORK PAYMENT SCHEDULE ........................................................................................................ 71.14 INTERIM COMPLETION MILESTONE ................................................................................................ 9

SECTION 2 PROJECT MANAGEMENT ....................................................................................... 10

2.1 DESIGN-BUILDER’S ROLE .......................................................................................................... 102.2 DESIGN-BUILDER’S KEY PERSONNEL .......................................................................................... 102.3 MANAGEMENT PLANS AND SCHEDULES ....................................................................................... 12

2.3.1 Management Plans and Schedule Requirements .......................................................... 122.3.2 Workforce Participation Plan ......................................................................................... 122.3.3 Safety Plan ................................................................................................................... 122.3.4 Quality Control Plan ...................................................................................................... 132.3.5 Overall Design-Build Team Organizational Plan ............................................................ 132.3.6 Design Management Plan ............................................................................................. 132.3.7 Construction Management Plan .................................................................................... 142.3.8 Design Review Plan ..................................................................................................... 142.3.9 Transportation Management Plan/Emergency Response Plan ...................................... 14

2.4 BASELINE PROGRESS SCHEDULE ............................................................................................... 152.5 MEETINGS ............................................................................................................................... 152.6 COMPUTER AND NETWORKING REQUIREMENTS ........................................................................... 152.7 DEPARTMENT’S CONSULTATION AND WRITTEN COMMENTS ........................................................... 162.8 PROJECT WISE ........................................................................................................................ 16

SECTION 3 ENVIRONMENTAL ................................................................................................... 18

3.1 SCOPE .................................................................................................................................... 183.2 ENVIRONMENTAL APPROVALS .................................................................................................... 183.3 REQUIREMENTS ....................................................................................................................... 19

3.3.1 General ........................................................................................................................ 193.3.2 Environmental Plans ..................................................................................................... 193.3.3 Soil Erosion and Water Pollution Control ....................................................................... 193.3.4 Threatened And Endangered Species Coordination ...................................................... 203.3.5 Asbestos Containing Materials ...................................................................................... 203.3.6 Special Requirements for Removal of Abandoned Material from the former “NY Depot”Lease Site 213.3.7 Environmental Plan Deliverables .................................................................................. 22

SECTION 4 GENERAL PROJECT SCOPE OF WORK ................................................................ 23

4.1 SCOPE .................................................................................................................................... 23

Page 4: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway ii Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

4.2 STANDARDS ............................................................................................................................. 234.3 REQUIREMENTS ....................................................................................................................... 23

4.3.1 Field Office ................................................................................................................... 234.3.2 Salvage ........................................................................................................................ 244.3.3 Surplus Quantity ........................................................................................................... 244.3.4 Sidewalk Plowing Coordination During Winter Shutdown .............................................. 24

SECTION 5 SURVEYING AND GIS ............................................................................................. 25

5.1 SCOPE .................................................................................................................................... 255.2 STANDARDS ............................................................................................................................. 255.3 REQUIREMENTS ....................................................................................................................... 25

5.3.1 Project Survey Control .................................................................................................. 255.3.2 Department-supplied Data ............................................................................................ 255.3.3 Survey Reports, Records and Maps.............................................................................. 255.3.4 Permanent Survey Markers .......................................................................................... 26

5.4 SURVEYING AND GIS DELIVERABLES .......................................................................................... 26

SECTION 6 RIGHT-OF-WAY ....................................................................................................... 27

6.1 SCOPE .................................................................................................................................... 276.2 REQUIREMENTS ....................................................................................................................... 27

6.2.1 Right-of-Way Fencing ................................................................................................... 276.2.2 Property Interests Identified by the Design-Builder for its Convenience ......................... 276.2.3 Right of Way Markers ................................................................................................... 276.2.4 Work Limitations on Use and Occupancy Parcels ......................................................... 27

SECTION 7 PUBLIC INVOLVEMENT .......................................................................................... 28

7.1 SCOPE .................................................................................................................................... 287.2 STANDARDS ............................................................................................................................. 287.3 REQUIREMENTS ....................................................................................................................... 28

7.3.1 Public Outreach ............................................................................................................ 287.3.2 Media Relations ............................................................................................................ 297.3.3 Public Information Meeting ........................................................................................... 29

SECTION 8 UTILITIES ................................................................................................................. 30

8.1 SCOPE .................................................................................................................................... 308.2 STANDARDS ............................................................................................................................. 308.3 GENERAL REQUIREMENTS ......................................................................................................... 30

8.3.1 Utility Relocation Agreements ....................................................................................... 318.3.2 Other Utility Conflicts .................................................................................................... 31

SECTION 9 GEOTECHNICS ........................................................................................................ 32

9.1 SCOPE .................................................................................................................................... 329.2 STANDARDS ............................................................................................................................. 329.3 DESIGN REQUIREMENTS ........................................................................................................... 32

9.3.1 Geotechnical Work Plan ............................................................................................... 329.3.2 Geotechnical Investigations .......................................................................................... 339.3.3 Geotechnical Data Report ............................................................................................. 339.3.4 Excavations and Embankments .................................................................................... 349.3.5 Geotechnical Design Report ......................................................................................... 349.3.6 Retaining Walls ............................................................................................................ 359.3.7 Geotechnical Instrumentation and Construction Monitoring ........................................... 359.3.8 Temporary Works ......................................................................................................... 36

9.4 CONSTRUCTION REQUIREMENTS ................................................................................................ 369.4.1 Dewatering and Groundwater Control ........................................................................... 369.4.2 Structure Foundations .................................................................................................. 369.4.3 Excavations and Embankments .................................................................................... 37

Page 5: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway iii Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

9.4.4 Condition Surveys ........................................................................................................ 399.5 DELIVERABLES ......................................................................................................................... 39

SECTION 10 STRUCTURES .......................................................................................................... 40

10.1 SCOPE .................................................................................................................................... 4010.2 STANDARDS ............................................................................................................................. 4010.3 DESIGN REQUIREMENTS ......................................................................................................... 40

10.3.1 Components ................................................................................................................. 4010.3.2 Aesthetics..................................................................................................................... 40

10.4 DEMOLITION REQUIREMENTS ............................................................................................ 4110.4.1 Scope ........................................................................................................................... 4110.4.2 Standards ..................................................................................................................... 41

10.5 CONSTRUCTION REQUIREMENTS ...................................................................................... 4110.5.1 Construction Vehicles on Bridge ................................................................................... 41

10.6 LOAD RATING REQUIREMENTS .......................................................................................... 4110.7 DELIVERABLES ......................................................................................................................... 41

SECTION 11 LANDSCAPE ARCHITECTURE ............................................................................... 42

11.1 SCOPE .................................................................................................................................... 4211.2 STANDARDS ............................................................................................................................. 4211.3 GENERAL LANDSCAPE DEVELOPMENT ........................................................................................ 42

11.3.1 Existing Vegetation ....................................................................................................... 4211.3.2 Tree Replacement Factors ........................................................................................... 4211.3.3 Replacement Locations ................................................................................................ 4311.3.4 Proposed Planting ........................................................................................................ 43

SECTION 12 SIGNAGE, PAVEMENT MARKING AND SIGNALS .................................................. 49

12.1 SCOPE .................................................................................................................................... 4912.2 STANDARDS ............................................................................................................................. 4912.3 REQUIREMENTS ....................................................................................................................... 49

12.3.1 Design Requirements ................................................................................................... 4912.3.2 Construction Requirements .......................................................................................... 5012.3.3 Conduit/Cabling Requirements ..................................................................................... 5212.3.4 Signal Heads/ Signal Poles ........................................................................................... 5212.3.5 Cabinet/Disconnect Switch ........................................................................................... 5312.3.6 Pullbox ......................................................................................................................... 5312.3.7 Power Supply ............................................................................................................... 53

12.4 DELIVERABLES ......................................................................................................................... 53

SECTION 13 LIGHTING ................................................................................................................. 54

13.1 SCOPE .................................................................................................................................... 5413.2 STANDARDS ............................................................................................................................. 54

13.2.1 Standards ..................................................................................................................... 5413.2.2 References ................................................................................................................... 54

13.3 REQUIREMENTS ....................................................................................................................... 5413.3.1 General Requirements .................................................................................................. 5413.3.2 Permanent Lighting System .......................................................................................... 5513.3.3 Temporary Lighting System .......................................................................................... 56

13.4 DELIVERABLES ......................................................................................................................... 56

SECTION 14 INTELLIGENT TRANSPORTATION SYSTEMS (ITS) ............................................... 57

14.1 SCOPE .................................................................................................................................... 5714.2 STANDARDS ............................................................................................................................. 58

14.2.1 Standards ..................................................................................................................... 5814.3 REQUIREMENTS ....................................................................................................................... 58

14.3.1 Variable Message Sign (VMS) ...................................................................................... 58

Page 6: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway iv Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

14.3.2 IP Dome Camera .......................................................................................................... 5914.3.3 Fiber Optic Backbone ................................................................................................... 5914.3.4 Traffic Signal Interconnection........................................................................................ 6014.3.5 INFORM TMC Integration ............................................................................................. 6114.3.6 Electrical Work ............................................................................................................. 61

14.4 SYSTEM TEST PROCEDURES ..................................................................................................... 6214.4.1 Factory Testing ............................................................................................................. 6214.4.2 Operational Stand Alone Testing .................................................................................. 6214.4.3 Group Site Verification Testing ..................................................................................... 6314.4.4 Subsystem Integration Testing ...................................................................................... 6314.4.5 System Acceptance Testing.......................................................................................... 63

14.5 DOCUMENTATION REQUIREMENTS .............................................................................................. 6414.5.1 Shop Drawings and Test plans ..................................................................................... 64

SECTION 15 WORK ZONE TRAFFIC CONTROL AND ACCESS .................................................. 65

15.1 SCOPE .................................................................................................................................... 6515.2 STANDARDS ............................................................................................................................. 6515.3 REQUIREMENTS ....................................................................................................................... 65

15.3.1 General Requirements .................................................................................................. 6515.3.2 Work Zone Traffic Control Plan ..................................................................................... 6515.3.3 General Restrictions ..................................................................................................... 6615.3.4 Access to Commercial Properties and Driveways ......................................................... 6615.3.5 Closure Restrictions ..................................................................................................... 6615.3.6 Minimum Lane Widths during Construction ................................................................... 6715.3.7 Portable Variable Message Signs ................................................................................. 6715.3.8 Temporary and Interim Pavement Markings .................................................................. 6715.3.9 Coordination with Regional Traffic Management Center ................................................ 6715.3.10 Emergency Response and Transportation Management Plans ..................................... 6715.3.11 Lifting Operations ......................................................................................................... 68

SECTION 16 PAVEMENT DESIGN AND CONSTRUCTION .......................................................... 6916.1 SCOPE .................................................................................................................................... 6916.2 STANDARDS ............................................................................................................................. 6916.3 REQUIREMENTS ....................................................................................................................... 69

16.3.1 Full Depth Reconstruction ............................................................................................. 6916.3.2 Milled and Resurfaced Roadways ................................................................................. 7016.3.3 Temporary Pavement ................................................................................................... 7016.3.4 Utility Trench Restoration.............................................................................................. 70

SECTION 17 DRAINAGE AND STORMWATER ............................................................................ 71

17.1 SCOPE .................................................................................................................................... 7117.2 STANDARDS ............................................................................................................................. 7117.3 REQUIREMENTS ....................................................................................................................... 71

17.3.1 Drainage Report ........................................................................................................... 7117.3.2 Connections to Existing Systems .................................................................................. 7117.3.3 Spill Management ......................................................................................................... 72

17.4 DELIVERABLES ......................................................................................................................... 72

SECTION 18 HIGHWAY DESIGN .................................................................................................. 73

18.1 SCOPE .................................................................................................................................... 7318.2 STANDARDS ............................................................................................................................. 7318.3 REQUIREMENTS ....................................................................................................................... 73

18.3.1 General ........................................................................................................................ 7318.3.2 Design Requirements ................................................................................................... 7318.3.3 Barrier Systems and Impact Attenuators ....................................................................... 7718.3.4 Clear zone .................................................................................................................... 77

Page 7: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway v Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

18.4 DESIGN EXCEPTIONS AND NON-STANDARD FEATURES ................................................................. 77

SECTION 19 STANDARDS............................................................................................................ 78

19.1 GENERAL REQUIREMENTS ......................................................................................................... 7819.2 SPECIFIC REQUIREMENTS ......................................................................................................... 78

SECTION 20 SECURITY ................................................................................................................ 79

Page 8: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

This Page is intentionally left blank

Page 9: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 1 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 1 GENERAL

1.1 PURPOSE

This Part 3 establishes the basic Requirements of the Project. The Contract Documents,NYSDOT standard drawings, manuals and specifications, and the referenced Design Codesand Manuals shall be followed for the preparation of design and construction documents andthe execution of the Work. Any proposed deviation from the Contract requirements or NYSDOTstandards shall be submitted to the Department’s Design Quality Assurance Engineer forreview, and shall require the submission of a Non-conformance Report, where the Design-Builder is to identify, explain, and justify any deviation from the established criteria to theDepartment’s Design Quality Assurance Engineer.

All designs shall be prepared in U.S. Customary units. The Design-Builder shall be responsiblefor converting any mapping, plans, etc. into U.S. Customary units as necessary for thecompletion of the Project.

The design and construction shall be in conformance with the latest edition of the New YorkState Department of Transportation, Standard Specifications, with addenda, issued by theOffice of Engineering, current as of the date of Proposal submission, excluding Section 100,which is superseded by Part 2, Section DB 100 of the Contract Documents, and except asotherwise noted in these Contract Documents.

The Design-Builder shall prepare Project Specifications for the Project, for Work Items notcovered by the NYSDOT Standard Specifications or applicable Special Specifications, and shallprepare Design Plans for the Project in accordance with NYSDOT standards for general contentand format, and in accordance with the Contract.

The Design-Builder shall prepare and submit a Non-conformance Report (in accordance withthe provisions of DB §105-16) for any Work proposed to be or actually performed that does notconform to the Contract requirements and for any deviations from NYSDOT standards.

1.2 SCOPE

The Design-Builder shall be responsible for complying with all terms of the Contract Documents.The Design-Builder shall review and understand all terms and conditions of the ContractDocuments prior to the commencement of the Project and shall be responsible for determiningthe full Scope of the Project by undertaking a thorough examination of the Contract Documents,the Reference Documents and the Project Site.

1.3 SCOPE OF WORK – MAJOR ITEMS

The scope of work for the Project includes but is not limited to the following items:

A. Raising NY Route 878 to an elevation above the 100-year base flood elevation as part ofthe Emergency Coastal Storm Evacuation Route;

B. Widening of Nassau Expressway and Bay Boulevard to add auxiliary lanes andshoulders;

C. Ground Settlement Treatment Mitigation;

Page 10: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 2 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

D. Installation of a closed stormwater drainage system with detention/water quality basin;

E. Mitigation of wetland impacts;

F. Removal and disposal of the soil debris pile located at Incinerator Road and BayBoulevard for constructing a detention pond as well as an area for wetland mitigation;

G. Pavement reconstruction including; paving, pavement markings, and traffic signalization;

H. Installation of new traffic signals;

I. Replacement of the 48” NYCDEP Water Main within the project limits;

J. Relocation and/or preservation of other existing utilities;

K. Modification of existing leased areas impacted by the project;

L. Installation of street lighting; and

M. Construction of a new shared use path for bicyclists and pedestrians

1.4 COORDINATION WITH OTHER PROJECTS

The Design-Builder shall coordinate the work so as not to conflict with others projects occurringwithin or abutting the Contract limits. It is expected that the following projects will be underconstruction during construction of this Contract:

There are no known projects currently scheduled to occur within or adjacent to the Contractlimits prior to the Project Completion Date

1.5 THIRD PARTY AGREEMENTS (NON-UTILITY)

No Third Party Agreements have been developed in connection with this Project.

For information regarding Preliminary DB Utility Work Agreements, refer to Section 8 of this Part3.

1.6 DESIGN CODES AND MANUALS

In addition to this Part 3, Project Requirements, the Design-Builder must comply with allapplicable engineering codes and standards, including those of the various Federal, State, andlocal jurisdictions.

If codes, standards and/or manuals are specified herein for the design of an element of theProject, then the edition(s) in effect on the Proposal due date shall be applicable to the Project.Responsibility for design remains with the Design-Builder in accordance with the terms andconditions of the Contract. If a code, manual or standard is subsequently modified by theissuer, the Design-Builder shall notify the Department of such modification(s) and request theDepartment’s decision regarding application of the modification(s).

All Work shall conform to the following documents. In the event of a conflict between the codesand the referenced documents listed below, the more stringent requirements, as determined by

Page 11: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 3 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

the Department, shall apply.

For Work not specifically covered by the individual sections of the Project Requirements, theDesign-Builder shall, at a minimum, apply the Standards normally applied by NYSDOT for suchWork, to the extent they do not conflict with express requirements in the Contract Documents.The Design-Builder shall be solely responsible for ensuring that it identifies and applies allcorrect Standards.

AASHTO:

· A Guide for Accommodating Utilities within Highway Right-of-Way

· A Policy on Design Standards - Interstate System

· A Policy on Geometric Design of Highways and Streets

· Construction Handbook for Bridge Temporary Works

· Guide for Bicycle Facilities, 2012 Forth Edition

· Guide Design Specifications for Bridge Temporary Works

· Guide for the Design of Pavement Structures (with Supplement)

· Guide Specification for Bridge Railings (1989)

· Guide Specifications for LRFD Seismic Bridge Design

· LFRD Bridge Construction Specifications

· Manual for Assessing Safety Hardware (MASH)

· Manual for Bridge Evaluation

· Manual on Subsurface Investigations

· Mechanistic-Empirical Pavement Design Guide (MEPDG),

· Roadside Design Guide

· Roadway Lighting Design Guide

· Standard Specifications for Structural Supports for Highway Signs, Luminaires andTraffic Signals.

AISC:· Steel Construction Manual

ANSI· ANSI/AASHTO/AWS D1.5 Bridge Welding Code

· ANSI/IES Approved Recommended Practice for Roadway Lighting, RP-8-00

· ANSI Z133.1, Safety Requirements for Pruning, Trimming, Repair, Maintaining, andRemoving Trees and for Cutting Brush.

· APTA SS-SIS-RP-007-10, Crime Prevention through Environmental Design (CPTED) forTransit Facilities

Asphalt Institute:

Page 12: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 4 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· Drainage of Asphalt Pavement Structures

ASTM:· E2213-03 Standard Specification for Telecommunications and Information Exchange

Between Roadside and Vehicle Systems

· E2259-03 Standard Guide for Archiving and Retrieving ITS-Generated Data

· E2468-05 Standard Practice for Metadata to Support Archived Data ManagementSystems

· E2655-08 Standard Guide for Reporting Uncertainty of Test Results and Use of theTerm Measurement Uncertainty in ASTM Test Methods

Federal Geographic Data Committee:· GIS Standards

FHWA:· FHWA NHI-00-043 Mechanically Stabilized Earth Walls and Reinforced Soil Slopes

Design and Construction Guidelines

· FHWA NHI-01-004 River Engineering for Highway Encroachments

· FHWA NHI-05-123 Soil Slope and Embankment Designs

· FHWA NHI-11-032 GEC No. 3 LRFD Seismic Analysis and Design of TransportationGeotechnical Features and Structural Foundations

· FHWA HI-99-007 Rock Slopes Reference Manual

· HEC 18 Evaluating Scour at Bridges

· HEC 23 Bridge Scour and Stream Instability Countermeasures

· Manual of Uniform Traffic Control Devices (MUTCD)

· Pavement Publications

· Standard Highway Signs and Markings (SHSM) Book

· Steel Bridge Design Handbook

· Technical Advisory T6640.8A, 10/30/87 (environmental analyses)

· Traffic Monitoring Guide

NFPA:

· NFPA 70 – National Electrical Code (NEC)

· 502: Standard for Road Tunnels, Bridges, and Other Limited Access Highways

NYSDEC:· Standards and Specifications for Erosion and Sediment Control (SESC)

· Stormwater Management Design Manual (SMDM)

NYSDOT:· Annual Report titled "Axle Factor Update"

Page 13: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 5 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· Approved Materials List

· Bridge Detail (BD) Sheets US Customary (NYSDOT BD Sheets)

· Bridge Inspection Manual

· Bridge Inventory Manual

· Bridge Manual

· Bridge Safety Assurance Seismic Vulnerability Manual

· Comprehensive Pavement Design Manual

· Consultant Instructions (CIs)

· Design Consultant Manual

· Engineering Bulletins (EBs)

· Engineering Instructions and Directives (EIs and EDs)

· Environmental Procedures Manual (EPM) / The Environmental Manual (TEM)

· GCP-17, Procedure for the Control of Granular Materials

· Geotechnical Design Manual, including all appendices

· Highway Design Manual (HDM)

· Land Surveying Standards and Procedures Manual

· NYSDOT LRFD Bridge Design Specifications

· Manual for Uniform Record Keeping

· Materials Bureau - Applicable Sampling and Testing Manuals, Inspection Manuals, andMaterials Methods.

· New York State Supplement to the Manual on Uniform Traffic Control Devices

· Overhead Sign Structure Design Manual

· Policy and Standards for the Design of Entrances to State Highways

· Policy on Highway Lighting

· Prestressed Concrete Construction Manual (PCCM)

· Project Development Manual

· Reference Marker Manual

· Rules and Regulations Governing the Accommodation of Utilities within the StateHighway Right of Way

· Special Specifications as indicated in the Contract Documents

· Standard Specifications for Construction and Materials

· Steel Construction Manual (SCM)

· Structures Design Advisories

· Structures Technical Advisories

Page 14: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 6 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· U.S. Customary Standard Sheets

· Work Zone Traffic Control Manual

· ROW Mapping Procedure Manual

The above is a partial listing of applicable NYSDOT Engineering Manuals and Guidelines. TheDesign-Builder shall perform the Work in conformance with all NYSDOT Engineering Manualsand Guidelines in effect on the Proposal due date.

OSHA:

· PART 1926 - Safety And Health Regulations For Construction

SPC:· Society of Protective Coatings Standards

USDOJ:· ADA Accessibility Guidelines for Buildings and Facilities

USDOT:· ADA Standards for Transportation Facilities

1.7 REQUIREMENTS

The “Requirements” subsection of the individual sections of Part 3 – Project Requirementsestablishes the Department’s expectations with respect to specific Project elements. Theseinclude administrative, managerial and technical considerations as deemed appropriate to thesubject, and encompass performance specifications, design criteria, and directive instructionsas the Department deems best suited to the subject. The Design-Builder shall develop itsDefinitive Design, Design Plans and Project Specifications in conformance with this Part 3 –Project Requirements.

The Design-Builder shall be responsible for meeting all requirements and terms contained inthis Part 3 – Project Requirements unless explicitly stated otherwise.

The specific requirements in this Part 3 – Project Requirements may be more stringent and shallgovern over the criteria given in the Standards. Where a specific requirement in this Part 3 –Project Requirements is more stringent than the criteria specified in a Standard, said specificrequirement shall become the basis for determining compliance. Non-standard features needingjustification and FHWA and/or NYSDOT approval are defined as those not meeting the criteriacited in the Standards listed in this Part 3 – Project Requirements.

1.8 DELIVERABLES

Deliverables to be submitted by the Design-Builder throughout the design and construction ofthis Project, and upon completion of the Project, are specified in the NYSDOT manuals listed inSection 1.6 of this Part 3 – Project Requirements. These shall supplement the review plan andconsultation and written comment cycles cited in DB §111-8 through DB §111-14. The Design-Builder may submit deliverables for the Department’s consideration or consultation and written

Page 15: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 7 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

comment in addition to those cited in the NYSDOT manuals. The Design-Builder shall includesuch additional submittals in its review plan and revise the review plan as necessary toincorporate sufficient advance notice to the Department. It is the goal of the Department that allreview and comments be completed within 10 business days.

Unless otherwise indicated elsewhere in the Contract Documents, or directed by theDepartment’s Project Manager, all deliverables shall be submitted in both electronic format andhardcopy format. Acceptable electronic formats include Bentley Microstation .dgn format andBentley InRoads.alg and dtm format, Microsoft Word®, Microsoft Excel®, ArcMAP, orsearchable portable document format (PDF) files, with no copy or password protection on thefile content, unless otherwise indicated in a specific section of this Part 3 - Project Requirementsor a Standard cited in a specific section of this Part 3 - Project Requirements.

1.9 INDICATIVE PLANS

The Indicative Plans, if provided to the Design-Builder in Part 6 – RFP Plans, convey an overallpotential solution to the Project’s needs that the Design-Builder may choose to consider indeveloping its design. The designs presented herein have been developed to a point sufficientto present the general concepts of the Project and specifically to show the current highwayboundaries and the extent of property acquisitions provided by the Department. The IndicativePlans are not mandatory, with the exception of elements specifically mentioned elsewhere inthis Part 3.

1.10 DIRECTIVE PLANS

The Directive Plans, if provided to the Design-Builder in Part 6 – RFP Plans, depict requiredelements and components of the Project within specifically defined parameters. The Design-Builder has no latitude to adjust components or details shown on Directive Plans, unlessspecifically noted or through an approved Alternative Technical Concept (ATC).

1.11 CADD

CADD formatting for Design and As-Built Plans shall conform to the Department’s CADDDrafting Standards and CADD Design Standards in effect on the Proposal due date.

1.12 SCHEDULE OF PROJECT COMPLETION

All work on the design and on the construction shall be completed in accordance with Part 1, DBAgreement, Article 2, Contract Time, but in no case shall the Project Completion Date be laterthan December 31, 2019.

1.13 WORK PAYMENT SCHEDULE

Progress Payments will be made as each Work Item is completed to the satisfaction of theDepartment’s Construction Quality Assurance Engineer. Progress payments shall be subject tothe requirements of DB §109-2. Payments for Design, Construction Inspection and Laboratoryactivities will be made in conformance with DB § 109-2.2.

WORK PAYMENT SCHEDULE

Page 16: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 8 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM

PRICE (To becompleted by D-

B)1

Unclassified Excavation & Disposal (Roadway C & DMat’l.)

10%

Debris Mound Removal to El. 10 30%Embankment Settlement Mitigation (Geotech) 20%Roadway Embankment, Subbase, Paving, ConcreteBarrier, Curbs & Sidewalks

8%

Pav’t Markings / Signing & Striping 2%Drainage System 4%48” Watermain Relocation 12%Utility Relocations 2%ROW Lease Area Work (Nursery / COSTCO / BattingCage)

2%

Retaining Walls 4%Street lighting 2%Traffic Signals & ITS 4%Landscaping & Plantings 2%Wetland Mitigation / Water Quality Basin / Culvert 6%WZTC 11%Survey 1%Punch list work, Site Cleanup and Restoration 2% (fixed)Final Acceptance (Per DB §109-12.1) 1% (fixed)Final Agreement (Per DB §109-12.2) 2% (fixed)

Notes: (1) See Work Payment Schedule included in ITP, Appendix E. Percent of Lump SumPrice to be completed by the Proposer. Total percentage for all work items shallequal 100%.

(2) Subsequent to Selection of Best Value, the Design-Builder may submit to theDepartment a more detailed Work Payment Schedule which breaks individual workitems into multiple stages, for the Department’s review and acceptance. However,the sum of the percentages proposed for each stage shall equal the percentage forthat work item submitted by the Design-Builder included on Form WPS, and in nocase shall the payment for any individual stage be more than 50% nor less than 10%of the total percentage bid for that work item.

Page 17: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 9 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

1.14 INTERIM COMPLETION MILESTONE

This Project’s Interim Completion Milestones, if applicable, are defined as shown in Part 5 –Special Provisions.

The Interim Completion Milestone Dates may not be changed without written approval by theDepartment’s Project Manager.

Page 18: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 10 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 2 PROJECT MANAGEMENT

2.1 DESIGN-BUILDER’S ROLE

The Design-Builder shall have responsibility for controlling and managing the Work, includingthe responsibility for quality management as defined in the Contract Documents, Part 2 - DB §§111, 112 and 113. This section identifies the Design-Builder’s Key personnel and summarizesthe Management Plans to be produced by the Design-Builder in accordance with the ContractDocuments.

2.2 DESIGN-BUILDER’S KEY PERSONNEL

The positions listed below shall be the Design-Builder’s key personnel for the Project. KeyPersonnel are preferred to have experience on projects of a similar size, type of work, andcomplexity as this Project, and should meet the qualifications described below. Proposed staffwith qualifications less than those described below will receive a reduced score compared tostaff that meet or exceed the described qualifications. Any requirements described as “shallhave...” or “shall be…”are determined to be minimum response requirements. The Design-Builder shall provide personnel that meet these minimum requirements.

The Design-Builder’s Project Manager shall be the Design-Builder’s representative and singlepoint of contact with the Department.

The Department’s Project Manager may designate other Key Personnel positions as needed atany time during the Contract.

A) Project Manager: Shall have a minimum of 10 years, but preferably15 years, demonstrated experience in construction and constructionmanagement of bridge and transportation and infrastructure projectswith preferably similar size and type of work as this Project, andpreferably including projects with compressed timelines, andcommunity information requirements. Such experience inconstruction and management-of-construction should include at leastone bridge construction project having a construction value in excessof $25,000,000. The Project Manager, who should have Design-Buildexperience and have extensive project management experience, canhold only this one Key Personnel position. It is preferred, but notrequired, that this individual be licensed and currently registered as aProfessional Engineer in the State of New York. The ProjectManager shall dedicate no less than 50% of their work time to thisProject.

B) Design Manager: Shall be licensed and currently registered as aProfessional Engineer in the State of New York, shall be an owner oremployee of the Designer and shall have a minimum of 15 yearsdemonstrated experience in managing design for infrastructure andbridge projects preferably of similar scope as this Project. TheDesign Manager should have Design-Build experience, and shouldhave specific experience on projects of similar size and type. TheDesign Manager can hold only this one Key Personnel position. The

Page 19: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 11 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

Design Manager shall dedicate no less than 75% of their work timeto this Project.

C) Quality Manager: Shall have demonstrated experience in bridgedesign and major infrastructure construction with at least 10 yearsexperience in quality assurance and quality control activities,including preparation and implementation of Quality Plans andprocedures for design and construction. The Quality Manager canhold only this Key Personnel position. The Quality Manager shallhave experience of quality systems based on ISO 9001, and shouldhave experience with the quality systems of the Department. TheQuality Manager shall dedicate no less than 40% of their work timeto this Project

D) Resident Engineer: Should be licensed and currently registered asa Professional Engineer in the State of New York and should havedemonstrated at least 10 years experience in bridge and highwayconstruction inspection, including at least 5 years as a ResidentEngineer. The Resident Engineer shall have performed ResidentEngineer duties on a project within the last 3 years.

E) Lead Civil Engineer: Shall be licensed and currently registered as aProfessional Engineer in the State of New York and shall have atleast 10 years experience in civil roadway design, includingcongestion management and the preparation of Work Zone TrafficControl Plans.

F) Lead Geotechnical Engineer: Shall be licensed and currentlyregistered as a Professional Engineer in the State of New York andshall have a minimum of 10, but preferably 15, years of experiencewhich should include the following: planning and overseeingsubsurface exploration programs for highway structures/facilities; thedevelopment of design soil/rock profiles, for the purpose ofgeotechnical analysis, design, and construction; design of structurefoundations and earth support structures; analysis and design forstatic and dynamic (seismic) loading under current LRFD; analysisand design of mitigation measures for embankment settlement andstability; analysis and design of both temporary and permanent earthsupport structures; and interpreting geotechnical instrumentationprograms.

G) Project Superintendent: Should have at least 10, but preferably 15years of demonstrated experience overseeing work on highwayconstruction projects. Experience should include directing andcoordinating the activities of a contractor’s workforce and allsubcontractors, ensuring work progressed according to schedule,within budget and that material and equipment were delivered to thesite on time. The Project Superintendent should have experience as

Page 20: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 12 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

Project Superintendent on a highway project valued at $50M ormore.

2.3 MANAGEMENT PLANS AND SCHEDULES

2.3.1 Management Plans and Schedule Requirements

The Design-Builder shall submit to the Department’s Project Manager, for review and commentor approval (as applicable), all the Management Plans listed in Table 2-1. Following receipt ofthe Department’s acceptance or approval of the individual Management Plans, as described inthe Contract Documents, the Management Plans shall be resubmitted to the Department’sProject Manager as the Design-Builder’s consolidated Project Management Plan for the Project.

Table 2-1 – Project Management Plans

Plan Title Contract DocumentReference

Initial PlanSubmitted withthe Proposal?

SubmittalDeadline

Workforce Participation Plan DB § 102-9.4B No 60 Days after NTP

Safety Plan* DB § 107-7.5 No

30 Days after NTPor 30 days prior to

beginning anyconstruction Work

Quality Control Plan* DB § 113 Yes 45 Days after NTPOverall Design-Build TeamOrganization Plan

Project RequirementSection 2.3.5 Yes 25 Days after NTP

Design Management Plan Project RequirementSection 2.3.6 No 30 Days after NTP

Construction Management Plan Project RequirementsSection 2.3.7 No 45 Days after NTP

Design Review Plan DB § 111-7 No 10 Days after NTPTransportation ManagementPlan/Emergency Response Plan

Part 3, Section15.3.10 No 30 Days after NTP

Initial Baseline Progress Schedule Project RequirementsSection 2.4 Yes 15 Days after NTP

* Requires Department approval

2.3.2 Workforce Participation Plan

The Design-Builder shall develop a Workforce Participation Plan to meet the requirements ofDB §102-9.4B and submit it to the Department’s Project Manager for review and comment.

2.3.3 Safety Plan

The Design-Builder shall develop a Safety Plan to meet the requirements of Part 2, DB §107-7.5and submit it to the Department’s Project Manager for written approval in accordance with DB§107-7.7. No construction Work shall progress and no payment shall be made to the Design-Builder until the Safety Plan is approved by the Department.

Page 21: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 13 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

2.3.4 Quality Control Plan

The Design-Builder shall use the Initial Quality Control Plan submitted with the TechnicalProposal, modify and develop it, as necessary, to include the content required by Part 2, andsubmit it to the Department’s Project Manager for written approval in accordance with Part 2 DB§113. The Quality Control Plan shall be revised and resubmitted to the Department’s ProjectManager within 14 calendar days of receipt of the Department’s written comments andresubmitted as required until Approved by the Department’s Project Manager. No offsitefabrication Work or Construction Work shall commence before the Quality Control Plan hasbeen approved by the Department’s Project Manager. No payment will be made to the Design-Builder until the Quality Control Plan has been approved by the Department.

2.3.5 Overall Design-Build Team Organizational Plan

The Design-Builder shall update the Initial Overall Design-Build Team Organization Plan bycombining the Organizational Structure Chart and the Communication Protocol Graphic andnarrative and expanding upon these initial submittals into a more comprehensive document. Itshall describe the design and construction organizational arrangements it intends to implement.The organizational arrangements described should clearly identify responsibilities and reportinglines of staff, particularly relating to Key Personnel.

The Design-Builder shall include an organization chart and communication protocol graphic (onan 11" x 17" sheet of paper), illustrating the Proposer’s Key Personnel and their prospectiveroles and responsibilities, as well as other principal participants and any known Subcontractorshaving a material role in the Project’s design Work, design check Work, construction Work andconstruction inspection Work.

The Design-Builder shall describe the interrelationships and interfaces between each disciplinewithin the Proposer’s organization (e.g., design, design check, shop drawing preparation andreview, construction, and quality management).

The Overall Design-Build Team Organization Plan shall also describe the interrelationships andinterfaces between the Design-Builder’s organization, the Department and other governmentalagencies, utility owners, stakeholders, businesses, the public and other contractors working inthe vicinity and impacted by the construction of the Project. This description shall also, at aminimum, address the following activities:

A) Reviews of plans and permits;

B) Progress, workshop, partnering and utility coordination meetings; and

C) Construction, engineering and inspection activities.

2.3.6 Design Management Plan

The Design-Builder shall provide a Design Management Plan and submit it to the Department’sProject Manager for Review and Comment.

The Design Management Plan shall include the Design-Builder’s approach to managing theProject, including:

Page 22: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 14 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

A) The Design-Builder’s understanding of the Project Requirements.

B) The Design-Build Team’s organizational structure and lines of responsibility.

C) The Design Builder’s approach to delivering the Project, including how the Design-Builder will address logistical challenges of the Project, scheduling to complete theProject on time and on or under budget with emphasis on quality, design, andconstruction.

D) How the Design-Builder will manage and coordinate the design, design quality controland design reviews.

E) The means of reporting on the design progress; the means of tracking quality controlreviews and the resolution of comments on the design and describes how design non-conformance issues will be resolved.

F) How the design effort will be coordinated with construction activities and constructionmeans and methods for the Project.

G) A description of the proposed methods to control the design progression for the overallproject to support the construction schedule.

2.3.7 Construction Management Plan

The Design-Builder shall provide a Construction Management Plan, which may include relevantmaterial submitted with its Proposal and submit it to the Department’s Project Manager forReview and Comment.

The Construction Management Plan shall provide how well the Design-Builder understands andis organized to manage construction, construction quality control and the tools that will beimplemented to provide seamless interaction with the Department’s Construction QualityAssurance Engineer for the construction of a quality Project; provides how the progress of theconstruction work is reported to the Department and for control of the Work; provides how non-conformance issues in construction will be resolved; provides the method of updating theBaseline Schedule; provides how the work will be progressed in coordination with otheragencies; provides the methods of maintaining detours and evaluates how the interaction withthe Construction Inspection Professional Engineering Firm and the Materials TestingFirm/Laboratory will occur and how these firms will contribute to the Construction Managementand quality of the Project.

2.3.8 Design Review Plan

The Design-Builder shall develop a Design Review Plan to meet the requirements of DB §111-7and submit it to the Department’s Project Manager for review and comment.

2.3.9 Transportation Management Plan/Emergency Response Plan

The Design-Builder shall develop a Transportation Management Plan/Emergency ResponsePlan to meet the requirements of Part 3, Section 15.3.10 and submit it to the Department’sProject Manager for review and comment.

Page 23: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 15 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

2.4 BASELINE PROGRESS SCHEDULE

The Design-Builder shall submit the Initial Baseline Progress Schedule that was submitted withthe Technical Proposal, including any updates that may be necessary due to a NTP datechange.

In addition, the Design-Builder shall expand and develop the Initial Baseline Progress Schedulein accordance with DB §108-1 and Part 5, Special Provision SP-3.

Design shall be considered complete when all Design related documents have been completedand accepted by the Department including: all calculations, specifications, records of designquality control reviews and procedures; descriptions of and justification for any non-standardfeatures created or retained as a result of the design; resolution of any non-conformancereports; and submission of “As Built” drawings.

Construction shall be considered complete when: the entire Scope of Work has beencompleted; any damage to the area caused by the Design-Builder’s performance of the Workhas been repaired to the satisfaction of the Department; all construction quality controldocuments, test and inspection reports and forms have been completed; As-Built drawings havebeen completed; and the work site(s) have been cleaned of any debris.

2.5 MEETINGS

The Design-Builder shall convene or participate in meetings as indicated in Part 2 DB §105-17.

It is the Department’s policy to use the principles of partnering to guide the management ofDesign-Build contracts and the Design-Build program within the parameters covered by thelaws, regulations, and other policies that govern the work. The Design-Builder shall convene orparticipate in meetings designed to foster the principles of partnering in accordance with Part 2DB §103-2.

The Design-Builder shall record the minutes for each meeting.

2.6 COMPUTER AND NETWORKING REQUIREMENTS

The Department will issue Citrix connection accounts to the Design-Builder and its ConstructionInspection Professional Engineering Firm (CIPE).

Upon request, the Department will also supply the Design Builder with a CSMIN networkconnection at the CIPE Field Office with the following Computer and Networking equipmentthrough a third party vendor:

· 1 Wireless connection with Router· 3 fully configured laptops w/ accessories (for RE, OE, and Chief Inspector)· 1 Multi Function Printer

The Design-Builder shall provide ALL additional Computer and Networking equipment to theCIPE as necessary. The Design-Builder will need to provide separate high-speedcommunication into the CIPE office for all non-CSMIN users. A separate printer will be neededfor the non-CSMIN users, as their laptops/computers will not be networked to the CSMIN MFP.It is recommended that the Design-Builder test the network connection success prior to fullyequipping its staff and the CIPE firm, to ensure both hardware and software compatibility.

Page 24: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 16 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The following computer related specifications reflect the current technology utilized by theDepartment when making Citrix Connections and are provided for informational purposes only:

• 2/HM65 Chipset, and Intel HD Graphics 3000 (or equivalent);• 2nd Generation Intel Core i5 2620M Processor, 2.70GHz (Turbo up to 3.40GHz),

1333MHz, 4MB L3 Cache;• Mobile Intel HM65 Chipset;• 14” diagonal LED-backlit HD anti-glare (1366x768);• Intel HD Graphics 3000;• 4 GB 1333 MHz DDR3 SDRAM – Dual Channel Active;• 250 GB 7200 RPM 2.5 inch hard drive – or 120 GB Intel SSD;• DVD R/W SuperMulti DL Drive;• Full Keyboard;• Broadcom 4313 GN 802.11 g/b/n 1x1 Wi-Fi Adapter;• 65W Hardware Kit;• 6 cell Li-ion Battery; and• Integrated Gigabit Ethernet

Computers shall have Citrix Receiver installed, which can be accessed at:

http://receiver.citrix.com/

2.7 DEPARTMENT’S CONSULTATION AND WRITTEN COMMENTS

The Department’s review, oversight, audit, and inspection activities are referred to as“consultation and written comment” (see Part 2, DB §105-16). The Department’s consultationand written comment will be provided to the Design-Builder in writing. The Design-Builder shallbe responsible for addressing the Department’s comments and shall indicate in writing whetherit concurs with the comments. If the Design-Builder does not concur with the Department’scomments, then the Department and Design-Builder will work together to resolve the issuebefore proceeding.

If agreement cannot be reached, the issue must be resolved as provided in the ContractDocuments for dispute resolution in accordance with Part 2 DB §109-10.

2.8 PROJECT WISE

ProjectWise is the preferred platform to be used to organize, manage, distribute/share andarchive electronic Project design documents for NYSDOT. However, the Design-Builder maypropose to utilize another internet-based platform for these purposes, subject to theDepartment’s acceptance. Should an alternate platform be selected, access is to be provided toFHWA-NY Division personnel. The documents to be posted to the selected platform typicallyinclude but are not limited to:

· Final design report and any modifications predicated by the Design-Builder’s actions;

· All studies and supporting reports;

· Permit Applications and Permits;

· Survey and ROW mapping;

· Photos taken prior to and during design;

Page 25: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 17 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· CADD and 2D/3D models files including current NYSDOT-supported Microstation andInRoads file formats;

· Engineering calculations to support designs;

· All drawing submissions (Definite, Interim, RFC, Final, As-Built, etc.);

· Engineer of Record’s estimate based on Work Payment Schedule; and

· Public Information.

All files posted to the selected platform shall be in accordance with the file naming conventionand submission procedures as defined in Appendix 14 of the NYSDOT Project DevelopmentManual.

The Design-Builder shall ensure that all electronic design documents are stored on the selectedplatform. Updates of engineering documents shall be provided on a monthly basis.

Regardless of the platform utilized during the progression of the Project, prior to Projectcompletion all files shall be posted to ProjectWise in accordance with the criteria listed above.

The Design-Builder may obtain a ProjectWise account by contacting the Department’s ProjectManager and providing the required account information per Appendix 14 of the ProjectDevelopment Manual.

Page 26: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 18 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 3 ENVIRONMENTAL

3.1 SCOPE

Except as otherwise detailed herein, the Design-Builder shall be responsible for preparing itsdesign, obtaining environmental approvals, carrying out construction activities, performingQuality Control, and undertaking other activities, including hazardous materials inspection andtesting, as needed to ensure compliance with the Project’s Environmental Requirements and allapplicable environmental laws and regulations.

This Project Requirement identifies certain required actions to be performed by the Design-Builder to ensure that the Environmental Requirements are complied with throughout theduration of the Project.

3.2 ENVIRONMENTAL APPROVALS

The Department has determined that this Project is a NEPA Class II, Categorical Exclusion.Class II actions that do not individually or cumulatively have a significant environmental effectare excluded from the requirement to prepare an Environmental Impact Statement (EIS) or anEnvironmental Assessment (EA).

The Department has determined that this project is a SEQRA Type II Action in accordance with17 NYCRR, Part 15. No further SEQRA processing is required.

The following environmental approvals/permits have been obtained or are in the process ofbeing obtained by the Department:

· NYSDEC Article 25 and Section 401 Water Quality Certification· USACE Section 10/404 Nationwide Permit #23 Authorization· NYS DOS Coastal Zone Program Consistency Concurrence· USFWS/NMFS Endangered Species Act Concurrence

The Design-Builder is responsible to obtain all other environmental permits and approvalsneeded for the Project and not previously obtained by the Department. Approvals previouslysecured for the Project are included in Part 7 – Engineering Data.

It is advisable that the Design-Builder hold a pre-application meeting with NYSDEC andcoordinate with NYCDEP, as appropriate, within 60 days from NTP.

The Design-Builder may request a review by the Department of any permit/approvalapplications which must be submitted to third parties. For any such review requested, theDesign-Builder shall allot five (5) business days for the Department to review and comment onthe completeness and adequacy of the application materials. It shall then be the Design-Builder’s discretion to address any Department comments or elect to move forward with theapplication materials as submitted.

If during detailed design and/or construction the Design-Builder introduces design elements,variations, or methodologies that potentially induce environmental impacts not covered underthe obtained approvals/permits by the Department, then the Design-Builder shall re-evaluate theNEPA process for this Project and obtain the necessary Environmental Approvals/Permits forthe Project prior to proceeding with construction. This requirement also applies to proposed

Page 27: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 19 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

variations which may affect resources covered under Section 106, Section 4(f), Executive Order11990 (wetlands), and other applicable federal and state environmental regulations.

3.3 REQUIREMENTS

3.3.1 General

A) The Design-Builder shall procure all Environmental Approvals as needed for all Design-Builder-located areas, including staging, borrow and disposal sites, and any other areasused by the Design-Builder, for its convenience, in the execution of the Project;

B) The Design-Builder shall be responsible for preparing all permit application materials andobtaining all Environmental Approvals necessary for the Project and not already obtainedby the Department, including those that are precipitated by the Design-Builder’s design oractions that deviate from the requirements of any acquired permit(s) (if any). For any suchapprovals required to be obtained by the Design-Builder that must formally be issued in theDepartment's name, the Department will cooperate with the Design-Builder as reasonablyrequested by the Design-Builder, including execution and delivery of appropriateapplications and other documentation as prepared by the Design-Builder;

C) The Design-Builder shall be solely responsible for compliance with and violations of anyEnvironmental Requirements;

D) The Design-Builder is responsible for any fines, non-compliance, violations, or damagesincurred by reason of failure of the Design-Builder to comply with Environmental Approvals.Resulting fines or damages shall be deducted from monies owed the Design-Builder; and

E) NYSDEC Article 15 – Streams

For any locations involving work in or within 50 feet of a stream, compliance with theNYSDEC-NYSDOT Memorandum of Understanding (MOU) regarding EnvironmentalConservation Law Articles 15 and 24 is required. The MOU is provided as a ReferenceDocument.

3.3.2 Environmental Plans

The Design-Builder shall be responsible for preparing the following documents in conformitywith all Environmental Requirements:

A) State Pollutant Discharge Elimination System (SPDES) Permit application; see Soil Erosionand Water Pollution Control;

B) Stormwater Pollution Prevention Plan (SWPPP).

3.3.3 Soil Erosion and Water Pollution Control

The Design-Builder shall prepare and maintain on file a SWPPP complying with the New YorkState SPDES General Permit for Stormwater Discharges from Construction Activities (GP-0-15-002 or current version). The SWPPP is to include but is not limited to construction entrance(s),construction phasing, drawings showing size and location of permanent (e.g., swales, checkdams, etc.) and temporary (e.g., silt fence, temporary seed, mulch, etc.) erosion controls, and

Page 28: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 20 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

details. The SWPPP shall include plans and details for water quality volume, runoff reductionvolume, stream channel protection, overbank flood, and extreme flood controls, as appropriate.The Design-Builder shall apply for coverage under the SPDES General Permit for StormwaterDischarges from Construction Activities after preparing a compliant Erosion Control Plan andSWPPP as noted. The Design-Builder shall prepare the final SWPPP and a conforming Noticeof Intent (NOI), sign/complete the Contractor/Subcontractor SPDES Permit Certification form(CONR 5), and submit the NOI to NYSDEC for approval. Discharges covered under the SPDESgeneral permit shall not commence until the date authorized on the SPDES AcknowledgementLetter from NYSDEC.

3.3.4 Threatened And Endangered Species Coordination

The Design-Builder shall be aware that the northern long-eared bat (NLEB) is listed as athreatened species under the Endangered Species Act of 1973. Under consultationprocedures, the Department contacted the US Fish and Wildlife Service regarding any potentialmeasures to minimize harm to NLEB’s due to the proposed tree removals. To avoid adverseeffects on the NLEB, removal of 7 acres containing potential habitat trees is authorized, andmay only occur between August 1st and April 30th. In addition, a determined number ofreplacement trees shall be planted upon completion of the highway replacement work. SeeSection 11 for replacement conditions. In addition, should the Design-Builder require theremoval of more than 7 acres of treed area (3” or greater diameter at breast height (DBH)), orshould any removals be required after April 30th and before August 1st, the Design-Builder shallbe responsible for coordinating with and obtaining necessary approvals from the US Fish andWildlife Service and FHWA.

All potential habitat tress within the mound and the Nursery area will be felled and left in placeby others prior to Notice to Proceed (NTP). Clearing of the felled trees and grubbing shall be theresponsibility of the Design Builder. Please refer indicative plan showing the limits of treeremoved by others.

3.3.5 Asbestos Containing Materials

Generally, asbestos-containing materials should not be encountered on this project. However,the as-built plans for Contract NE 74-1 do show the presence of a small amount of asbestostraffic signal conduit near the intersections NY 878 with Rockaway Tpke. and Bay Blvd. Thesematerials if encountered shall be removed as asbestos waste.

The Design-Builder shall be responsible for the abatement design, asbestos abatement, wastedisposal and any required project monitoring/compliance air sampling during abatement of allconfirmed and assumed asbestos containing materials if such materials will be disturbed duringthe performance of the Work. All asbestos abatement and waste disposal shall be performed inaccordance with applicable safety and health codes and all applicable State and Federalregulations. See also DB Section 112-5.5, Asbestos.

The Design-Builder (in particular, the lead constructor on the Design-Build team) is also madeaware that 12 NYCRR 56 specifically prohibits the abatement contractor from directlycontracting project monitoring and/or compliance air monitoring services. In order to complywith this regulatory requirement, no Principal Participant may perform any asbestos abatementwork for this Project. The Design-Builder shall subcontract asbestos abatement and Projectmonitoring/compliance air sampling services to separate and independent firms.

Page 29: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 21 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

If during the course of work, any asbestos-containing materials not already documented in theasbestos screening/assessment report or Project record plans are encountered and requiredisturbance, the Design-Builder shall be responsible for any needed additional asbestosassessment, abatement design, asbestos abatement, waste disposal, and Projectmonitoring/compliance air sampling. All additional work shall be paid for under the ForceAccount pay item.

New York State Department of Labor (NYSDOL) asbestos licensure and applicable staffcertification(s) are required for Work where confirmed or presumed asbestos-containingmaterials are impacted. All necessary asbestos assessment and Project design Work shall beperformed in conformance with policy and guidance provided in NYSDOT’s The EnvironmentalManual (TEM).

Any ACMs associated with private utilities located within the Project limits shall be theresponsibility of the private utility owner. The Design-Builder shall coordinate with the privateutility owners for the remediation of any ACMs which may be identified.

3.3.6 Special Requirements for Removal of Abandoned Material from the former“NY Depot” Lease Site

The Contractor shall remove all material from the site consistent with the limits shown on theNYSDOT-approved project plans and as described in this RFP. Prior to performing any siteactivities, the Contractor shall submit a “Site Management Plan” (SMP) to the NYSDEC Region1 Office (Div. of Materials Management) for their review and acceptance. The Site ManagementPlan, at a minimum, will include the necessary details describing the following activities:

· clearing and grubbing/excavation methods;

· processing/sorting;

· staging/order of operations/transportation details;

· hours of operation

· health and safety measures;

· erosion/dust control methods;

· disposal options and location of such including tracking of thematerial;

· re-use options of any Beneficial Use Determination (“BUD”) material(including classification as general use/restricted use/limited use fill)in accordance with 6NYCRR Part 360.13;

· any additional testing requirements for re-use (BUD material) ordisposal (contaminated material) options.

NYSDEC will review and give comments or approve the SMP within 30 days of receipt. No workshall be commenced without NYSDEC approval.

The Contractor shall submit a draft of the SMP as part of their proposal/response to this RFP.

Page 30: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 22 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The soil sampling reports and plans prepared by the consultant EPM, Inc are available to thebiddersincluded in Part 7, Engineering Data.

In addition, soil sampling done during the project planning phase revealed the presence of somecontaminated soil on and adjacent to the Lease Site. The results indicate that some excavatedsoil will require special handling, transportation and disposal procedures. In particular, two soilsamples contained PCB contamination exceeding the 6NYCRR Part 375 “Unrestricted”threshold.

The location and depth of contaminated materials are identified in the soil sampling reportsprepared by the consultant EPM, Inc. The soil sampling reports and plans are available to thebiddersincluded in Part 7, Engineering Data.

Contaminated soil shall be handled in conformance with NYSDOT Standard SpecificationsSection 205 and applicable NYSDEC regulations.

3.3.7 Environmental Plan Deliverables

Deliverables shall be as stated elsewhere in the RFP documents.

Page 31: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 23 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 4 GENERAL PROJECT SCOPE OF WORK

4.1 SCOPE

The Design-Builder shall perform all Work necessary to prepare the Project site(s) forconstruction, maintain the site(s) in suitable condition during all stages of construction andprovide cleanup and restoration of the construction site(s) and all disturbed areas.

4.2 STANDARDS

The Design-Builder shall perform the Work in accordance with the applicable Standards, Codesand Manuals cited in Section 1.6, unless otherwise stipulated in this Project Requirement, orotherwise applicable to the Project.

4.3 REQUIREMENTS

The Design-Builder shall prepare site work plans showing the extent of site works; disposal andstorage locations; facility removal details; and approximate volumes; and shall provide foruninterrupted Department maintenance and operations. All regulated waste shall be handledaccording to Section 3 – Environmental Compliance.

The site work may include but not be limited to: clearing and grubbing; excavation andembankment; removal of pavement and pavement markings, road barriers, soil, drainagefacilities, fencing, signs, and miscellaneous structures; subgrade preparation and stabilization;dust control; removal of abandoned above-ground and shallow piping and wiring, valves,meters, and other waste materials; and aggregate surfacing.

Unless specified otherwise in the Contract Documents, the Design-Builder shall remove allobstructions down to a minimum of 2 feet below the existing or proposed surrounding groundelevation or to the elevation necessary to properly construct the Work, whichever is lower.

The Design-Builder shall grade and restore all disturbed areas to match the existing surroundingground elevation unless otherwise specified elsewhere in the Contract Documents. TheDesign-Builder shall cut pavement or sidewalk to full depth with straight lines at removalterminations.

The Design-Builder shall over-excavate as necessary to remove unsuitable material from underthe footprint of pavements and structures and backfill with properly compacted suitable material.Topsoil may be stripped, stockpiled, and reused within the Project Limits.

The Design-Builder may only reuse materials on the Project that meet the requirements forgrading and backfill materials. Disposal of obsolete, unsuitable, and surplus material is notallowed within the Right-of-Way and shall be removed.

4.3.1 Field Office

The Design-Builder shall provide, furnish and maintain a Field Office for use by the Departmentin accordance with the NYSDOT Standard Specifications. The Field Office shall be a Type 1Office as described in the NYSDOT Standard Specifications.

Page 32: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 24 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

4.3.2 Salvage

All materials removed from the Project site shall become the property of the Design-Builder,unless specifically stated elsewhere in this Part 3 - Project Requirements.

4.3.3 Surplus Quantity

Section not used.

4.3.4 Sidewalk Plowing Coordination During Winter Shutdown

Prior to the end of the construction season, the Design-Builder shall provide the State a list ofnew sidewalks that are open to the public that will need to be plowed by the municipality duringthe winter months. Before winter shutdown, the Design-Builder shall ensure that all sidewalksare free and clear of obstructions, barricades, fixed objects, etc. that would interfere with thesnow plowing effort.

Page 33: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 25 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 5 SURVEYING AND GIS

5.1 SCOPE

The Design-Builder shall perform all surveying tasks necessary to undertake and complete theProject including but not limited to: acquisition of terrain data (topography); mapping ofroadways and appurtenances, features, bridges, and utilities as needed; locating boundaries;waterway surveys; contract control plan; construction and stakeout surveys; As-Built surveys;surveys that arise from other Project Requirements; asset inventory; and all other surveyingservices as necessary.

5.2 STANDARDS

The Design-Builder shall perform the surveying activities in accordance with the applicableStandards, Design Codes and Manuals cited in Section 1.6, unless otherwise stipulated in thisProject Requirement or otherwise applicable to the Project.

5.3 REQUIREMENTS

5.3.1 Project Survey Control

Survey control, if available, will be provided as Reference Documents. The Design-Builder maysupplement that information or conduct complete new survey as necessary to perform all thenecessary surveys required to complete the Project, as the Design-Builder deems appropriate.

5.3.2 Department-supplied Data

The Department will provide the Design-Builder with the following Survey-Related Data asReference Documents:

· ROW / Highway Boundary Geometry;· Survey / Photogrammetric Base Mapping Planimetrics;· Survey / Photogrammetric Digital Terrain Model; and· Record Plans.

The Design-Builder shall be responsible for verifying any data used for the Project.

5.3.3 Survey Reports, Records and Maps

The Design-Builder shall submit to the Construction Inspection Professional Engineering Firm,all information listed under the ‘Documentation’ sub-section of each chapter of the NYSDOTLand Surveying Standards and Procedures Manual that is applicable to its survey work. TheDesign-Builder shall index and submit all calculations, notes, computer files, raw data, Projectreports, meeting notes, correspondence, digital images, maps, corner records, records ofsurvey, aerial photogrammetric products, centerline alignment maps, and other maps andrelated items.

The Design-Builder shall be responsible for ensuring that information submitted is compatiblewith the applicable NYSDOT CADD standards, software and operating systems and formats.

All survey reports and maps, including bathymetric survey plans, shall be signed-and-sealed bya New York State licensed professional land surveyor.

Page 34: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 26 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

5.3.4 Permanent Survey Markers

This Section not used.

5.4 SURVEYING AND GIS DELIVERABLES

Deliverables shall be as stated elsewhere in the RFP documents.

Page 35: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 27 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 6 RIGHT-OF-WAY

6.1 SCOPE

Plans showing the existing State owned Right-of-Way (ROW) are included in the ReferenceDocuments. The Design-Builder shall perform all the permanent Project Work within theexisting State owned ROW.

Maps for any Temporary Easement that is in the process of being obtained or has beenobtained specifically for this Project are included in Part 7 – Engineering Data of these ContractDocuments.

Property releases for driveway reconnections or other work that is required are the responsibilityof the Design-Builder, in close coordination with the Construction Quality Assurance Engineer.

Right of ownership of all ROW and the improvements made thereon by the Design-Builder shallremain at all times with the Department. The Design-Builder’s right to entry and use of theROW arises solely from permission granted by the Department under the Contract.

6.2 REQUIREMENTS

6.2.1 Right-of-Way Fencing

Any ROW fencing that has been damaged due to construction of the Project or removed by theDesign-Builder shall be replaced by the Design-Builder with new ROW fencing meeting currentNYSDOT standards.

6.2.2 Property Interests Identified by the Design-Builder for its Convenience

The Design-Builder shall be responsible for the acquisition and all costs associated therewith forany temporary land or other property required for the Design-Builder’s convenience outside theROW Limits, such as for staging, lay-down, access, office space, temporary works, or otherpurposes. The Design-Builder shall assume responsibility for satisfying all Federal and Stateregulations, identifying, analyzing, and documenting the environmental impacts associated withthe additional space and securing all necessary consent, including that of the Department, priorto initiating use of the space, in accordance with DB §107-22.

6.2.3 Right of Way Markers

This section not used.

6.2.4 Work Limitations on Use and Occupancy Parcels

Within the State owned ROW, there are several parcels that are leased to tenants under a Useand Occupancy Lease. Plans showing these Leased Areas are included in Part 7, EngineeringData. The Design Builder is permitted only to utilize the areas shown in the Directive Plans.The Design-Builder shall not encroach on the Leased Areas beyond the limits specified on theDirective Plans. The Design-Builder is responsible for restoration of the Leased Areas prior toProject Completion. The Design-Builder must coordinate/notify the tenants of any constructionactivities within their leased parcels. The Design-Builder must comply with any NYSDOTcommitments made the leases, as shown on the Directive Plans.

Page 36: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 28 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 7 PUBLIC INVOLVEMENT

7.1 SCOPE

The goal of the public involvement activities is to inform the public and agency participants byproviding timely information throughout the design and construction process. The Design-Builder shall be responsible for supporting and cooperating with the Department for all publicinvolvement activities.

7.2 STANDARDS

The Design-Builder, in close coordination with the Department, shall perform the PublicInvolvement activities in accordance with the NYSDOT Project Development Manual: Appendix2, Public Involvement Manual.

7.3 REQUIREMENTS

7.3.1 Public Outreach

The Design-Builder shall have the primary responsibility for performing public outreach activitiesfor the Project, but the lead in all public outreach activities shall be the Department. All publicoutreach activities shall be coordinated through the Department’s Construction QualityAssurance Engineer (CQAE). All public communication activities must be reviewed andapproved by the Department. This includes communication and notifications of keystakeholders (motorists, general public, area residents, educational institutions, emergencyservices, businesses, etc.) of road closure information, Project milestones or Projectconstruction related activities that have the potential to affect the general public and/or residentsin proximity to the Project area. Project milestones include, but are not limited to: the visible startof construction activities; travel pattern changes; significant Project accomplishments, andconstruction completion.

The Design-Builder shall be aware that outreach to the public is a critical component to thesuccessful completion of any NYSDOT project. Design-Build projects by their nature introduceunknowns and variables that the public is not aware of due to the fact the design is notcomplete. In an effort to offset those potential concerns and anxieties that a yet fully vetteddesign could create, in the eyes of the public, outreach to the public shall commence early onthis project. The Design-Builder shall be prepared to meet with appropriate stakeholders and theelected officials and the general public within 75 days following the issuance of the Notice toProceed. The Department remains the lead on this activity but the Design-Builder will assist incoordinating the logistics, preparing the presentation material, the announcement of themeeting(s), and other outreach efforts necessary to capture the communities interest andparticipation. The Design-Builder shall be prepared at this time to discuss the design, the reasonfor said design, the construction methods, the schedule of the construction contract, the timeperiods of the day that the work will be on-going, and how traffic and pedestrians will beaccommodated, as a minimum. This will all be coordinated with the Department’s ProjectManager and the discussion of this meeting and coordination will begin at the Design Workshopand shall be so listed as an agenda item for the Design Workshop.

The Design-Builder shall coordinate with and provide a minimum of two weeks advance noticeto the CQAE prior to all changes to traffic patterns and the following Project milestones: start ofconstruction; Project completion; and any other interim completion milestone(s) determined bythe Department.

Page 37: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 29 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The Design-Builder shall provide the Department with a minimum of two weeks advancenotification for each public information activity (press announcements, travel advisories, PVMSpostings, etc.) to allow for proper review and comment by the Department.

The Design-Builder shall provide the Department’s CQAE with a written work Schedule(including anticipated traffic changes) two weeks in advance of work that will change trafficpatterns.

7.3.2 Media Relations

Media Inquiries: All media inquiries, requests for interviews from local print or broadcast newsmedia, trade magazines or other media outlets must be referred to the CQAE for direction. TheDepartment will coordinate and respond to all media requests. The Design-Builder shall alert allproject personnel about this policy.

Travel Advisories: To allow for timely notice to the public, two weeks advance notice of thestart of work, any lane closures, road closures, or changes to traffic patterns is required to begiven to the CQAE and the Department’s Project Manager.

Notifications referenced above are in addition to the written work schedule discussed in Section7.3.1. The Department will develop a draft travel advisory for content and quality review by theDesign-Builder and other Department staff as deemed appropriate. The travel advisories will befinalized and distributed to the press and appropriate state elected officials, and posted on theProject website by the Department. However, the Design-Builder is responsible for thenotification of local public officials, emergency service providers, schools, residents, businesses,and other affected parties, of any major travel pattern change.

The strategies described above are consistent with the requirements of Part 3 Section 15 –Work Zone Traffic Control and Access, and shall include Construction Bulletins published by theDepartment, based on information provided by the Design-Builder, especially focused on trafficchanges, night time work, higher-noise construction periods or locations, or other constructionactivities of potential concern to the public. The Design-Builder shall be responsible forinteraction with the affected homeowners, tenants and businesses with regards to issuesincluding but not limited to, security of and access to their property or properties, utility services,night time operation, etc.

7.3.3 Public Information Meeting

Section not used.

Page 38: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 30 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 8 UTILITIES

8.1 SCOPE

The utility requirements set forth in Part 4 – Utility Requirements and DB §102-5 present theDesign-Builder’s responsibilities as they relate to existing and/or new utilities, the manner inwhich utilities shall be protected, relocated, upgraded, constructed or incorporated into theconstruction, and responsibilities for the Work.

8.2 STANDARDS

The Design-Builder shall perform all utility activities in accordance with the ContractRequirements, the applicable Standards, Codes and Manuals listed in Section 1.6 or otherwiseapplicable to the Project, and the standards required by the various utility companies affected bythe work.

8.3 GENERAL REQUIREMENTS

The Design-Builder shall examine the record plans of the work site, make a field survey of thework site and examine all other available documents to determine the type and location of allutilities that may be affected by the Design-Builder’s Work. Before any work begins the Design-Builder shall inform the Department’s Project Manager what utilities are present and how theymay be affected by the work.

The Design-Builder, in coordination with the Department’s Project Manager (or designee) andthe Regional Utility Engineer, shall meet with all the affected Utility owners or operators for thepurpose of discussing the effect on the utility facilities and to agree on a plan to maintain,protect, relocate, reinstall, or other action that may be necessary for the work to progress.

All utilities must be maintained, supported and protected during construction, unless otherwisedirected by the utility owner.

Any utility conduit, conductor, splice box, pull box or other item that is part of a utility system orstreet light system that is embedded in a concrete deck, sidewalk or other concrete element thatis being removed and replaced as part of this Project shall be replaced and its locationcoordinated with the utility owner unless the utility owner indicates that replacement is notrequired. The design and construction of the replaced utility shall be in conformance with thecurrent standards of the Utility owner.

The Design-Builder shall be responsible for repair to any damage and consequential damagesto those utilities caused by his operations at the Design-Builder’s expense. If the nature of thedamage is such as to endanger the satisfactory operations of the utilities and the necessaryrepairs are not immediately made by the Design-Builder, the work may be done by therespective owning companies and the cost thereof charged against the Design-Builder.

The Design-Builder shall provide notice to the Construction Quality Assurance Engineer (CQAE)at least two weeks before construction begins on any portion of the Project. The CQAE willnotify the Regional Utility Engineer of the pending construction and of any planned interruptionsto service. It should be noted that utility companies set their own notification time frames andrequirements. Preliminary time frames have been identified in Part 4 – Utility Requirements ofthese Contract Documents. The Design-Builder shall coordinate with respective Utility Owners.

Page 39: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 31 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

8.3.1 Utility Relocation Agreements

It is anticipated that the required Final Utility Work Agreements will be executed between theDepartment, the Design-Builder and the owners of impacted utilities once the Design-Builderhas determined the final locations of the impacted utilities. See Part 4 for details on utilityinventory, coordination and relocations.

The Design Builder shall be responsible for the design and construction of these facilities asoutlined in Part 4 - Utilities.

8.3.2 Other Utility Conflicts

Please see Part 4 – Utility Requirements for additional utilities in the project vicinity that mayrequire relocation and modification.

Page 40: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 32 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 9 GEOTECHNICS

9.1 SCOPE

The Design-Builder shall be responsible for all Geotechnical Work necessary for the design andconstruction of all permanent and temporary structures, including assessing availableinformation, planning and implementing subsurface investigations, geotechnical analysis andreporting, geotechnical instrumentation and monitoring, and protection of existing infrastructure,structures and utilities in accordance with the requirements of the Contract Documents.

These requirements are considered as a minimum and do not include all possible conditionsthat may be encountered in the Design-Builder’s final design.

The Department has performed limited subsurface investigations in the vicinity of the ProjectSite. Information from these previous subsurface investigations has been provided asReference Documents. Presentation of this information in no way implies that subsurfaceconditions are the same at other locations.

The Design-Builder shall be familiar with available geotechnical, geologic, seismic,hydrogeology, soils literature, and existing site conditions (both native and man-made), andshall interpret the existing geotechnical data pertaining to the Project Site. The Design-Buildershall form its own interpretation of the existing geotechnical data, and any additionalgeotechnical data the Design-Builder may obtain from its own investigations, and shall producedesigns compatible with geotechnical site conditions and provide for the durability of the finishedproduct.

Existing substructures and retaining walls shall not be re-used or incorporated into new workunless the Design-Builder provides detailed analysis showing that current design standards arebeing met, and verification that the condition of the existing structure demonstrates a remainingservice life that meets or exceeds project requirements.

9.2 STANDARDS

The Design-Builder shall perform geotechnical activities in accordance with the ContractRequirements and the applicable Standards, Design Codes and Manuals cited in Section 1.6 orotherwise applicable to the Project.

The Design-Builder shall use Bentley gINT® or similar commercial software to develop andmaintain an electronic database of subsurface information including in-situ test and laboratorytest results, and to produce all final subsurface exploration logs or records.

9.3 DESIGN REQUIREMENTS

9.3.1 Geotechnical Work Plan

The Design-Builder shall prepare a Geotechnical Work Plan for the project that identifies thegeotechnical scope of work that the Design-Builder plans to complete for the design andconstruction of the project. The Geotechnical Work Plan shall include:

A) Design-Builder’s knowledge and understanding of the geotechnical, geologic,hydrogeologic and seismic settings of the Project Site and how the nature and behavior

Page 41: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 33 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

of the soil, rock, groundwater and subsurface conditions will affect the investigation,design and methods of construction;

B) Identification of key constraints, site and subsurface conditions, and a description of howthe geotechnical activities will be designed and constructed to meet these constraintsand conditions;

C) Types of subsurface investigations to be carried out for the Project, including locationsand depths of borings and other field testing with a narrative of the in-situ tests (ifapplicable) and laboratory tests to be carried out.

D) A summary of the proposed geotechnical works including identification of major designand construction risks, and how these risks will be managed and mitigated;

E) A narrative on the proposed geotechnical instrumentation and how it will be used fordesign verification and to demonstrate prior to final project acceptance that measuredperformance meets predicted performance; and

F) Corrective actions to be taken if geotechnical instrumentation shows that measuredperformance does not meet predicted performance

9.3.2 Geotechnical Investigations

The Design-Builder shall plan and conduct geotechnical investigations in accordance with theDepartment’s and AASHTO Standards for subsurface exploration programs, and as deemednecessary by the Design-Builder’s Lead Geotechnical Engineer to establish the geotechnicalconditions and to perform all geotechnical and foundation design and analysis.

Information from existing borings provided by the Department as Reference Documents may becombined by the Design-Builder with the Design-Builder’s subsurface investigation to complywith the requirements of the applicable standards. It is the sole responsibility of the Design-Builder to determine if the existing borings are suitable for use in the Project. It is the soleresponsibility of the Design-Builder to determine the extent to which further borings by theDesign-Builder are necessary for the Project.

For each new subsurface exploration, the Design-Builder shall be responsible for keeping acontinuous and accurate log.

The Design-Builder shall determine the State Plane coordinate location and ground surfaceelevation for each boring and field exploration position, and shall show the actual coordinatesand the datum version, the station and offset, and the elevation for each individual boring log orexploration record in accordance with Department standards. Boring shall be located usingNAD83 Geodetic Reference System. Elevations shall be referenced to the Project datum andhorizontal control system.

9.3.3 Geotechnical Data Report

The Design-Builder shall be responsible for preparing a Geotechnical Data Report, signed andstamped by the Lead Geotechnical Engineer. The Geotechnical Data Report shall serve as afactual depiction of the subsurface conditions and at a minimum it shall include:

Page 42: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 34 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

A) A detailed description of the investigation methods;

B) Complete records with summary tables of investigation;

C) Complete records with summary tables of laboratory test results; and

D) An exploratory hole location plan, showing locations of any existing (pre-award)explorations for which data was used by the Design-Builder plus locations of post-awardexploration locations undertaken by the Design-Builder; and

E) Final logs for all subsurface explorations progressed by the Design-Builder.

9.3.4 Excavations and Embankments

The Design-Builder shall be responsible for assessing the stability and impacts of any new filland cut slopes (permanent and temporary) required for the Project, and ensuring the short andlong term stability of these slopes.

The Design-Builder shall assess the settlement induced by fill placements, including immediatesettlement in granular soils, and both immediate and consolidation (time-dependent) settlementin cohesive soils.

Embankments for roadway foundations shall be designed so that post construction settlementwithin a 50-year timeframe is expected to remain within two inches of the design grade line atany point along the entire roadway surface, and differential settlement along the travel lane orshoulder surfaces shall not exceed one inch over a 100-foot length in the longitudinal directionand one-half inch along a 10 foot length in the transverse direction, or one-half inch along a 10foot length within 10 feet of an approach slab or edge of structure. The effect of settlement onexisting and proposed buried utilities shall be considered over a 100-year timeframe.

9.3.5 Geotechnical Design Report

The Design-Builder shall prepare a Geotechnical Design Report for areas where a proposedpermanent raise in grade exceeds two feet, or where ground improvement is proposed toimprove foundation soil conditions for embankment construction. Ground improvement isdefined as the use of lightweight materials (expanded polystyrene, foamed lightweight concrete,expanded shale, etc.), excavation and replacement with granular soils, or ground improvementtechniques as detailed in FHWA NHI-16-027 and NHI-16-028. The Geotechnical Design Reportshall be signed and stamped by the Lead Geotechnical Engineer, and as a minimum shouldinclude:

A. Description of the geology and subsurface conditions at the site;

B. A summary and interpretation of geotechnical engineering conditions based on theavailable subsurface information;

C. Recommended geotechnical treatment(s) and geotechnical design parameters, includingdesign assumptions, design methods, design criteria, calculations, and design softwareoutput files;

D. Assessment of short-term and long-term performance of embankment constructionand/or proposed ground improvement including slope stability, effects of time-relatedsettlement, and lateral deformation;

Page 43: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 35 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

E. Construction considerations including dewatering, support of excavation, impact onexisting structures and utilities, and staging requirements;

F. Proposed geotechnical instrumentation for monitoring project performance. Proposedinstrumentation shall verify at project acceptance that measured performance is in linewith predicted performance. Details for the proposed instrumentation shall be included inthe Geotechnical Instrumentation and Construction Monitoring Plan.

9.3.6 Retaining Walls

The Design-Builder shall design and construct retaining walls, if required, in accordance withSection 10 of this Part 3 - Project Requirements. The Design-Builder shall provide retaining walldesigns to address internal, external, and global (overall) stability and settlements (total anddifferential) of the walls in accordance with the AASHTO LRFD Bridge Design Specifications.

All retaining walls shall be evaluated and designed for seismic stability internally and externally(i.e. sliding and overturning). With regard to overall seismic slope stability (global stability)involving a retaining wall, with or without liquefaction, the Lead Geotechnical Engineer shallevaluate the impacts of failure due to seismic loading, if failure is predicted to occur.

Gabion and crib walls (stretcher and header type) shall not be used.

Metal reinforcing elements for MSES structures is prohibited.

9.3.7 Geotechnical Instrumentation and Construction Monitoring

The Design-Builder shall develop, implement, and maintain a Geotechnical Instrumentation andConstruction Monitoring Plan to monitor vibrations, accelerations, vertical settlement, and lateralmovement of temporary support structures and adjacent ground, and existing structures andinfrastructure during construction, including ancillary structures and infrastructure within thezone of influence of construction.

The Geotechnical Instrumentation and Construction Monitoring Plan shall also include, whennecessary, details of design verification geotechnical instrumentation such as settlementmonitoring for embankment construction, groundwater monitoring for dewatering operations,and monitoring of other geotechnical operations proposed by the Design-Builder.

Wherever vibration-producing activities are located within 100 feet of a structure, building, orutility, the Design-Builder shall perform vibration monitoring in accordance with NYSDOTSpecial Specification 634.99020017 to address the potential impacts to nearby receptors due toconstruction or demolition activities associated with this Project. The term “receptor” includesbuildings, utilities, newly constructed elements, and existing structures, for which constructionimpacts or Work above recommended limits may be detrimental.

The Design-Builder shall provide weekly construction instrumentation monitoring reports to theDepartment. Monitoring reports shall be interpretive in nature, and shall enumerate anycorrections applied to the data including, but not limited to any notification measures takenregarding data. The weekly reports shall include clear and explicit statements of readingsexceeding any pre-determined threshold values. The Design-Builder shall maintain theinstrumentation and monitor the measurements during and after construction up to FinalAcceptance.

Page 44: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 36 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

At a minimum, the Geotechnical Instrumentation and Construction Monitoring Plan shall include:

A. Identification of receptors, including structures and/or utilities located within 100 feet ofvibration-producing activities that require vibration monitoring;

B. The types and quantities of instruments to be used for monitoring, and the proposedlocation of the instruments;

C. Alert and Action level vibration limits for monitored structures and/or utilities, andnotification protocol for instances where the limits are exceeded;

D. The frequency and duration of instrument readings; and

E. When necessary, geotechnical instrumentation for design verification including thetypes, quantities, locations, and frequency of readings for proposed instrumentation.

The Design-Builder shall install and take readings on vibration monitoring instruments at leasttwo weeks prior to construction activities within the 100 foot zone of influence to establishbaseline readings.

The geotechnical instrumentation shall be used to demonstrate at project acceptance thatmeasured geotechnical performance is in line with predicted performance.

The Geotechnical Instrumentation and Construction Monitoring Plan shall be signed andstamped by the Lead Geotechnical Engineer.

9.3.8 Temporary Works

The Design-Builder shall be responsible for the design and construction of all temporary worksrequired for the Project.

9.4 CONSTRUCTION REQUIREMENTS

9.4.1 Dewatering and Groundwater Control

The Design-Builder shall be responsible for evaluating the potential need for dewatering andgroundwater control, and for implementing such measures as appropriate, and shall evaluatethe effects on existing facilities resulting from any dewatering and draw down.

9.4.2 Structure Foundations

The Design-Builder shall provide integrity, verification, and proof testing of all deep foundationelements as stated below and in accordance with Department standards. The belowrequirements supplement, but do not supersede, Department standards.

Drilled Shafts

· Static axial compressive load tests must be performed on 1% of all drilled shafts, with aminimum of one per substructure. This testing must be completed on a non-productionshaft at each substructure prior to production shaft installation. Alternatively, a bi-directional static load test may be performed on the first production drilled shaft installedat each substructure (1% requirement still applies).

Page 45: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 37 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· Crosshole sonic logging must be performed on all drilled shafts. This testing may besupplemented by thermal integrity profiling.

· The bottom of drilled shafts shall be inspected using a shaft inspection device (SID) ifthe shaft design relies on end bearing resistance.

· All production drilled shafts must have a similar design and be constructed using similarmethods, including concrete placement volumes and installation pressures, as theclosest test shaft. All installation data and observations must be recorded on aninstallation log.

Micropiles

· Static axial compressive load tests must be performed on 1% of all micropiles, with aminimum of one test per substructure. This testing must be completed on a non-production test pile at each substructure prior to production micropile installation. If theDesign-Builder decides to alter the installation methods, or if changed subsurfaceconditions are encountered, additional load tests are required on non-productionmicropiles installed with the new methods/subsurface conditions.

· Proof testing of production micropiles must be performed on a minimum of two piles persubstructure. Tension testing is allowed if site conditions permit.

· All production micropiles must have a similar design and be constructed using similarmethods, including grout placement volumes and installation pressures, as the closesttest pile. All installation data and observations must be recorded on an installation log.

Driven Piles

· Dynamic pile load tests, or equivalent verification testing, must be performed on aminimum of 2% of all driven piles, with a minimum of two tests per substructure.

· All driven piles must have a similar design and be driven to similar termination criteria asthe closest load tested pile.

Augercast piles and helical piles are not allowed for structure foundations.

As part of the As-Built Plans, the Design-Builder shall provide installation records for all deep

foundations installed in accordance with Department standards.

9.4.3 Excavations and Embankments

The Design-Builder shall progress all excavations in accordance with Department standardsand specifications. Trench boxes are not allowed to support live traffic.

The Design Builder shall construct embankments in accordance with Department standards andspecifications. For ground improvement methods not covered by Department standards andspecifications, construction methods, quality control, and quality assurance shall be inaccordance with: FHWA NHI-16-027 and NHI-16-028, Ground Improvement Methods Volumes1 and 2, and FHWA GEC 8, Design and Construction of Continuous Flight Auger Piles.

Page 46: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 38 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

9.4.3.1 Expanded Polystyrene

Verification testing must be performed on a minimum of one block per 10,000 cubic feet ofexpanded polystyrene to ensure specification compliance. Random blocks are to be selectedfrom material delivered to the job site, and are to be sent to the NYSDOT Soil MechanicsLaboratory for testing.

9.4.3.2 Column Supported Embankments

Column Supported Embankments consist of stiff vertical columns that are designed to transferthe load of the embankment through a soft compressible soil layer to a bearing stratum. Thesupport columns may consist of conventional driven piles (h-piles, CIP, precast, timber) or mayutilize formed in place methods (soil mix columns, aggregate columns, cement based columns).A load transfer platform is typically used to distribute the embankment load to the columns.

The Design-Builder shall provide verification, integrity, and proof testing of columns as statedbelow and in accordance with Department and FHWA standards. The below requirementssupplement, but do not supersede, Department and/or FHWA standards.

Driven Columns

· Dynamic pile load testing, or equivalent verification testing, must be performed on aminimum of 2% of all driven columns, with a minimum of one test per pile design and/orrepresentative subsurface condition at the project site.

· All driven columns must have a similar design and be driven to similar terminationcriteria as the closest load tested column.

Drilled Columns

· Static axial compressive load tests must be performed on 0.2% of all drilled columns,with a minimum of one test per column design and/or representative subsurfacecondition at the project site. This testing must be completed on non-production columnsand is to be used for design verification. For sites requiring more than 5 static axial loadtests that have demonstrated consistent load test results, the Department may elect tosubstitute additional proof tests for required static axial compressive load tests.

· Integrity testing shall be performed on a minimum of 10% of all drilled columns. Integritytesting shall consist of, as a minimum, low strain impact and/or thermal integrity profiling.

· Proof testing of production columns must be performed on a minimum of 1% of allcolumns.

· All production columns must have a similar design and be constructed using similarmethods, including grout/concrete placement volumes and installation pressures, as theclosest test pile. All installation data and observations must be recorded on aninstallation log.

Page 47: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 39 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

As part of the As-Built Plans, the Design-Builder shall provide installation records for all columnsinstalled in accordance with Department standards.

9.4.4 Condition Surveys

9.4.4.1 Pre-Construction Condition Survey

The Design-Builder shall conduct a pre-construction inspection and survey of the existingcondition of all structures and properties within 100 feet of vibration or settlement causingconstruction activities and generate photographic and video documentation of existing damage,leaks and cracks, in accordance with the requirements of NYSDOT Special Specification634.99010017. The pre-construction condition survey shall form the basis against which all newcracks, existing progressive cracks, or damage will be measured.

The Design-Builder shall ensure that the pre-construction condition survey encompasses at aminimum all properties within areas that are identified by the Design-Builder to be potentiallyprone to: (i) ground vibration levels, expressed as resultant peak particle velocity, in excess of2.0 inches per second; and (ii) predicted ground settlements of greater than ¼ inch.

The Design-Builder shall record the results of the pre-construction condition survey, which shallbe signed and stamped by a Professional Engineer registered in the State of New York.

9.4.4.2 Post-Construction Condition Survey

The Design-Builder shall conduct a post-construction inspection and survey of the propertiescovered by the pre-construction survey. The post-construction condition survey shall beperformed by the Design-Builder within 20 calendar days of Project Completion, and it shallcompare the post-construction conditions with the conditions documented in the pre-construction condition survey. A summary of the damages observed, if any, shall be provided atthe end of the report. The location and scope of the post-construction condition survey shallmatch those of the pre-construction condition survey. The complete documentation of the post-construction survey, describing the comparison with the preconstruction conditions and signedby a Professional Engineer registered in the State of New York, shall be submitted to theDepartment, both in hardcopy and electronic format.

9.5 DELIVERABLES

Deliverables shall be as stated elsewhere in the RFP documents.

Page 48: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 40 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 10 STRUCTURES

10.1 SCOPE

The Design-Builder shall be responsible for all work necessary to complete the design andconstruction of all permanent and temporary structures required to complete the Project,including, but not limited to, the bridges, culverts, bikeway/walkway, retaining walls, barriers,sign structures, foundations and miscellaneous structures. The design and construction of allstructural systems and components shall provide functionality, durability, ease of maintenanceand inspection, and safety.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The review and approval process shall be in conformance withthe Design-Builder’s Quality Control Plan.

10.2 STANDARDS

The Design-Builder shall perform structural design and construction activities in accordance withthe Contract Requirements and the applicable Standards, Design Codes, and Manuals cited inSection 1.6, unless otherwise stipulated in this Project Requirement or otherwise applicable tothe Project.

10.3 DESIGN REQUIREMENTS

10.3.1 Components

A) Earth Retaining Structures: The Design-Builder shall determine the location(s) and typesof earth retaining structures. Wall type selection and design by the Design-Builder shallmeet all applicable Project Requirements.

B) Foundations: The Design-Builder shall calculate settlements for the different geotechnicalconditions. Settlements likely to occur during construction shall be calculated separatelyfrom long term settlements.

C) Mass Concrete: Mass Concrete Placements shall be defined as those placements havinga minimum dimension greater than 54 inches in all directions. There shall be no minimumvolume limitation to this definition. If the placement meets this definition, the placementshall be made in accordance with ITEM 555.02 01 – CONCRETE FOR STRUCTURESCLASS MP (MASS PLACEMENT). Specifically, a thermal control analysis shall beperformed and a system used to manage temperature of the placement.

All reinforcement located in the mass placement(s), except for footings, shall be epoxycoated reinforcement. The combination of reinforcement and concrete mixturepermeability shall meet any defined service life requirements of the RFP.

Footings shall have epoxy coated reinforcement when placed in seawater.

10.3.2 Aesthetics

Aesthetic treatments shall include...

Page 49: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 41 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

10.4 DEMOLITION REQUIREMENTS

10.4.1 Scope

Section not used.

10.4.2 Standards

Section not used.

10.5 CONSTRUCTION REQUIREMENTS

Section not used.

10.5.1 Construction Vehicles on Bridge

Section not used.

10.6 LOAD RATING REQUIREMENTS

Section not used.

10.7 DELIVERABLES

Section not used.

Page 50: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 42 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 11 LANDSCAPE ARCHITECTURE

11.1 SCOPE

The Design-Builder shall perform the landscape architectural activities as described in thisSection 11.

The aesthetic details and concepts described within this contract were developed to createvisual unity and connectivity along the Nassau Expressway corridor to help calm traffic, toreduce visual impacts, and to improve the aesthetics, environment, and multi-modelfunctionality.

11.2 STANDARDS

The Design-Builder shall perform site work in accordance with the Contract Requirements andthe applicable Standards, Design Codes and Manuals cited in Section 1.6, unless otherwisestipulated in this Project Requirement or otherwise applicable to the Project.

11.3 GENERAL LANDSCAPE DEVELOPMENT

11.3.1 Existing Vegetation

Existing vegetation removal and disturbance should be minimized to the cut/fill limits and anyremovals, whether within the cut/fill limits or beyond those areas, shall be replaced in kind withnative species appropriate for USDA NY Plant Hardiness Planting Zone 7a, as described inSection 11.3.2.

Prior to the removal of any trees or shrubs, an inventory of existing trees and shrubs shall beprepared by the Design-Builder and a copy provided to the CQAE. The inventory shall includemajor deciduous trees over 6 inches in diameter at breast height (DBH), coniferous trees over 6feet in height, and deciduous or evergreen shrubs between 3 feet and 6 feet in height. Theinventory shall include the size, location and species of each tree or shrub. Only living trees andshrubs shall be included in the existing tree inventory.

Vegetation outside the limits of disturbance shall be protected with temporary plastic barrierfence along the limit of disturbance line.

Disturbed areas shall receive topsoil and turf establishment. The type of topsoil and turfestablishment, either roadside or lawn, will vary based on location.

11.3.2 Tree Replacement Factors

A) Every live, deciduous tree greater than six inches diameter at breast height (“DBH”) whichis removed must be replaced with a total quantity of deciduous trees a minimum of 2 inchcaliper (size measured 6 inches above the base of the tree) equal to the total DBH size ofthe tree removed. For example, a 10 inch DBH tree removed could be replaced with (5)two inch caliper trees or (2) three inch and (1) four inch caliper trees; however thereplacement quantity will go down if larger caliper trees are used for replacement.

Page 51: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 43 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

B) Every live, coniferous tree removed must be replaced with a total quantity of coniferoustrees equal to the height and width of the tree removed. For example, a 20 ft high x 10 ftwide coniferous tree could be replaced by two (2) 10 ft high x 5 ft wide coniferous trees.

C) Every live shrub, between 3 foot height and 6 foot height, removed must be replaced witha total quantity of shrubs equal to the quantity of shrubs removed.

D) The minimum replacement sizes shall be as follows: 2-inch caliper for major deciduoustrees, 1.5-inch caliper for minor deciduous trees, 6-foot height for coniferous trees, 3-footheight for deciduous shrubs, and 2-foot height for evergreen shrubs.

11.3.3 Replacement Locations

Replacement planting may be located in the available right-of-way near the original locations ofthe trees that were removed.

Replacement planting may also be done near the right-of-way line or on private property.Planting on private property may only be done if private property owners provide writtenpermission to the Design-Builder and agree to take over the long term care and maintenance ofthe plant material, and the appropriate release is obtained by the Design-Builder and inconsultation with the adjoining property owner in accordance with NYSDOT EI 11-010.

11.3.4 Proposed Planting

The Design-Builder shall not use invasive plant species for any of the proposed planting asrequired by the New York State 2012 Invasive Species Prevention Act, or a monoculture ofplant species, to reduce the potential for disease or invasive insect species to eradicate theproposed plantings.

Planting shall be located in a manner that does not interfere with the safe use of travel ways orin any sight triangle as determined by the Engineer.

Planting shall be designed in a manner that provides a mix of plant material species to createseasonal interest for the traveling public. Design-Builder shall provide shrubs in naturalistmassings and non-linear groupings with all plant bed layouts accepted by the RegionalLandscape Architect prior to final installation.

No trees to be planted within eight feet of the relocated 48” water main.

All planting beds shall be mulched. All mulch applied to planting beds, including mulch requiredunder the planting item shall conform to NYSDOT Standard Specifications Section 713-05, TypeA seasoned wood chips or Type C USDA-aphis protocol wood chips.

All planting areas are considered planting beds and shall be mulched uniformly to a depth of 3inches minimum. All plant beds adjacent to pavement, walls, fencing, guiderail or other fixedobjects shall extend to the structural element up to 5 feet away and be mulched, as directed.

Mycorrhizal Fungi: Shall be applied in accordance with manufacturers recommendations. Theadditive is for use with all plants within the project limits. For estimating purposes, it has beenassumed that mycorrhizae shall be applied at the rate of 3 oz. per each caliper inch of tree or 12inches of root ball.

Page 52: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 44 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· Major Deciduous Trees: 10.5 Oz. Per Tree

· Minor Deciduous Trees: 6.0 Oz. Per Tree

· Coniferous Trees: 8' Height, 7.0 Oz. Per Tree

· Shrub Item: 4.0 Oz. Per Shrub

· Vine: 5.0 Oz. Per Shrub

· Herbaceous: 5.0 Oz. Per Shrub

Moisture Retention Additive: Shall be applied in accordance with manufacturersrecommendations. The additive is for use with all plants on the landscape development table.For estimating purposes, it has been assumed that the additive shall be applied at the rate of 1oz. per each caliper inch of tree or 12 inches of rootball. Refer to landscape table for plantsizing.

· Major Deciduous Trees: 3.5 Oz. Per Tree

· Minor Deciduous Trees: 2.0 Oz. Per Tree

· Coniferous Trees 8' Height: 2.5 Oz. Per Tree

· Shrub:1.25 Oz. Per Shrub

· Vine: 0.75 Oz. Per Shrub

· Herbaceous: 0.75 Oz. Per Shrub

Watering of vegetation shall be applied at the following rates:

· Turf, wildflowers, sod, and planting beds: in the absence of 1" of rainfall within 5 consecutivecalendar days the Design-Builder shall water all turf, sod, wildflower and planting beds oncea week to a depth of 1".

· Trees and planting beds: between April 1st and November 15th, in the absence of 1" ofrainfall within 5 consecutive calendar days, the Design-Builder shall apply water to trees andplanting pits once per week, except during July and August when water shall be appliedtwice per week, with a minimum of 2 days between applications. Soil saucers shall be filledonce per watering.

Compost shall be included for all tree, shrub, and vine plantings. The ratio for each plant pitshall be 1/3 compost to 2/3 existing backfill.

Limestone shall be applied at the manufacturer's suggested rate.

Fertilizer shall be a 3-1-1 (approximate analysis)-type with a minimum 50% water insolublenitrogen and with a salt index of less than 50 and applied at the manufacturer's suggested rate.

All trees shall be staked using a minimum of two (2) wooden stakes per plant. Stakes shall berounded cedar poles with bark not less than five (5) feet in length. Guying shall be removedupon completion of the Period of Establishment.

11.3.4.1 Plant Selection Requirements

The Design-Builder shall utilize the Codes and Standards in developing plant palettes.

Page 53: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 45 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The Design-Builder shall provide plant selections based on the intended plant function in thelandscape and site conditions. Plant selection shall utilize native, hardy, drought-tolerant, andlow maintenance materials capable of surviving in the harsh urban conditions in which they willbe planted.

Plants shall be selected that can survive on local rainfall after an initial one year establishmentperiod provided by the Design-Builder.

Plant material selections shall emphasize native species and shall not include invasive species.No plants appearing on the Emerald Ash Borer or Asian Long Horned Beetle quarantined listsshall be permitted.

Other considerations for plant selections shall include:

· Suitable size and form for the proposed location.

· Resistance to disease and pests.

· Tolerance to drought.

· Tolerance of harsh urban conditions including heat, pollutants, and salt spray.

· Requirements for soil and drainage conditions.

· Trees proposed along public walk areas shall have a minimum branching height of seven (7)feet.

11.3.4.2 Right-of-Way Landscaping

Trees planted within a street ROW in sidewalk areas shall be installed in a minimum 5’ by 5’planting pit. The planting pit shall be covered with a cast iron tree grate. Design-Builder shallsubmit catalog cut information for acceptance. All trees shall be native to New York andapproved by NYSDOT Bureau of Landscape Architecture.

Any existing trees, within or outside street ROWs, excluding the mound area, removed due toconstruction operations shall be replaced with similar total caliper of new trees. (E.g.: one (1) 6-inch caliper tree removed may be replaced with either one (1) 6 -inch caliper tree, or two (2)three-inch caliper trees, or three (3) two-inch caliper trees) etc.

Minimum size for new street trees shall be two and one half (2 ½”) inch caliper measured at sixinches above the trunk flare at the root ball.

The Design-Builder shall provide 2 ½” caliper shade trees as a first priority andflowering/understory trees as a second priority where vertical and horizontal restrictions limit theuse of shade trees.

New tree spacing along street rights-of-way shall not exceed 40’ on-center.

All areas in street rights-of-way not covered in hardscape or tree planting areas shall besupplied with six (6”) inches of screened NYSDOT Type -A top soil and established turf withgrass seed maintained until final acceptance.

Low maintenance shrubs at a minimum of three feet (3’) and a maximum of four and a half feet(4 ½’) on center spacing shall be established in all plant beds. Low maintenance groundcovers

Page 54: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 46 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

accepted by the NYSDOT Landscape Architecture Bureau shall be in plant beds at a maximumof one foot (1’) on-center spacing.

A minimum of 60% of the plantable square footage within cloverleaf areas or open areas shallbe vegetated with a mix of 75% deciduous and 25% evergreen trees and shrubs, excluding themound site. For the purpose of this section, “plantable area” shall mean all unpaved areaswithin NYSDOT right-of way and outside of the clear zone. The Major tree spacing shall be atapproximately 30 feet on center (48 trees per acre). Minor tree spacing shall be approximately15’ on center. Groundcovers shall be used on the mowing edges of all shrub beds to restrictweed growth. Shrub bed edges shall be designed for ease of mowing by large equipment usedby the Department. The remaining plantable area shall consist of turf.

Sloped areas: Shrub beds with plants at a minimum of 3’ on center shall be indicated on 100%of all sloped areas to eliminate the need for mowing. Major and minor trees shall be indicated onthe slopes spaced at 30’ on center and 15’ on center respectively as described above in theplanting area types section.

11.3.4.3 Wetland / Water Quality Basin Planting

Within the State ROW at the southwest corner of Bay Boulevard and Incinerator Road, there isa very large and visible pile of soil and debris west of the Nassau Expressway. The Design-Builder shall remove the mound and transform the area into wetlands and a water quality basin,as shown in the directive plans found in Part 6.

Design-Builder shall use species specified in the permit application for the wetland mitigationarea found in Part 7, Engineering Data.

11.3.4.4 Monument and Landscape Features

At the Rockaway Turnpike / Nassau Expressway southeast quadrant is a planted landscapefeature that will be impacted by the raising of the roadway grades. Design-Builder shall restorethe feature with native and low-growing shrubs and groundcover.

There is a monument and a series of flag poles dedicated to the victims of the 9/11 at thenorthwest corner of Bay Boulevard and the COSTCO access driveway. After consulting theTown of Hempstead and other stakeholders, the Design-Builder shall raise the monument andflag poles to match the new grades of the intersection and plant with native shrubs andgroundcover.

11.3.4.5 Screening

Screening type planting shall be located near to the ROW, around retaining walls, the waterquality basin, or other roadway related features to block industrial properties and transportationinfrastructure views either as viewed from residential properties or transportation system users.Screening type planting shall be comprised of vegetation that maximizes visual screeningthroughout the year. A combination of evergreen plant material and a low, wood, screeningfence shall be used adjacent to abutting shopping centers.

The minimum screening type planting shall consist of:

· 2 staggered rows of evergreen trees (10-15 foot spacing, minimum 6-ft height);

Page 55: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 47 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· 2-5 staggered rows of evergreen shrubs (3-4 foot spacing, minimum 3-ft height); and

· Groundcover (10-12 inch spacing, minimum 1-gallon size) located in a row along thehighway side.

11.3.4.6 Landscape Establishment Period

All plant materials and turf that have been identified in the design shall be planted in accordancewith the Contract Requirements as soon as portions of work area are completed. Whengrowing season or construction conditions do not permit planting upon completion, the Design-Builder may wait until the next growing season but in no case shall plantings occur later than theend of 2019.

Between planting and the end of the 1-year Warranty Period, the Design-Builder shall replaceany plant materials and turf that are not in healthy and thriving condition, such that all such plantmaterials and turf identified in the design have achieved Vegetative Success. VegetativeSuccess means:

· A minimum of 90% ground cover and adequate establishment to control erosion.

· All plant materials in a healthy, thriving condition;

· All plant materials are reflective of the species and requirements of the Contract Documents.

· The Design-Builder shall conduct a Vegetative Success Survey (dead count of trees andreplacement) within 30 days of end of Warranty Period. The Design-Builder shall submit theVegetative Success Survey for Review and acceptance.

· The Design-Builder shall be responsible for post planting care and replacement plantingincluding watering. A minimum of 14 waterings shall be applied to all plant material duringthe growing season. Watering schedule shall be submitted to the CQAE at the time ofplanting.

· Post planting care and replacement plantings including tree stakes shall be as per therequirements of NYSDOT Standards for Post Planting Care with Replacement.

· Care shall be taken to ensure that all stakes and wires are removed from newly plantedtrees prior to project completion.

· Weeding of all planting areas shall occur on June 1 and August 1.

· The Design-Builder shall water, mow, and weed the turf establishment areas for the durationof the contract or until turf areas are accepted.

· All seeded areas shall be protected from construction traffic and the General public trafficduring the entire length of the contract.

11.3.4.7 Aesthetic Treatment for Median Pavement and Retaining Walls

All center concrete medians along the expressway roadway and other roadways where shownshall be integrally colored concrete with a stamped surface that emulates a traditional New Yorkcobblestone pavement. The Design-Builder shall submit color and pattern manufacturers to beaccepted by the NYSDOT Regional Landscape Architect and an in-place mock-up shall beaccepted before median barrier construction.

Page 56: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 48 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The surfaces of all new retaining walls within the project area shall have an architecturaltreatment consistent with the look of a masonry wall with capstone. The Design-Builder shallsubmit formliner manufacturers’ pattern numbers for acceptance by the NYSDOT RegionalLandscape Architect. Alternate treatments can be provided for a wetland edge wall. Once thepattern has been accepted, the Design-Builder shall provide an in-place mock-up foracceptance before any final wall is constructed.

11.3.4.8 Fencing

Low ROW fencing, 4 feet high, should be provided at adjacent shopping centers along theNassau Expressway.

High ROW fencing, 8 feet high, should be provided adjacent to industrial properties.

High fencing (6 feet tall chain link fence slat) to be placed at the perimeter of the water quality /detention basin and wetland mitigation area. Access gates to be provided as approved by theNYSDOT Regional Landscape Architect Fencing shall also be placed around the new nurserysite and around the temporary parking area for the batting cage. A new access gate shall beprovided for the Nassau County Pump Station at the south end of Incinerator Road

Page 57: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 49 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 12 SIGNAGE, PAVEMENT MARKING AND SIGNALS

12.1 SCOPE

The Design-Builder shall provide all permanent fixed signing, permanent pavement markingsand signal work (if applicable) required for the Project.

The Design-Builder shall be responsible for identifying, designing, detailing, fabricating,delivering and installing all signing (including reference markers) and pavement markingmaterials and shall install all components necessary for a complete and functional systemwhich, in addition to meeting the design and construction criteria specified above, meets thefollowing requirements:

A) Provides for the orderly and predictable movement of all traffic;

B) Provides such regulation, guidance, warnings and advisories as are needed to ensuresafe and informed operation;

C) Is fully and seamlessly integrated into the existing signing elements beyond the Projectlimits; and

D) Is integrated into the existing intelligent transportation system (ITS) components, ifapplicable.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The Design-Builder shall install new LED VMS on new cantileversign structures in the NB NY878 shoulder approximately 1000 FT south of Burnside Ave and inthe SB NY878 shoulder approximately 700 FT North of Burnside Ave as noted in ITS Section14. The new structures shall be designed to support the two line VMS sign as described.Minimum clearance to the bottom of the sign and structure shall be a minimum of 17.5 feet. Thereview and approval process shall be in conformance with the Design-Builder’s Quality ControlPlan.

12.2 STANDARDS

The Design-Builder shall perform the signage, pavement marking and signals activities inaccordance with Contract Requirements and the applicable Standards, Design Codes andManuals cited in Section 1.6, unless otherwise stipulated in this Project Requirement orotherwise applicable to the Project.

12.3 REQUIREMENTS

12.3.1 Design Requirements

The Design-Builder shall develop a signing and pavement marking plan and a traffic signal planfor the Project that shall:

A) Provide for all components as called for in this Section 12;

B) Encompass the replacement of all existing signs within the Project limits;

Page 58: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 50 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

C) Provide signing, traffic signals and pavement markings for bicycle and pedestrian facilitieswithin the Project Limits, where applicable;

D) Locate signs in accordance with the MUTCD and the NYS supplement; and

E) Provide signs with high reflectivity with Type IX sheeting such as to not warrant signlighting.

12.3.2 Construction Requirements

12.3.2.1 Signs

The Design-Builder shall not reuse any existing NYSDOT sign materials as part of thepermanent signing installation and shall be responsible for the disposal of all signing materialsand structures that are removed from the Project. Standard signs owned by municipalities otherthan NYSDOT, and non-standard signs owned by private entities but placed within NYSDOTright-of-way, with the acceptance of the Department, shall be removed, stored and reinstalled asrequired.

The Design-Builder shall be responsible for the provision of all signs, posts, frames and otherstructural components required for the installation and support of the sign panels.

Sign panels shall meet the requirements of the Department’s Special Specifications645.03010011, 645.03020011, 645.03030011 and 645.03040011.

12.3.2.2 Pavement Markings

All cross-hatching pavement markings shall be installed in accordance with the Department’sSpecifications for 15 MILS, Epoxy Reflectorized Pavement Marking, Items 685.07150410 and685.07150710. All stop bars and crosswalks shall be installed in accordance with theDepartment’s Specifications for 20 MILS, Epoxy Reflectorized Pavement Marking, Item685.07200510. All linear roadway pavement markings shall be installed in accordance with theDepartment’s Specifications for 15 MILS, Epoxy Reflectorized Pavement Markings, Items685.07150110 and 685.07150610. All letter and symbol pavement markings shall be installedin accordance with the Department’s Specifications for 20 MILS, Epoxy Reflectorized PavementMarking, Items 685.07200210 and 685.07200310.

12.3.2.3 Traffic Signals

There are signalized intersections within the limits of the Project that include traffic signals aswell as pedestrian crossing signals, locations of which are listed below:

Upgrade Traffic signal at the intersection of Nassau Expressway and RockawayBoulevardTurnpike.

Upgrade traffic signal at the intersection of Nassau Expressway and Bay Boulevard.

Upgrade traffic signal at the intersection of Nassau Expressway and Burnside Avenue.

The Design-Builder shall replace the existing traffic and pedestrian crossing signals with thelatest current standard of traffic signal pole and cable supports, and also the latest standard forthe push button control systems with count-down timers at the pedestrian safety walks.

Page 59: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 51 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

At each intersection, the Design-Builder shall design and install new traffic signal infrastructure.The traffic signal infrastructure shall include installation of a new cabinet and controller, spanpoles and foundations, signal heads including backplates with retro-reflective tape in alldirections, pedestrian signal poles, pedestrian signals and push buttons, cable and conduits,interconnect cable to adjacent signalized intersections, and loop detectors.

New LED Pedestrian signal and Countdown Timer displays along with ADA compliant latchingpushbuttons shall be installed at the intersection. Unless otherwise directed by the Department,the Design-Builder shall maintain the existing signal phasing for the new system.

The Design-Builder will be responsible for maintaining the existing signal until the new signal isactivated.

Two weeks prior to beginning any construction work on traffic signals associated with theproject, the Design-Builder shall notify the regional traffic signal section to perform an inspectionof the existing traffic signal equipment. After the inspection, the Design-Builder shall submit tothe Department a written notification of the date they will assume responsibility for traffic signalmaintenance. No construction work shall proceed until traffic signal maintenance is assumed bythe Design-Builder. The existing traffic signal shall be maintained by the Design-Builder underthe requirements of Section 619 of the Standard Specifications, except for the controller,programming, and timing which shall be maintained by the Department.

Traffic signal activation shall be done by NYS Traffic Signal Personnel only. The Design-Buildershall notify the NYS traffic Signal section two weeks prior to the requested date of activation.

The Design-Builder shall integrate the signals into the existing ITS system.

12.3.2.4 Loop Detectors

The Design-Builder shall replace all existing loops at each signalized intersection and providedetection zones on all approaches. All presence loops shall have a set of two 6 ft x 20 ft loopsspaced 10 ft apart installed at the stop bar, centered in the respective lane, with three turnswired in parallel. All side street lanes and all mainline turn lanes shall have presence actuationand all mainline through lanes shall have point detection. All point loops shall have a set of two6ft x 6ft loops spaced 10 ft apart, centered in the respective lane, with four turns wired in parallelinstalled at an appropriate distance from the stopbar for mainline approaches. The DesignBuilder shall splice each set of parallel loops to a twisted pair shielded lead-in cable, which shallin turn be wired to the cabinet. Only one pair of loops per lead-in cable. Each pair of loops shallbe contained in one lane. These lead-in cables are to be terminated inside their respectivecontroller cabinets. No more than six loop home runs can be cut to one pullbox and home runsshould not be cut across more than two lanes from the loop. Shielded lead in cable shall be runonly on the span wire, in poles or in underground conduit.

Existing vehicle and pedestrian detection shall be maintained at all times. The Design-Buildershall utilize video detection for temporary detection for all actuated phases. At the conclusion ofthe contract, all existing video detection equipment (cameras, arms, cables, cards, etc.) shall bereturned to the State.

Page 60: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 52 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

12.3.3 Conduit/Cabling Requirements

The following cables shall be utilized during the installation of new signal heads,pedestrian/countdown timers, interconnect and pushbutton signs:

A) Pedestrian/Countdown Timer and pushbutton sign: furnish and install 5C#14 awg cable foreach set display;

B) One way signal heads: furnish and install a minimum of 5C#14 awg cable;

C) Two way signal heads: furnish and install a minimum of 10C#14 awg cable;

D) Three way signal heads: furnish and install a minimum of 15C#14 awg cable.

The Design-Builder shall furnish and install fiber optic cable for any underground interconnectinstallation. A drop cable meeting the requirements of the Department’s Special Specification683.92150010 shall be connected to the cabinet. The interconnect shall be coordinated withITS plans.

The Design-Builder shall furnish and install the following conduit as a minimum:

A) Detection loop conduits shall be 1” Flex between the first junction box and loop.

B) Conduits under roadway shall be 3” RGS.

C) Conduits between Span or Mast Arm poles and nearest junction box shall include a 1”RGS and 4” RGS.

D) Conduits between Pedestrian poles and nearest junction box shall use a 2” RGS.

E) All other underground conduit installations shall be 2” RGS.

12.3.4 Signal Heads/ Signal Poles

All signal faces to be installed as part of this Project shall be 12” LED. Mainline approachesrequire one through head for every through lane for multilane approaches. For the purposes oftraffic signal design, signal heads not facing the mainline approach shall have 5” back plateswith 3” yellow reflective tape.

All pedestrian signals shall be 16” LED and shall consist of combination “Walking Man”/”Hand”symbols with countdown timers. Pedestrian signal installations shall also include audiblesignals, countdown timers and ADA compliant pedestrian pushbuttons for all marked, signalizedcrosswalks. Pedestrian countdown timers shall meet the requirements of Special Specification680.81500010.

Span Pole Analysis shall be carried out using the latest version of the Department’s Span WireAnalysis Program to determine the signal pole sizes and foundations needed. Span pole sizesidentified by the Span Wire Analysis Program shall be increased by a minimum of 15% loadingrounded up to the nearest 1000 lb increment. Footing size shall be increased to accommodatethe maximum loading of the pole.

Page 61: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 53 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

12.3.5 Cabinet/Disconnect Switch

The Design-Builder shall install one state supplied microcomputer cabinet at each of thesignalized intersections. The Design-Builder shall also install a disconnect generator transferswitch on the span pole to which the cabinet has been mounted, at a minimum of 8’ aboveground level. The cabinet and disconnect switch shall meet the requirements of SpecialSpecifications 680.80324515 and 680.94997008, respectively.

12.3.6 Pullbox

Where a fiber optic interconnect exists, a 30” square fiber optic pullbox shall be installedadjacent to the cabinet. All other pullboxes required shall be standard 26”x18” pullboxes.Pullboxes may be either reinforced concrete or reinforced concrete/bituminous fiber.

12.3.7 Power Supply

Power shall be supplied to the microcomputer cabinet from the nearest available utility pole.The power supply cable shall be a 2 conductor, 6awg cable conforming to the requirements ofSpecial Specification 680.95020615.

12.4 DELIVERABLES

Section not used.

Page 62: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 54 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 13 LIGHTING

13.1 SCOPEThe Design-Builder shall conduct all Work necessary to provide all required lighting and lightingcomponents required for the Project. This includes design, fabrication and construction of alltransportation related permanent and temporary roadway lighting of the bridge and roadwaywithin the Project Limits. The lighting design shall be consistent with the Town of HempsteadDivision of Street Lighting requirements as shown in the directive plans found in Part 6 – RFPPlans. The Design-Builder shall coordinate the lighting design with the Town of HempsteadDivision of Street Lighting.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The review and approval process shall be in conformance withthe Design-Builder’s Quality Control Plan.

13.2 STANDARDS

The Design-Builder shall perform the lighting activities in accordance with the ContractRequirements and the applicable Standards, Design Codes and Manuals listed in Section 1.6,or otherwise applicable to the Project, and the following additional Standards:

13.2.1 Standards

A) ANSI/IES ANSI Approved Recommended Practice for Roadway Lighting, RP-8-00

B) ANSI/IES ANSI Approved Recommended Practice for Roadway Sign Lighting, RP-19-01

C) FAA Advisory Circular 70/7460-1K, Obstruction Marking and Lighting

D) IES Recommended Lighting for Walkways and Class 1 Bikeways, DG-5-94

E) NFPA NFPA 70 – National Electrical Code (NEC)

F) NYSDOT Policy on Highway Lighting

G) USCG 33 CFR 118 – Bridge Lighting and Other Signals

13.2.2 References

A) IES Guideline for the Application of General Illumination (“White”) Light-EmittingDiode (LED) Technologies G-2-10

B) NFPA NFPA 70E Standard for Electrical Safety in the Workplace

C) NFPA NFPA 780 Standard for the Installation of Lightning Protection Systems

13.3 REQUIREMENTS

13.3.1 General Requirements

The Design-Builder shall be responsible for designing, furnishing and installing all componentsrequired for the implementation of the lighting system for the Project including new luminaires,controls, poles, foundations, junction boxes, enclosures, mounting hardware, wiring, conduits,and support hardware, as necessary for delivering a complete and functional lighting system.

Page 63: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 55 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The Lighting System within the Project limits shall be fully maintained by the Design-Builder forthe duration of the Project or as until the agency owning and maintaining the lighting systemapproves the completion of the work and accepts the ownership.

13.3.1.1 Power Supply Requirements

For reference, the lighting installation shall comply with the following:

A) Meet all requirements of NFPA 70 – National Electrical Code (NEC);

B) All outdoor electrical enclosures shall be type 316 stainless steel, rated NEMA 4X or ahigher degree of protection; and

C) Meet all requirements of applicable IEEE and ANSI power engineering standards.13.3.1.2 Removal of Existing Equipment

All disconnected luminaires, light poles, and associated equipment shall be removed anddisposed of by the Design-Builder. All wiring, switches, panels, cabinets, enclosures, and otherelectrical equipment shall be removed and disposed of by the Design-Builder.

The Design-Builder shall return the following to the Town of Hempstead:

A. Davit Arm Aluminum anchor base pole

B. Existing arm, bracket and luminaire

The Design-Builder shall dispose of the concrete base.

13.3.2 Permanent Lighting System

13.3.2.1 General

The Design-Builder shall be responsible for ensuring that the permanent lighting system meetsthe following requirements:

A) Provides illumination such that the road surface illumination meets or exceeds theuniformity and the illuminance and/or luminance criteria during darkness;

B) Utilizes energy efficient and long-life, low maintenance lighting technologies that are foundon the Department’s approved lists;

C) Can be fully and seamlessly integrated into the existing permanent lighting elementsadjacent to the Project limits;

D) Utilizes a photo-control switch system that automatically activates lighting before dusk anddeactivates the system past dawn;

E) Contains surge suppression devices for protection against damage by lightning strikes andcomplying with NFPA-780 and UL 96;

F) Provides fixtures that are water tight and intended for a marine/industrial environment; and

Page 64: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 56 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

G) Utilizes lighting components that are readily available and not proprietary equipment.

H) Light poles shall be constructed of aluminum and shall be + 30’ in height.

I) Arms shall be 15' truss arms. A twin arm shall be used for Street and Shared Use Pathlight.

J) Luminaire shall be LED Series – XSP2 LED Street / Area Light – Double Module – VersionC

13.3.2.2 Construction Requirements

The Design-Builder shall use materials listed on the NYSDOT approved list of materials andconsistent with the details shown on the Department’s Standard Sheets.

The Design-Builder shall provide permanent lighting materials that satisfy the ProjectRequirements and applicable codes. In addition, the Design-Builder shall:

A) Ensure that all exposed raceways/conduits are made of PVC coated rigid galvanized steel(RGS). Short runs (no longer than 5 feet) of liquid-tight flexible metal conduit may only beused to make a final connection between the main power feeder and a light pole or fixture;

B) Ensure that all outdoor electrical enclosures and attached parts (e.g. breather drain) shallbe type 316 stainless steel, rated NEMA 4X or a higher degree of protection;

C) Ensure that any new electrical enclosures shall have a key lock;

D) Ensure all lighting shall include breakaway devices, unless protected by concrete barrier.Light poles shall feature a breakaway base, except where located behind bridge rails.

13.3.3 Temporary Lighting System

The Design-Builder shall ensure that the existing lighting levels within the Project limits aremaintained at all times. A temporary lighting system shall be installed as necessary to meet thisrequirement. The temporary system shall be energized either separately or though connectionto the existing lighting system.

13.4 DELIVERABLES

Deliverables shall be as stated elsewhere in the RFP documents.

Page 65: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 57 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 14 INTELLIGENT TRANSPORTATION SYSTEMS (ITS)

14.1 SCOPE

The Design-Builder shall perform all work necessary to design, furnish, build, and installtemporary and permanent replacement of all ITS communication system field devices foruninterrupted service of the INFORM traffic management and traffic signals.

The ITS System work in the Project shall consist of the following:

A. Installation of a fiber optic backbone system including all trunk and drop fiber cable,splices, fiber backbone conduit with 4 innerduct cells, traffic pullboxes, fiber opticpullboxes, and aerial fiber messenger cable on NY878 from the intersection signalcontroller corner of Rockaway Blvd Turnpike to the intersection controller corner of BayBlvd.

B. Replacement of the existing INFORM ITS system aerial fiber optic backbone systemwithin with new underground conduit fiber optic backbone including all trunk and dropfiber cable, splices, fiber backbone conduit with 4 innerduct cells, traffic pullboxes, fiberoptic pullboxes, and aerial fiber messenger cable on NY878 from the intersectioncontroller corner of Bay Blvd. to the intersection controller corner of Burnside Ave.

C. Installation of NYS furnished IP dome cameras on the intersection span poles atRockaway BlvdTurnpike, Bay Blvd and at Burnside Ave. on new 5 foot mast arms.

D. Installation of new LED VMS on new cantilever sign structures in the NB NY878shoulder approximately 1000 FT south of Burnside Ave and in the SB NY878 shoulderapproximately 700 FT North of Burnside Ave.

E. Installation and integration of NYS furnished fiber optic modems and Ethernet switch androuter equipment associated with the 3 project intersection signal controllers, 2 VMScontrollers, and 3 IP Dome cameras.

F. All underground conduit, pullbox, and fiber splicing connection and integration to theexisting INFORM NY878 fiber system south of Burnside Ave.

The Design-Builder shall design, furnish and install a complete, operational and tested ITSsystem including all required electronic devices for the System, all associated mountinghardware, and all associated cabling and integrate those devices into the NYSDOT INFORMTransportation Management Center. Final underground conduit, pullbox, and fiber splicingconnections and integration to the existing INFORM NY878 fiber system south of Burnside Ave.shall be completed by the Design-Builder. The Design-Builder shall be responsible for all workrelated to ITS within the Project limits.

None of the functionality of the existing ITS equipment, Signal equipment, or associatedcommunication system equipment may be lost or negatively affected by the project work. Thisincludes the existing signal and ITS related fiber system south of Burnside Ave.

The Design-Builder shall be responsible for 100% continuity of operations of the existingINFORM ITS during the project including furnishing and installing any and all temporarycommunications including new temporary or permanent cable TV drops, connections andintegration if needed. Any operational disruptions to the existing ITS or signal systems caused

Page 66: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 58 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

by the Design-Builders operation shall be repaired at the Design-Builders expense at noadditional cost to the department.

The Design-Builder shall maintain and protect the existing Fiber Optic trunk cables located inthe NYSDOT Right of Way. Should any disruptions of the existing Fiber Optic network berequired due to the Design-Builders operations, a temporary communication system or bypasscommunication linked to the NYSDOT TMC shall be provided at the Design-Builders expense.None of the current functionality of the existing system may be lost or negatively affected byconstruction activities related to this Project.

Any disruptions to the existing system caused by the Design-Builder’s operations shall berepaired by the Design-Builder at no additional cost to the Department.

14.2 STANDARDS

The Design-Builder shall perform ITS activities in accordance with the Contract Requirements,the applicable Standards, Design Codes and Manuals cited in Section 1.6, unless otherwiseapplicable to the Project, and the following additional Standards:

14.2.1 Standards

NFPA:

· NFPA 502 Recommended Practice on Fire Protection for Limited Access Highways,Tunnels, Bridges, Elevated Roadways and Air Right Structures

NTCIP:

· 1101 NTCIP Simple Transportation Management Framework

· 1102 NTCIP Octet Encoding Rules (OER)

· 1201 NTCIP Global Object (GO) Definitions

· 1203 NTCIP Object Definitions for Dynamic Message Signs

NYCRR:

· Part 56 of Title 12 of the Official Compilation of Codes, Rules; and Regulations of theState (12NYCRR, Part 56)

14.3 REQUIREMENTS

14.3.1 Variable Message Sign (VMS)

The Design-builder shall furnish and install two new TYPE 3, 2-line Light Emitting Diode (LED)variable message sign (VMS), CALTRANS Type 334 ground mounted VMS controller cabinets,new cantilever sign structures, and all related installations and equipment for the operation ofthe sign. The communications from the roadside cabinet to the sign shall be over a dedicatedlocal fiber optic link.

Page 67: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 59 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The VMS controller shall be connected to the Fiber Backbone cable via a new 12 fiber dropcable and backbone cable splice.

The VMS shall meet or exceed the requirements of the following NYSDOT SpecialSpecification:

· 683.84029110 – LED VARIABLE MESSAGE SIGN, TYPE 3

The ground mounted VMS cabinet shall meet or exceed the requirements of the followingNYSDOT Special Specification:

· 680.84430110 – VMS 334 CABINET

The Design-Builder shall furnish a separate conduit and pullbox system to supply utility ACpower to the VMS equipment using a dedicated minimum 3” diameter rigid galvanized steelconduit or as larger as required.

The backbone conduit shall meet the following Specification:

· 680.520108 – CONDUIT, METAL STEEL, ZINC COATED, 3"

The Design-Builder shall furnish and install new guiderail to protect the new VMS and cantileversign structure.

14.3.2 IP Dome Camera

The Design-Builder shall Install NYS furnished IP dome cameras on the intersection controllerspan poles at Rockaway BlvdTurnpike, Bay Blvd, and Burnside Ave. on new Design-Builderfurnished and installed NYS approved 5 foot mast arms. The position and view of the cameraand the height of the camera and mast arm on the signal pole shall be approved by NYSDOTR10 INFORM.

The IP Dome Camera Installations shall meet the requirements of the following SpecialSpecification:

· 683.03100010 – INSTALL NYSDOT FURNISHED IP CCTV ASSEMBLY

The Design-Builder shall furnish and install a 12 fiber patch panel in the 3 project intersectioncontroller cabinets to provide fiber patching to the backbone for the signal controller and IPcamera communication circuits.

The patch panels shall meet the requirements of the following Special Specification:

· 683.07101210 – FIBER OPTIC CABLE PATCH PANEL - 12 PORT

14.3.3 Fiber Optic Backbone

Design-Builder shall furnish install the new fiber optic backbone cables in new 4” NPSGalvanized Steel Conduit using two runs of continuous 2 channel innerduct between fiber opticpullboxes.

Page 68: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 60 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The backbone conduit shall meet the following Specification:

· 680.520110 – CONDUIT, METAL STEEL, ZINC COATED, 4"

The 2 channel innerduct shall meet the following Special Specification:

· 683.07010010 - FIBER OPTIC INNERDUCT, 2 CHANNEL

The Fiber Optic Cable installed for the fiber optic backbone cables shall meet or exceed therequirements of the following NYSDOT Special Specification:

· 683.07207210– SINGLE MODE FIBER OPTIC TRUNK CABLE, 72 FIBERS

The Fiber Optic cable drop cable installed from the ITS and signal equipment to the fiber opticbackbone shall meet following NYSDOT Special Specification:

· 683.07021210 – FIBER OPTIC ARTERIAL DROP CABLE, 12 FIBERS

The Design-Builder shall also furnish and install all required fiber optic cable connectors,splices, splice trays, splice cases, patch cables, and breakout kits as necessary to perform thework.

14.3.3.1 Fiber Optic Pullboxes

The fiber backbone design shall include a Fiber pullboxes at each signal and VMS drop andintermediate Traffic pullboxes such that the average spacing between any two pullboxes doesnot exceed 225 feet.

The Power distribution conduit system for the project VMS sites shall include Traffic pullboxes atthe two VMS sites and intermediate Traffic signal pullboxes such that the average spacingbetween any two pullboxes does not exceed 225 feet.

Concrete Fiber Optic Pullboxes installed at the base of the traffic signal poles and VMScantilever structures where the traffic signal and VMS control cabinets are located and shallmeet or exceed the requirements of the following NYSDOT Special Specification:

· 680.51400010 – CONCRETE FIBER OPTIC PULLBOX

Standard Traffic Signal Pullboxes to be installed between the concrete fiber optic pullboxes inthe fiber optic backbone system at shall meet or exceed the requirements of the followingNYSDOT Special Specification:

· 680.51050010 – PULLBOX, RECTANGULAR REINFORCED CONCRETE (26INCH X 18 INCH)

14.3.4 Traffic Signal Interconnection

As part of this project the Design-Builder shall install NYS furnished Ethernet switchesand fiber modems at the 3 project signalized intersections on NY878. The Design-Buildershall configure and integrate the fiber modems and Ethernet switches for compatibility andcommunication with the INFORM Naztec central software and system.

Page 69: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 61 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

14.3.5 INFORM TMC Integration

All ITS and signal equipment will be controlled from the existing NYSDOT INFORM ITS controlcenter in Hauppauge, NY. The Design-Builder shall integrate the ITS and signal Equipmentinstalled in the project limits so that it operates seamlessly from the INFORM TMC.

The IP address assignments for all project ITS and signal equipment shall be provided to theDesign-Builder by NYSDOT INFORM.

All ITS equipment and related communication equipment installed under the contract shall beconsistent with the Region 10 ITS Architecture including compatibility with the INFORM COVALInc. Foundation III and Naztec central software.

14.3.6 Electrical Work

The Design-Builder shall provide all 120/240VAC power necessary for the construction andSystem installation and shall include the furnishing and installation of all labor and equipment.Surge protection for all power, video and data circuits entering or exiting the cabinets shall befurnished with surge lightning protection. The Design-Builder shall maintain the integrity of allcircuits in service that may be affected by the work.

The Design-Builder shall furnish and install cabling and conduit between the controllercabinet and the ITS equipment cabinet, the ITS cabinet and the fiber optic pullbox, the cameraand the ITS equipment cabinet, the fiber and communication manholes and the power source.It shall be the responsibility of the Design-Builder to verify that the cabling and its routing aresufficient for their needs.

14.3.6.1 Cabling Requirements

All cable used for power branch distribution shall be #6AWG minimum, or sized larger to suit thespecific application. Voltage drop calculations shall be performed for each equipment cabinetserviced showing actual power used and the cable distance from the power distribution panel.

Power cabling and wires installed outdoors and underground shall be rated for 600V, ratedfor wet locations and gasoline and oil resistant.

All cables provided shall be provided with terminations, connectors and splices as neededand shall be installed within the existing or proposed conduits. All termination cables providedshall be provided with terminations, connectors and splices as needed.

Video cable furnished for connections shall be rated outdoor use.

All cables shall be clearly labeled with identifying label or tags clearly indicating the circuitnumber and/or camera number.

All electrical enclosures and boxes provided by the Design-Builder shall be stainless steelNEMA 4X.

All conduits shall be hot-dipped Rigid Galvanized Steel (RGS). All fittings and conduit bodiesshall be hot-dipped galvanized.

Page 70: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 62 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

14.4 SYSTEM TEST PROCEDURES

The Design-Builder’s ITS System Integrator shall be responsible for testing the installedequipment to verify that it has been installed correctly, is performing as specified, and supportsoverall system operations. This testing will be accomplished in a sequence of procedures thatbegin with basic components and culminate in exercising the total system in its operationalconfiguration.

For all tests, the Integrator is responsible for providing detailed, step-by-step procedures for thetesting. These procedures shall specifically identify:

· The equipment configuration;

· The sequence of operations for the test,

· The test setup including environmental conditioning;

· The required test equipment and its configuration;

· The expected results and pass/fail criteria;

A copy of the test procedures shall be furnished to the Department’s Construction QualityAssurance Engineer for review prior to the commencement of the tests.

14.4.1 Factory Testing

Factory testing verifies that the performance of equipment being supplied meets or exceeds theminimum performance established in the specifications. For off-the-shelf equipment andcomponents, the Integrator can establish compliance through third party verification and amanufacturer’s quality assurance plan. The manufacturer shall supply documentation toverify that the performance of the equipment has been measured against themanufacturer’s equipment specification over the entire environmental range.

For equipment and components that are unique to and specifically manufactured for the project,the Integrator shall schedule an acceptance test at the factory to demonstrate compliancewith the specifications. These tests shall demonstrate compliance with all aspects ofthe specifications over the entire range of environmental conditions. For tests thatrequire environmental chambers of special conditions, the Manufacturer may substitutedocumented test results in lieu of actually performing the procedure.

14.4.2 Operational Stand Alone Testing

The operational standalone testing demonstrates that the equipment has been installedcorrectly and is operational. These tests involve only single items of equipment or equipmentassemblies. Portable laptop computers and test equipment supplied by the Design-Builder cansimulate control of the standalone equipment. Typical tests would include but are not limited to:

· Physical inspection of the installation;

· Continuity tests;

Page 71: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 63 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· Power-on tests;

· Voltage measurements;

· Cable performance tests (twisted-pair, video and fiber optic). For optical fibers,this would include OTDR and attenuation measurements. For video cable, this wouldinclude frequency attenuation measurements. For twisted-pair cable, this would includechecks for grounds, splits, crosses, and opens.

· Cabinet assembly-performance tests (e.g. Cabinet to CCTV camera functionality orcabinet to radar detector);

· Verification of radar detector measurements;

· Functional performance of Camera and communications;

· Wireless radio measurements (output power, signal levels, etc.).

Operational standalone testing should also include equipment setup. This would includeconfiguring the equipment’s options and setting the equipment’s system identification,including its network address.

14.4.3 Group Site Verification Testing

Group site verification testing that measures the performance of “linked” equipment andcomponents shall be preferred. Typical tests include but are not limited to:

· Communications links with modems connect to optical fibers or microwave radios

· Multiplex connections and performance between nodes such as minihubs orshelters and operations centers such as the TMC.

· Modem circuits

· Data circuits

14.4.4 Subsystem Integration Testing

Subsystem integration testing shall be preferred that includes all components in the subsystemand demonstrates that the subsystem is totally functional and capable of supporting operations.Each subsystem shall be tested in its operational configuration, demonstrating completecompliance with all components between and including the operations center and the fieldelements.

14.4.5 System Acceptance Testing

A system acceptance test shall be preferred which demonstrates that the installedequipment will operate as specified and support operations for an extended period of time, notless than 30 days. The system acceptance test also provides a controlled burn-in period for theinstalled equipment. Procedures shall be provided to fully utilize all aspects of theequipment and associated functions throughout the course of the test.

Page 72: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 64 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

If any equipment should fail during the 30-day period, those subsystems affected by the failedequipment shall be subject to an additional 30-day test period. The Department will determinewhich equipment has been affected by the failure and subject to an additional 30-day period oftesting.

14.5 DOCUMENTATION REQUIREMENTS

The Design-Builder shall prepare all Documentation as required and submit to the Departmentfor review. The Department’s review of system documentation does not waive the Design-Builder’s responsibility in furnishing and installing a fully operational and functional systemmeeting the specifications herein.

14.5.1 Shop Drawings and Test plans

Test plan submittals shall be furnished by the Design-Builder to the Department to demonstratethat the System and associated products he intends to supply for this Contract have thecapability to meet the functional objectives required by the Technical Parameters. Systemdocumentation submittals required shall consist of:

· Factory Acceptance Test Plan and Report.

· Field Acceptance Test Plan and Report.

· Operational Acceptance Test Plan and Report.

· Operating Documentation.

The Design-Builder shall provide the Department with the following documentation at theconclusion of the project:

· A minimum of five copies of all manufacturers’ documentation for all equipment to besupplied as part of this project. This documentation shall include all operations,maintenance, software support, and protocol descriptions available from themanufacturer of each component.

· All documentation specifically requested in the individual item specifications.

· A minimum of three copies of written documentation which contains the correcthardware (dip switch settings) and software adjustable configurations for all equipmentused in the project.

· A chart which details the pin-outs of all cable assemblies and actual interconnectionof all system components.

Page 73: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 65 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 15 WORK ZONE TRAFFIC CONTROL AND ACCESS

15.1 SCOPE

The Design-Builder shall be responsible for the planning and provision of Work Zone TrafficControl (WZTC), required to perform the Project Work until Project Completion. This ProjectRequirement applies to any roads, ramps, cross roads, local streets, maintenance roads,driveways, and active paths within and/or affected by the Project.

The Design-Builder shall provide WZTC for the safe and efficient movement of people, goods,and services through the Project area(s) while maintaining access and minimizing negativeimpacts to residents, commuters, businesses, and NYSDOT maintenance operations.

Note that, as used in this section, “Work Zone Traffic Control plan” or “WZTC plan” is theequivalent of “Maintenance and Protection of Traffic plan” or “MPT plan” as described inChapter 16 of the Highway Design Manual (HDM).

15.2 STANDARDS

The Design-Builder shall perform the work zone traffic control activities in accordance with theContract Requirements and the applicable Standards, Design Codes and Manuals listed inSection 1.6, unless otherwise stipulated in this Project Requirements, or otherwise applicable tothe Project.

15.3 REQUIREMENTS

15.3.1 General Requirements

No offsite detours are allowed.

15.3.2 Work Zone Traffic Control Plan

The Design-Builder shall prepare and submit a WZTC Plan for managing traffic operations andcontrolling access until Project Completion. A WZTC Plan must be submitted in advance of anywork that restricts the roadway cross section and includes durations and traffic pattern changesthat will exceed 10 hours in any 24-hour period.

The WZTC Plan shall be submitted to the Department’s Design Quality Assurance Engineer aminimum of two weeks prior to initiation of any Work requiring a lane closure or theimplementation of any change in traffic patterns.

The WZTC Plan shall include:

A) Contingency plans for reasonable unforeseen interruptions;

B) Duration of each WZTC stage, including duration of lane closure(s), if any;

C) Provisions for maintaining pedestrian traffic through the Project area at all times at alllocations where pedestrian access through the Project area currently exists.

Page 74: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 66 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The Design-Builder shall notify local officials, and affected police jurisdictions to facilitate safeand effective enforcement. The WZTC Plan shall recognize the need for approval of the use oflocal public roads, if applicable.

The Design-Builder shall be responsible for updating the WZTC Plan as necessary throughoutthe Contract, so that at all times the current traffic control on site is representative of the designdrawings that have been accepted by NYSDOT.

15.3.3 General Restrictions

The Design-Builder shall be aware that no work shall be performed and no temporary laneclosures and/or shoulder closures shall be permitted on the following State recognized holidays:

A) New Year’s Day;

B) Memorial Day;

C) Independence Day;

D) Labor Day;

E) Veterans Day;

F) Thanksgiving Day;

G) Christmas Eve, Christmas Day.

H) New Year’s Eve

Construction activities using temporary lane closures shall be suspended to minimize traveldelays associated with road work for major holidays as follows:

· Friday, Saturday, Sunday and Monday Holidays – Beginning 5:00 a.m. the business daybefore the holiday and ending 5:00 a.m. the business day following the holiday.

· Tuesday Holidays – Beginning 5:00 AM the Friday before the holiday and ending 5:00AM the next business day.

· Wednesday Holidays – Beginning 5:00 AM the Tuesday before the holiday and ending5:00 AM the next business day.

· Thursday Holidays – Beginning 5:00 AM the Wednesday before the holiday and ending5:00 AM the following Monday.

15.3.4 Access to Commercial Properties and Driveways

The Design-Builder shall provide uninterrupted access to all commercial properties anddriveways within the Project Limits at all times.

15.3.5 Closure Restrictions

During peak period (5 AM and 9PM) The Contractor shall maintain the number of lanes asshown below:

1. At least two through lanes in each direction on Nassau Expressway.

2. At least three through lanes in each direction on Rockaway Turnpike

Page 75: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 67 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

3. At least one through lane in each direction on Bay Blvd between Rockaway Turnpikeand Rason Road

The Contractor shall maintain all existing lanes on Burnside Avenue during peak hours (5AM to9PM)

A single lane closure will be allowed between 9:00 p.m. and 5:00 a.m.

15.3.6 Minimum Lane Widths during Construction

The Design-Builder shall maintain a minimum travel lane width of 11 feet during construction.

15.3.7 Portable Variable Message Signs

The Design-Builder shall provide, as a minimum, 11 Portable Variable Message Signs, but moreshould the Design-Builders design dictate, for the duration of this Contract. The PortableVariable Message Signs shall be deployed as necessary for the various WZTC schemesdeveloped in coordination with, and with concurrence/acceptance from, the Department’sProject Manager. The portable variable message signs provided shall meet the requirements ofNYSDOT Item No. 619.110512 (Portable Variable Message Sign (PVMS) STANDARD SIZE -FULL MATRIX (LED) NO OPTIONAL EQUIPMENT SPECIFIED, CELLULARCOMMUNICATIONS).

The development of messages for the Variable Message Sign(s) shall be the responsibility ofthe Department’s CQAE and operations staff at the NYSDOT’s Transportation ManagementCenter.

The Design-Builder shall contact the Department’s CQAE at least two weeks prior to placementof any Variable Message Sign regarding their location and receive concurrence of the location.

15.3.8 Temporary and Interim Pavement Markings

The Design-Builder shall provide temporary and interim pavement markings during allconstruction phases conforming to the requirements of the NYSDOT Standard Specifications.

15.3.9 Coordination with Regional Traffic Management Center

The Design-Builder is advised that the NYSDOT’s Traffic Management Center will providesupport for the Project’s WZTC activities. Therefore, coordination among the Department’sConstruction Quality Assurance Engineer, Design-Builder, and NYSDOT’s Traffic ManagementCenter, will be required for all WZTC activities, particularly with respect to the use of VariableMessage Signs (VMS)) in the Project area.

15.3.10 Emergency Response and Transportation Management Plans

The Design-Builder shall notify the Department’s CQAE immediately following any impacts tomotorists due to construction activities and/or unforeseen circumstances. The CQAE will beresponsible for disseminating the information to the appropriate personnel/entities forappropriate response to mitigate impacts to motorists.

Page 76: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 68 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

The Design-Builder shall prepare an Emergency Response Plan to be implemented in the eventthe roadway is shut down for unforeseen or unplanned circumstances. The Plan shall beimplemented when the anticipated duration of closure exceeds twenty (20) minutes. The Planshall be submitted to the Department’s Project Manager for review and comment a minimum oftwo weeks prior to the beginning of Work. Work on this Project shall not begin until the Design-Builder receives written notification from the Department’s Project Manager that the EmergencyResponse Plan has been reviewed by the Department and all Department comments have beenresolved.

The Emergency Response Plan shall include a notification and communication plan thatdescribes how the Design-Builder will promptly inform the appropriate personnel/entities of anunforeseen or unplanned circumstance. No later than 30 calendar days following NTP, theDepartment’s Project Manager will provide the Design-Builder with a list of personnel andentities that need to be contacted in this section of the Emergency Response Plan.

The Design-Builder shall also provide the Department’s Project Manager a TransportationManagement Plan (TMP) per FHWA’s Final Rule on Work Zone Safety and Mobility, 23 CFR630 Subpart J. The intent of the TMP is to minimize impacts to the travelling public and toprovide continuity of reasonably safe and efficient road user flow and highway worker safety.The Emergency Response Plan shall be a component of the TMP and shall be located in thecontingency section of the TMP.

15.3.11 Lifting Operations

The Design-Builder shall be aware that under no circumstances shall lifting operations for bridgesuperstructure elements, overhead sign structures, or any other items, be carried out overactive traffic lanes. All such operations shall at a minimum require short-duration roadwayclosures in accordance with the provisions of this Section 15.

Page 77: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 69 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 16 PAVEMENT DESIGN AND CONSTRUCTION

16.1 SCOPE

The Design-Builder shall perform all Work necessary to provide all pavement required for theProject. This includes design, furnishing of materials, fabrication and construction of alltemporary and permanent pavement for roadways within the Project Limits.

The Design-Builder shall be responsible for the review and approval of all submittals needed forthe scope of work. The review and approval process shall be in conformance with the Design-Builder’s Quality Control Plan.

16.2 STANDARDS

The Design-Builder shall perform the pavement activities in accordance with the ContractRequirements and the applicable Standards, Design Codes and Manuals listed in Section 1.6,unless otherwise stipulated in this Project Requirement, or otherwise applicable to the Project.

16.3 REQUIREMENTS

All pavement materials and construction methods shall be in accordance with the requirementsof the NYSDOT Standard Specifications and the NYSDOT materials and pavement installationmethods.

Limestone and/or dolomite, regardless of the acid insoluble residue content, shall not beallowed for Type 1 or F1 friction aggregate requirements.

If the existing roadway section at the limits of work varies from the standards applicable for newor resurfaced sections, the roadway features (lane & shoulder widths and cross slope) shall betransitioned to meet the existing conditions.

16.3.1 Full Depth Reconstruction

The Design-Builder shall develop and construct pavement section(s) for full depthreconstruction, including subbase, of the Project roadways in conformance with theComprehensive Pavement Design Manual, using the ESAL-based pavement design method.

ESAL calculations should be done for 50 years.

Full depth reconstruction is required within the limits of any horizontal alignment changes, orvertical alignment changes until such point as the revised alignment meets the existingalignment. However, increases in profile elevations, up to eight inches (8”), may be madethrough asphalt overlays without the requirement of full depth reconstruction unless full depthreconstruction is required elsewhere in the RFP. No partial-width full depth reconstruction willbe permitted; any roadway requiring full depth reconstruction shall be reconstructed for its fullwidth, including shoulders, curbs and/or sidewalks.

If any roadway is permanently widened for the purpose of providing additional travel and/orturning lanes, new full depth pavement need only be developed and constructed for the widenedsection, provided that no other portion of the pavement within the widened section requires fulldepth reconstruction for any other purpose. However, the existing pavement within the widened

Page 78: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 70 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

section shall be milled and resurfaced from curb to curb or edge of pavement to edge ofpavement to provide a uniform pavement as specified in Section 16.3.2.

Full depth pavement should continue throughout the entire roadway including shoulders.

Top course shall be 9.5mm or finer aggregate mix.

The Shared Use Path shall be constructed with Asphalt pavement with a 6” minimum subbase,a 2.5” minimum binder course and a 1.5” minimum top courseof 1.5” Top Course, 2.5” BinderCourse and 6” subbase, except where noted below.

Where the shared use path is located over the 48” water main or the edge of the path is lessthan 10 feet from the edge of the water main, the path shall be constructed of 2” Top Course, 3”Binder Course, 6” Base Course and 12” subbase.

16.3.2 Milled and Resurfaced Roadways

The Design-Builder shall mill and resurface pavement areas as necessary to provide for asmooth transition between the existing and fully reconstructed pavement surfaces inaccordance with the applicable Standard Sheets. The Design-Builder shall mill a minimum of50’ beyond the limits of any full depth reconstructed pavement sections.

Within the horizontal limits of any widened pavement section, the existing pavement shall bemilled and resurfaced in conjunction with the top course placement for the widened section inorder to provide a uniform pavement within the widened section of roadway.

Any existing pavement that is milled and does not correspond to the proposed pavementthickness, must be reconstructed to agree with proposed pavement thickness.

16.3.3 Temporary Pavement

Shall be designed as per NYSDOT Comprehensive Pavement Design Manual.

Minimum Sub-Base course of 12 inches thick and minimum Binder layer of 4 inches with 19.5mm stone size.

16.3.4 Utility Trench Restoration

Outside areas of full depth reconstruction, pavements in trench restoration areas shall matchthe adjacent pavement section.

Page 79: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 71 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 17 DRAINAGE AND STORMWATER

17.1 SCOPE

The Design-Builder shall design and construct a drainage system as needed for the estimatedstorm runoff that provides functionality, durability, ease of maintenance, maintenance access,safety, and pleasant aesthetics.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The review and approval process shall be in conformance withthe Design-Builder’s Quality Control Plan.

Where drainage patterns will or must be changed from existing patterns, the Design-Buildershall be responsible for securing all necessary permits prior to construction of any drainagefacilities.

Prior to Project Completion, the Design-Builder shall be responsible for cleaning all new andexisting drainage facilities within the Project Limits.

17.2 STANDARDS

The Design-Builder shall perform the drainage and stormwater activities, including highway,bridge and site systems, in accordance with the Contract Requirements and the applicableStandards, Design Codes and Manuals listed in Section 1.6, unless otherwise stipulated in thisProject Requirement or otherwise applicable to the Project.

Stormwater shall be conveyed from point to point through the use of a single pipe. Smallerpipes in parallel shall not be permitted.

17.3 REQUIREMENTS

17.3.1 Drainage Report

The Design-Builder shall provide a Drainage Report to the Department and any other entitieswhose facilities will be impacted by the Project in accordance with HDM Chapter 8. TheDesign-Builder shall be responsible for coordination in advance with any third party to determinethe necessary document submission required by the third party. At least two weeks prior toproviding documents to any third party, the Design-Builder shall submit a draft Drainage Reportto the Department’s Design Quality Assurance Engineer for consultation and written comment.

The Drainage Report shall document the design criteria used, final design basis, and allsupporting calculations and computer model output.

17.3.2 Connections to Existing Systems

The Design-Builder shall develop Design Plans and Project Specifications for any connectionsto existing storm systems and / or a proposed water quality detention system within the projectlimit. The Design-Builder shall be responsible for calculations performed to ensure there issufficient capacity to accommodate any increase in flow due to changes in drainage catchmentarea and/or to land use. This paragraph shall not be construed to relieve the Design-Builder ofthe obligation to treat runoff water that requires treatment.

Page 80: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 72 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

In addition, the Design-Builder shall design positive drainage systems for a high tailwaterconditions. The Design-Builder shall not utilize check valves as part of the proposed drainage.Leaching basins may not be used except in the COSTCO parking lot lease work area and only ifthey are interconnected with piping connected to the replacement pipe of the 54” pipe draininginto the channel (‘C’) north of Bay Boulevard and west of the Nassau Expressway.

17.3.3 Spill Management

Spill prevention and response measures shall be described in the SWPPP.

17.4 DELIVERABLES

Deliverables shall be as stated elsewhere in the RFP documents.

Page 81: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 73 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 18 HIGHWAY DESIGN

18.1 SCOPE

The Design-Builder shall be responsible for the design, construction and reconstruction of thepermanent roadway(s) to be constructed within the Project Limits, and any other roadsdamaged by construction operations, or necessary for permanent operations, all in accordancewith the design requirements stated herein. Highway design, construction and reconstructionshall be understood to include the design, furnishing, and construction of all roadappurtenances, protections, and safety devices not specifically cited in other ProjectRequirements.

In addition, the Design-Builder shall be responsible for the removal of non-standard systemsthat currently exist within the Project limits, whether they are affected by the proposed work ornot, and replacement with systems meeting current Department Standards, unless specifieddifferently in the Project Requirements Sections 1-17 and 19-20.

18.2 STANDARDS

The Design-Builder shall perform the Work in accordance with the Contract Documents and theApplicable Standards, Design Codes and Manuals listed in Section 1.6, unless otherwisestipulated in this Project Requirement or otherwise applicable to the Project.

18.3 REQUIREMENTS

18.3.1 General

The Design-Builder shall be responsible for performing the detailed highway design andconstruction within the Project Limits in accordance with the Project Requirements set forthherein.

18.3.2 Design Requirements

Design requirements for the reconstruction of Project roadways shall be as specified below.

NASSAU EXPRESSWAY (NY 878)

· Design Speed: 40 mph

· Lane Widths: 12 feet minimum width for through, auxiliary, and turn lanes.

· Number of Lanes: Two through lanes in each direction plus auxiliary and turn lanesdescribed in the “Turning and Axillary Lanes” section below.

· Shoulder Widths: 10 feet right shoulder with two lanes; 6 feet right shoulder withauxiliary and right turn lanes.

· Shared Use Path: 12 feet width along west side of the expressway. 11 feet wide grassbuffer from Rockaway Turnpike to wetland retaining wall by the new nursery site. Nobuffer adjacent to retaining wall to Burnside Avenue. The Shared Use Path shall beconstructed beginning at the northwest quadrant of Burnside Avenue and the NassauExpressway, Station BS18+36.6. The path will continue along the west side of theNassau Expressway, ending on the west side of Rockaway Turnpike at StationR39+76.5.

Page 82: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 74 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

BAY BOULEVARD (ROCKAWAY TURNPIKE TO NASSAU EXPRESSWAY)

· Design Speed: 35mph

· Lane Widths: 11 feet minimum width for through and turn lanes.

· Number of Lanes: Two through westbound lanes plus turning and auxiliary lanes asdescribed in the “Turning and Auxiliary Lanes” section below. Two through eastboundlanes plus turning and auxiliary as described in the “Turning and Auxiliary Lanes” sectionbelow. Two lanes for Ramp NB.

· Shoulder Widths: 5 feet right shoulder. 5 feet right and left shoulders for Ramp NB.

· Concrete Sidewalks: 5 feet minimum width with 5 feet offset to curb-line along northfrontage. Retain existing south frontage sidewalk where present.

BAY BOULEVARD (NASSAU EXPRESSWAY TO RASON ROAD)

· Design Speed: 30mph

· Lane Widths: 12 feet minimum width for through and turn lanes.

· Number of Lanes: One through westbound lane for entire length Two througheastbound lanes from Incinerator Road to Nassau Expressway and one througheastbound lane from Rason Road to Incinerator RoadTurn lanes as described in the“Turning and Auxiliary Lanes” section below.

· Shoulder Widths: 5 feet right shoulders from Nassau Expressway to Incinerator Road.12 feet shoulders from Incinerator Road to Rason Road.

· Concrete Sidewalks: 5 feet minimum width with 5 feet curb offset on both sides fromNassau Expressway to Incinerator Road. Special plaza area at Memorial site atnorthwest quadrant at Costco – Driveway A. 5 feet minimum sidewalk with 5 feet curboffset along south frontage from Incinerator Road to Rason Road.

INCINERATOR ROAD (ACCESS DRIVE TO NASSAU COUNTY PUMP STATION)

· Design Speed: 30 mph

· Lane Widths: 12 feet minimum

· Number of Lanes: One in each direction

· Shoulder widths: 6 feet right shoulders

TURNING AND AUXILARY LANES

· 200 feet long Nassau Expressway northbound and southbound left turn lanes at BayBoulevard intersection.

· a northbound Nassau Expressway third (auxiliary) lane from Ramp NB to RockawayTurnpike.

· a southbound Nassau Expressway third (auxiliary) lane from 400 feet north of BayBoulevard to 300 feet south of Bay Boulevard, including a combined thru and right turnlane approaching Bay Boulevard.

· dual southbound Nassau Expressway right turn lanes approximately 700 feet longapproaching the roadway split at Burnside Avenue.

Page 83: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 75 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

· 200 feet long dual westbound left turn lanes on Bay Boulevard approaching NassauExpressway.

· 200 feet long combined westbound thru and right turn lane on Bay Boulevardapproaching Nassau Expressway.

· Right turn lane on westbound Bay Boulevard from Nassau Expressway to IncineratorRoad.

· Combined eastbound through and right turn lane on Bay Boulevard from IncineratorRoad to Nassau Expressway.

· Left turn lane on eastbound Bay Boulevard from Incinerator Road to NassauExpressway.

· Left turn lane on eastbound Bay Boulevard from Ramp NB to Rockaway Turnpike.

· Combined thru and right turn lane on eastbound Bay Boulevard from Ramp NB toRockaway Turnpike.

ROADWAY ELEVATIONS

· See following table for minimum roadway elevation requirements.

Page 84: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 76 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

Page 85: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 77 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

LIMITS OF FULL DEPTH/WIDTH ROADWAY RECONSTRUCTION

· Nassau Expressway: STA N1+26.76 to STA N29+50

· Bay Boulevard: STA B2+81.36 to STA B18+00

· Rockaway Turnpike: STA R39+00 to STA R43+50

· Incinerator Road: STA IP1+76.8 to STA IP11+66.0

18.3.3 Barrier Systems and Impact Attenuators

The Design-Builder shall remove and dispose of all existing barrier systems within the Projectlimits, and replace with new barrier systems to current NYSDOT Standards.

The limits of work for new roadside and new median barrier shall be the lesser of the following:

1) The point where barrier is no longer warranted; or

2) A point where the proposed barrier can be transitioned to an existing barrier systemwhich conforms to current standards.

All existing barrier systems that are removed shall become property of the Design-Builder.

18.3.4 Clear zone

The Design–Builder shall document clear zone on the final record plans.

18.4 DESIGN EXCEPTIONS AND NON-STANDARD FEATURES

It is the responsibility of the Design-Builder, in coordination with the Department, to obtainacceptance of any non-standard features included in the final design.

Page 86: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 78 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 19 STANDARDS

19.1 GENERAL REQUIREMENTS

The Design-Builder shall identify the specific version of each Standard it uses. It is the Design-Builder’s responsibility to obtain clarification of any apparent error, omission, ambiguity orconflict regarding any Standard in accordance with DB §102-2.

19.2 SPECIFIC REQUIREMENTS

The Design-Builder shall assume that all provisions of the Standards, including the figures andtables, are mandatory and guidelines contained therein shall be assumed to be requirements.All words such as “should,” “may,” “must,” “might,” “could,” and “can” shall mean “shall” unlessthe context requires otherwise, as determined in the sole discretion of the Department. It shallbe in the Department’s sole discretion to determine when the context does not require aprovision to be mandatory.

Except as expressly otherwise provided in the Contract Documents, any reference to NYSDOTunder a Standard shall mean the Department.

When a Standard refers to an action being necessary, needed, or recommended, the Design-Builder shall construe the action as required unless the context requires otherwise, asdetermined in the sole discretion of the Department.

Where reference is made in the Standards to items that are indicated in the plans or specialprovisions or required in the plans or special provisions, the plans or special provisions shallmean the Design-Builder’s Plans or the Special Provisions.

References in the Standards to approved products or materials shall mean approved by theDepartment.

All references in the Standards to the inspector, the field inspector, the project engineer, theengineer, the materials engineer, the district materials engineer, the survey crew, the projectsupervisor, the agency certified technician, the certified plant technician, and the representativeof the Office of Materials shall mean the Design-Builder, except as otherwise expressly providedin the Contract Documents or otherwise directed by the Department.

When a Standard refers to an approval of any correction or repair that deviates from theContract requirements, the Acceptance must be by the Department.

When a Standard refers to items that will be performed or provided by NYSDOT or by a divisionor employee of NYSDOT, the Design-Builder shall construe the requirements as applying to theDesign-Builder unless otherwise specified in the Contract Documents, or unless the contextrequires otherwise. It shall be in the Department’s sole discretion to determine when the contextrequires otherwise.

Page 87: NASSAU EXPRESSWAY OPERATIONAL & RESILIENCY … · 2017-12-20 · nassau expressway operational & resiliency improvements pin 0072.14, contract d900042 db contract documents part 3

New York State Department of Transportation

Nassau Expressway 79 Part 3 - Project RequirementsPIN 0072.14, Contract D900042 Final December 20, 2017

SECTION 20 SECURITY

Section not used.