Page 1: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

email:[email protected]

NASA University Student

Launch Initiative

(Sensor Payload)Jason G Renner

Patrick R Williamson

Tin T Tran

Michael A Bizanis

Payload Name: G.A.M.B.L.S

CPE496-01 Computer Engineering Design II

Electrical and Computer Engineering The University of Alabama in Huntsville

Page 2: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

2CPE495/496 Project Proposal, G.A.M.B.L.S.

GAMBLS Members

■ Jason G Renner - Project Manager■ Patrick R Williamson - Software development■ Michael A Bizanis – Software development■ Tin T Tran – Hardware development

Page 3: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

3CPE495/496 Project Proposal, G.A.M.B.L.S.

The Need■ Gather, store, and transmit data about flight

characteristics from an accelerometer,

magnetometer, gyroscope, barometer, and pitot

probe pressure sensors.

■ Data sampling rate shall be 500 Hz

■ Lightweight payload shall fit into a 3.5”x4.5”

space

■ Who is affected and who will benefit?

■ Charger Rocket Works will fly this payload on their

USLI rocket

Page 4: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

4CPE495/496 Preliminary Design Review Team Acronym

Finished Package Sample

■ Current Transmitter/Power

Board

■ GAMBLS payload will be

used by future CRW design

teams

Page 5: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

5CPE495/496 Project Proposal, G.A.M.B.L.S.

Marketing Requirements

■ Shall operate under the under the rigors of flight

■ Shall operate effectively for multiple launches

■ Shall be able to idle on the launch pad for up to

■ forty-five minutes and still be able to operate during

flight

■ Shall take data from an accelerometer, gyroscope,

magnetometer, barometer, pitot probe pressure sensors

and have the capability to add more sensors

■ Shall store data on the rocket and transmit data to a

ground station

Page 6: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

6CPE495/496 Project Proposal, G.A.M.B.L.S.

Engineering Requirements

The payload must contain the following instruments:

■ 3-axis accelerometer (3 channels)

■ 3-axis gyroscope (3 channels)

■ 3-axis magnetometer (3 channels)

■ One pressure sensor for ambient pressure (up to 15

psia)

■ Develop a way to synchronize data between multiple

copies of this payload in order to compare events

between payloads.

■ Five additional channels of data which may be used for

sensors chosen by the USLI team

Page 7: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

7CPE495/496 Project Proposal, G.A.M.B.L.S.

Engineering Requirements cont.The payload must also meet the following requirements:

■ Minimum 500 Hz sampling rate

■ Sensors and five additional channels must have a 12-bit

minimum resolution

■Capable of making 5 voltage measurements (0 - 5 V) at up to

four feet from the payload. These are the five additional

channels.

■Noise tolerant digital or differential analog signaling required

for the five additional channels and any other signals traveling

more than five inches.

■ System shall provide a minimum of 1W power to sensors and

associated support components (e.g. ADCs, bus transceivers)

for remote sensors

Page 8: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

8CPE495/496 Project Proposal, G.A.M.B.L.S.

Engineering Requirements cont.

■ Capable of operating under a 50g acceleration loading

■ Capable of operating under vibration experienced during a rocket flight.

■ Have a means of confirming operational state when the rocket is on the

launch pad

■ Have a means of powering on and off via an external switch when the

payload is in the assembled rocket

■ Must be capable of being integrated with the rest of the rocket, powered up,

and operational within 45 minutes

■ Must be ready for re-flight (new batteries installed, data transferred to

ground station, and empty memory) within 45 minutes

■ Capable of operating for up to one hour in the powered up (standby) state

on the rocket pad

■ Capable of fitting inside of a 3.5-inch cylinder with a 4 inch height

■ Weigh under 1 kg

■ Contain an independent power source (i.e. not require power from other

systems in the rocket)

Page 9: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

9CPE495/496 Preliminary Design Review Team Acronym

Survey: Market & Competition■ Raspberry Pi and Arduino supply breakout boards

with the needed sensors

■ These boards are too large for the USLI rocket

■ Arduino and Raspberry Pi systems cannot meet the

500 Hz minimum sampling requirements

Page 10: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

10

Design Strategy■ Previous senior design teams have attempted

this project with partial success

■ Rather than start from scratch, we will build on

the design from last year

■ We will reuse the transmitter board but redesign

the sensor board and pitot probe board

CPE495/496 Project Proposal, G.A.M.B.L.S.

Page 11: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

11

Survey: Existing Projects

■ The hardware design last year was completed

but had problems with flash memory and

reading the inertial measurement unit

■ Embedded software was begun but never

finished

■ Ground station code is reusable

CPE495/496 Preliminary Design Review Team Acronym

Page 12: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

12

Alternative Approaches■ We initially planned to use an Arduino board to

utilize the breakout board sensors, but the board

did not have the amount of storage space

required to hold the sampled data.

■ We next looked at the Raspberry Pi board,

which had the option for a micro SD card,

which solved the storage space problem, but the

operating system that was on the board was not

fast enough to support the sampling frequency

we are aiming for.

CPE495/496 Preliminary Design Review Team Acronym

Page 13: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

13

Project SummaryGAMBLS will measure rotation, acceleration, direction,

and atmospheric pressure while ascending through the

atmosphere, beginning at launch and ending at

approximately 5280 feet (1 mile). The payload will

sample sensor data at a minimum of 500 samples per

second and store this data on board. After apogee, the

rocket will begin transmitting all data to a ground station

so that there will be two copies of acquired data, one on

the rocket and one at ground station. GAMBLS will

synchronize data sampling by use of a GPS time stamp,

and transmit data to ground using an RF transmitter.

CPE495/496 Project Proposal, G.A.M.B.L.S.

Page 14: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

14

System Design Description

CPE495/496 Preliminary Design Review Team Acronym

Off StateStandby

State

Flight

State

Power On Launch

detected

Landing

State

Apogee

detected

Page 15: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

15

System Design Description

Sensor Board

CPE495/496 Preliminary Design Review Team Acronym

Page 16: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

16

System Design Description

RF-Power board

CPE495/496 Preliminary Design Review Team Acronym

Page 17: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

17CPE495/496 Preliminary Design Review Team Acronym

Current Progress■ We have finished schematics and CAD layout

design for sensor board

■ Currently creating parts order list

■ Labor hours spent:

■During CPE496 35hrs/week

■During CPE495 10hrs/week

Page 18: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

18CPE495/496 Preliminary Design Review Team Acronym

Current Progress - Pitot

Page 19: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

19CPE495/496 Preliminary Design Review Team Acronym

Current Progress - Power/RF

Page 20: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

20CPE495/496 Preliminary Design Review Team Acronym

Current Progress - Sensor

Page 21: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

21CPE495/496 Preliminary Design Review Team Acronym

Current Progress

Page 22: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

22CPE495/496 Preliminary Design Review Team Acronym

Current Progress

Page 23: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

23CPE495/496 Preliminary Design Review Team Acronym

Current Progress

Page 24: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

24CPE495/496 Preliminary Design Review Team Acronym

Response to Feedback■ After project proposal, we had a lot of feedback from our

professor, students, and guests. All feedback was very helpful

■ Feedback from our professor and our mentor revealed we

would not be able to use a Raspberry Pi or Arduino with our

sensors. Therefore we chose to modify last year’s project instead

of starting from scratch

■ Since beginning the modification of last year’s project, we have

been receiving help from the previous design team regarding

problems and accomplishments of the design

Page 25: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

25CPE495/496 Preliminary Design Review Team Acronym

Testing Plan Requirement Number Verification Requirement Success Criteria Verification Method

P1 Pitot Probe Measurement Sample atmospheric pressure at 500

Hz up to 15 psi

Test Launch

P2 Acceleration Measurement Sample rocket acceleration at 500 Hz

up to 50g

Ground Test

P3 Rotation Measurement Sample rocket rotation at 500Hz up

to 2000 dps

Ground Test

P4 Magnetism Measurement Sample magnetism around rocket at

500 Hz up to 12 gauss

Ground Test

P5 Data Stored to Flash Memory Flight data can be recovered through

USB download

Ground Test

P6 Data Transmitted to Ground Flight data is transmitted to ground

after apogee

Test Launch

Page 26: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

26CPE495/496 Preliminary Design Review Team Acronym

Testing Plan ▪ Unit Tests

▪ Verify Embedded System correctly for each sensor

▪ Retrieve data from flash memory

▪ Test wireless communication via subscale rocket launch or alternative scenario

▪ Integration Tests

▪ Test the wireless state controls from Ground Station

▪ Verify packet retrieval at ground station and process data

▪ Acceptance Tests

▪ Dedicated MAE Team decides acceptance testing.

Page 27: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

27CPE495/496 Preliminary Design Review Team Acronym

The Project Timeline ■ January 6-15

■ Design Sensor Board

■ Critical Design Review

■ January 20-29

■ Order parts

■ Begin ARM embedded Code

■ January 30-February 11

■ Solder circuit boards

■ Finish Software

■ February 12-14

■ Payload Test Flight

■ February 15-March 10

■ Correct Software Problems

■ Acceptance Tests

■ March 11-14

■ Flight Readiness Review

■ March 15

■ Final launch

Page 28: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

Safety Analysis■ Soldering can create hot surface, fire and smoke which can

damage your eyes and skin.

■ Battery also creates fire risks during flight because of high speeds

and temperature changes fast which can be problems for the

LiPo battery.

■ The battery also requires a precise charging profile to avoid

damage which is accomplished with a LIPO charging circuit.

■ The payload itself poses very little danger as the boards operate

at 3.3 volts.

28CPE495/496 Preliminary Design Review Team Acronym

Page 29: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

29CPE495/496 Preliminary Design Review Team Acronym

Individual Responsibility ■ The team now is split into two sub-teams

■ Hardware development

■ Jason G Renner

■Tin T Tran

■ Software development

■Patrick R Williamson

■Michael A Bizanis

Page 30: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

30CPE495/496 Preliminary Design Review Team Acronym

Cost Estimation■ Type Item Cost ea.

Qty required Total Cost

■ Microcontroller Atmel ATSAM-4S 6.17

2 12.34

■ Accelerometer, 3-axis, ± 100G

STMicroelectronics H3LIS331DL 10.96

2 21.92

■ Accelerometer, 3-axis, ± 12G

STMicroelectronics LIS331HH 5.37

2 10.74

■ Barometric Pressure / Altimeter Measurement

Specialties MS5607-02BA03 5.42

2 10.84

■ Flash Memory IC Spansion S25FL256S 3.44

4 13.76

■ Gyroscope, 3-axis Bosch BMG160 6.25

2 12.50

■ Magnetometer, 3-axis

STMicroelectronics LIS3MDL 1.79

2 3.58

■ ADC, 4-channel Maxim Integrated MAX11060 6.48 2

12.96

■ GPS Module GlobalTop Technology

FGPMMOPA6H 29.95

1 29.95

■ Radio Module Xbee Pro S3B 900HP 39.00

Page 31: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

Cost Estimation Continued

■ 30 PSI Pressure Sensor Honeywell NBPDLNN015 12.32 1

12.32

■ 150 PSI Pressure Sensor TruStability NSCDANN100 29.91 1

29.91

■ Passive components (R, C, L, etc.) Various 30.00

1 30.00

■ Wires, Cables, Connectors Various 25.00

1 25.00

■ Solder Paste Zephyrtronics SPE-0012 24.75

1 24.75

■ PCBs, 2-layer, 1 oz copper Various, 2"x3" 30.00

6 180.00

■ Antenna, 900 MHz omnidirectional Abracon APAMS-104 6.00

1 6.00

■ Antenna, 900 MHz, directional Data Alliance AYA-9012 21.99 1

21.99

■ Shielded Cable

0.42 15 6.30

■ Structual Components Hardware

300.0

■ Ground Component FTDI Serial to USB 25.00

1 25

■ TOTAL 951.7231

Page 32: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

32CPE495/496 Preliminary Design Review Team Acronym

Updated CPE 496 Deliverables■ At the end of CPE 496, the team will able to deliverable three

finished GAMBLS packages with working embedded software

and provide a specific schematics, and software for ground

station.

■ The GAMBLS package will be included:

■ 3 x RF/POWER Boards

■ 3 x SENSOR Boards

■ 3 x PITOT PROBE Boards

■ Finished embedded code for the system.

■ Ground station Receiver

Page 33: NASA University Student Launch Initiative (Sensor Payload) · Current Progress We have finished ... Test the wireless state controls from Ground Station Verify packet retrieval at

Questions?

33