nasa phillip young john-david jenkins and jack beckerdbeale/mech4240-50/excavator_cdrpres_f0… ·...
TRANSCRIPT
Corporation 4 – NASA
Project Manager – Phillip Young
Presenting – John-David Jenkins and Jack Becker
Outline Electrical Engineer Progress Report
EE Interface Diagram
Project Management
Systems Engineering (SE) – Mission Objectives
SE – Concept of Operation
SE – Architecture and Design
Overall Dimensions
Frame Subsystem
Linkage Subsystem
Bucket Subsystem
Bearing Selection
Bolt Selection
Wheel Geometry
Gator Interface
SE –Verification and Validation
EE Progress Report Progress has gone as planned and on schedule (We have a
working demo)
All components are mounted
Xbox 360 controller
Joystick controls actuator
A Button turns motor ON/OFF
Power system was overheating
Add heat sink to voltage regulators
Add a cooling fan
EE Interface Diagram
Project Management
Presentation Goals1. To present a detailed design of hardware (i.e. drawings and
specifications to fabricate)
2. Establish the basis for proceeding with manufacture
- Show that the correct design option has been
selected
- Dimension all parts and prepare for manufacture
- Prepare Manufacture and Assembly plan
-Verification methods have been established
Project Management (cont)
Program Manager (Dr. Beale)
Frame Subsystem (Lead Alan Gaskins)
Subsystem Member
(Jack Becker)
Bucket Subsystem (Lead JD Jenkins)
Subsystem Member
(Joe Bryant)
Linkages Subsystem (Lead Bryant Hains)
Force Analyst
(Luke Weniger)
Project Manager (Phillip Young)
Systems Engineer
(John Andress)
Management Structure
Project Management (cont)
Milestones
Project Management (cont)
NASA Lunar HarvesterCorporation 4
Project Lead: Phillip Young
Today's Date: 12/5/2008
[42] Start Date: 8/18/2008 (Mon) 0
WBS Tasks Task Lead Start End Du
ratio
n (
Da
ys)
% C
om
ple
te
Wo
rkin
g D
ays
Da
ys C
om
ple
te
Da
ys R
em
ain
ing
1 Frame Subsystem Alan 10/02/08 12/15/08 75 100% 53 75 0
1.1 Frame 10/02/08 10/21/08 20 100% 14 20 0
1.2 Wheel Structure 10/15/08 10/21/08 7 100% 5 7 0
1.3 Subsystem Interface 10/20/08 11/08/08 20 100% 15 20 0
1.4 Gator Interface 11/09/08 11/28/08 20 100% 15 20 0
2 Bucket Subsystem John-David 10/02/08 12/15/08 75 75% 53 56 19
2.1 Bucket 10/02/08 10/18/08 17 100% 12 17 0
2.2 Blade 10/02/08 10/18/08 17 100% 12 17 0
2.3 Front Door 10/02/08 11/09/08 39 0% 27 0 39
2.4 Subsystem Interface 10/02/08 10/29/08 28 100% 20 28 0
3 Linkage Subsystem Bryant 10/02/08 12/15/08 75 98% 53 73 2
3.1 Mechanical Links 10/02/08 10/18/08 17 100% 12 17 0
3.2 Actuator 10/02/08 10/18/08 17 90% 12 15 2
3.3 Joints 10/02/08 11/07/08 37 100% 27 37 0
3.4 Subsystem Interface 10/02/08 10/30/08 29 100% 21 29 0
8 /
18 /
08
8 /
25 /
08
9 /
1 /
08
9 /
8 /
08
9 /
15 /
08
9 /
22 /
08
9 /
29 /
08
10 /
6 /
08
10 /
13 /
08
12 /
1 /
08
12 /
8 /
08
12 /
15 /
08
12 /
22 /
08
10 /
20 /
08
10 /
27 /
08
11 /
3 /
08
11 /
10 /
08
11 /
17 /
08
11 /
24 /
08
12 /
29 /
08
HELP
- Modify the GREEN cells and the WBS, Tasks, and Task Lead columns. The rest of the columns are formulas.- The number of weeks shown in the gantt chart is limited by the maximum number of columns available in Excel.- The Start Date that you choose determines the first week in the gantt chart, starting on a Monday.- Use the slider to adjust the range of dates shown in the gantt chart.- Only 48 weeks can be shown/printed at one time, because each week uses up 5 columns.
Q: The Working Days column shows "###". How do I fix that?You need to install the Analysis ToolPak add-in that comes with Excel. Go to Tools > Add-ins, and select Analysis ToolPak.
Q: How do I make Task 2 start the day after the end of Task 1?
Gantt Task Chart
SE – Mission Objectives Mission Statement
“Create a tele-operated lunar harvester prototype targeting less than 150 W power usage and weighing less than 100 kg for studies on the earth fulfilling environmental requirements of the moon.”
Mission Level Requirements
Shall be designed to conduct studies on earth but be able to operate in a Lunar environment
Shall interface with Gator utility vehicle
Shall be designed to integrate Electrical Engineering subsystems into the mechanical design
Shall collect and hold at least 50 kg soil per hour
SE – List Concept of Operations
i) Lunar Prototype to harvest position, “scrape” soil from behind Gator in lane-like fashion until bucket reaches capacity
ii) Lunar Prototype to transport position, Gator returns to collection point with Lunar Prototype pulled behind, only surface contact is Lunar Prototype wheels
iii) Gator drives up and over soil ramp to position Lunar Prototype over hopper opening
iv) Lunar Prototype to dump position, empty bucket contents into hopper
v) Lunar Prototype to transport position, Gator returns to harvest area
vi) Lunar Prototype to harvest position, begin “scrape” process
Harvesting Position
Transporting Position
Dumping Position
SE – Graphical Concept of Operations
SE – Mechanical Architecture and Design
Lunar Harvester Prototype
Bucket
Blade
Container
Welded Bucket
Sealed Bearings
Socket Cap Screw
Frame
Wheel Structure
Tire
Wheel Bracket
Wheel Axle
Gator Interface
Hitch
Frame Mount
Frame Bracket
Bucket/Linkages/
Frame Interfaces
Sealed Bearings
Socket Cap Screw
Washers and Spacers
Linkages
Linear Actuator
Interface Bracket
Slider Base
Slider
Pivot Bar
Sealed Bearings
Socket Cap Screw
Transfer Bar
Sealed Bearings
Socket Cap Screw
Linkage Actuator Connection Rod
Rotational Bar
Sealed Bearings
Socket Cap Screw
Overall Dimensions
Total Prototype Dimensions
Weight: 121.5 lbs (55.23 kg)
Length:72 inches
Width:28.5 inches
Frame SubsystemSwitch was made from standard
square metal tubing to 80/20 Square
Tubing for ease of manufacture and
assembly
Standard brackets for frame are
provided by 80/20
Non-standard brackets and tabs will
be manufactured in house
Requirements:•Shall interface with a Gator utility
vehicle
•Shall maintain horizontal orientation of
harvester frame for optimal harvesting
and dumping positions
•Shall maintain or enhance structural
rigidity/strength of frame subsystem
•Shall accommodate yaw motion required
for “trailing” Gator
Frame Isometric View
Linkage Subsystem
Derived Requirements
Shall be able to move bucket into the three desired mechanical
positions
Shall be powered by motorized actuator
Shall provide mechanical advantage in operating bucket
Shall constrain bucket movement to safe bounds
Shall allow variable digging depth that includes the range of 1-
5cm
Linkage Subsystem (cont)
At 1.25” Digging Depth (In inches)
Provides variable 1-5 cm
cutting depth
Linkage Subsystem (cont)
70˚ angle achieved to ensure dirt removal Bumper stop could be implemented to restrain
linkages from obtaining toggle position
Dumping Position
Linkage Subsystem (cont)
Linkage Interface Rod
Linkage Interface Rod allows 1 linear actuator
to use both sets of mechanical linkages
½” Diameter Alloy Steel
Link Subsystem Cont.
General Description
Tolomatic mxe32s Linear Slide
High degree of customizability
Critical Review Update
Single Actuator with Linkage Interface Rod
Brackets integrated with actuator
Can handle extremely large vertical forces
Maximum Forces the MXE-S can handle
Shock Load Information
Worst case scenario shock load for FEA was 500 lb
Calculated using impulse
For Normal Traveling Velocity:
If traveling just above the required velocity of
2.2 cm/min (3.67x10-4 m/s) and a maximum
mass of 150kg stopping nearly instantaneously
(.001s), the impulse average force is calculated
to be 12.36lb-force. If this force were translated
through the linkage system, the actuator would
experience a force of about 26lbs acting
vertically and about 8lbs acting along the axial
direction.
Force Transfer Bar Force Load Case
Force Transfer Bar FEA (stress)
Pivot Bar Load Case
Pivot Bar FEA (stress)
Rotational Bar Load Case
Rotational Bar FEA (stress)
Linkage Interface Bar
2
max
4
max
/7.30557/96000/
5.
64/4/
300025012
inlbsIMy
iny
rI
inlblbsinM
F=250 lbs F=250 lbs
F=250 lbsF=250 lbs
Bucket Load Case
Bucket FEA (Stress)
Blade Load Case100 lbs distributed across the front of the blade
Blade FEA (stress)
Bearings
Manufacturer: Daemar Bearings Inc Dry slide self-lubricating bearing with PTFE coating
Bearings (cont)Bearing Specs
(in) Max. Load (N/mm 2̂) (psi)
Outer dia. 0.375 Static Load 250 36250
Inner dia. 0.3125 Very Slow Speed 140 20300
Width 0.75 Rotating/Oscillating 60 8700
Shaft Diameter (in) Width (in) Load on Bearing (lbs) P (psi)
0.3125 0.75 100 426.6667
200 853.3333
300 1280
400 1706.667
500 2133.333
600 2560
700 2986.667
800 3413.333
900 3840
1000 4266.667
Radial Load (lbs. to psi)
Bolts•Bucket and Linkage Bolt
•5/16” -18 socket cap screw
•1-1/4” long
•Linear Actuator Interfacing Bolt
•¼” – 20 socket cap screw
Wheel Geometry•Tires have built in bearing
•Axle is stationary
•Wheel Diameter – 13.5”
Tire Type Pneumatic
Rim Size (in.) 6
Tire Size 13.5 x 400 x 6
Diameter (in.) 3/4
Bearings Included Yes
Hub Width (in.) 6
Load Capacity (lbs.) 300
Rim Included Yes
Tubeless Tire Yes
Tread Type Ribbed
Shipping Weight (lbs) 7Aluminum Bracket
Gator Interface
•Hitch will be purchased off the shelf
•Brackets will be manufactured in house using .25 inch thick aluminum
plate
•Will be replaced by interfacing plate on final lunar design
Bill of MaterialsItem # Part Item Quantity Material Part # Cost Supplier
1 Frame Rail Square Tubing - 28.5" 2 80/20 9701 $10.55 BA
2 Cross Beam Bracket 80/20 2 Hole Bracket 12 80/20 4302 $35.40 BA
3 Frame Bracket 80/20 4 Hole Bracket 8 80/20 4303 $35.20 BA
4 Straight Tongue Style Coupler 2 " Ball with 2" Channel Coupler 1 21128 $15.90 AAC
5 Gator Interface Beam 2" square tubing (.25" thick), 24" long 1 Al 6063 T52 - $28.00 OM
6 Hitch Ball 2" Regular Duty, Zinc Trailer Hitch Ball 1 Zinc 63831 $7.45 TPS
7Hitch Mount
Adjustable Quick Release 2" sq. Hitch Ball
Mount 1 Black Powder Coated Al 5223026 $69.95 TPS
8 Extruded Aluminum Rectangle 1.5" x 3" x .25" 1 Al 6061 T6 - $7.00 OM
9 Linear Slider Actuator MXE32S BN08 SK17 LMI Actuator 1 - - $1,212.36 TI
10 Carrier Bracket 3 X 3 X 12 inch Aluminum Square 1 Al 6061 SQ33 $81.00 MD
11 Actuator Grounding Bracket Included with Actuator 4 - - $0.00 TI
12Wheel
Wheelbarrow Assembly, 3/4in. Bore — 13.5
x 400 x 62 - 121024 $49.88 NTE
13 Wheel Structure Bracket 1/4" thick sheet aluminum 12" x 12" 2 Al Alloy 6061 9246K13 $23.46 MCC
14 Wheel axle 3/4" diameter steel rod 6' in length 1 4140/4142 Alloy Steel 8935K39 $29.97 MCC
15 Bucket Sides 24" x 24" x 1/2" Square Sheet 2 1018 Steel 1388K181 $462.24 MCC
16 Bucket Rear Plate " - " - - MCC
17 Bucket Bottom Plate " - " - - MCC
18 Blade 5/8" x 3.5" x 24" 1 ASTM A36 9517K38 $70.70 MCC
198 1/4" Pivot Bar
Rectangular Bar 1/2" Thick, 4" Width, 3'
Length2 4140/4142 Alloy Steel 6554K323 $147.12 MCC
20 18 3/4" Force Transfer Bar " " - - MCC
21 7 1/4" Rotational Bar " " - - MCC
22 Rotational Bar Bracket " " - - MCC
23Linkage Interfacing Rod
1L40 Alloy Steel Rod 1/2" Diameter, 3'
Length1 41L40 Alloy Steel 6776T132 $18.21 MD
24 Frame/Bucket/Linkage Nut 5/16" 18 nut (100 per box) 1 Steel 90499A030 $3.78 MCC
25 Actuator Nut 1/4"-20 (25 per box) 2 Steel 90630A110 9.78$ MCC
26
All Purpose Washer
Zinc & Yellow Stl SAE HI-Strength Flat Washer
5/16" Screw Sz, 11/32" ID, 11/16" OD, .055"-
.080" Thk (50 per box)
2 Zinc 98023A030 $8.40 MCC
Bill of Materials (cont.)27 Actuator Bolts 1/4"x1"-20(100 per box) 1 Steel 91251A542 14.72$ MCC
28 Frame/Bucket/Linkages Bolts 5/16"id 1 1/4" socket cap screw 1 Steel 901284586 10.49 MCC
29 Bearing 5/16" i.d. Self Lubricating Bushing 30 Steel/Bronze/Teflon 05TH06 $67.50 ABI
30
Bucket/Linkage Ream
Solid-Carbide Fractional Chucking Reamer
3/8" Dia (.3750"), 3-1/2" L O'all, .3745"
Shank Dia
2 HS Steel 3026A37 122.58 MCC
31Bucket/Linkage Drill Bit
Jobbers Twist Drill Bit Black-Oxide, 3/8" Size,
5" L Overall, 3-5/8" L Flute8 HS Steel 2931A34 27.52 MCC
32
Bucket/Linkage Center BitSolid-Carbide 2 in 1 Countersink Trade Size 2,
5/64" Drill Size, 3/16" Body Diameter1 HS Steel 2925A54 19.55 MCC
33Bucket/Linkage Bottom Tap
Bright Finish High-Speed Stl Spiral Point Tap
1/4"-20, H3 Pitch Diameter, 2 Flute1 HS Steel 2523A411 $5.05 MCC
34 Layout Fluid Blue 16 oz. Layout Fluid 1 - 2131A17 $7.61 MCC
35 NA Cold Saw Blade (180) 1 - 4190A61 $92.97 MCC
36 NA Vert. Band Saw Blade 1 - 4179A316 $43.26 MCC
37 NA Horz. Band Saw Blade 1 - 4179A979 $55.05 MCC
38 End Mill 5/8" 2-Flute 4 HS Steel 2782A77 22.05$ MCC
39 End Mill 1/2" 4-Flute 1 HS Steel 8912A45 $26.12 MCC
40
Total $2,840.82MCC - Mc Master Carr
BA - Bertelkamp Automation
AAC - Automotive Accessories Connection
OM - OnlineMetals.com
TI - Tolomatic, Inc.
TPS - Trailor Parts Superstore
NTE - Northern Tool + Equipment
MD - MetalsDepot.com
ABI-Alabama Bearing Inc.
Manufacturing Plan
Linkages will be purchased as close to final design as possible
Linkage machining will be carried out using mills
Brackets will be made out of sheet metal
Bracket machining will also be carried out using mills
All machining will take place in the Design and
Manufacturing Lab
All parts will be measured to insure correct tolerances
before being approved
Bucket will be manufactured out of sheet metal and welded
Assembly Plan Frame will be assembled using pre-existing bolt pattern and
brackets purchased from 80/20
All brackets and attachment points will be connected to the frame
Linkage sub-assembly will be attached to their respective mounting points
Bucket will be attached to rotational and pivot bars
Actuator will be mounted to frame
Actuator and force transfer bar will be connected
Tire axle will be attached to frame
Tire will be attached to tire brackets
Trailer hitch will be attached
SE – Verification and Validation Phase C Verification:
Determine forces acting on individual links.
Verify linkage/frame construction by performing FEA using ALGOR.
Total picture verification
Plan for Phase D Verification:
Assemble linkages separately to test effectiveness.
Assemble total system for manual proof of concept testing. This could consist of manual movement of bucket positions, manual pushing of bucket through pseudo-regolith.
Conduct proof of concept testing at USDA facility using all components and interfacing to the Gator vehicle
Summary Electrical Engineer Progress Report
EE Interface Diagram
Project Management
Systems Engineering (SE) – Mission Objectives
SE – Concept of Operation
SE – Architecture and Design
Overall Dimensions
Frame Subsystem
Linkage Subsystem
Bucket Subsystem
Bearing Selection
Bolt Selection
Wheel Geometry
Gator Interface
SE –Verification and Validation