naperville woman’s club landmark remodeling project
TRANSCRIPT
Naperville Woman’s ClubLandmark Remodeling Project
Summer of 2015
Professional Expertise
March 11, 2015
Sequoia General Contracting Corp.
Terry Oppermann, AIA
Neville Structural Engineering
Packing
June 9, 2015
Demolition
June 19, 2015
Demolition
June 19, 2015
Groundbreaking
June 25, 2015
Groundbreaking
June 25, 2015
Mayor Steve Chirico explains the importance of making the NWC Landmark accessible to the community.
Groundbreaking
June 25, 2015
Preparation for a Ramp
June 29 and 30, 2015
Excavation
July 6, 2015
Note the trenchis flooded
Concrete Forms
July 10, 2015
Ramp Takes Shape
July 12, 2015
Framing
July 13, 2015
Starting to look like an entrance
July 15, 2015
Sidewalk and stairs added
July 17, 2015
Pipes and evac from kitchen brought up to code
July 21, 2015
Plumbing passes inspection, electrical panel, not as easy.
July 22, 2015
Original subfloor
July 29, 2015
Drywall
August 3, 2015
New entry and railing.
August 12, 2015
Old entry closed, new ceiling arch, electric panel up to code
August 13, 2015
Tile
August 15 & 16, 2015
Cabinets
August 17-20, 2015
Fixturesinside andoutside
August 19, 2015
Accessories
August 20, 2015
Exterior light and TYVEK®
August 21, 2015
Backsplash, extra tile, varnished cabinets, balanced arches
August 26, 2015
Final inspection
August 31, 2015