n. hayashi, k. kanai, m. kiyozuka, (japan water research ...a few cases in japan in which a...
TRANSCRIPT
IWA World Water Congress
10 -14 September 2006Beijing, China
M. Fujiwara, ◎N. Hayashi, K. Kanai, M. Kiyozuka, (Japan Water Research Center); Y. Matsui, (Hokkaido University); K. Mori, (Ebara Corporation); Y. Sakakibara, (Nihon Suido Consultants Co., Ltd)
Application of Life Cycle Assessment (LCA) to Water Purification Facilities
Water purification: Conventional ⇒ “Coagulation Sedimentation & Sand Filtration” Newly ⇒ “Membrane Filtration ”, a measure against Cryptosporidium
Introduction
A few cases in Japan in which a purification process was selected by considering the environmental loads.I present a case study in which inventory analysis, as an element of life cycle assessment (LCA), choosing from the two alternatives processes.
Water supply facilities need a great amount of energy.
Selection of purification process involves such conventional indexes as treatability, maintainability or cost: ⇒Very conventional approach
Establishment of a research technique of a purification plant considering reduction of environmental loads
Background
Being worked on under the e-Water project
Quantitative identification and evaluation of environmental impact ⇒Insufficient
What is e-Water ?BackgroundEnvironmental, Ecological, Energy-saving and
Economical Water Purification SystemResearcher: Japan Water Research Center Subsidization: Ministry of Health, Labour and WelfareParticipants: Academia, Waterworks Utilities, and Private
companies
Detailed Info: go to Poster Gallery, Poster No.27
Research Cost: $ 6 MillionResearch Period: fiscal 2002-2004
Scope of ResearchScope:Purification Plant: Construction Stage - Operation Stage
Scope of Research
Construction Stage
Procurement and Construction
Fabrication and Assembly
Operation Stage
Used as Purified Water
Power, Fuel and Chemicals
Disposal Stage
Demolition and Disposal
Future Tasks
Items:Life Cycle Energy Consumption (LC-E)Life Cycle CO2 Emissions (LC-CO2 )
Scope of ResearchRaw Water
Coagulant and ChlorineChlorine
To water Distribution
To Disposal of Sludge
Water Receiving
Basin
Coagulation Sedimenta-tion Basin
Rapid Filtration
Basin
Clean Water Reservoir
Discharging Basin
Sludge Settling Basin
Thickening Tank
Sludge Dehydrator
Returned Water
Purified Water
Sludge
Supernatant Supernatant
Administration Building and Electric
Instrumentation Equipment
Typical Rapid Filtration
Scope of Research
Raw Water
Coagulant and Chlorine
To Water Distribution
To Disposal of Sludge
Water Receiving
Basin
Membrane Filtration
Clean water Reservoir
Sludge Dehydrator
Chlorine
Administration Building and Electric
Instrumentation Equipment
Coagula-tion Basin
Membrane Filtration
Structuring of Scope of ResearchC
onst
ruct
ion Civil
EngineeringWater
Receiving Basin
Building Frame
Pipes/Valves
Earthwork
Reinforced Concrete Casting (21-8-25)
Paddled Short Pipes (φ600×1,000)
Excavation and Machines
Major Sector Classification
Middle Classification
Small Classification
Detailed Classification
Sedimenta-tion Basin
Filtration Basin
・ ・ ・ ・ ・
・ ・ ・ ・ ・
・ ・ ・ ・ ・990 items
Mechanical Equipment
Electric Equipment
Building
Ope
ratio
n
・ ・ ・ ・ ・・ ・ ・ ・ ・
Calculation Conditions and MethodPurification Treatment FlowCoagulation Sedimentation + Sand Filtration (typical flow, based on an actual plant), Membrane Filtration (virtual plant)Treatment Capacity20,000 m3/d (av. treatment capacity of Rapid Filtration in Japan)Characteristics of Purification PlantGravity flow from water receiving basin to clean water reservoirScope of ResearchConstruction and operation stage of facilities and equipment in the plant
⇒ Energy and CO2Research Method →LCA ⇒ Unit Process Analysis
Embodied Intensities (Basic Unit)Values taken from existing literature (e.g. 3EID) are mainly used
LC-E and LC-CO2 Calculation Sample
♨ Energy:562m3×2,020.2MJ/m3=1,135,352MJ♨ CO2:562m3×62.97kg-c/m3=35,389kg-C
Calculated using the basic units for concrete of temporary plant
Life Cycle Period
Civil engineering structures: 60 yearsMechanical equipment: 15 yearsElectric equipment: 20 yearsBuilding utilities: 50 years
To convert energy consumption and CO2 emissions to an annual total:
♨ The same calculation method is used for other items
LC-CO2 of Major Sector Classification
35%
Construction(civil engineering)
Construction (building)
20%
9% Construction (mechanical)
Construction (electric)
3%
Operation(electric)
14%
Operation(mechanical)
19%
Results of Research
LC-CO2 of Major Sector Classification
44%
Construction (civil engineering)
Construction (electric)
Construction (mechanical)
6%Construction
(building)
Operation(mechanical)
45%
Operation(electric)
5%
Results of Research
Life Cycle CO2
Construction stageCoagulation Sedimentation + Sand Filtration 67%
Membrane Filtration 50%
Results of Research
Operation stageCoagulation Sedimentation + Sand Filtration
⇒ Mechanical + ElectricMembrane Filtration ⇒ Mechanical
LC-E of Major Sector Classification
Construction (building)
19%
Construction(Civil engineering)
18%
Construction (mechanical)
5%
Construction (electric)
3%
Operation(electric)
24%
Operation(mechanical)
31%Construction (mechanical)
33%
Construction (building)
4%Operation
(mechanical)57% Operation
(electric)
6%
Results of Research
Life Cycle Energy
Construction stageCoagulation Sedimentation + Sand Filtration 45%
Membrane Filtration 37%
Results of Research
Operation stageCoagulation Sedimentation + Sand Filtration
mechanical+electricMembrane Filtration
mechanical
LC-E Analysis for Middle Sector Classification ItemsResults of Research
Rapid Filtration Membrane FiltrationImprovement work in the
compound
Land development workStandby generator
Substation
Monitoring control and instrumentation
Power and control
Administration building
On-site piping
Dehydrator
Discharging basin and thickening tank
Clean water reservoir
Sedimentation basin and filtration basin
Chemical feeding equipment
Chemical mixing tank
Substation
Monitoring control and instrumentation
Power and control
Administration building
Membrane module
Membrane filtration facility
Chemical feeding equipment
Chemical mixing tank
Water receiving basin MJ / Y / m3MJ / Y / m3
Conclusions
LC-E and LC-CO2 for the life cycle of a water purification plant (materials, construction, operation and maintenance) were calculated by applying LCA.
The calculation results were obtained under special prerequisites; they will vary depending on the calculation conditions.
LC-E and LC-CO2 of the Membrane Filtration facility is highly likely to be equal to that of the conventional Coagulation Sedimentation + Sand Filtration facility.
Thank you for your attention.