n eutrinos options at cern
DESCRIPTION
N eutrinos options at CERN. R. Garoby – 27/04/2009. OUTLINE. Context: plans for future LHC injectors Potential neutrino options 2.1 “Conventional” n beams: CNGS SPS with the new injectors Low energy n “Super-beam” 2.2 Neutrino Factory 2.3 Beta beams 3.Summary. - PowerPoint PPT PresentationTRANSCRIPT
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
NNeutrinos optionseutrinos options
at CERNat CERN
R. Garoby – 27/04/2009
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20092
OUTLINEOUTLINE
1.1. Context: plans for future LHC injectorsContext: plans for future LHC injectors
2.2. Potential neutrino optionsPotential neutrino options2.1 “Conventional” 2.1 “Conventional” beams: beams:
- CNGSCNGS- SPS with the new injectorsSPS with the new injectors- Low energy Low energy “Super-beam” “Super-beam”
2.2 Neutrino Factory2.2 Neutrino Factory2.3 Beta beams2.3 Beta beams
3.3. SummarySummary
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20093
Plans for future LHC injectorsPlans for future LHC injectors
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20094
MotivationMotivation
parameters icrelativist classical :
raccelerato theof radiusmean :
emittances e transversnormalized :
nchprotons/bu ofnumber :with
,
2,
R
N
RNQ
YX
b
YX
bSC
1. Reliability The present accelerators are getting old (PS is 48 years old !) and they operate far beyond their initial design parameters
need for new accelerators designed for the needs of SLHCneed for new accelerators designed for the needs of SLHC
2. Performance Brightness N/* of the beam in LHC must be increased beyond the capability of the presentinjectors to allow for phase 2 of the LHC upgrade.[Excessive incoherent space charge tune spreadsQSC at injection in the PSB and PS].
need to increase the injection energy in the synchrotronsneed to increase the injection energy in the synchrotrons• Increase injection energy in the PSB from 50 to 160 MeV kinetic
• Increase injection energy in the SPS from 25 to 50 GeV kinetic
• Design the PS successor (PS2) with an acceptable space charge effect for the maximum beam envisaged for sLHC => injection energy of 4 GeV.
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20095
DescriptionDescription
PSB
SPS SPS+
Linac4
(LP)SPL
PS
LHC / SLHC DLHC
Out
put e
nerg
y
160 MeV
1.4 GeV4 GeV
26 GeV50 GeV
450 GeV1 TeV
7 TeV~ 14 TeV
Linac250 MeV
LP-SPL: Low Power - Superconducting Proton Linac (4-5 GeV)
PS2: High Energy PS(~ 5 to 50 GeV – 0.3 Hz)
SPS+: Superconducting SPS(50 to1000 GeV)
sLHC: “Super-luminosity” LHC(up to 1035 cm-2s-1)
DLHC: “Double energy” LHC(1 to ~14 TeV)
Proton flux / Beam power
PS2
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20096
PS2 parametersPS2 parametersPS2 goals:• to provide the beam brightness required by all sLHC options• to improve SPS operation in fixed target mode
Reason Physical parameter Value Space charge PS2 Injection energy (kinetic) 4 GeV SPS improvement Ejection energy (kinetic) 50 GeV LHC Transverse normalized 1 sigma emittances at
ejection for LHC 3 mm.mrad
LHC Longitudinal emittance/bunch with 25 ns bunch spacing at ejection
0.35 eVs
2.2 ultimate brightness for LHC (includes 10% loss)
Nb of protons / bunch with 25 ns bunch spacing at ejection for LHC (total 168 bunches)
41011 (6.71013)
Flux for SPS / PS2 fixed target physics
Nb of protons / bunch with 25 ns bunch spacing (total)
61011 (~11014)
Possible bunch spacings in LHC (25, 50 & 75 ns)
Size (ratio PS2/SPS) 15/77 Circumference 1346.4 m hRF for 25 ns (resp. 50 or 75 ns) bunch spacing 180 (resp. 90 or 60)
Flux for SPS / PS2 fixed target physics + LHC filling time
Cycling period to 50 GeV (case of no injection flat porch)
2.4 s
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20097
PS2 injectorPS2 injector
Reason Physical parameter Value Space charge Injection energy (kinetic) 4 GeV Twice the ultimate brightness + 20 % margin for beam loss
Nb of protons per PS2 cycle for LHC 6.71013
SPS / PS2 fixed target physics Nb of protons per PS2 cycle for PS2 / SPS fixed target physics
1.11014
Requirements of PS2 on its injector:
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20098
Why an SPL?Why an SPL?
• An H- linac combined with charge exchange injection in the following synchrotron is a proven solution for reliably reaching high beam brightness,
• Superconducting accelerating structures allow for reaching 4 GeV with a single accelerator (minimum beam loss/irradiation + maximum reliability),
• An SPL provides a large potential of extension to adapt to future needs. Among the identified possibilities:– Radioactive ion beam facility (4 MW at ~ 2.5 GeV)– Proton driver for a neutrino factory (4 MW at 5 GeV) [design available]– e+/e- acceleration to ~20 GeV (using recirculation in the =1 part of
the SPL) for LHeC [preliminary study in progress]
• Large synergy with other projects (ESS, ADS, EURISOL, SNS…) and access to EU support for R & D.
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/20099
Implementation of the new injectors: Stage 1 (1/2)Implementation of the new injectors: Stage 1 (1/2)LINAC4
Ion species H-
Output kinetic energy 160 MeV
Bunch frequency 352.2 MHz
Max. repetition rate 1.1 (2) Hz
Beam pulse duration 0.4 (1.2) ms
Chopping factor (beam on) 62%
Source current 80 mA
RFQ output current 70 mA
Linac current 64 mA
Average current during beam pulse 40 mA
Beam power 5.1 kW
Particles / pulse 1014
Beam characteristics
HH- - sourcesource RFQRFQ choppechopperr
DTLDTL CCDTLCCDTL PIMSPIMS
3 MeV 50 MeV 102 MeV
352.2 MHz
160 MeV
Layout
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200910
Implementation of the new injectors: Stage 1 (2/2)Implementation of the new injectors: Stage 1 (2/2)
Milestones
End CE works: December 2010
Infrastructure: 2011
Installation:2011-2012
Commissioning: 2012-2013
Modifications PSB: shut-down 2013/14
Beam from PSB: 1rst of April 2014
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200911
Implementation of the new injectors: Stage 2 (1/4)Implementation of the new injectors: Stage 2 (1/4)LP-SPL + PS2
HH- - sourcesource RFQRFQ choppchopperer DTLDTL CCDTLCCDTL PIMSPIMS
3 MeV 50 MeV 102 MeV
352.2 MHz
β=0.6β=0.655
β=0.9β=0.922
643 MeV 4 GeV
704.4 MHz
160 MeV
Linac4 (160 MeV) SC-linac (4 GeV)
Kinetic energy (GeV) 4
Beam power at 4 GeV (MW) 0.12
Rep. period (s) 0.6
Protons/pulse (x 1014) 1.1
Average pulse current (mA) 20
Pulse duration (ms) 0.9
LP-SPL beam characteristics
Length: 470 m
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200912
Implementation of the new injectors: Stage 2 (2/4)Implementation of the new injectors: Stage 2 (2/4)LP-SPL + PS2
Construction of LP-SPL and PS2 will not interfere with the regular operation of Linac4 + PSB for physics.
Similarly, beam commissioning of LP-SPL and PS2 will take place without interference with physics.
First milestones Project proposal: 2011- 2012 Project start: January 2013
Critical path: Design
Study & Civil Engineering! DRAFT
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200913
Implementation of the new injectors: Stage 2 (3/4)Implementation of the new injectors: Stage 2 (3/4)Site layoutSPS
PS2
SPL
Linac4
PS
ISOLDE
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200914
Implementation of the new injectors: Stage 2 (4/4)Implementation of the new injectors: Stage 2 (4/4)
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200915
Implementation of the new injectors: Stage 3 (1/2)Implementation of the new injectors: Stage 3 (1/2)HP-SPL
HH- - sourcesource RFQRFQ chopperchopper DTLDTL CCDTLCCDTL PIMSPIMS
3 MeV 50 MeV 102 MeV
352.2 MHz
β=0.65β=0.65 β=1.0β=1.0
643 MeV 5 GeV
704.4 MHz
160 MeV
Linac4 (160 MeV) SC-linac (5 GeV)
Option 1 Option 2
Energy (GeV) 2.5 or 5 2.5 and 5
Beam power (MW) >2 MW (2.5 GeV)
or
>4 MW (5 GeV)
4 MW (2.5 GeV)
and
4 MW (5 GeV)
Rep. frequency (Hz) 50 50
Protons/pulse (x 1014) 1.1 2 (2.5 GeV) + 1 (5 GeV)
Av. Pulse current (mA) 20 40
Pulse duration (ms) 0.9 0.8 (2.5 GeV) + 0.4 (5 GeV)
HP-SPL beam characteristics
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200916
Implementation of the new injectors: Stage 3 (2/2)Implementation of the new injectors: Stage 3 (2/2)HP-SPL
The upgrade from LP-SPL to HP-SPL will depend upon the approval of major new physics programmes for Radioactive Ion beams (EURISOL-type facility) and/or for neutrinos (Neutrino factory).
Staged hardware upgrade during shutdowns
Earliest year of operation: >2020
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200917
Potential neutrino optionsPotential neutrino options
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200918
CONVENTIONAL CONVENTIONAL BEAMS: CNGS (1/2) BEAMS: CNGS (1/2)
CERN
Gran Sasso
• From SPS: 400 GeV/c• Cycle length: 6 s• Extractions:
– 2 separated by 50ms• Pulse length: 10.5s• Beam intensity:
– 2x 2.4 · 1013 ppp• 0.5 mm• Beam performance:
– 4.5· 1019 pot/year
Proton beam characteristics
732 km baseline– From CERN to Gran Sasso (Italy) [Elevation of 5.9°]– Far detectors:
OPERA (1.21 kt), Icarus (600 t)Commissioned 2006Operational since 2007
from E. Gschwendtner
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200919
CONVENTIONAL CONVENTIONAL BEAMS: CNGS (2/2) BEAMS: CNGS (2/2)
43.4m100m
1095m 18m 5m 5m67m
2.7m
TBID
Air cooled graphite target magazine– 4 in situ spares– 2.7 interaction lengths– Target table movable horizontally/vertically for alignment
• TBID multiplicity detector• 2 horns (horn and reflector)
– Water cooled, pulsed with 10ms half-sine wave pulse of up to 150/180kA, 0.3Hz, remote polarity change possible
• Decay pipe: – 1000m, diameter 2.45m, 1mbar vacuum
• Hadron absorber: – Absorbs 100kW of protons and other hadrons
• 2 muon monitor stations: muon fluxes and profiles
p + C (interactions) , K+
(decay in flight)
from E. Gschwendtner
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200920
CONVENTIONAL CONVENTIONAL BEAMS: SPS with new injectors (1/3) BEAMS: SPS with new injectors (1/3)from M. Meddahi
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200921
CONVENTIONAL CONVENTIONAL BEAMS: SPS with new injectors (2/3) BEAMS: SPS with new injectors (2/3)fromM. Meddahi
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200922
CONVENTIONAL CONVENTIONAL BEAMS: SPS with new injectors (3/3) BEAMS: SPS with new injectors (3/3)
Performance range: 2 – 4 x flux for CNGS
fromM. Meddahi
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200923
FACTORY: SPL-based proton driver (1/4)FACTORY: SPL-based proton driver (1/4)
An HP-SPL based 5 GeV – 4 MW proton driver has been designed [HP-SPL + 2 fixed energy rings (accumulator & compressor)]
CERN-AB-2008-060 BI
Feasibility Study of Accumulator and Compressor for the 6-bunches SPL based Proton Driver
M. Aiba
Table 1: Requirements for the neutrino factory proton driver. Taken from the summary of 3rd ISS [4]. * Maximum bunch spacing ~50/(Nb-1) for the number of bunches Nb >2.
Parameters Values
(basic/range) Unit
Kinetic energy 10 / 5-15 GeV Burst repetition rate 50 / - Hz Number of bunches per burst 4 / 1-6 Bunch spacing 16 / 0.6-16 * s Total duration of the burst ~50 / 40-60 s Bunch length 2 / 1-3 ns
from M. Aiba
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200924
Compressor[120 ns bunch -V(h=3) = 4 MV]
Target[2 ns bunches
– 5 times]
FACTORY: SPL-based proton driver (2/4)FACTORY: SPL-based proton driver (2/4)
Accumulation Duration = 400 s
Compression t = 0 s
t = 12 s
t = 24 s
t = 36 s
etc. until t = 84 s
Accumulator[120 ns pulses
-95 ns gaps]
SPL beam[42 bunches -
33 gaps]
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200925
FACTORY: SPL-based proton driver (3/4)FACTORY: SPL-based proton driver (3/4)
-40 -20 0 20 40-2
-1
0
1
2
x' (
mra
d)
x (mm)
Injection Rotated
-10 -5 0 5 10-0.6
-0.4
-0.2
0.0
0.2
0.4
0.6 Injection Rotated
y' (
mra
d)
y (mm)
-40 -20 0 20 40-0.15
-0.10
-0.05
0.00
0.05
0.10
0.15 Injection Rotated
dE (
GeV
)
RF phase/3 (deg.)
-3 -2 -1 0 1 2 30
5
10
15
Cou
nts/
bin
(%, b
in=
0.2
deg)
RF phase/3 (deg)
Rotated=1.98 ns
from M. Aiba
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200926
FACTORY: SPL-based proton driver (4/4)FACTORY: SPL-based proton driver (4/4)
SPL for proton driver Output beam Parameters Values Parameters Values
Kinetic beam energy 5 GeV Kinetic beam energy 5 GeV Repetition rate 50 Hz Repetition rate 50 Hz Average current during the burst 40 mA No. of bunches per cycle 6 Beam power 4 MW Bunch length (r.m.s.) ~2 ns Bunch spacing ~12 s
Transverse emittance (r.m.s., physical) 3 mm-mrad
Accumulator Compressor Parameters Values Parameters Values
Circumference 318.5 m Circumference 314.2 m Transition gamma 6.33 Transition gamma 2.3 RF voltage - RF voltage 4 MV Harmonics number - Harmonic number 3 No. of arc cells 24 No. of arc cells 6 Super periodicity 2 Super periodicity 2 Nominal transverse tune 7.77/ 7.67 Nominal transverse tune 10.79/5.77 No. of turns for accum. 400 No. of turns for comp. 36 Maximum no. of bunches 6 Maximum no. of bunches 3
Main quadrupole Bore radius Field gradient Magnetic length
56 mm 5.5 T/m 1.2 m
Main quadrupole Bore radius Field gradient Magnetic length
148 mm 7.1 T/m 1.9 m
Main bending Full gap Full width Field stength Magnetic length
103 mm 162 mm
1.7 T 1.5 m
Main bending Full gap Full width Field strength Magnetic length
125 mm 379 mm
5.1 T 3 m
from M. Aiba
Only the accumulator would be needed for
a low energy superbeam
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200927
=100
BEAM FACILITY: PrincipleBEAM FACILITY: Principle
Aim: production of (anti-)neutrino beams from the beta decay of radio-active ions circulating in a storage ring– Similar concept to the neutrino factory, but parent particle is a beta-
active isotope instead of a muon.Beta-decay at rest
– spectrum well known from electron spectrum– Reaction energy Q typically of a few MeV
Accelerate parent ion to relativistic max
– Boosted neutrino energy spectrum: E 2Q– Forward focusing of neutrinos: 1/
Pure electron (anti-)neutrino beam!– Depending on +- or - - decay we get a neutrino or anti-neutrino– Two different parent ions for neutrino and anti-neutrino beams
Physics applications of a beta-beam– Primarily neutrino oscillation physics and CP-violation– Cross-sections of neutrino-nucleus interaction
Aim: production of (anti-) beams from the decay of radio-active ions circulating in a storage ring
• Similar concept to the factory, but parent particle is a -active isotope instead of a .
Beta-decay at rest• spectrum well known from electron spectrum• Reaction energy Q typically of a few MeV
Accelerate parent ion to relativistic max
• Boosted energy spectrum: E 2Q• Forward focusing of : 1/
Pure electron (anti-) beam!• Depending on +- or - - decay we get a or anti-• Two different parent ions for and anti- beams
Physics applications of a beta-beam• Primarily oscillation physics and CP-violation• Cross-sections of -nucleus interaction
from E. Wildner
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200928
BEAM FACILITY: EURISOL scenarioBEAM FACILITY: EURISOL scenarioBased on CERN boundariesIon choice: 6He and 18NeBased on existing technology and machines
– Ion production through ISOL technique– Bunching and first acceleration: ECR, linac– Rapid cycling synchrotron– Use of existing machines: PS and SPS
Relativistic gamma=100 for both ions– SPS allows maximum of 150 (6He) or 250 (18Ne)– Gamma choice optimized for physics reach
Opportunity to share a Mton Water Cherenkov detector with a CERN super-beam, proton decay studies and a neutrino observatory
Achieve an annual neutrino rate of – 2.9*1018 anti-neutrinos from 6He– 1.1 1018 neutrinos from 18Ne
The EURISOL scenario will serve as reference for further studies and developments: Within Euro we will study 8Li and 8B
top-down approach
from E. Wildner
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200929
BEAM FACILITY: Ions production schemes (1/2)BEAM FACILITY: Ions production schemes (1/2)
ISOL method at 1-2 GeV (200 kW)• > 1 1013 6He per second• < 8 1011 18Ne per second• Studied within EURISOL
Direct production• > 1 1013 (?) 6He per second• 1 1013 18Ne per second• Studied at LLN, Soreq, WI and GANIL
Production ring• 1014 (?) 8Li • > 1013 (?) 8B• Will be studied within EURO-
Courtesy M. Lindroos
Aim:He 2.9 1018 (2.0 1013/s) Ne 1.1 1018 (2.0 1013/s)
from E. Wildner
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200930
BEAM FACILITY: Ions production schemes (2/2)BEAM FACILITY: Ions production schemes (2/2)
Courtesy M. Lindroos
from E. Wildner
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200931
SummarySummary
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200932
(1/2)(1/2)
• There has been significant progress during the past years in the definition of CERN future proton accelerators for the needs of LHC
• The possibility to upgrade to high beam power has been studied and kept compatible with the proposals
HOWEVER
• Schedule is continuously shifting (level of resources + better understanding of Civil Engineering needs…)
• Numerous issues deserve special investigation to prepare for multi-MW proton drivers (Beam dynamics and hardware design for the accelerators, Design of target and target area…)
• The possibility to upgrade to high beam power will have a cost: approval by the CERN Council cannot be taken as granted.
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200933
(2/2)(2/2)
MILESTONES
• 2009: “Definition of the CERN scientific strategy”• 10-13 May 2009: workshop on New Opportunities in the Physics
Landscape at CERN• September 2009: workshop on neutrino physics (organized by a working
group of the CERN SPC)
• 2012: “Authorization of the new projects”• June 2012: Council decision (the whole planning is locked on the starting
date)
If the case for a high power SPL is strong, it would be ideal to immediately implement it.
If the high power option is considered of too low interest, the investment required to implement it later can be rejected.
• End of 2010’s: “Start of commissioning of sLHC”
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200935
SPARE SLIDESSPARE SLIDES
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200936
PIMS
A 70 m long transfer line connects to the existing line Linac2 - PS Booster
RFQ DTL CCDTL PIMS Output energy 3 50 102 160 MeV Frequency 352 352 352 352 MHz No. of resonators 1 3 7 12 Gradient E0 - 3.2 2.8-3.9 4.0 MV/m Max. field 1.95 1.6 1.7 1.8 Kilp. RF power 0.5 4.7 6.4 11.9 MW No. of klystrons 1 1+2 7 4+4 Length 6 18.7 25.2 21.5 m
Linac4 accelerating structuresLinac4 accelerating structuresLinac4 accelerates H- ions up to 160 MeV energy:
in about 80 m length
using 4 different accelerating structures, all at 352 MHz
the Radio-Frequency power is produced by 19 klystrons
focusing of the beam is provided by 111 Permanent Magnet Quadrupoles and 33 Electromagnetic Quadrupoles
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200937
Linac4 civil engineeringLinac4 civil engineering
Linac4 tunnel
Linac4-Linac2 transfer line
Equipment building
Access building
Low-energy injector
ground level
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200938
Equipment Hall (Bld. 400)Equipment Hall (Bld. 400)
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200939
700mm
RF
Services Généraux
Sécurité
Linac4 tunnel cross-sectionLinac4 tunnel cross-section
Final position of cable trays:
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200940
REFERENCESREFERENCES- SPL -- SPL -
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200941
http://cdsweb.cern.ch/record/1136901/files/CERN-AB-2008-067.pdf
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200942
704 MHz 1408 MHz 352 MHz (spoke) + 1408 MHz
length 439 m +14% +10%
Ncavities 239 +16% +12%
Nβ-families 2 3 2+1
tr. beam loss - - -
jitter medium medium medium
ε-growth (x/y/z) 5.6/8.2/6.8 6.3/7.8/12.1 1.5/5.3/2.5
trans. beam loading - - -
BBU (HOM) IBBU,704 1/(8..128) higher/lower
trapped modes normal risk 2..4 higher risk ?/higher
SC gradients - - -
field control more complex
Comparison of frequencies (1/2)Comparison of frequencies (1/2)
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200943
704 MHz 1408 MHz 352 MHz (spoke) + 1408 MHz
cryo-modules ~ ILC ~ ILC2 different
types
cooling power @4.5 K 15.3 kW 15.5 kW ?
klystronscomfortable:
MBKdifficult existing/difficult
RF power coupler feasible feasible feasible
RF power density limit (distribution) ok problematic
bulky/problematic
overall power consumption
(RF+cryo, nom. SPL)28 MW -30% ?
power converter more bulkysaves tunnel
space-
synergy with ESS yes no no
Comparison of frequencies (2/2)Comparison of frequencies (2/2)
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200944
Conclusions of the assessmentConclusions of the assessment
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200945
SPL cryomodulesSPL cryomodules
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200946
REFERENCESREFERENCES- Site Layouts (Stage 3) -- Site Layouts (Stage 3) -
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200947
Plan for a Radioactive Ion Beam Facility (Stage 3)Plan for a Radioactive Ion Beam Facility (Stage 3)HP-SPLTARGETS RADIOACTIVE
IONS LINAC
EURISOL EXPERIMENTAL HALLS
ISOLDE OREURISOL HIGH ENERGY EXPERIMENTAL HALL
TRANSFER LINES SPL to EURISOL
TRANSFER LINE SPL to ISOLDE
GDR NEUTRINO - SESSION 200927-28 April, 2009 - LPNHE
R.G. 27/04/200948
Plan for a Neutrino Factory (Stage 3) Plan for a Neutrino Factory (Stage 3)
MUON PRODUCTION
TARGET
MUON ACCELERATORS
MUON STORAGE
RING
SPL
ACCUMULATOR & COMPRESSOR