Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013. MUON Campus Program. MUON Campus Program. MUON Campus Program. MC-1 Building GPP. MC-1 Building GPP Org Chart. General Plant Project (GPP) Approved: April 20, 2012. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

Muon Campus AIP ReviewMC-1 Building GPP Update

Russ AlberFESS Engineering

January 23, 2013

Page 2: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MUON Campus Program

Page 3: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MUON Campus Program

Page 4: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MUON Campus Program

Page 5: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP

Page 6: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP Org Chart General Plant Project (GPP) Approved: April 20, 2012

Page 7: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP Funding Profile

$1M transferred to FY14

Page 8: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP Milestone Schedule

MILESTONE DEFINITION BASELINE PERCENT COMPLETE

Start Project Directive signed April 2012 100%

Start Engineering Engineering work for the project starts when a task is entered into the Task Database

May 2012 100% Site Prep90% Building

Begin Construction Notice To Proceed/Purchase Order Issued

January 2013 NTP Site PrepJanuary 10, 2013

Construction Complete Final acceptance of all work September 2014 0%

Engineering Complete Completion of Close-out Documents

December 2014 0%

Project Complete Project Closed March 2015 0%

Page 9: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP ScopeConstruction split into two packages to expedite construction:

Package A – MC-1 Building Site Prep ($742.5K FY13)Goal is to 1) relocate all utilities out of building excavation, and

2) perform all shutdown work during current shutdown Relocate/tap into utilities:

Chilled Water Supply & Return (CHWS, CHWR)

Domestic Water Supply (DWS)

Gas (GAS)

Industrial Cooling Water (ICW)

Sanitary Sewer and new lift station (SAN)

Electrical ductbank and manholes

Communication ductbank and handholes

Relocate Well Pond Road (shutdown work)Install cryo line supports and under-road piping

(shutdown work)

Page 10: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP ScopePackage A – MC-1 Building Site Prep – CURRENT STATUS

Cost Estimate: $1.096M – Low Bid: $742.5K Whittaker Construction Construction documents are located here:ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/6-10-20A - Issued for Bids/

Notice of Intent & Storm Water & Pollution Prevention Plan (NOI & SWPPP) has been submitted to Illinois Environmental Protection Agency (IEPA) on November 1, 2012. Construction can begin December 1, 2012.

• Revision No. 1 to incorporate entire Muon Campus including Mu2e approved.

ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/NOI & SWPPP/

Radiation Safety Drawings created for all work within the vicinity of the 8 GeV beamline. Reviewed by AD/Radiation Safety and awaiting final approval for construction.

ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/Radiation Drawings/

Page 11: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building GPP ScopePackage B – MC-1 Building ($4.0M FY13, $0.8M FY14)60% Review completed October 24, 201295% Review (Lab Wide) – February 1, 2013 (est.)Issue for Bids – March 2013 (est.)

Pre-procurements (FY13) 1,500 kVA Transformer - $125K(pad installed under building package for current and future transformers)

15 kV Switch - $20K

30 Ton Building Crane - $175K

Page 12: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – Site Plan

Page 13: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – First Floor Plan

Page 14: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – Basement Plan

Page 15: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – Second Floor Plan

Page 16: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – Elevations

Page 17: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – Elevations

Page 18: Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

MC-1 Building – Cross Sections