Munitions Remediation at RCRA Facilities Kim Meacham Project Engineer USACE, Huntsville Center Environmental Protection and Utilities Branch 30 May 2013 US Army Corps of Engineers BUILDING STRONG ®

Upload: others

Post on 08-Oct-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

Munitions Remediation at RCRA Facilities Kim Meacham Project Engineer

USACE, Huntsville Center Environmental Protection and Utilities Branch

30 May 2013

US Army Corps of Engineers BUILDING STRONG®

Page 2: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

      

BUILDING STRONG®

Agenda

Brief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS

2

Page 3: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

RCRA – What is it?

RCRA is the Resource Conservation and Recovery Act [42 USC 6901 et seq.] , which was enacted by Congress in 1976. RCRA is the primary Federal statute regulating the generation, transportation, treatment, storage, and disposal of solid and hazardous waste. RCRA was enacted by Congress to require proper management of waste generated at existing facilities.

- EM1110-35-1 Chapter 9

3 BUILDING STRONG®

Page 4: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

RCRA – What is it?

RCRA has kept in stride with current waste management issues and problems by way of Congressional amendments, the most notable being the Hazardous and Solid Waste Amendments (HSWA).

- EM1110-35-1 Chapter 9

4 BUILDING STRONG®

Page 5: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

RCRA – What is it?

Under provisions of HSWA, Congress established the authority for corrective action requirements at permitted or interim status hazardous waste management facilities.

Some states are RCRA-authorized states and have the authority to regulate the hazardous and solid waste within their state

- EM1110-35-1 Chapter 9

5 BUILDING STRONG®

Page 6: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

   

   

   

RCRA Permits

Authorized RCRA States ►Achieve Primacy by EPA Acceptance of State

Legislation/Codes/Rules • Georgia EPD RCRA Guidance

Selecting Media Remediation Levels at RCRA SWMUs

• Utah Administrative Code Title R315 Environmental Quality, Solid and Hazardous Waste

6 BUILDING STRONG®

Page 7: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

   

RCRA Permits

RCRA Part A ► Consists of EPA Form 8700-23 (includes both

the RCRA Subtitle C Site Identification Form and the Hazardous Waste Permit Information Form), maps, drawings, and photographs, as required by 40 CFR 270.13

► Or, State form that requires information not requested in the EPA form

► May obtain interim status until Part B permit is issued

7 BUILDING STRONG®

Page 8: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

   

             

BUILDING STRONG®

RCRA Permits

RCRA Part B ► Hazardous waste permit application contains

detailed, site-specific information ► Negotiations maybe required ► Organized in Modules

• Standard Permit Conditions • General Facility Conditions • Corrective Action • Post Closure Conditions • Attachments – Plans, Management requirements…

8

Page 9: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

       

   

Permit/Management

Other Requirements may include, as applicable ► Air Modeling ► Waste Analysis Plans ► Inspection Plans ► Contingency Plans ► Closure Plans ► Container Management

Notice of Violation can come with Fines and Penalties

9 BUILDING STRONG®

Page 10: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

   

     

SWMU/HWMU

Solid Waste Management Unit Hazardous Waste Management Unit

►RCRA permitted • Regulator is Lead Agency • Environmental Remediation

Follows RCRA programmatic requirements

Facility specific requirements

SWMU in the past called Operable Units

10 BUILDING STRONG®

Page 11: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

BUILDING STRONG®

CERCLA vs RCRA

- EM 1110-1-502

11

Page 12: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

BUILDING STRONG®

CERCLA vs RCRA

- EM 1110-1-502

12

Page 13: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

      

Project SWMUs

Site Description ►Multiple burial pits

• Munitions • Drums

►Open burning and/or dumping trenches,

►Open burn/open demolition sites, including ash piles

13 BUILDING STRONG®

Page 14: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

         

Objectives

First SWMU ►Perform surface stabilization

• Surface clearance for Kick-outs from OB/OD • Removal of materials from pits and trenches • Collect surface samples to determine presence/

absence of contamination ►Surface items were removed from burial pits

as long as no digging was required ►Dispose of conventional munitions

14 BUILDING STRONG®

Page 15: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

   

   

Specifics to the RCRA Permit

Air Modeling required for burning of incendiaries ►Resulted in Modification of the Permit

Unacceptable to move items BIP’d ►Required Emergency Permit

Staging of Hazardous Waste ►No Hazardous Waste left the SMWU until

properly manifested and ready for shippment

15 BUILDING STRONG®

Page 16: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

             

   

BUILDING STRONG®

Objectives

Second SWMU ►Perform Interim Removal ►Achieve Response Complete

• Sampling to confirm presence/absence • Remove contaminated soil • Resample • Prepare required closure Documents

HWMU ►Achieve Closure

16

Page 17: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

     

   

Specifics to the RCRA Permit

Air Modeling Unacceptable to move items BIP’d Closure Plan part of RCRA Permit

►Required to use EPA Regional Screening Levels

►RCRA Facility Quality Assurance Project Plan ►RCRA Facility Risk Assumptions Document

17 BUILDING STRONG®

Page 18: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

     

     

   

   

Specifics to the RCRA Permit

Federal government is exempted from the financial requirements of: ► 40 CFR § 270.14(b)(15)

• Closure Cost Estimate • Financial Assurance

Mechanism for Closure

► 40 CFR § 270.14(b)(16) • Post-Closure Cost Estimate • Financial Assurance

Mechanism for Post-Closure Care

► 40 CFR § 270.14(b)(17) • Liability Requirements

► 40 CFR § 270.14(b)(18) • State Financial Mechanism

18 BUILDING STRONG®

Page 19: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

   

   

MRS

Munitions Response Site ►RCRA or CERCLA ►Regulator may allow CERCLA

• Must still meet the substantive requirements of the RCRA Permit

►RCRA Facility risk assessment may be more streamlined than required in CERCLA

19 BUILDING STRONG®

Page 20: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

       

Project MRS

Site Description ►Potential for multiple munitions burial pits ►Open burning and/or dumping trenches, ►Barracks

20 BUILDING STRONG®

Page 21: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

         

Objectives

Perform RCRA Facility Investigation ►Reacquire/Resolve anomalies ►Collect samples for Risk Assessment ►Prepare RFI Report ►If required, perform Corrective Measures

Study

21 BUILDING STRONG®

Page 22: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

BUILDING STRONG®

   

Specifics to the RCRA Permit

Little difference from CERCLA Disposal of DMM and Unacceptable to

move items ►Required Emergency Permit

Followed RCRA Facility Risk Assessment Protocols

22

Page 23: Munitions Remediation at RCRA FacilitiesBrief Overview of RCRA RCRA vs CERCLA SWMU/HWMU MRS . 2 . 3 RCRA – What is it? RCRA is the Resource Conservation and Recovery Act [42 USC

BUILDING STRONG®

Questions?