multinational - côte d’ivoire-liberia-sierra leone and ... · pdf filetranslated...

41
Translated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, LIBERIA, SIERRA LEONE AND GUINEA NETWORKS INTERCONNECTION (CLSG) COUNTRY : MULTINATIONAL (Côte d’Ivoire, Liberia, Sierra Leone, Guinea) PROJECT APPRAISAL REPORT ONEC DEPARTMENT October 2013

Upload: lamdung

Post on 10-Feb-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

Translated Document

AFRICAN DEVELOPMENT BANK GROUP

PROJECT : CÔTE D’IVOIRE, LIBERIA, SIERRA LEONE AND GUINEA

NETWORKS INTERCONNECTION (CLSG)

COUNTRY : MULTINATIONAL (Côte d’Ivoire, Liberia, Sierra Leone, Guinea)

PROJECT APPRAISAL REPORT

ONEC DEPARTMENT

October 2013

Page 2: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

TABLE OF CONTENTS

I. STRATEGIC THRUST AND OBJECTIVES ....................................................................... 1 1.1 Project Linkages with Country Strategy and Objectives ............................................ 1 1.2 Rationale for Bank Involvement ................................................................................. 1 1.3 Donor Coordination..................................................................................................... 2

II. PROJECT DESCRIPTION ................................................................................................... 3 2.1 Project Description and Components .......................................................................... 3 2.2 Technical Solution Adopted and Alternatives Explored ............................................. 4 2.3 Project Type ................................................................................................................ 5 2.4 Project Cost and Financing Arrangements .................................................................. 5 2.5 Project Areas and Beneficiaries .................................................................................. 6 2.6 Participatory Approach for Project Identification, Design and Implementation,

inlcuding Active Participation of the Private Sector and Civil Society ...................... 7 2.7 Bank Group Experience and Lessons Reflected in Project Design ............................ 7 2.8 Key Performance Indicators ........................................................................................ 8

III. PROJECT FEASIBILITY ................................................................................................... 8 3.1 Economic and Financial Performance. ............................................................................ 8 3.2 Environmental and Social Impacts .............................................................................. 9

IV. PROJECT IMPLEMENTATION ...................................................................................... 10 4.1 Implementation Arrangements .................................................................................. 10 4.2 Monitoring ................................................................................................................. 14 4.3 Governance................................................................................................................ 14 4.4 Sustainability ............................................................................................................. 15 4.5 Risk Management ...................................................................................................... 16 4.6 Knowledge Building ................................................................................................. 17

V. LEGAL FRAMEWORK..................................................................................................... 17 5.1 Legal Instrument ....................................................................................................... 19 5.2 Conditions Associated with Bank Intervention ......................................................... 19 5.3 Compliance with Bank Policies ................................................................................ 21

VI. RECOMMENDATIONS ................................................................................................... 21

ANNEX I: Comparative socio-economic indicators in Côte d'Ivoire, Liberia, Sierra

Leone and Guinea

ANNEX II: Table of Bank Portfolio in Cote d'Ivoire, Liberia, Sierra Leone and Guinea

ANNEX III: Major related projects financed by the Bank and other development

partners in Côte d'Ivoire, Liberia, Sierra Leone and Guinea

ANNEX IV: Map of Project Area

Page 3: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

i

Currency Equivalences April 2013

1 UA = USD 1.49920

1 UA = EUR 1.16987

1 UA = GNF 10 590.1

1 UA = SLL 6 546.156

1 UA = LRD 111.6904

1 UA = XOF 767.3844

Fiscal Year

1 January - 31 December

Weights and Measures

Km Kilometre = 1 000 meters

kV Kilovolt = 1 000 volts

kW Kilowatt = 1 000 watts

MW Megawatt = 1 000 000 watts or 1 000 kW)

kWh Kilowatt-hour = 1 000 watt-hours

Acronyms and Abbreviations

ADF

:

African Development Fund

AfP : Agenda for Prosperity

AfT : Agenda for Transformation

CI-ENERGIES : Société des Énergies de Côte d’Ivoire (Cote d’Ivoire Electricity

Corporation)

CO2 : Carbon Dioxide

ECOWAS : Economic Community of West African States

EDG : Electricité de Guinée (Guinea Electricity Corporation)

ERR : Economic Rate of Return

ESIA : Environmental and Social Impact Assessment

ESMP : Environmental and Social Management Plan

EU : European Union

FIRR : Financial Internal Rate of Return

FSF : Fragile States Facility

GDP : Gross Domestic Product

GHG : Greenhouse Gas

IDA : International Development Agency

LEC : Liberia Electricity Corporation

NDP : National Development Plan

NELSAP : Nile Equatorial Lakes Subsidiary Action Program

NPA : National Power Authority

NPC : National Power Corporation

NPV : Net Present Value

NTF : Nigeria Trust Fund

OMVS : Senegal River Development Organization

PAP : Project-Affected Person

PRSP : Poverty Reduction Strategy Paper

RAP : Resettlement Action Plan

Page 4: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ii

RBCSP : Results-Based Country Strategy Paper

SCADA : Supervisory Control and Data Acquisition System

SOFRO : Strategic and Operational Framework for Regional Operations

SPC : Special Purpose Company

TOR : Terms of Reference

UA : Unit of Account

WAPP : West Africa Power Pool

WAPP JIC : West African Power Pool Joint Implementation Committee

Page 5: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

iii

PROJECT INFORMATION SHEET

CLIENT INFORMATION SHEET

GRANTEES/BORROWERS Republic of Cote d'Ivoire

Republic of Liberia

Republic of Sierra Leone

Republic of Guinea

EXECUTING BODIES Special Purpose Company, known as Regional Electricity Transmission Company for CLSG (TRANSCO CLSG)

Related Activities:

Ministry of Mines, Petroleum and Energy of Côte d'Ivoire

Ministry of Lands, Mines and Energy of Liberia

Ministry of Energy of Sierra Leone

Ministry of State for Energy and the Environment of Guinea

EXECUTING AGENCIES Regional Electricity Transmission Company for CLSG (TRANSCO

CLSG)

Related Activities:

Énergie de Côte d’Ivoire (CI- Énergies)

Liberia Electricity Corporation (LEC)

National Power Authority (NPA) of Sierra Leone

Électricité de Guinée (EDG)

West African Power Pool (WAPP)

FINANCING PLAN

Source

Amount in UA million*

Instrument Côte

d’Ivoire Liberia

Sierra

Leone Guinea Total

ADF (country allocation) 13.49 5.93 11.83 31.25 Loan

13.20 3.69 4.97 21.86 Grant

ADF (regional operations allocation) 11.45 8.57 17.08 37.10 Loan

19.80 3.43 6.92 30.15 Grant

FSF 1.12 1.12 Grant

NTF 6.67 6.67 Loan

Total Grant 33.00 1.12 7.12 11.89 53.13 Grant

Total Loan 24.94 21.17 28.91 75.02 Loan

Total Bank Group 33.00 26.06 28.29 40.80 128.15

World Bank 88.57 88.57 Loan

EIB 61.98 61.98 Loan

KfW 26.27 26.27 Grant

EU/Africa Trust Fund 8.55 8.55 Grant

Republic of Cote d’Ivoire 2.87 2.87 Investment budget

Republic of Liberia 8.62 8.62 Investment budget

Republic of Sierra Leone 3.67 3.67 Investment budget

Republic of Guinea 2.83 2.83 Investment budget

TOTAL COST 35.87 149.52 102.49 43.63 331.51

Page 6: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

iv

IMPORTANT FINANCIAL INFORMATION ON BANK GROUP LOANS AND GRANTS

ADF loan to Liberia,

Sierra Leone and Guinea

ADF grant to Cote

d'Ivoire, Sierra Leone

and Guinea – FSF

grant to Liberia

NTF loan to Sierra Leone

Loan/Grant Currency Unit of Account (UA) Unit of Account (UA) United States Dollar (USD)

Type of Interest N/A N/A N/A

Interest Rate Margin

N/A N/A N/A

Service charge on

ADF loans

0.75% per year on the

disbursed portion of the loan

outstanding.

N/A 0.75% per year on the disbursed portion

of the loan outstanding.

Commitment charge

on ADF loans

0.5 % on the undisbursed

portion of the loan with effect

from 120 days after the signing

of the Loan Agreement

N/A

0.5 % on the undisbursed portion of the

loan with effect from 120 days after the

signing of the Loan Agreement

Loan maturity 50 years N/A 20 years

Grace period and

ADF loan repayment 10 years N/A 7 years

FIRR 12.0 % NPV UA 55.47 million

ERR 26.5 % ENPV UA 697.51 million

TIMEFRAME – MAIN MILESTONES (EXPECTED)

Concept note approval 23 May 2012

Project approval November 2013

Effectiveness of grants and loans May 2014

Completion report February 2018

Last disbursement December 2017

Last repayment December 2064

Page 7: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

v

PROJECT SUMMARY

1. Project Overview

1.1. The Côte d'Ivoire, Liberia, Sierra Leone and Guinea (CLSG) electricity networks

interconnection project involves the construction of a 1,357-km-long double circuit high

voltage (225 kV) line to connect the national networks of the four countries. The construction

of this line is part of the backbone of the Mano River Union countries and the priority projects

of the West African Power Pool (WAPP) Master Plan. The project will help establish a

dynamic electric power market in the West African sub-region and secure power supply for

participating countries which have a comparative advantage in importing power rather than

producing it at high costs using their national systems. The project, estimated at an overall

cost of UA 331.51 million, net of taxes, will be implemented over the 2014-2017 period. The

contribution of the Bank Group (ADF, FSF and NTF) amounts to UA 128.15 million (or

38.66% of the total cost).

1.2. The direct beneficiaries of the project are the residents of its impact area (24 million

inhabitants) who will have reliable electric power at competitive cost. The project will raise

the average electricity access rate in the four countries from 28% in 2012 to 33% by 2017.

The increased electricity access will generally contribute to improving the welfare of the

beneficiaries and lead to the development of social and income-generating activities. More

particularly, the project will electrify about 115 communities located along the power line and

supply electric power to 70 schools, 30 health centres, and approximately 1,500 small

handicrafts, commercial and industrial businesses, 25% of which are operated by women.

These achievements will help improve the performance of schools and health’s services, as

well as increase the incomes of the people. The project will have direct spin-offs on national

power corporations whose financial situation will improve as a result of the savings on

production costs and the increased income generated by exporting countries.

2. Needs Assessment: The socio-political crises in Liberia and Sierra Leone led to the

destruction of the public electric power infrastructure of these countries. Owing to the low

levels of investment in the sector in recent years, the power infrastructure has become

obsolete with the attendant outcome of extremely poor quality of service. The cost of electric

power production per kWh remains very high in these countries whose energy mix is

predominantly thermal (62% on average) and where the electricity access rate is among the

lowest in the world (2% in Liberia and Sierra Leone, 10% in Guinea). The unavailability of

electric power and its high cost are among the main obstacles to economic development and

poverty reduction in these countries. Of all the Mano River Union countries, Côte d’Ivoire

enjoys a more favourable situation with an electrification rate of 34% and a low-cost

production capacity. The CLSG project is a structuring project which, in its first phase, will

enable Liberia, Sierra Leone and Guinea to import electricity from Côte d’Ivoire. The

construction of the power line will also foster development of the huge hydroelectric potential

of the sub-region (by the States and/or the private sector) by offering the possibility of electric

power trade between the countries within the WAPP larger market.

3. Bank’s Added Value: The Bank has a good knowledge of the electricity sector in

West Africa and rich experience in the definition and implementation of regional projects. On

account of its involvement right from the feasibility study stage, it was able to guide the

technical choices and take into account all aspects of the project, especially the environmental

and social aspects. Drawing on its experience, the Bank ensured all appropriate measures

would be taken for effective mitigation of the project’s environmental and social impacts.

Page 8: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

vi

Indeed, the complexity of the project and the important basic legal documents necessary for

its success required the Bank’s involvement. In this regard, the Bank contributed to the

preparation of such important documents as the International Project Agreement, the Treaty

establishing the Project Company, and the Power Purchase Agreement. In addition, the

Bank’s intervention facilitated the mobilization of huge resources from other donors for the

financing of the project.

4. Knowledge Management: The preparation of the above documents and the

establishment of a Specific Purpose Company (SPC) for the construction and operation of the

interconnection are innovations in the appraisal and management of the regional project. The

experience gained during the project preparation and the assessment of the SPC performance

will be used for the design and improvement of the regional project management mechanism

at the Bank. The project will include a capacity building component to ensure the transfer of

knowledge to national structures so as to improve the management of future interconnections

in West Africa. This project will also provide an opportunity to improve knowledge in the

area of regional infrastructure, especially through joint project supervision missions by

donors, close monitoring by the Bank’s field offices, the consulting engineer responsible for

works control and project accounts auditors, all of whose reports will constitute sources of

information on the achievement of project objectives.

Page 9: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

vii

Results-Based Logical Framework of the Project

Country and Project Name: Multinational – Côte d’Ivoire, Liberia, Sierra Leone and Guinea Electricity Networks Interconnection Project

Project Goal: Facilitate sustainable energy trade between Côte d’Ivoire, Liberia, Sierra Leone and Guinea

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION RISKS/MITIGATION MEASURES

Indicator

(including CSI) Baseline Situation Target

IMP

AC

T

A sustainable energy market is established and

strengthened between the countries involved and at

regional level

Energy consumption per

capita (kWh)

In 2012:

Cote d’Ivoire: 290

Liberia: 83

Sierra Leone: 24

Guinea: 97

In 2017:

Côte d’Ivoire: 305

Liberia: 120

Sierra Leone: 30

Guinea: 110

Annual reports of national

electricity corporations

RISKS

1. Risk of delays by governments in

ratifying the Treaty on the establishment of

the SPC;

2. Risk of difficulties and/or delays in mobilizing national counterpart funds and

risks of delays in the release of the right-of-

way due to delays in the payment of compensation by the governments of the

four countries;

3- Risk of poor performance by the SPC; 4- Risk of inadequacy of national grid sub-

stations to sustain effective consumption of

the energy traded; 5- Risk of significant procurement delays;

6- Risk of shortage of energy in Côte

d'Ivoire for its own consumption needs and for export to other countries;

7- Commercial risk related to the inability

of national power corporations to pay their

SPC bills;

8- Risk related to coordination and State

intervention;

9- Risk related to the fragile nature of the

four countries.

MITIGATION MEASURES

1- WAPP and the Joint Implementation

Committee strive to adhere to the project

preparation and implementation schedule;

2- The countries' counterpart funds are not

substantial and represent less than 10% of the project cost. Furthermore, the Ministries

of Finance of the four countries are

informed well in advance so that they may take necessary steps in terms of budgeting.

- Confirmation by the four countries of the

budgeting of resources required to compensate affected persons prior to the

start-up of works;

- Strengthening of the capacity of national

Electrification rate

28% on average in 2012

CI: 34%, Liberia: 2%

SL: 2%, Guinea:12%

33% on average in 2016

Côte d’Ivoire: 40%, Liberia: 6%

Sierra Leone: 6%, Guinea: 20%

EX

PE

CT

ED

OU

TC

OM

ES

Volume of energy trade N/A More than 590 GWh from

2016

Reports of ADB

supervision missions

Quarterly progress reports

Project completion reports

Reports of Ministries of

Trade

Reports of Ministries of

Energy and the Economy

and Finance

Average electricity

production cost per

kilowatt/hour

More than 20 cents USD

in 2012

15 cents USD as from 2020

Outage times Guinea, Sierra Leone: 1/3

coverage

Liberia: no load-shedding

CI: 55 hours of outage

per year/no load-

shedding

100% coverage during peak

periods in participating

countries

Number of jobs

N/A

Creation of 5,000 direct jobs

and 2,000 indirect jobs during

the implementation phase, and

450 permanent jobs at the end

of the project

Women's access to

electricity

Income generated for women

by access to electricity

0% electricity along the

corridor

70% of women have

incomes below the

poverty line

- 70% rate of electrification of

localities along the corridor,

50% of whose population are

women

- 30% of women have incomes

below the poverty line

Page 10: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

viii

Reduction in carbon dioxide

(CO2) emissions

N/A

3.36 million tonnes avoided

from 2016

institutions responsible for implementing

the compensation plan and establishment of

a Grievance Committee; 3. Establishment of an Executive Committee

and a Steering Committee to monitor the

SPC’s performance; and recruitment of an

Internal Auditor;

4. The rural electrification component of the project;

5. The executing body will be supported by

a Procurement Expert; 6. Côte d’Ivoire is already taking steps to

balance the country’s energy supply and

demand (implementation of a project to generate 1,097 MW of reserves in Côte

d'Ivoire in 2016);

7. Setting up of reimbursement accounts for

the SPC;

8. Under the Treaty signed by the Heads of

State, the SPC will own the line.

9. Intensification of regional dialogue

among Mano River Union countries - the

Heads of State of participating countries has

signed the Treaty.

Increased availability and reliability of

telecommunications (ICT) in the four countries

Length of optical fibre lines

N/A

1,357 km of backbone line from

2016

OU

ITP

UT

S

1. Construction of high voltage lines;

2. Construction of sub-stations and high- and medium-voltage reactive power

compensation banks;

3. Construction and modernization of the regional SCADA;

4. Rural electrification;

5. Institutional support to WAPP and the countries;

6. Compensation of affected persons and

mitigation of adverse impacts; 7. Audit reports and quarterly reports.

Length of high-voltage line

constructed;

Number of sub-stations

constructed;

Logistical and operations

equipment installed;

Number of connected

localities;

Training program

implemented;

Adverse impact mitigation

measures;

Timely submission of audit

and quarterly reports.

N/A

1,357 km of 225-kV power line

constructed in 2016;

12 sub-stations constructed by

2016;

Construction of the SCADA in

Guinea;

Logistical and operations

equipment procured;

115 localities connected (CI:

29; Liberia: 28; SL: 26; Guinea:

32);

Training program implemented

in 2014;

RAP fully implemented by

2015.

ADB supervision mission

reports;

Progress reports produced

by implementation agency;

Project completion report.

COMPONENTS

KE

Y A

CT

IVIT

IES

-

I. Infrastructure (UA 233.51 million)

Construction of the line;

Construction of sub-stations;

Installation of the supervisory control and data acquisition system (SCADA);

Static VAR compensators (SVC);

Frequency compensation equipment.

II. Studies, supervision & control (UA 56.51 million)

Audit;

Project Implementation Unit (SPC/Management Unit/Consulting Engineer);

Capacity building for WAPP and the countries;

Interim interests during the construction;

Environmental and social impact mitigation measures.

III. Rural electrification (UA 41.49 million)

Total: UA 329.88 million

INPUTS

Bank Group UA 128.15 million (38.66%)

World Bank UA 88.57 million (26.70%)

EIB UA 61.98 million (18.70%)

KfW UA 26.27 million (7.90%)

EU/Africa UA 8.55 million (2.6%)

Governments (IDC +

ESIA)

UA 17.99 million (5.4%)

TOTAL UA 331.51

Page 11: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ix

CLSG Project Implementation Schedule

Page 12: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

1

MANAGEMENT’S REPORT AND RECOMMENDATION

Management hereby submits the present report and recommendations concerning (i) an

exceptional waiver of the Application of the Rule of Origin for the Procurement of Goods, Works and

Services financed by the Nigeria Trust Fund; and (ii) the following proposals for (a) a Fragile State

Facility (FSF) grant of UA 1.12 million to Liberia; (b) Nigeria Trust Fund (NTF) loan of USD 10

million to Sierra Leone; (c) African Development Fund (ADF) loan of UA 24.94 million to Liberia;

(d) ADF loan of UA 14.50 million to Sierra Leone; (e) ADF loan of UA 28.91 million to Guinea; (f)

ADF grant of UA 33.00 million to Côte d’Ivoire; (g) ADF grant of UA 7.12 million to Sierra Leone;

and (h) ADF grant of UA 11.89 million to Guinea.

I. STRATEGIC THRUST AND OBJECTIVES

1.1 Project linkages with country strategies and objectives

1.1.1 This project is in line with the development strategies of the participating countries. Indeed, it

is consistent with: (i) the fifth pillar of the National Development Plan (NDP) 2012-2015 for Côte

d’Ivoire: Repositioning of Côte d'Ivoire on the regional scene; (ii) the second strategic pillar of

Liberia’s Agenda for Transformation 2012-2020: Improving infrastructure and basic services; (iii) the

first pillar of Sierra Leone’s Agenda for Prosperity (AfP) 2013-2017: Diversifying the economy to

promote inclusive growth; and (iv) the third and fourth pillars of Guinea’s PRSP 2013-2015, namely:

Development of infrastructure to support growth and Reinforced access to basic social services and

resilience of households.

1.1.2 At regional level, the project is consistent with the energy development strategy of the

Economic Community of West African States (ECOWAS) as reflected in the West African Power

Pool (WAPP)1. As such, the project is one of the five priority sub-programmes of the WAPP Master

Plan, and represents a segment of the backbone of Mano River Union countries.

1.1.3 As regards the country strategies at the Bank, the project is consistent with: (i) Pillar 1 of

Côte d'Ivoire’s CSP 2013-2017 on support for revitalization of production; (ii ) Pillar 1 of Liberia's

CSP 2013-2017: “Promotion of inclusive economic growth through transformative infrastructure

investments”; (iii) Pillar 2 of Sierra Leone’s CSP 2013-2017: “Support for Transformational and

Sustainable Infrastructure Development”; (iv) Pillar 2 of Guinea’s RBCSP 2012-2016 relating to the

development of basic infrastructure. The project is consistent with the Bank’s Strategic and

Operational Framework for Regional Operations (SOFRO) which states that “The Bank Group will

continue to support the WAPP during the ADF 12 period by funding several interconnection projects

in the existing reserve.” Moreover, the project will also contribute to the implementation of the

priority infrastructure identified in the Bank’s Regional Integration Strategy Paper (RISP 2011-2015)

for West Africa and in the Program for Infrastructure Development in Africa (PIDA).

1.2 Rationale for Bank Involvement

1.2.1 The four Mano River Union countries are fragile and have just emerged from long socio-

political crises. The damage caused by these crises make this region one of the poorest in Africa. The

Bank Group, following the visit of Senior Management to the countries in 2012, intends to offer

1 WAPP: The West African Power Pool was established in 2006. It seeks to pool energy resources of the countries of the sub-region through the integration of national power grids for the creation of a unified regional electricity market.

Page 13: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

2

assistance to Côte d'Ivoire, Liberia, Sierra Leone and Guinea so as to boost regional cooperation in the

area of infrastructure, including electricity.

1.2.2 The electricity sector in the Mano River Union countries is facing major constraints, namely:

(i) low electricity access rate (28% on average in 2010 and 2% for Liberia); (ii) a structural deficit in

electric power supply which meets no more than 30% of demand that is growing at an average annual

rate of about 7%; (iii) predominance of thermal energy production (62%) in the sub-region’s energy

mix which, on account of the soaring oil prices, contributes substantially to the rising cost of

electricity and increases greenhouse gas emissions; and (iv) limited financial and institutional

capacities of national electricity corporations.

1.2.3 These countries have significant energy resources, located mainly in Guinea and Côte

d'Ivoire, both of which are endowed with water resources. The project will help put in place structural

infrastructure in the regional electricity sector and a regional electricity market through the gradual

integration of isolated and small-scale national grids into a unified interconnection system.

Furthermore, the infrastructure will promote the development of hydroelectric sites (clean and low-

cost electric power) along the route of the power lines by facilitating transmission of the energy

produced. By easing transmission, the project will help overcome the structural weaknesses caused by

the small size of national economies and create a favourable and attractive environment for the private

sector which would be able to invest in major electricity-producing infrastructure, thereby achieving

economies of scale.

1.2.4 The Bank's involvement is justified by: (i) the project's alignment with the Bank's long-term

strategy (LTS) for the 2013-2022 period, which advocates transformation towards an inclusive and

green growth, particularly through regional integration; (ii) the consistency of the project with the

Bank's energy policy which aims to support the efforts of regional member countries to provide their

entire populations and production sectors with access to modern, reliable and low-cost energy

infrastructure and services; (iii) the fact that the CLSG project is a segment of the backbone of the

Mano River Union countries and one of WAPP's priority sub-programmes, thus acting as a driving

force in the economic development of the Mano River Union and, by extension, of ECOWAS; (iv) the

leading role of the CLSG project in the implementation of the Action Plan of the Program on

Infrastructure Development in Africa (PIDA); and (v) the crucial experience that this project will

provide in the area of regional project implementation.

1.3 Donor Coordination

1.3.1 Table 1.3 below and Annex 3 provide a list of technical and financial partners, and their

respective amounts of financing for the beneficiary countries of this project. These interventions are

coordinated within thematic working groups, of which the Bank is a member, formed in Cote d'Ivoire,

Liberia and in Guinea. Such groups have not yet been set up in Sierra Leone. However, this project

was jointly prepared and appraised by the various donors involved, under WAPP coordination. In

addition, consultations were held to prepare the various legal documents.

Page 14: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

3

Table 1.3

Donor Coordination

Electricity Sub-sector

Amount

GDP Exports Labour

Côte d’Ivoire 2% 4% 3% Liberia 0.5% 0% 1%

Sierra Leone 0.7% 0% 0.2%

Guinea 0.58% 0% 1.0%

Stakeholders

Government Donors

CI: UA 150 million

(24.5%) UA 460 m (75.5%) EU (7%), IDA (7%), BOAD (21%), Eximbank China (67%), other donors (2%)

LR (3.8%) UA 265 million WB (40%), USAID (20%), EU (17%), Germany (14%), others (7%)

SL UA 167 million WB (88%), UE (6%), JICA (6%) GU: UA 139.6 million

(29%) 336.7 (71%) ADF (6.01%), IDA (5.74%), Eximbank China (65.58%), other donors (22.67%)

Aid coordination level

CI LB SL GU

Existence of thematic working groups in the sub-sector Yes Yes No Yes

Existence of an overall sector-based program Yes No No Yes

ADB’s role in aid coordination Member Member N/A Member

II. PROJECT DESCRIPTION

2.1 Project Description and Components

2.1.1 The project consists mainly in the construction of a high voltage interconnection network

linking Côte d’Ivoire, Liberia, Sierra Leone and Guinea. Other activities related to the construction of

infrastructure are also envisaged, including the electrification of localities situated along the power

line, capacity building for WAPP and the countries, conduct of studies on the planning and feasibility

of hydroelectric power stations to strengthen energy trade and the project management. The project

implementation will help complete the WAPP interconnection network and enhance power supply

security by 290 MW.

Table 2.1

Project Components

Name of

Component

Total

Project

Cost (UA

million)

Bank

Financing

(UA

million)

% Description

Infrastructure 233.51 86.32 36.97

* Construction of a 1,357 km-long 225-kV power line; a

54 km-long 66-kV power line; eleven 225/33-kV

transformer stations and strengthening of a 225/33-kV

transformer station;

*Construction of a control centre in Guinea and

strengthening of a control centre Côte d’Ivoire;

* Static VAR compensators (SVC) in CI;

* Frequency regulation equipment (Static VAR

compensator - SVC)

Rural

Electrification 41.49 32.94 79.39

* Services (implementation study, audit, control and

works supervision);

* Construction of networks and sub-stations for 115

communities;

* Operating costs: Executing agencies of the rural

electrification component.

Page 15: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

4

Project Studies

and Management 56.51 8.89 15.73

* Audit;

* Operating costs of the SPC and WAPP;

* Control and supervision of the high voltage construction

works;

* Capacity building (WAPP + countries);

*Implementation and monitoring of the ESMP and RAP;

*Various studies (feasibility of dams in Côte d’Ivoire and

Sierra Leone, study on the Linsan Fomi power line, study

on Liberia’s Master Plan);

*Compensations.

Total 331.51 128.15 38.66

2.2 Technical Solution Adopted and Alternatives Explored

2.2.1 The project involves the construction of a 1,357-km-long high voltage (225 kV) transmission

network, with a transit capacity of 290 MW, 12 sub-stations and two control centres. The technical

solution adopted consists in constructing a line equipped with double circuit towers for the installation

of two power transmission circuits. However, in the first phase, a single circuit will be installed to

allow transit of 83 to 145 MW of power for the pool by the end of the project. The installation of the

second circuit provided for in a second phase will allow the network to operate at full capacity of 290

MW, which will be achieved after the commissioning of the new plants (including Yiben, Bikongor in

Sierra Leone, Kassa B in Guinea and Mano in Liberia). This phased installation of the transmission

network is a common practice in the electrical industry. It offers better supply security and optimizes

investment costs. The alternatives explored include: continuation of the development of national grids

without considering energy pooling possibilities and the immediate construction of a double circuit

transmission line and the construction of two single circuit transmission lines. The reasons for their

rejection are summarized in the table below.

Table2.2

Alternative solutions explored and causes of rejection

Alternative

Solution

Brief Description Cause of Rejection

Continuation of the

development of

national systems

No electricity network

interconnection between

countries: each country will

continue on its own to cope with

the increasing demand,

depending on the type of energy

sources

The respective countries alone

cannot, for the time being,

absorb all the power generated

by the huge dams, nor can they

export the surplus for want of

interconnection infrastructure

Higher average cost of production per kWh;

Lower supply security;

Cost of investment in hydroelectric plants extremely

high and difficult to be borne by each country;

Not consistent with the regional development plan

and does not allow for optimization of production

plans;

For the time being, the respective countries alone

cannot absorb all the power generated by the huge

dams, nor can they export the surplus for want of

interconnection infrastructure.

Construction of a

double circuit 22-

kV power line with

the installation of

two circuits

A two-circuit interconnection

power line with immediate

installation of the two circuits.

High immediate investment;

Capacity too huge for the countries’ current needs;

Inadequacy of available production.

Construction of two

single-circuit 225-

kV power lines

Two parallel 225-kV power

lines, with each line having a

single circuit.

Very expensive solution in terms of investment,

requiring a larger power line corridor;

Impossibility of achieving optimal integration of the

power grids of the four countries into the WAPP.

Page 16: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

5

2.3 Project Type

2.3.1 The project is a multinational investment operation. The proposed financing instruments are

loans and grants from ADF, NTF, FSF and EU-Africa Infrastructure Trust Fund resources.

2.4 Project Cost and Financing Arrangements

2.4.1 The total project cost, net of taxes and customs duties, was estimated by the project studies

and updated at appraisal at UA 331.51 million. It includes a 5% provision for physical contingencies

and a 5% provision for price escalation.

Table 2.3

Cost Estimate by Component

Components UA Million

% Foreign Exchange Foreign Exchange Local Currency Total

Infrastructure 180.03 31.77 211.80 63.9%

Rural electrification 31.99 5.64 37.63 11.4%

Project studies and management 36.19 15.51 51.70 15.6%

BASE COST 248.21 52.93 301.14 90.8%

Physical Contingencies 12.24 2.57 14.82 4.5%

Provision for price escalation 12.85 2.70 15.56 4.7%

TOTAL PROJECT COST 273.31 58.20 331.51 100.0%

Percentage 82.4% 17.6% 100.0%

2.4.2 The project will be financed by: (a) the Bank Group (ADF - national allocations of the four

countries, resources earmarked for regional operations, the FSF and NTF under the conditions

specified in the project information sheet on page iv that were negotiated and accepted by the

governments of the four countries [the exchange rates used are those on page i]; (b) the World Bank

and KfW in Liberia; (c) the EIB and the EU/Africa Trust Fund in Sierra Leone; and (d) the

governments of Côte d'Ivoire, Liberia, Sierra Leone and Guinea as shown in Tables 2.4 and 2.5 below.

2.4.3 The Bank is engaged in parallel co-financing with the World Bank, the EIB and KfW, and

joint financing with the EU/Africa Trust Fund, all of which approved the project in 2012. The EIB

loans will be enhanced by additional funding from the EU/Africa Trust Fund to make them

concessional and, in particular, to settle the interests during the grace period of the repayment of the

principal.

2.4.4 Given that the four countries are in principle eligible for Bank financing for the project up to

more than 90%, their counterpart funding for Bank-financed components was limited to payment of

compensations to project affected persons (PAPs) (see Technical Annex B.2 Table 2 for details) and

bank interests incurred during the power line construction.

Table 2.4

Cost Estimate by Source of Financing

Sources of Financing UA million

% total Foreign Exchange Local Currency Total

ADF (grant) 43.04 8.97 52.01 15.7%

ADF (loan) 58.10 10.25 68.35 20.6%

Nigeria Trust Fund (NTF) 5.67 1.00 6.67 2.0%

Fragile States Facility (FSF) 0.78 0.34 1.12 0.3%

EU/Africa Trust Fund 7.27 1.28 8.55 2.6%

World Bank 70.84 17.73 88.57 26.7%

European Investment Bank 52.69 9.30 61.98 18.7%

KFW 22.33 3.94 26.27 7.9%

Governments 12.60 5.40 17.99 5.4%

Total 273.31 58.20 331.51 100.0%

Percentage 82.4% 17.6% 100.0%

Page 17: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

6

Table 2.5

Costs by Category of Project Expenditure

Expenditure Category Total Financing (UA million)

Foreign Exchange Local Currency Total % of Foreign Exchange

Works 226.80 40.02 266.82 80.5%

Goods 1.62 0.34 1.966 0.6%

Services 22.09 8.36 30.450 9.2%

Recurrent 9.70 3.87 13.57 4.1%

Others 13.09 5.61 18.69 5.6%

Total 273.31 58.20 331.51 100.0%

Percentage 82.4% 17.6% 100%

2.4.5 Bank Group resources will be used to finance the entire infrastructure in Guinea and Côte

d'Ivoire, the segment from the Côte d'Ivoire-Liberia border to the Liberia-Guinea border, the section

of the line from the Guinean border to Yiben in Sierra Leone, including the Kamakwi and Yiben sub-

stations; the partial financing of capacity building for WAPP and executing agencies within the States,

as well as full financing of rural electrification (see details in technical Annex Table B2.1).

Table 2.6

Expenditure Schedule by Components (AU million)

Components UA Million

% 2014 2015 2016 2017 TOTAL

Infrastructure 0.00 69.64 94.01 69.86 233.51 70.4%

Rural electrification 0.14 12.45 16.60 12.31 41.49 12.5%

Project studies and management 15.24 12.79 17.06 11.41 56.51 17.0%

TOTAL 15.38 94.89 127.66 93.58 331.51 100.0%

Percentage 4.6% 28.6% 38.5% 28.2% 100%

Table 2.7

Cost Estimate by Component and Source of Financing

UA Million

ADF NTF FSF EU/

Africa WB EIB KFW GOVTS TOTAL

Infrastructure 79.65 6.67 0.00 0.00 58.95 61.98 26.27 0.00 233.51

Rural electrification 32.94 0.00 0.00 8.55 0.00 0.00 0.00 0.00 41.49

Project studies and

management 7.77 0.00 1.12 0.00 29.62 0.00 0.00 17.99 56.51

Total project cost 120.36 6.67 1.12 8.55 88.57 61.98 26.27 17.99 331.51

Percentage 36.3% 2.0% 0.3% 2.6% 26.7% 18.7% 7.9% 5.4% 100.0%

2.5 Project Area and Beneficiaries

2.5.1 The interconnection line runs from Man in Côte d’Ivoire through Liberia and Sierra Leone to

Linsan and Nzérékoré in Guinea. However, considering its regional character, the extended impact

area covers large part of the ECOWAS region that extends from Guinea to Nigeria. The incidence of

poverty is fairly high in the project area (PA), with a prevalence rate of 23.8% in Côte d’Ivoire, 35.2%

in Liberia, and unknown for Guinea and Sierra Leone.

2.5.2 The project will benefit the populations, especially those living in the direct project impact

area and the various sectors of the economy of the four countries. These populations are estimated at

24 million and comprise mostly women (51%) and youths under 30 years of age (70%). These people

are severely affected by unemployment and under-employment. Thus, the project will have a

significant positive impact on the activities of the PA inhabitants in general, and on those of women

and young people in particular, in terms of new employment opportunities, increased business

activities, improved access to socio-economic infrastructure, reduced load-shedding times and the

lower electricity rates that it will engender. The most significant positive impacts expected are: (i)

Page 18: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

7

increased productivity of socioeconomic development sectors, including school performance; (ii)

increased value added of national economies; (iii) increased incomes for young people and women

thanks to training and the creation of job opportunities; and (iv) sharp decline in poverty levels among

the populations.

2.6 Participatory approach for project identification, design and implementation, including

active participation of the private sector and civil society

2.6.1 The stakeholders held more than 30 meetings, including Ministerial meetings, during the

project appraisal and feasibility studies, and in the course of the environmental and social impact

assessment (ESIA). Consultations were also organized in Abidjan, Monrovia, Freetown, Conakry and

in the areas crossed by the power line, in an effort to address the needs and concerns of the project

beneficiaries. The meetings were held under the auspices of WAPP, the services of the Ministries and

agencies involved in the energy sector in the four countries, the local population, civil society, donors

and development partners involved in the sector and the Secretariat of the Mano River Union. All

these meetings made it possible to: (i) collect information and available data required to analyse the

situation in the sector; (ii) establish the project institutional framework and prepare the draft legal

documents; (iii) strengthen project ownership by the countries and donor coordination; (iii) define

project components on the basis of the needs, strategies and priorities expressed by key stakeholders,

including the local population; and (iv) share proposed solutions with the populations to address the

needs or avert the adverse impacts identified. During the project implementation phase, this

collaboration will continue and include the implementation of the Environmental and Social

Management Plan (ESMP), the Resettlement Action Plan (RAP), and the infrastructure component

prior to the establishment of the SPC.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 The project drew on the Bank's rich experience in the financing of multinational

infrastructure projects, including the Ghana, Togo and Benin interconnection project in West Africa,

the Senegal River Development Organization (OMVS) project and the NELSAP interconnection

project. The project design incorporated the lessons learned from these projects and detailed in

Technical Annex B1, the recommendations of the analysis of regional project completion reports

carried out by the Bank's Operations Evaluation Department (OPEV), and governance-related

recommendations expressed in the Outliers and Exceptions Report.

2.7.2 The main problems mainly concern: (i) the plethora of project stakeholders who usually have

different technical and operational capacities; (ii) lack of harmonization and coordination of project

activities in the various countries; (iii) inadequacies of the countries and national electricity

corporations in procurement, mobilization of financial compensation and performance monitoring;

(iv) inadequacy of the resources proposed in the project design and supervision, and significant delays

in the project completion; (v) delays in fulfilling the disbursement conditions due to long delays in the

preparation and signing of project agreements; (vi) delays in mobilizing government counterpart funds

which in turn delay the compensation of project-affected persons (PAPs)

2.7.3 To address these shortcomings, this project envisages: the establishment of an SPC to

coordinate project activities in the four countries; the development of a series of agreements, including

an international project agreement, an electric power purchase agreement and a transmission service

agreement; support for national public services and WAPP through the project's capacity building sub-

component; the inclusion of the detailed project design in the bidding documents to limit

contingencies during project implementation; budgeting of the project counterpart funds by the

countries for 2014; and donor and WAPP assistance in preparing the project and all documents

required for its smooth implementation.

Page 19: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

8

2.8 Key Performance Indicators

2.8.1 The major expected outcomes and means of verification are detailed in the project matrix.

The impact measurement indicators are: (i) electricity access rate; and (ii) the number of direct and

indirect jobs created. The baseline for these indicators as defined in the logical framework will be

verified and an evaluation conducted at mid-term and at the end of the project by the relevant national

electricity corporations, namely CI-ÉNERGIES, LEC, NPA, EDG, and by the SPC.

2.8.2 Project implementation performance indicators will also be monitored. They were selected on

the basis of the Bank's institutional performance indicators. These mainly include: (i) the timeframe

for implementation and fulfilment of the conditions precedent to first the disbursement; (ii) the

procurement timeframes; and (iii) changes in the disbursement rate depending on expenditure

schedules. These indicators will be monitored during supervision missions and in the day-to-day

project management.

III. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

The following are the key financial and economic performance indicators of the project:

Table 3.1

Key financial and economic performance indicators of the project

Baseline scenario FIRR: 12.0% NPV: UA 55.47 million

ERR: 26.5% Eco NPV: UA 697.51 million

NB: Detailed assumptions and calculations are presented in Technical Annex B.7

3.1.1 Financial Performance

3.1.1.1 The financial internal rate of return (FIRR) and the net present value (NPV) were calculated

on the basis of the cost-benefit method for the implementation and commissioning of the project. The

financial benefits taken into account consist of revenue from the transit of energy through the line and

the share, attributable to the line, of profits accruing from the sale of imported energy by the

participating countries. These are project costs, excluding the provision for price escalation, and the

costs of management, operation and maintenance of the structures. The analysis covers a period of 30

years, comprising 4 years of project implementation and 26 years of operation of project structures,

covering the medium-term repayment of the SPC’s financial commitments (see Technical Annex

B.7.1).

3.1.1.2 The tariffs for energy transit through the line will be set at levels that cover the operating

expenses of the SPC and ensures its capacity to repay debts with an average coverage ratio of 1.5 per

annum, while remaining accessible to the importer who will always have an interest in using the line.

Furthermore, the present average cost of energy production in importing countries (Liberia, Sierra

Leone and Guinea) during the first year of operation of the power line will still be higher than the cost

of imported energy from Côte d’Ivoire (purchase cost and transit fees), which shows the advantage of

constructing the power line.

3.1.2 Economic and Financial Performance

3.1.2.1 The economic costs used to calculate the economic rate of return (ERR) and the economic

net present value (ENPV) are project costs net of taxes and net of provision for price escalation,

adjusted for appropriate conversion factors for equipment, works, services and labour. Maintenance

costs and other operating expenses are subject to the same process. The economic benefits derived

from the project comprise, in addition to the rights to use the line, savings realized on the cost of

production by the energy-importing countries, compared to a situation without project where they

Page 20: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

9

would generate their own electricity at a higher cost. The project will reduce CO₂ emission by 5.6

million tons, compared to a situation without project. The value of this carbon reduction by

hydroelectric power-importing countries would further enhance the project's economic performance

(see Technical Annex Table B.7.2).

3.2 Environmental and Social Impacts

Environment

3.2.1 The project is classified in Category 1 based on the scope of works and especially the adverse

environmental and social impacts identified. The detailed Environmental and Social Impact

Assessment (ESIA), the Environmental and Social Management Plan (ESMP) and the Resettlement

Action Plan (RAP) were completed in 2011 and updated in 2013. The respective summaries of the

ESIA and RAP were posted on the Bank's website and distributed to the Board of Directors on 3 July

2013. Considering that the project is classified in Category 1, summaries will be posted for 120 days

prior to the date of the Board meeting.

3.2.2 The main negative environmental impacts of the project were clearly identified in the ESIA.

These impacts will be mitigated by implementing the appropriate measures contained in the ESMP.

For more details, see the ESIA summary published on the Bank's website. Furthermore, the main

constraints on implementing the ESMP in the four countries have been assessed, and appropriate

measures incorporated into the project framework (see Annex B.8.1 for more details). The main

positive impact concerns the reduction of emission of greenhouse gases such as CO₂. The total cost of

ESMP implementation (excluding the RAP cost) is estimated at USD 3,263,234 comprising: (i) USD

874,561 for Côte d'Ivoire; (ii) USD 1,060,000 for Liberia; (iii) USD 892,160 for Sierra Leone; and

(iv) USD 436,513 for Guinea. A portion of these costs will be financed by ADF, particularly those

related to capacity building and monitoring of ESMP implementation and the rest will be borne by the

countries. In addition, the electrification of communities along the power line constitutes an

enhancement measure for the populations.

Climate Change

3.2.3 Climate-related risks and vulnerabilities identified in the project area are: (i) increased

frequency and intensity of floods and storms; (ii) rising sea levels, which could lead to coastal erosion;

and (iii) prolonged flooding and high exposure to corrosion, specifically for Liberia where a segment

of the power grid runs close to the coast between the Monrovia and Mano sub-stations. The

transmission line will be designed and constructed according to the best international engineering

standards to ensure physical resistance to the major climate risks identified. This will entail taking into

account such factors as: (i) the speed of high winds/wind storms; (ii) water levels; (iii) geotechnical

conditions; and (iv) corrosion safeguards. The project will contribute to the mitigation of climate

change by avoiding the emission of approximately 5.6 million tons of CO2 when the countries resort

to hydroelectric energy imports.

Gender

3.2.4 The project beneficiaries are diverse and include young people and women. The project will

have impacts on gender issues in its impact area. By allowing household access to electricity services,

improved livelihoods and better social services, the project will improve the lives of children,

adolescents, youths, men and women, in particular. The project will help reduce electricity

expenditure for households that already have electricity access, thus enabling them to save and

reallocate the saved resources to other priority needs such as food, health and education, or use them

to meet the needs of children, the elderly and people with disabilities. Social and economic

vulnerability prevails throughout the project area. In addition, the project will reduce the time spent in

search of energy sources, especially for girls and women who may use the time saved for productive,

Page 21: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

10

educational or recreational activities. Rural electrification will help to: (i) strengthen existing activities

carried out by women, particularly in the processing and marketing of agro-pastoral products; (ii)

create new income-generating activities for women; and (iii) improve safety for women and children.

Social

3.2.5 The project will have positive and negative social impacts. The main positive impacts are

related to rural electrification of over 115 communities, 70 schools, 30 health centres, 50 carpenters’

workshop and mills, and the creation of income-generating activities in the villages concerned,

development of small and micro-enterprises, and the creation of 5,000 direct jobs and 2,000 indirect

jobs, during the implementation phase, and 450 permanent jobs at the end of the project. Finally, the

project will improve the living conditions and well-being of the populations. The negative social

impacts include the loss of land, crops and incomes related thereto, and the destruction of residential

structures and buildings; land ownership problems; conflicts related to land use; spread of

communicable diseases such as sexually transmitted infections (STIs) and HIV/AIDS due to the high

number of temporary jobs, risks of electrocution and falling of pylons. These negative impacts will be

mitigated by appropriate ESMP measures such as provision of personal protection gear during

construction, carrying out STI/HIV/AIDS awareness campaigns targeted at workers and communities,

educating the public about the risks of wildfire and encouraging contractors to recruit local labour.

Forced Resettlement

3.2.6 The project will cause the physical displacement and/or economic displacement of a total of

5,267 people in the four countries, comprising 112 in Guinea, 3,312 in Sierra Leone, 1,151 in Liberia,

and 692 in Côte d'Ivoire. The project will result in loss of business, the total or partial loss of crops

and farmland, loss of access to community infrastructure, and loss of residential structures.

3.2.7 Resettlement Action Plans (RAPs) have been prepared for each country. These plans have

identified the project-affected persons (PAPs), the affected property and its value, as well as measures

to compensate and/or assist PAPs and restore livelihoods. Resettlement costs will be funded by the

four governments. The resettlement process is scheduled to last a year. The RAP and ESMP will be

implemented by the four governments in collaboration with the SPC. Monitoring and evaluation of

PAPs and the communities will be conducted through concrete mechanisms in the four countries,

including qualitative and quantitative indicators and with the participation of civil society.

3.2.8 The total cost of the RAPs stands at USD 15,579,647, broken down as follows: (i) 1,680 138

for Côte d'Ivoire; (ii) 9,108,286 for Liberia; (iii) 2,924,854.80 for Sierra Leone; and (iv) 1,866,368 for

Guinea. Each country must, in accordance with the RAP, provide evidence of having compensated the

PAPs prior to the start-up of works. That will be a condition precedent to the first disbursement of the

Bank’s financial assistance.

IV. IMPLEMENTATION

4.1 Implementation Arrangements

Executing Agency

4.1.1 The project implementation will be entrusted to the Special Purpose Company (SPC) and that

related activities associated with the project will be carried out by the five executing agencies, namely

WAPP and the four National Power Corporations.

4.1.2 Cote d'Ivoire, Liberia, Sierra Leone and Guinea have agreed, jointly and severally, to

establish, by treaty, a supranational SPC for the financing, construction, operation, development and

ownership of the electric interconnection line (CLSG). The share capital will be owned equally by the

national power corporations of the four countries. Pending the establishment of the SPC, expected by

Page 22: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

11

end-2013, preliminary procurement and recruitment operations will be implemented by the Joint

Implementation Committee referred to as WAPP-JIC2, established in 2008 and comprising WAPP

Secretary-General and country representatives. The Treaty, By-laws and Shareholders' Agreement

have been drawn up by the four governments with the assistance of donors' lawyers. An International

Project Agreement is being finalized. Evidence of the establishment of the SPC is a condition

precedent to first disbursement of Bank financing.

4.1.3 The SPC will comprise a Project Manager, a Financial Officer, an Accounting Officer, a

Technical Coordinator, an Environmental and Social Management Coordinator, a Procurement

Expert, an Internal Auditor, a Legal Counsel and heads of the three project implementation units. It

will be assisted and controlled by three supervisory bodies, namely the Management Committee, the

Steering Committee, and the Treaty Secretariat.

4.1.4 Given that the related activity - capacity building - is one that transcends individual States, it

will be carried out by WAPP. The four countries have agreed to transfer the allocations for this

component to WAPP.

4.1.5 The related activity titled “Rural Electrification” will be performed by national entities on

behalf of each State. The four countries have agreed to delegate the overall coordination of this

component to WAPP. The project envisages supply of equipment and operating resources to national

project implementation units and the payment of monthly allowances to unit staff.

4.5.1.1 In Côte d’Ivoire, the executing agency is the Ministry of Petroleum and Energy. The

executing agency tasked with implementing the “Rural Electrification” component will be located

within the CI-Energy Corporation (CI-ÉNERGIES). A unit will be established under the responsibility

of the Project Coordinator, consisting of two engineers, an environmental expert, an administrative

and financial officer, an accountant, a procurement expert, an assistant and a driver.

4.5.1.2 In Liberia, the executing agency is the Ministry of Lands, Mines and Energy. The executing

agency of the “Rural Electrification” component will be located within the Liberia Electricity

Corporation (LEC). A unit will be established under the responsibility of the Deputy Director-General

of Planning and will consist of two Engineers, an Environmental Expert, an Administrative and

Financial Officer, an Accounting Officer, a Procurement Expert, an Assistant and two drivers. The

project will also support the unit through technical assistance consisting of a Procurement Expert who

will, in the course of the activities, transfer skills and build capacities, and an expert who will handle

the organization of the procurement unit.

4.5.1.3 In Sierra Leone, the executing agency is the Ministry of Energy. The executing agency will

be located within the National Power Authority (NPA). The current project implementation unit will

be strengthened by an Engineer, an Environmental Expert, an Accounting Officer, an Assistant and

two drivers. Due to the limited capacity of NPA’s procurement unit, the project will also support the

unit by way of technical assistance consisting of a Procurement Expert who will, as the activities

unfold, transfer skills and build capacities.

4.5.1.4 In Guinea, the executing agency is the Ministry of State for Energy. It was decided that the

Guinea Electricity Corporation (Electricité de Guinée - EDG) should be the executing agency acting

as the Coordination Unit for ADB projects within the EDG Directorate of Studies and Planning.

Under the responsibility of the Project Coordinator, the unit will be strengthened by two Engineers, an

Accounting Officer, a Procurement Expert and two drivers.

4.1.6 Implementation of the CLSG project will cover the 2014-2017 period, and the power line is

expected to begin operating in 2017.

2 WAPP JIC: West African Power Pool - Joint Implementation Committee

Page 23: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

12

Procurement Arrangements

4.1.7 The procurement of goods, works and services financed by the ADF and the EU/Africa Trust

Fund under this project, will be in accordance with the Bank’s Rules and Procedures for the

Procurement of Goods and Services or, as appropriate, the Rules and Procedures for the Use of

Consultants (May 2008 Edition, revised in 2012), using appropriate standard bidding documents of

the Bank.

4.1.8 Works on the construction of power lines and Regional Control Centres (SCADA) and goods

(IT equipment and vehicles) for the SPC will be procured by the SPC and WAPP. The latter will act on

behalf of the SPC or on behalf of the project's Steering Committee pending the effective setting up of the

SPC.

4.1.9 Procurement relating to capacity building for WAPP and the countries, as well as the purchase

of goods (IT equipment and vehicles) for capacity building purposes will be undertaken by WAPP.

4.1.10 Procurement activities in respect of the rural electrification component of the project will be

undertaken by CI-Energy Corporation (CI-ÉNERGIES) in Côte d'Ivoire, Liberia Electricity Corporation

(LEC) in Liberia, the National Power Authority (NPA) in Sierra Leone and the Guinea Electricity

Corporation (Électricité de Guinée - EDG) for Guinea.

4.1.11 Apart from funding from ADF resources, the Republic of Sierra Leone has access to financing

from the resources of the Nigeria Trust Fund (NTF) for high voltage infrastructure and the EU-Africa

Infrastructure Trust Fund for the rural electrification component. In compliance with the Bank's

procurement rules and procedures, the proceeds of any loan, investment or other financing undertaken as

part of the NTF operations will be used for procurement of goods and works, including the related

services, provided by bidders from eligible member countries. As such, and considering that this project

is funded almost entirely from ADF resources for which the rule of eligibility and origin has been

cancelled, a waiver for non-application of the Bank’s criteria of eligibility and origin is requested

from the Board of Directors, in accordance with Article 4.1 of the Agreement establishing the NTF. Regarding operations of the EU-Africa Infrastructure Trust under which the rural electrification

component is being financed, pursuant to Board of Directors Resolution No. B/BD/2010/15 of

20/07/2010, the Bank agreed to extend procurement eligibility for operations financed from the

resources of the EU-Africa Trust Fund to: (i) members of the European Union that are not members of

the Bank; and (ii) member States of the African, Caribbean and Pacific Community (ACP) which are

not members of the Bank. Accordingly, under this extension and considering that the rule of origin

was waived with regard to ADF funding, the same treatment will be applied to procurement financed

by NTF and the EU-Africa Fund.

4.1.12 Following assessment of the procurement systems of the four countries, the use of national

procedures is recommended for national competitive bidding initiated by the project implementation

unit for the case of Côte d'Ivoire, subject to addressing the disparities that were identified and

summarized in the overall Action Plan presented in Annex B5. However, given that the use of national

procedures is not recommended for Liberia, Sierra Leone and Guinea, the ADF rules and procedures

will be used in the national competitive bidding process initiated by the respective project

implementation units of these countries.

Disbursement

4.1.13 With regard to the SPC, which will be known as the CLSG Regional Electricity Transmission

Company (TRANSCO), the four methods of disbursement recommended in the Bank's Disbursement

Handbook may be used for withdrawals. For the funding of each CSLG Member State, this company

will open, where applicable, a special account with the Central Bank and an advance account with a

commercial bank. These accounts, which will revert to the Company, must be managed separately,

Page 24: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

13

according to the Bank's disbursement rules and procedures and, where appropriate, in collaboration

with the structures in charge of the debt of the borrower/grantee Member States and in accordance

with the disbursement rules and procedures.

4.1.14 Concerning the other executing agencies, the direct payment and special account methods

will be used for withdrawals. For the funding of CSLG Member States, the executing agencies will

also open, where applicable, a special account with the Central Bank and an imprest account with a

commercial bank. These accounts, which will revert to the executing agencies, will be managed

separately, according to the Bank's disbursement rules and procedures and, where appropriate, in

collaboration with the structures in charge of the debt of borrower/grantee Member States.

Financial Management

4.1.15 The financial management of CLSG Interconnection Project will be conducted within the six

executing agencies: (i) the CLSG Regional Electricity Transmission Company, as concerns the

Transmission Infrastructure; (ii) the four National Power Corporations (NPCs) of the CSLG Member

States, as concerns the Rural Electrification and Studies component; and (iii) WAPP, as concerns the

management of capacity building activities.

4.1.16 The funding allocated by the Bank to this project will be on-lent to each executing agency by

the beneficiary governments under the same terms and conditions as specified in the project

information sheet on page iv, which were negotiated and accepted by the governments of the said

countries.

Table 4.1

Onlending between the governments and the executing agencies (in UA million)

Borrowers/

Secondary Donors

Borrowers/ Primary Grantees

Côte

d'Ivoire Liberia Sierra Leone Guinea

Total

ADF Grant ADF

Loan

FSF

Grant

ADF

Loan

ADF

Grant

NTF

Loan

EU-

Africa

ADF

Loan

ADF

Grant

SPC 26.173 8.102 14.50 1.535 6.67 28.91 0.834 86.724

WAPP 0.721 0.703 0.781 2.205

NPC 6.112 16.838 1.12 4.882 8.55 10.275 47.771

Total 33.00 24.94 1.12 14.50 7.12 6.67 8.55 28.91 11.89 136.7

4.1.17 Each executing agency will adopt an automated and integrated information system. The

system should be able to ensure accruals-based private accounting, distinct from the account of the

executing agency and enabling the recording of project operations by source of funding, by

component, and by expenditure category.

4.1.18 For the CLSG Regional Electricity Transmission Company, the project provides for an Audit

Committee for the Management Committee and an Internal Auditor. They will supervise the project’s

internal controls.

4.1.19 Each executing agency will also have an administrative, financial and accounting procedures

manual describing the main features of the financial management system, and applicable financial

policies and procedures. The terms of reference for preparing the procedures manual will be subject to

Bank approval.

External Audit

4.1.20 Project accounts will be audited separately by executing agency. The audit will cover all the

activities assigned to the executing agency concerned.

Page 25: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

14

4.1.21 The CLSG Regional Electricity Transmission Company will be audited by a world-class

accounting audit firm on the basis of standard terms of reference for the audit of Bank-financed

projects and following an international competitive bidding consistent with international best

practices. The other executing agencies will be audited by firms selected through a request for

expression of interest from external and independent audit firms. The terms of reference for the audit

will be prepared based on the template provided by the Bank and subject to the latter’s no-objection.

4.1.22 The audit reports of each executing agency will be submitted to the Bank within six months

following the end of each fiscal year. Four audits are envisaged for this project, covering the years

2014, 2015, 2016 and 2017.

4.2. Monitoring

4.2.1 Monitoring will be conducted by the executing agencies using project resources. The

Consulting Engineer in charge of works supervision and control will participate in establishing and

strengthening monitoring capacities within the SPC in charge of the physical implementation of the

project. WAPP will be responsible for monitoring the electrification component in the four countries.

A mechanism will also be set up to monitor and evaluate the socio-economic impact of the project in

each country.

4.2.2 The Bank will assist these authorities by providing institutional support to strengthen their

capacities so as to improve the management and monitoring of environmental and social aspects.

4.2.3 The project monitoring will comprise internal and external aspects, launching missions, Bank

supervision missions with resources from the Bank’s Offices in the CLSG countries and the

Headquarters, a mid-term review (scheduled to be conducted within 24 months following project start-

up) and a final evaluation, including the completion report of the executing agencies. Monthly and

quarterly works execution reports will be prepared by the Consulting Engineer. The executing

agencies will submit a project implementation report to the Bank on a quarterly basis. A completion

report will be submitted to the Bank by each executing agency within six months following project

completion.

4.2.4 Monitoring of the project impacts will help identify and analyse the indicators impact

attributable to the project and contributing to the achievement of expected outcomes. The donors

financing the project have agreed to conduct joint supervision and mid-term review missions.

Table 4.2

Monitoring of project activities/feedback loop

Duration Stages Monitoring Activities

January-Sept. 13 Preparation of bidding documents WAPP JIC

Nov. 13-March 2014 Invitation for bids WAPP JIC

April 14-June 2014 Bid evaluation WAPP JIC

June 14- July 2014 Preparation of contracts Contractor - SPC-WAPP – National Project Units

August 2014 Start of construction works SPC-WAPP – National Project Units

June 2016 Mid-term review ADF-SPC-WAPP-National Project Units

January 2018 Country completion report SPC- National Project Units-WAPP

February 2018 ADF completion report ADF

4.3. Governance

4.3.1 It is generally acknowledged that poor governance practices, compounded by fraud and

corruption, are the main causes of the current crisis in the electricity sub-sector in Côte d'Ivoire,

Liberia, Sierra Leone and Guinea. However, in these four countries, Bank-financed projects to

improve governance and strengthen capacities are currently being implemented.

Page 26: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

15

4.3.2 In addition to these challenges to good governance in the energy sector, the project also

carries fiduciary risks such as timeliness and transparency in procurement, transparency in financial

management, and possible political interference by the four governments. The institutional framework

for effective implementation of the CLSG Interconnection Project provides for supervisory bodies,

each with a specific role in the financial management of the project, and for the use of the Bank's rules

and procedures. The supervisory bodies are three in number: (i) The Management Committee, which

is the highest body of the Treaty. It considers the Steering Committee's progress report on the

implementation of the Shareholders’ Agreement and approves the budget of the Steering Committee

and the Treaty Secretariat. Its budget is borne proportionally by Member States; (ii) the

implementation Committee, which is the body charged with overseeing the project development and

implementation. It submits to the Management Committee a report on the activities of the Steering

Committee and the Treaty Secretariat, and the estimated operating budget for the following 24

months; (iii) The Treaty Secretariat, which assists the Management Committee and the Steering

Committee in their duties. During the project preparation phase, this role will be performed by WAPP.

4.3.3 The project provides for an audit committee for the Management Committee, an internal

auditor, a legal counsel, technical assistance in procurement, and prior review and approval by the

Bank of all procurement activities. In addition, the project provides for independent external auditors

to carry out financial and technical audits of the project. The legal documents prepared on the project,

such as the International Project Agreement, took into consideration the lessons learned from similar

projects and the provisions on fraud and corruption. The project design also includes the application of

procedures manuals and specific measures for mitigating governance risk so as to ensure that

resources are used efficiently and for their intended purpose.

4.4 Sustainability

4.4.1 The project is technically, economically and financially sustainable.

4.4.2 Country commitment, ownership and policies: The Energy Ministers of Energy of Côte

d'Ivoire, Liberia, Sierra Leone and Guinea issued a release relating to the adoption of the Treaty

establishing the SPC on 5 March 2012. The Treaty was signed by the Heads of State of the four

countries, is currently being ratified by the respective parliaments and is expected to be completed by

end-2013.

4.4.3 Pooling of resources: The project will help to remedy the small size of national markets, and

thereby create a favourable and attractive environment for the private sector to construct major

electricity infrastructures that may be pooled for the benefit of the countries of the Mano River Union

and the sub-region.

4.4.4 Strengthening of national networks: In Sierra Leone and Liberia, the transmission

infrastructure to be constructed under this project will form the backbone of the national transmission

system.

4.4.5 Capacity to construct, operate and maintain the interconnection: The main infrastructure of

the project, particularly the 225-kV power line and associated stations, will be constructed under the

responsibility of the SPC by competent contractors recruited following an international invitation for

bids. The SPC will be supported by a consulting firm in the monitoring and control of the works to

ensure compliance with the specifications and quality of the works to be built. To ensure proper

operation and maintenance of the power line, the CVs of the SCP staff will be subject to the Bank’s

no-objection opinion. The “strengthening of country capacities” component will enable the Energy

Ministries and National Power Corporations (NPCs) to monitor the project implementation. As

regards the infrastructure proposed for the “rural electrification” component, it will be built by

qualified contractors selected on the basis of an international competitive bidding supervised by the

Page 27: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

16

relevant national structures with the skills and experience required for the operation and maintenance

of this type of facilities.

4.4.6 Financial Balance: The Protocol Agreements to be signed between the governments of the

four countries involved in the project will make it possible to set the price of electricity transit at a

minimum level that guarantees the financial stability of the SPC and enables it to meet its financial

commitments (loan repayment) as well as proper operation, maintenance and renewal of

infrastructure. These agreements must be signed no later than December 2013.

4.4.7 Sector Regulation: The ECOWAS Energy Protocol has established a regulatory framework

for the development of the sector, one of whose objectives is to set up the deregulated and competitive

energy market. The ECOWAS Regional Electricity Regulatory Authority (ERERA) is currently

harmonizing the policies and commercial framework of the sector. These developments will help

regulate the electricity market, including this project.

4.5 Risk Management

4.5.1 The main risks that could hamper implementation of the project and the expected outcomes

are: (i) delays by the governments in ratifying the treaty establishing the SPC; (ii) long timeframes and

delays in the procurement process; (iii) difficulties and/or delays in mobilizing national counterpart

funding which could delay payment of compensation for release of the right-of-way; (iv) poor

performance of the SPC; (v) inadequate national networks from sub-stations for effective consumption

of the traded energy; (vi) inadequate availability of power in Côte d’Ivoire for the country to meet its

own consumption needs and export some to other countries in the short term; (vii) inability of national

electricity corporations to settle their SPC bills; (viii) the plethora of bodies involved in the project

management, particularly the four governments, the four Energy Ministries, and the four National

Power Corporations; (ix) the political risk of the project; (x) the commercial risk related to non-

recovery of transmission bills by the SPC; and (xi) the risk associated with the fragile state of the four

countries.

4.5.2 The first risk is mitigated by the fact that WAPP and the project’s Joint Implementation

Committee are striving to adhere to the project preparation and implementation schedule. The second

risk is mitigated by the fact that the executing agency will be supported by a procurement expert, and

WAPP has requested the Bank to initiate advance procurement action. As for the third risk, it is

mitigated by the relatively small size of the countries’ counterpart funding, which accounts for less

than 10% of the project cost. Furthermore, the Finance Ministries of the four countries were informed

well in advance to take appropriate steps for the budgeting, and they have confirmed their readiness to

secure the resources required to compensate the project-affected persons (PAPs) prior to the start-up

of works. The capacity of national institutions in charge of the implementation of the compensation

plan will also speed up the process for compensation and release of right-of-way. Finally, the

establishment of the Grievance Committee will substantially mitigate this risk in each country. The

fourth risk is mitigated by: (a) the establishment of the Management Committee and the Steering

Committee to monitor the performance of the SPC; and (b) the recruitment of an internal auditor. The

fifth risk is mitigated by the distribution networks rehabilitation and expansion projects in the pipeline

or currently underway in the countries involved, and also by the project’s rural electrification

component. The sixth risk is mitigated by the fact that Côte d’Ivoire has initiated an ongoing program

to boost its production capacity so as to meet domestic demand as well as export to neighbouring

countries, especially CLSG countries; the program comprises the construction of the Ciprel IV, Azito

III and Soubre power plants (see Technical Annex A.1.2). To mitigate the seventh risk, a repayment

accounts will be opened into which some major and reliable customers of National Power

Corporations will pay their bills directly and from which the SPC will be paid for its services. The

eighth risk is mitigated by the fact that the SPC will have ownership of high-voltage power structures

to avoid any interference by the governments in the management of the network. The ninth risk is

mitigated by the collective interests of the various countries in pooling their resources and

Page 28: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

17

infrastructure. The commercial risk is mitigated by the ongoing reforms and measures to improve

recovery in most CLSG countries. Finally, the risk of fragility is mitigated by the intensification of

regional dialogue. The Mano River Union Members States have taken concrete steps that could

contribute to the consolidation of peace at their borders.

4.6 Knowledge Building

4.6.1 By virtue of the special character of the project, stemming from the fact that it will be

implemented in four fragile countries, the Bank will derive practical knowledge from the assessment

of the legal and operational framework established for the project implementation. The legal

documents developed during the project preparation phase will provide the Bank with valuable

information that may be used in the design and implementation of future projects. In addition, the

knowledge learned from the project implementation will focus on best practices on the management of

power transmission projects and the conduct of monitoring and evaluation in a regional context. The

best practices will be disseminated among the stakeholders through regular meetings and briefing

notes issued by the Management Committee. The focus on building the capacities of the entities

involved in the project aims particularly to meet knowledge development needs. Indeed, providing

training and equipment to WAPP and electricity corporations will help ensure the transfer of

knowledge on project management, and especially of similar technologies that may be used for other

projects in the near future.

4.6.2 Establishing the baseline situation before the start of project activities will provide a basis for

comparison and obtaining a realistic assessment of project impacts. Comparison data will be derived

from the project outcome assessment conducted at project completion. The main knowledge and

lessons learned will be managed from a relational database at the SPC. This database will effectively

facilitate the management of accumulated knowledge on the activities, outputs, major outcomes and

lessons learned from this project. Abstracts will be posted on the Bank's website.

V. LEGAL FRAMEWORK

5.1 Legal Instrument

The Fund/Bank will provide financing in the form of grants and loans to the Republics of Côte

d'Ivoire (ADF Grant), Liberia (ADF Loan, FSF Pillar 1 Grant), Sierra Leone (ADF Loan, ADF Grant,

NTF Loan, EU-Africa Infrastructure Trust Fund Grant) and Guinea (ADF Loan, ADF Grant) to

support the implementation of the project and will act as executing agency within the framework of

the grant provided to Sierra Leone by EU- Africa Infrastructure Trust Fund.

5.2 Conditions associated with Bank intervention

A. Conditions precedent to effectiveness of the ADF grants to Côte d'Ivoire, Sierra Leone and

Guinea, the ADF loans to Liberia, Sierra Leone and Guinea, the NTF loan to Sierra Leone,

and the FSF Pillar 1 grant to Liberia

(i) Effectiveness of the ADF and FSF grants shall be subject to the signing of the

respective Protocol Agreements by the parties; and

(ii) Effectiveness of the ADF loans and NTF loan shall be subject to fulfilment, by the

borrowers, of the conditions set forth in Section 12.01 of the General Conditions.

Page 29: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

18

B. Conditions precedent to the first disbursement of the ADF grants to Côte d'Ivoire, Sierra

Leone and Guinea, the ADF loans to Liberia, Sierra Leone and Guinea, the NTF loan to

Sierra Leone, and the FSF Pillar 1 grant to Liberia.

In addition to fulfilling the conditions relating to the effectiveness of the above-mentioned grant and

loan agreements, the borrowers/recipients should fulfil the following the conditions precedent to the

first disbursement:

1. Conditions precedent to first disbursement of the ADF grants, ADF loans, and the NTF loan

on-lent/ on-granted to the Special Purpose Company (SPC) for the construction, operation

and maintenance of the CLSG transmission line and substations

(i) Each State shall provide the Bank/ Fund with evidence of signing an on-lending/

on-granting agreement with the SPC, upon terms and conditions acceptable to the

Fund/Bank ;

(ii) Where applicable, the concerned State shall provide the Bank/Fund with evidence

of the opening, by the SPC, of a special account with a bank acceptable to the

Bank/Fund to receive the funds on-lent/ on granted to the SPC ; and

(iii) The State hosting the SPC Headquarters shall provide the Bank/ Fund with

evidence of: (1) ratification of the Treaty by the CLSG Member States; (2)

evidence that the share capital for the SPC has been paid in full; and (3)

appointment of the manager and of the accountant for the SPC, whose skills and

qualifications are acceptable to the Fund.

2. Conditions precedent to the first disbursement of the ADF grants, the FSF Pillar 1 grant and

the ADF loans on-lent/ on-granted to the national electricity corporations (NECs) for

management of the rural electrification component

(i) Each State shall provide the Bank/ Fund with evidence of signing an on-lending/on-

granting agreement with the relevant NEC upon terms and conditions acceptable to

the Fund/Bank ; and

(ii) Each State shall provide the Bank/ Fund with evidence of opening of a special

account with a bank acceptable to the Bank/ Fund to receive the portion of the

Loan/ Grant to be on-lent/ on-granted to the relevant NEC.

3. Conditions precedent to the first disbursement of the ADF grants on granted to WAPP for the

management of capacity building activities

(i) Côte d'Ivoire, Sierra Leone and Guinea shall provide the Fund with evidence of signing

an on-granting agreement with WAPP upon terms and conditions acceptable to the

Fund ; and

(ii) The above-mentioned three States shall provide the Fund with evidence of the opening

by WAPP of a special account in a bank acceptable to the Fund to receive the on-

granted resources.

C. Other conditions relating to the ADF grants and loans, and the NTF loan

(i) Liberia shall submit to the Bank, not later than 20 June 2014, the agreements on the

funding of the Project by the World Bank and KfW;

Page 30: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

19

(ii) Sierra Leone shall submit to the Bank, not later than 30 June 2014, the agreement on

the funding of the Project by the EIB;

(iii) Each State shall, prior to commencement of works on its territory, provide evidence of:

(i) acquisition of land and/ or compensation of the Project Affected Persons (PAPs) in

each concerned lot, in compliance with the Bank rules and procedures and of the

ESMP; and / or (ii) provide evidence of having an escrow account and deposited

resources earmarked for the compensation of the PAPs that have not yet been

compensated, in accordance with the Environmental and Social Management Plan and

the Compensation Payment Schedule;

(iv) The State hosting the SPC Headquarters shall: (i) submit to the Bank/Fund a copy of

the International Project Agreement signed between the CLSG Member States and the

SPC, whose terms and conditions are acceptable to the Bank/Fund; (ii) a copy of the

Shareholders’ Agreement signed between the NECs; and (iii) preparation of the SPC

organization chart and adoption of the Project Implementation Manual and financial

manual by the SPC, within six months from the date of first disbursement; and

(v) Each state shall provide evidence of appointment of an accountant and an assistant

account at the Project Implementation Unit (PIU) of the relevant NEC, whose

qualifications are acceptable to the Bank/Fund.

D. Undertakings. Each State undertakes to:

(i) Implement and report on implementation of the Environmental and Social Management

Plan (ESMP) and the updated RAP on a semi-annual basis, no later than 30 days at the

end of each reporting period, in a form acceptable to the Fund/ Bank; and

(ii) Prior to commencement of works, submit an Environmental and Social Management

Framework for the rural electrification component of the Project.

5.3 Compliance with Bank policies

This project complies with all the applicable Bank policies.

VI. RECOMMENDATIONS

Management recommends that the Board of Directors approve:

i. A waiver to the application of Article 17 (1) (d) of the Agreement Establishing the

Bank and Article 4.3 of the Agreement Between the Federal Republic of Nigeria and

the African Development Bank for the Establishment of the Nigeria Trust Fund, to

permit procurement of goods, works and services, using the resources of the NTF, to

be open to countries that are not member countries of the Bank, provided however, that

other than as provided in this paragraph, the Rules and Procedures for the Procurement

of Goods and Works and the Rules of Procedures for the Use of Consultants shall

remain applicable and

Page 31: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

20

ii. The proposed financing of the Project, under the conditions set forth in this report, and

as follows:

(a) a FSF Pillar 1 grant amounting to UA 1.12 million to the Republic of Liberia,

(b) a NTF loan amounting to USD 10 million to the Republic of Sierra Leone

(c) an ADF loan amounting to UA 14.50 million to the Republic of Sierra Leone;

(d) an ADF loan amounting to UA 24.94 million to the Republic of Liberia;

(e) an ADF loan amounting to UA 28.91 million to the Republic of Guinea;

(f) an ADF grant amounting to UA 33 million to the Republic of Côte d'Ivoire;

(g) an ADF grant amounting to UA 7.12 million to the Republic of Sierra Leone;

(h) an ADF grant amounting to UA 11.89 million to the Republic of Guinea;

Page 32: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX I

Page 1/4

YearCôte

d'IvoireAfrica

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 322 30 323 98 458 35 811Total Population (millions) 2012 20,6 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 52,1 40,8 46,0 75,7Population Density (per Km²) 2012 62,5 34,5 70,0 23,4GNI per Capita (US $) 2011 1 100 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 37,8 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 38,2 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,468 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 168 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2011 23,8 40,0 22,4 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 2,2 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 3,6 3,4 2,3 0,7Population < 15 y ears (%) 2012 40,3 40,0 28,5 16,6Population >= 65 y ears (%) 2012 3,9 3,6 6,0 16,5Dependency Ratio (%) 2012 79,3 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 103,5 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 23,6 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 56,0 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 57,3 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 33,2 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 11,4 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 69,7 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 108,7 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 4,3 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 400,0 417,8 230,0 13,7Women Using Contraception (%) 2012 21,0 31,6 62,4 71,4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 14,4 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 48,3 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2006-2010 56,8 53,7 65,4 ...Access to Safe Water (% of Population) 2010 80,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 1988 60,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 24,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 3,0 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 327,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 74,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 49,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2007-2011 29,4 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 670 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 4,7 5,9 2,9 8,2

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2012 88,0 101,9 103,1 106,6 Primary School - Female 2010-2012 80,0 98,4 105,1 102,8 Secondary School - Total 2002-2012 27,1 42,3 66,3 101,5 Secondary School - Female 2002-2012 19,4 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 27,0 43,2 58,6 80,0Adult literacy Rate - Total (%) 2010 56,2 67,0 80,8 98,3Adult literacy Rate - Male (%) 2010 65,2 75,8 86,4 98,7Adult literacy Rate - Female (%) 2010 46,6 58,4 75,5 97,9Percentage of GDP Spent on Education 2008-2011 4,6 5,3 3,9 5,2

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 9,1 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 3,1 0,6 0,4 -0,2Forest (As % of Land Area) 2011 32,7 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,3 1,2 3,1 11,4

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Côte d'Ivoire

May 2013

60

65

70

75

80

85

2004

2005

2006

2007

2008

2009

2010

2011

2012

Infant Mortality Rate( Per 1000 )

Côte d'Ivoire Africa

0

200

400

600

800

1000

1200

1400

1600

1800

2003

2004

2005

2006

2007

2008

2009

2010

2011

GNI Per Capita US $

Côte d'Ivoire Africa

0,0

0,5

1,0

1,5

2,0

2,5

2004

2005

2006

2007

2008

2009

2010

2011

2012

Population Growth Rate (%)

Côte d'Ivoire Africa

1

11

21

31

41

51

61

71

2004

2005

2006

2007

2008

2009

2010

2011

2012

Life Expectancy at Birth (years)

Côte d'Ivoire

Africa

Page 33: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX I

Page 2/4

Year Liberia Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 111 30 323 98 458 35 811Total Population (millions) 2012 4,2 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 48,6 40,8 46,0 75,7Population Density (per Km²) 2012 37,1 34,5 70,0 23,4GNI per Capita (US $) 2011 240 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 33,4 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 47,6 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,430 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 174 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2007-2011 83,8 40,0 22,4 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 2,8 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 3,6 3,4 2,3 0,7Population < 15 y ears (%) 2012 43,5 40,0 28,5 16,6Population >= 65 y ears (%) 2012 2,8 3,6 6,0 16,5Dependency Ratio (%) 2012 86,0 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 101,2 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 23,4 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 57,3 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 58,4 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 37,9 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 10,3 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 77,2 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 108,0 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 5,1 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 770,0 417,8 230,0 13,7Women Using Contraception (%) 2012 14,2 31,6 62,4 71,4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 1,4 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 27,4 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2007-2010 46,3 53,7 65,4 ...Access to Safe Water (% of Population) 2010 73,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 2000 39,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 18,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 1,0 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 299,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 73,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 40,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2007-2011 20,4 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 261 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 3,9 5,9 2,9 8,2

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2012 103,0 101,9 103,1 106,6 Primary School - Female 2010-2012 98,2 98,4 105,1 102,8 Secondary School - Total 2010-2012 44,8 42,3 66,3 101,5 Secondary School - Female 2010-2012 40,2 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 13,9 43,2 58,6 80,0Adult literacy Rate - Total (%) 2010 60,8 67,0 80,8 98,3Adult literacy Rate - Male (%) 2010 64,8 75,8 86,4 98,7Adult literacy Rate - Female (%) 2010 56,8 58,4 75,5 97,9Percentage of GDP Spent on Education 2008 2,7 5,3 3,9 5,2

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 4,7 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 2,0 0,6 0,4 -0,2Forest (As % of Land Area) 2011 44,6 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,1 1,2 3,1 11,4

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Liberia

May 2013

0

20

40

60

80

100

120

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Infant Mortality Rate( Per 1000 )

Liberia Africa

0

200

400

600

800

1000

1200

1400

1600

1800

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

GNI Per Capita US $

Liberia Africa

0,0

1,0

2,0

3,0

4,0

5,0

6,0

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Population Growth Rate (%)

Liberia Africa

1

11

21

31

41

51

61

71

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Life Expectancy at Birth (years)

Liberia Africa

Page 34: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX I

Page 3/4

YearSierra

LeoneAfrica

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 72 30 323 98 458 35 811Total Population (millions) 2012 6,1 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 39,1 40,8 46,0 75,7Population Density (per Km²) 2012 83,6 34,5 70,0 23,4GNI per Capita (US $) 2011 340 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 38,0 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 50,9 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,354 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 177 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2003-2011 53,4 40,0 22,4 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 2,1 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 3,1 3,4 2,3 0,7Population < 15 y ears (%) 2012 42,8 40,0 28,5 16,6Population >= 65 y ears (%) 2012 1,9 3,6 6,0 16,5Dependency Ratio (%) 2012 80,8 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 95,7 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 24,8 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 48,1 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 48,8 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 37,0 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 15,0 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 104,0 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 157,9 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 4,8 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 890,0 417,8 230,0 13,7Women Using Contraception (%) 2012 21,5 31,6 62,4 71,4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 1,6 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 16,8 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2008-2010 42,4 53,7 65,4 ...Access to Safe Water (% of Population) 2010 55,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 2000 38,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 13,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 1,6 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 723,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 96,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 80,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2008-2011 21,3 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 162 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 13,1 5,9 2,9 8,2

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2012 124,7 101,9 103,1 106,6 Primary School - Female 2010-2012 120,1 98,4 105,1 102,8 Secondary School - Total 2001-2012 27,6 42,3 66,3 101,5 Secondary School - Female 2001-2012 22,5 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 25,1 43,2 58,6 80,0Adult literacy Rate - Total (%) 2010 42,1 67,0 80,8 98,3Adult literacy Rate - Male (%) 2010 53,6 75,8 86,4 98,7Adult literacy Rate - Female (%) 2010 31,4 58,4 75,5 97,9Percentage of GDP Spent on Education 2008-2011 3,6 5,3 3,9 5,2

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 15,4 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 2,9 0,6 0,4 -0,2Forest (As % of Land Area) 2011 37,8 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,2 1,2 3,1 11,4

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Sierra Leone

May 2013

0

20

40

60

80

100

120

140

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Infant Mortality Rate( Per 1000 )

Sierra Leone Africa

0

200

400

600

800

1000

1200

1400

1600

1800

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

GNI Per Capita US $

Sierra Leone Africa

0,00,51,01,52,02,53,03,54,04,55,0

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Population Growth Rate (%)

Sierra Leone Africa

1

11

21

31

41

51

61

71

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Life Expectancy at Birth (years)

Sierra Leone

Africa

Page 35: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX I

Page 4/4

Year Guinea Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2011 246 30 323 98 458 35 811Total Population (millions) 2012 10,5 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 36,4 40,8 46,0 75,7Population Density (per Km²) 2012 41,6 34,5 70,0 23,4GNI per Capita (US $) 2011 440 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 39,7 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 45,2 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,425 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 178 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2007-2011 43,3 40,0 22,4 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2012 2,5 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 4,0 3,4 2,3 0,7Population < 15 y ears (%) 2012 42,6 40,0 28,5 16,6Population >= 65 y ears (%) 2012 3,3 3,6 6,0 16,5Dependency Ratio (%) 2012 85,0 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 102,2 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 23,1 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 54,5 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 56,2 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 37,9 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 12,5 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 85,0 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 135,4 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 5,1 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 610,0 417,8 230,0 13,7Women Using Contraception (%) 2012 12,2 31,6 62,4 71,4

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2010 10,0 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 4,3 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2007-2010 46,1 53,7 65,4 ...Access to Safe Water (% of Population) 2010 74,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 2000 80,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 18,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 1,4 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 183,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 93,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 58,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2008-2011 20,8 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 652 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 4,8 5,9 2,9 8,2

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2012 98,0 101,9 103,1 106,6 Primary School - Female 2010-2012 90,9 98,4 105,1 102,8 Secondary School - Total 2010-2012 41,7 42,3 66,3 101,5 Secondary School - Female 2010-2012 32,4 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 29,2 43,2 58,6 80,0Adult literacy Rate - Total (%) 2010 41,0 67,0 80,8 98,3Adult literacy Rate - Male (%) 2010 52,0 75,8 86,4 98,7Adult literacy Rate - Female (%) 2010 30,0 58,4 75,5 97,9Percentage of GDP Spent on Education 2008-2011 3,1 5,3 3,9 5,2

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 11,6 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 0,5 0,6 0,4 -0,2Forest (As % of Land Area) 2011 26,5 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,1 1,2 3,1 11,4

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Guinea

May 2013

0

20

40

60

80

100

120

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Infant Mortality Rate( Per 1000 )

Guine a Africa

0

200

400

600

800

1000

1200

1400

1600

1800

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

GNI Per Capita US $

Guine a Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Population Growth Rate (%)

Guinea Africa

1

11

21

31

41

51

61

71

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

Life Expectancy at Birth (years)

Guine a Africa

Page 36: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX II

Page 1/2

Table of ADB Portfolio in the Countries

COTE D’IVOIRE:

Project Type Approval Date Closing Date Amount

(in UA)

Disburseme

nt Rate

Ratin

g Age

AZITO Extension Loan 19.12.2012 27.02.2020 32,577,322 0%

Not

rated 0

Henri Konan BEDIE Toll Bridge Loan 03.2012 31.12.2020 50,107,990 29.59 %

Non PP

1

Agricultural Infrastructure Support Project in

Indénié-Djuablin Region Grant 03.2012 28.02.2018 21,600,000

7.31 %

Non

PP 1

Emergency Program to Restore Basic Social and

Administrative Services (PURSSAB).

Grant 03.06.2011

31.12.2011 60,000,000 100%

Non

PP 2

9.03.2013 5,500,000 30.13 %

31.12.2011 11,900,000 100%

31.12.2011 23,100,000 100%

Guru Integrated Watershed Management Project Grant 24.11.2010 31.12.2014 23,000,000 3.30 % Non

PP 3

MicroCred Côte - D’Ivoire Grant 04.2010 11.06.2013 . 950,323 0

Non PP

3

Targeted Support and Capacity Building Project Grant 01.03.2010 2,000,000 60 %

Non

PP 3

Post-Crisis Multi-sector Institutional Support Project. Grant 05.12.2007 31.08.2013 20,000,000 97.27

Non

PP 6

Grand Total – 8 projects 250,735,635 25 %

7

Non

PP

LIBERIA

Project Type Approval

Date

Closing

Date

Amount

(in UA

million)

Disbursement

Rate Rating Age

Urban Water and Sanitation Project Loan 05.2013 06.2015 26.09 3% Non PP 0

Fostering Innovative Sanitation and Hygiene in

Monrovia (FISH) Loan 01.2013 12.2015 0.71 0% Not rated 0

Rural Water Supply Sanitation and Hygiene Program Study

Loan 10.2012 02.2014 0.91 0% Not rated 0.5

Total Water and Sanitation 27.71 3

Equity in Access Bank (and supplementary Equity) Loan 04.2008/12.2012

10.2008 6.00 86% Non PP 5

Payments System Development Project (Liberia,

The Gambia, Guinea, S. Leone) Loan 11.2010 02.2011 5.00 5% Non PP 2.5

Total Finance and Banking Sector 11.00 45

Economic Governance and Competitiveness Support Program

Loan 06.2011 12.2011 30 47% Non PP 2

Integrated Public Financial Management Reform

Project Loan 09.2012 06.2016 3 17.5% Not Rated 1

Capacity Building from Fragile States Fund (LEITI, Dogliotti School, PFM)

Loan 04.2009 12.2013 1.11 82 Non PP 4

Support to Liberia Institute for Public

Administration Loan 05.2007 1.2012 66 80% Not Rated 6

Total Governance 100.1 55%

Agriculture Sector Rehabilitation Project Loan 04.2009 03.2010 12.50 36% Non PP 4

Smallholder Agriculture Productivity Enhancement

and Commercialization Loan 05.2012 12.2017 33.80 0% Not Rated 1

Total Agriculture and Rural Development 46.30 10%

ECOWAS for Peace and development. Project

(Guinea Guin. Bissau, Lib, SL) Loan 09.2004 06.2013 10 79% PP 9

Labour-Based Public Works Project Loan 12.2007 12.2015 15.24 84% Non PP 6

Page 37: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX II

Page 2/2

Suppl. Grant to Labour-Based PWP Loan 06.2011 12.2015 5 19% Non PP 2

Total Social Infrastructure 30.24 60

GRAND TOTAL – 13 Ongoing Projects

144 30 % 1 PP

8 Non PP

SIERRA LEONE

Project Type Date Closing Date Amount

(in UA)

Disburseme

nt Rate

Ratin

g Age

Port Loko - Lungi Road Upgrading Loan 06.2009 12.2013 26,260,000 40%

Non PP

4

Matotoka – Sefadu Road Loan 07.2012 06.2016 22,000,000 0%

Not

Rated 1

Agriculture Sector Rehabilitation Loan 08.2005 12.2012 12 000 000 30% PPP 8

ADDAX Bio Energy Loan 12.2011 12.2023 20,627,233 75%

Non

PP 2

PFM and Business enabling support Loan 11.2011 12.2014 4,000,000 13.4% 2

Support District Health Services Loan 10.2005 12.2012 17,000,000 71%

Non PP

8

Three Towns Water Project Loan 12.2010 12.2015 22,400,000 24%

Non

PP 3

Support to Teachers Record Management Loan 03.2011 10.2012 1 ,23,750 70%

Non

PP 3

Financial Sector Development Loan 06.2012 12.2013 807,018 0%

Not rated

1

Grand Total – 8 Projects 126,418,001 38%

5

Non

PP

GUINEA

Project Type Approval

Date Closing Date

Amount

(in UA

million)

Disbursement

Rate

Performa

nce Rating Age

REHABILITATION OF TOMBO-AEROP.

GBESSIA TWO-LANE HIGHWAY Grant 13.07.05 30.06.12 8.25 66.09 2.01 PPP 8.4

GUINEA – SUPPLEMENTARY GRANT Grant 29.04.09 30.11.12 5.17 58.78 - Not rated 6.6

REHABILITATION ELECTRICAL NETWORKS Grant 29.10.08 31.12.12 12.00 69.03 2.26 Non PP 2.8

RURAL ELECTRIFICATION PROJECT Grant 21.01.11 31.12.13 14.96 1.08 2.36 Non PP 3.3

STUDY ON GUINEA-MALI LINE Grant 12.01.11 31.12.15 1.667 0.00 - Not rated 1.1

Total Infrastructure/Energy 42.047 42.10 2.21

Education IV Grant 13.07.05 30.11.12 14.00 85.35 2.0 Non PP 6.6

PDSD HTE & M. GUINEA PHASE II Grant 09.02.11 31.12.13 5.00 33.04 2.78 Non PP 1.1

Total Social Sector 19.00 73.53 2.39

ECONOMIC AND FINANCIAL MANAGEMENT

CAPACITY BUILDING SUPPORT PROJECT (PARCGEF)

Grant 31.01.11 31.12.14 7.544 11.05 2.48 Non PP 1.1

SUPPORT FOR THE NATIONAL STATISTICAL

DEVELOPMENT STRATEGY Grant 30.06.11 31.12.13 1.136 60.00 - Not Rated 0.7

SUPPORT FOR PRSP III PROCESS Grant 27.06.11 30.06.13 1.337 60.00 2.31 Non PP 0.7

Total Multi-Sector 10.017 27.71 2.49 3 NR

GRAND TOTAL – 11 Ongoing Projects 71.064 48.48 % 2.61 1 PPP

7 Non PP

Page 38: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX III

Page 1/3

Key Related Projects Financed by the Bank and Other Development Partners in the

Countries

COTE D’IVOIRE

No. Project Description Source of

Financing

Financing Cost

(CFAF thousand) Year of Agreement

Year of Expiry of

Loan Agreement

1

Transmission and Distribution

Network Rehabilitation Project

(FDE)

BOAD

28,922,000 2012 2013

2

Transmission and Distribution

Network Rehabilitation Project

(BOAD1)

28,241,000 2012 2013

3

Transmission and Distribution

Network Rehabilitation Project

(BOAD2)

28,522,000 2012 2015

4

Emergency Program (PURE4):

Rural electrification covering 107

localities in the South-East

European

Union

10,338,544 2012 2014

5

Rural electrification covering 23

localities in the Centre-West and

North-West

9,712,552 2012 2014

6 Cross-border electrification: 18

localities

6,329,985 2012 2014

7 Electricity Sector Emergency

Rehabilitation Project (PURE) World Bank

25,000,000 2012 2014

8 Rehabilitation of the Soubre

Hydroelectric Plant Exim Bank of

China

33,077,4925 2013 2017

LIBERIA

No. Project Description Source of

Financing Financing Cost Year of Agreement

Year of Loan

Agreement Expiry

1 Catalysing Rural and Renewable

Energy in Liberia

World Bank

USD 3.2 million 2009 2012

2 Liberia Electricity Sector

Enhancement Project USD 10 million 2010 2013

3 Monrovia Improved Access

Project USD 10 million 2011 2014

4 LESEP Additional; Financing USD 23.4 million 2011 2014

5 WAPP CLSG USD 150 million 2012 2017

4

Institutional Capacity Building

and Strengthening of the Energy

and Water Resources in Liberia Government of

Norway

2008 2013

5 Funds for T/D equipment

6 Mount Coffee Rehabilitation USD 70 million 2013 2015

7

Transmission and Distribution in

Monrovia(Co-financed with

Norway) USAID

USD 21 million

8

Rural Energy Program

(Transmission in Sinkov

Monrovia)

USD 1.5 million

Page 39: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX III

Page 2/3

9

BANGA Transmission and

Distribution(Co-financed with

UNIDO)

USD 5.4 million

10 Mt Coffee European Union EUR 40 million 2013 2015

11 Electricity Grid in Monrovia EUR 16 million 2006 2011

12 Cross Border Electrification EUR 9.6 million 06/2008 06/2013

13

Support to Ministry of Health-

sustainable access to energy in

health centres

EUR 1.5 million

08/2011 08/2014

14

Developing demonstrating a rural

energy strategy and Master Plan

RREA

EUR 1.5 million

08/2011 08/2014

15 Mt. Coffee Government of

Germany

EUR 25 million

2013 2015

16 Interconnection Côte d’Ivoire,

Liberia, Sierra Leone and Guinea

EUR 31 million 2013 2018

16 10 MW HFO Plant JICA USD 30 million

2012 2015

SIERRA LEONE

No. Project Description Source of

Financing

Financing Cost

(Net of Taxes)

Year of

Signature of

Agreement

Year of Expiry

of Loan

Agreement

1 Technical Assistance

World Bank

USD 750,000.00 2012 2013

2

Energy Access Project 1

(Technical assistance and

investment support)

USD 19,500,000

2012 2016

3

Energy Access Project 2

(Technical assistance and

investment support)

USD 25,000,000

(tbc) 2013 2017

4

WAPP Integration and

Technical Assistance

Project),sub-program of the

WAPP APL program

USD 176,000,000

2012 2017

5 Transmission and

Distribution Networks EU

EUR 10,00,000

2009 2013

6 Solar PV panels EUR 2,200,000 2011 2014

7

Capacity building for

maintaining power supply

facilities

JICA USD 4,125,000 2010 2013

Page 40: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX III

Page 3/3

GUINEA

No. Project Description Source of

Financing

Financing

Cost (in

million)

Currency

Year of

Signing of

Agreement

Year of Expiry

of Loan

Agreement

1 Improvement of energy sector

efficiency (PAESE) World Bank 37.30 USD 2006 2014

Decentralized rural

electrification World Bank 4.10 USD 2002

Implemented in

full

2

Rehabilitation and Extension

of Electrical Grids in Conakry

(PREREC 1)

ADF 12.00 UA 2008 2013

3 Rural Electrification (REP) ADF 14.96 UA 2011 2015

Study on Guinea-Mali

Interconnection Line ADF 1.66 UA 2011 2015

6

Rehabilitation and Extension of

Electrical Grids in Conakry

(PREREC 1)

IDB 11.50 USD 2008 2013

Rehabilitation of Tombo power

stations IDB 17.47 USD 2012 2015

Rehabilitation of the grids of 4

regional capitals EBID 30.00 USD 2008 2015

Rehabilitation of power plants ECOWAS

Commission 10.00 USD 2011 2016

Procurement of fuel oil and

spare parts ECOWAS

Commission 20.00 USD 2011 2015

Studies and capacity building

Fund for the energy sector

French

Development

Agency

1.00 EUR 2012 2014

Rehabilitation of Kaléta

Hydroelectric Plant Eximbank China 334.50 USD 2012 2015

Page 41: Multinational - Côte d’Ivoire-Liberia-Sierra Leone and ... · PDF fileTranslated Document AFRICAN DEVELOPMENT BANK GROUP PROJECT : CÔTE D’IVOIRE, ... inlcuding Active Participation

ANNEX IV

Page 1/1

MAP OF COTE D’IVOIRE, LIBRIA SIERRA LEONE AND GUINEA

INTERCONNECTION PROJECT