multidisciplinary engineering senior design project 05002 micro turbine iii 2005 critical design...

47
Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering Department Team Members: Cliff Cummings Allison Studley Joe Calkins Mark Fazzio Team Mentor: Dr. Jeff Kozak Acknowledgements: Jon Ross, Dr. Fuller, John Bonzo, Borce Gorevski, Dave Hathaway Kate Gleason College of Engineering Rochester Institute of Technology

Post on 21-Dec-2015

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Multidisciplinary Engineering Senior Design

Project 05002 Micro Turbine III2005 Critical Design Review

May 13, 2001

Project Sponsor:Mechanical Engineering Department

Team Members:Cliff Cummings Allison StudleyJoe Calkins Mark Fazzio

Team Mentor:Dr. Jeff Kozak

Acknowledgements:Jon Ross, Dr. Fuller, John Bonzo, Borce Gorevski, Dave

Hathaway

Kate Gleason College of EngineeringRochester Institute of Technology

Page 2: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Background

• Current battery technology causes the battery to be up to half of the weight of the MAV.

• Research into lighter weight power generation methods led to micro-turbine generators.

• Third generation RIT Senior Design project

05002 Micro Turbine III Senior Design

Page 3: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Mission Statement

We will design and build a microturbine generator that can be integrated onto a micro air vehicle airframe and power the vehicle’s accessories. The microturbine will be a continuation of the previous team’s project with the application of their design to be used for MAV power production.

05002 Micro Turbine III Senior Design

Page 4: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Primary Objectives

• Produce a minimum constant 5 watts of power• Minimum flight time of 3 minutes• Overall weight of less than 45 grams• Integrated onto the MAV airframe

05002 Micro Turbine III Senior Design

Page 5: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Research Methods

• Preliminary Research

• Review of last year’s design

• Additional Research

05002 Micro Turbine III Senior Design

Page 6: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Feasibility Assessment

Last Year's Design 2 Inlet 2 Outlet ConceptCost 3 2Size 3 2Weight 3 3Availability 3 3Manufacturability 3 2

Average 3.00 2.40Normalized Average 1.00 0.80

• 2 Options – Direct Comparison

• >2 Options – Weighted ComparisonWeighting Air Bearings Magnetic Bearings Axial Bearings Radial Bearings

Cost 0.2 4 4 3 2Size 0.1 5 5 2 2Weight 0 3 3 3 3Availability 0.35 5 5 2 2RPM Rating 0.35 2 2 3 3

Weighted Average 3.75 3.75 2.55 2.35Normalized Average 1.25 1.25 0.85 0.78

05002 Micro Turbine III Senior Design

Page 7: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Feasibility Assessment

Considerations• Ability to meet the objectives• Overall Size• Total Weight• Availability of procured items• Ease of Manufacture• Cost of procurement/manufacture

05002 Micro Turbine III Senior Design

Page 8: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Efficiencies and Costs• 2-D Pelton Wheel

– Typically 15% efficient – Approx. $100

• 3-D Pelton Wheel– Approx. 80% efficient– Estimated above $1,000

• Axial Impulse (Katholieke University, Belgium)– Approx. 20% (for mechanical, 10% total)– Over $1,000

• Francis (large scale turbine)– 80-90%

05002 Micro Turbine III Senior Design

Page 9: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Turbine Feasibility

05002 Micro Turbine III Senior Design

Page 10: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Housing Concept• Cross flow design• 2 Inlets – 2 Outlets• Tight tolerances to prevent

flow from going around the turbine.

• 30% Fiberglass reinforced Nylon material

• Overall Size: 1.25” OD

0.6” Depth

05002 Micro Turbine III Senior Design

Page 11: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Housing Design• Cross flow design at 45o

• 2 Inlets – 2 Outlets• 0.005” – 0.010” tolerances on

all critical diameters.• 30% Fiberglass reinforced

Nylon material• Overall Size: 1.25” OD

0.75” Depth

05002 Micro Turbine III Senior Design

Page 12: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Housing Feasibility• Smaller OD ( 1.25” vs. 1.875” )

• Lighter weight ( 15g vs. 30g )

• O-Ring seal vs. Gasket seal

• Inlet/Outlet redesign

• Designed for manufacturability

05002 Micro Turbine III Senior Design

Page 13: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Housing Analysis

05002 Micro Turbine III Senior Design

Load: 300 psi

Maximum Stress: 1921.75 psi

Safety Factor: 10.49

Page 14: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Housing Analysis

05002 Micro Turbine III Senior Design

Load: 300 psi

Maximum Stress: 4130.67 psi

Safety Factor: 4.88

Page 15: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Propellant System Feasibility

Fuel• Compressed CO2 Cartridges• Compressed N2 Cartridges• Compressed Air TanksTubing• Flexible Nylon lines• Rigid metal linesRegulator• Bellows regulator to decrease

the inlet pressure• Micro nozzle to maintain a

choked flow• Pressure Regulator• Piercing device

05002 Micro Turbine III Senior Design

Page 16: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Other Design Concepts/Considerations

• Bearings: Sealed Air Shielded Magnetic

• Seals: Neoprene O-Ring at 40% compression Paper / Cork Gasket

05002 Micro Turbine III Senior Design

Page 17: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Safety Precautions

• “Safety Box” for protection during preliminary testing

• Mount for fuel canister during prototype testing– (picture)

05002 Micro Turbine III Senior Design

Page 18: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Prototype Financial Analysis

05002 Micro Turbine III Senior Design

Part Price per Qty Line Price

Turbine $96.00 1 1 $96.00

Housing Material $5.78 foot 0.08 $0.48

Shaft $4.64 1 1 $4.64

O - Ring $8.25 50 1 $0.17

Bearings $5.00 1 2 $10.00

Tape $0.97 1 0.25 $0.24

Housing Connections $24.15 1 1 $24.15

Flow Split $18.44 1 2 $36.88

Tubing $0.71 1 1 $0.71

Nozzle free 1 1 $0.00

Fuel $18.15 1 1 $18.15

Puncture Device $22.15 1 1 $22.15

Fuel Connections (Puncture device to Regulator) $6.20 1 1 $6.20

Regulator $207.55 1 1 $207.55

      Overall Cost $427.32

Page 19: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Overall Financial Analysis

05002 Micro Turbine III Senior Design

Page 20: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Schedule

05002 Micro Turbine III Senior Design

Page 21: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Testing• Three main phases of testing:

– Phase 1 (shop air)• Preliminary static testing

– No computer or nozzles

• Preliminary dynamic testing– No nozzles– LabView and DAQ system

– Phase 2 (shop air)• Dynamic testing with nozzles

– Phase 3 (fuel canisters)• Calibrate regulator• Repeat tests on best nozzles

05002 Micro Turbine III Senior Design

Page 22: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Test Setup (Phase 1 & 2)

• Test initially using

laboratory supplied

compressed air to prove feasibility of design (without nozzles)

• Determine which nozzle produces optimal power

• Provide data for mass flow calculations

Incoming Air

Plenum

Turbine System

Flo

w M

eter

Pressure Meter

Thermocouple

Thermocouple

Thermocouple

Oscilloscope

05002 Micro Turbine III Senior Design

Page 23: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Test Setup (Phase 3)

Turbine SystemFuel Canister

Thermocouple

ThermocoupleRegulator

Oscilloscope

• Replace shop air with compressed Nitrogen fuel canisters

• Duplicate test results from preliminary testing

• Prove feasibility of prototype

05002 Micro Turbine III Senior Design

Page 24: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Final Design

05002 Micro Turbine III Senior Design

Page 25: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Final Design

05002 Micro Turbine III Senior Design

Page 26: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Final Design

05002 Micro Turbine III Senior Design

Page 27: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Design Limitations

• Propellant cartridge & piercing device are 250g and 192g respectively

• Pressure regulator is an inefficient way of reducing the pressure from the canisters to the housing

• Miniature sealed bearings were unavailable at the required size

• Shrink tube coupling loses adhesion after extended use at 25,000+ rpm

05002 Micro Turbine III Senior Design

Page 28: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Major Design Issues

• Lead times – Machining of housing and cap– Delivery of turbine and regulator

• Production in a small quantity• Weight of fuel system components

– Canister, piercing device, regulator all greater than 190g each

• Compared to last year, fewer team members and more aggressive goals

05002 Micro Turbine III Senior Design

Page 29: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Analysis of Design• Outlet channels angled 45o to accommodate inlet/outlet

fittings

• Housing components tested using FEA and found to have a minimum SF of 4.88 using Nylon 6/6

• Cap contains the highest stress of the components at 4130 psi under a 300 psi load.

• Mass flow calculations were used to determine a nominal nozzle diameter of 100m

05002 Micro Turbine III Senior Design

Page 30: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Testing Results

• Phase 1– Static (maximum)

• 4.42 watts at about 100 psi and 25,000 rpm

– Dynamic (maximum)• 9.08 watts at 120 psi and 26,300 rpm (5 resistance)• 7.26 watts at 130 psi and 43,000 rpm (8 resistance)

• Phase 2– 100 micron nozzles

• Pending

• Phase 3• Pending

05002 Micro Turbine III Senior Design

Page 31: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Desired Outcomes• Produce 5 watts of power

• Weigh less than 45 g

• 3 minute run time (on N2 canisters)

• Integrate onto MAV airframe

Actual Outcomes• Produced a maximum of

9.08 watts of power

• System weight 48.9 g

• Run time pending final test

• Sized to fit onto MAV (without canisters and regulator)

05002 Micro Turbine III Senior Design

Page 32: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Actual Results• Weight

– 48.9g• Max Power

– 9.08 watts• Run Time

– Pending final test• Cost (for prototype)

– $

Alternative Fuel Sources• Batteries

– Cost ($30 - 50)– Power (10 – 20 watts)– Run time (10 – 30 min)– Weight (30 – 90 g)

• MIT Gas Turbine– Cost ($15 mil budget)– 30+ Faculty– Power (10-50 watts)– Run time (approx. 3 second)– Weight 85g

• Stanford Turbine (still in development)– Cost (?)– Power (designed for 100 watts

at 800,000 rpm, reached 420,000)

– Runtime (designed for 100 hours, reached ?)

– Weight (50 g)

05002 Micro Turbine III Senior Design

Page 33: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Conclusions

05002 Micro Turbine III Senior Design

Page 34: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Future Recommendations

05002 Micro Turbine III Senior Design

Page 35: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Questions?

05002 Micro Turbine III Senior Design

Page 36: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Backup Slides and References

05002 Micro Turbine III Senior Design

Page 37: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Data Acquisition GUI

05002 Micro Turbine III Senior Design

Page 38: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Data Acquisition Set-up

05002 Micro Turbine III Senior Design

Page 39: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

FEA Analysis

05002 Micro Turbine III Senior Design

Page 40: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

FEA Analysis

05002 Micro Turbine III Senior Design

Page 41: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

FEA Analysis

05002 Micro Turbine III Senior Design

Page 42: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Flow Calculations

RTMVexit

RT

Pflowflow

05002 Micro Turbine III Senior Design

Nozzle Exit Velocity:

Flow Density:

Mass Flow: 22 nozzleexitflow AVm

Page 43: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Test Results (Phase 1)

05002 Micro Turbine III Senior Design

Power Output vs. Plenum Pressure

0

1

2

3

4

5

6

7

8

9

10

60 70 80 90 100 110 120 130 140

Plenum Pressure (psi)

Po

wer

(W)

1 ohm

5 ohm

8 ohm

100 ohm

Page 44: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Housing Post-Machining

• Main Housing– Had to machine inlet and outlet holes separately– Deburr housing after CNC machining– Bearing holes were too small due to limited tooling– Turbine seat was not concentric due to CNC tooling

path

05002 Micro Turbine III Senior Design

Page 45: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Preliminary Budget05002 Micro-Turbine III Project

Component Description Price per Qty Line PriceHousing Turbine $96.00 1 2 $192.00

Nylon rod $5.97 foot 1 $5.97machining $10.00 1 1 $10.00fittings $1.00 1 4 $4.00bearings $40.00 10 10 $40.00coupling $14.09 10 10 $14.09Mini Stainless Steel Shaft $3.93 1 1 $3.93O-Ring $4.00 100 100 $4.00Nylon cheese head screw $5.60 100 100 $5.60black nylon 6/6 nut $10.00 100 10 $1.00

Fuel Systems Ni Canisters $20.00 1 2 $40.00Connector $0.62 1 2 $1.24O-Ring $7.50 1 2 $15.00Puncture components $20.00 1 2 $40.00Jets $100.00 50 50 $100.00

Electrical Generator $200.00 1 1 $200.00

Overall Cost $676.83

Final Budget

05002 Micro Turbine III Senior Design

Page 46: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Previous Design

Back

05002 Micro Turbine III Senior Design

Page 47: Multidisciplinary Engineering Senior Design Project 05002 Micro Turbine III 2005 Critical Design Review May 13, 2001 Project Sponsor: Mechanical Engineering

Previous Turbine DesignSenior Design Team 04013

05002 Micro Turbine III Senior Design