Page 1:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

www.zueblin.de

5D @ STRABAG | ZÜBLIN 5D Initiative, BIM, 5D Design Konstantinos Kessoudis

Page 2:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

2 © Ed. Züblin AG (05/2012)

STRABAG SE GROUP

Transportation

infrastructures

Building Construction

and Civil Engineering

Special Divisions &

Concessions

Chief brands Operational

Central Staff Units

Central Service Companies

LEGAL

AFFAIRS

CONTRACT

MANAGEMENT

AUDIT

DEPARTMENT

1) 2) 3) 4)

1)BRVZ Bau- Rechen- und Verwaltungszentrum 2)BMTI Baumaschinentechnik International 3)BLT Baulogistik und Transport 4)TPA Gesellschaft für Qualitätssicherung und Innovation

OVERVIEW

Page 3:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

3 © Ed. Züblin AG (05/2012)

CENTRAL TECHNICAL DEPARTMENT

TECHNICAL KNOW-HOW AT OUR FINGERTIPS

technical support for all Group divisions in winning and executing contracts

research, development and innovation

training, transfer of know-how, creation of tools and materials

public relations, talks and presentations, association and committee work

1 central department, 5 sub-divisions, 12 business units, 32 departments,

500 employees in 9 locations

Subdivisions

Central Technical Department (ZT)

Turnkey

Construction

Construction

Engineering

Ground

Eng./Tunnelling

ZT Vienna TGA Vienna

OVERVIEW

Page 4:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

4 © Ed. Züblin AG (05/2012)

5D DEPARTMENT

Definition of 5D

Development of methods of operation for defined 5D work steps

software, methods, tools

Implementation of 5D work step in selected projects

Definition of 5D work step as standard

process

Training of operational units in 5D methods

Implementation phase: 5D department supervision

to assure 100% performance even on the first project

Hotline and backup for operational units

BIM

-An

teil d

es P

roje

kts

Zeit

100%

Zusammen leisten 5D

und eigene Abteilung

immer 100% der

Projekte

5D

Eigene

Abteilung

Projekt 1 Projekt 2 Projekt 35D

perf

orm

ance

project 1 project 2

time

project 3

department

to be trained

OVERVIEW

Page 5:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

5 © Ed. Züblin AG (05/2012)

OVERVIEW

MOTIVATION FOR 5Di COLLABORATION

IMPORTANCE OF ZÜBLIN'S 5Di USE CASE

CURRENT SERVICES OF 5D

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

EXAMPLE 2: 5D "FROM SCRATCH"

OVERVIEW

Page 6:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

6 © Ed. Züblin AG (05/2012)

Processes

Project

Development& budget planningfeasibility studies

Co

ns

tru

cti

on

pro

jec

t ti

melin

e

Technical

Designconstruction

methods

sequencing &

scheduling

construction

site

planning

cost

estimation

technical

presentation

validation of

design concepts &

alternatives

Work

Preparationdetailed design

issued for construction

detailed sequencing /

scheduling

detailed site

installationbudgeting

construction

method

statements

Constructionquality assurance

& control

(de-)mobilisation

planning,

logistics, HRM

progress

monitoring

cost

controlprocurement

management of

design changes

Facility

Management

asset management,

material &

equipment lists

operation &

maintenance

costs of

utilisationmarketing

as-built

model

design concept marketing & CRM

5Di Process Managementdirect communication on model and database

Op

era

tio

nal

Dat

alis

tin

gs /

an

alys

is

5Di Modeller3D / object oriented / parametric

5Di Viewernative interface to 2D/3D/database

5Di Expert Systemsstructural / MEP / estimation /

simulation / scheduling /ERP / etc.

5Di Data Management

2D

Dra

win

gsar

chit

ectu

ral /

str

uct

ure

/ e

tc.

graphics-driven database-driven

5Di – COLLABORATION IN DEVELOPMENT AND

IMPLEMENTATION

company implementation knowledge

guidelines

structure

knowledge on processes linkage

templates quality control

training concept knowledge on hard- and software

IT-platform processes

5Di MOTIVATION

Page 7:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

7 © Ed. Züblin AG (05/2012)

5Di – COLLABORATION IN DEVELOPMENT AND

IMPLEMENTATION

company implementation knowledge

guidelines

structure

knowledge on processes linkage

templates quality control

training concept knowledge on hard- and software

IT-platform processes

The industry challenge for process integration, is a challenge we share with other construction companies within 5Di

the overall goal is too big for one company to describe it for the software industry

software industry needs to understand the “overall goal” and the variety of implementation strategies in construction to develop sustainable 5D solutions

we participate within 5Di to define our most critical requirements to software partners

we profit from partners covering other critical focus points

assurance of our investments in software, company methods and training the company implementation is structurally compatible to other companies' solutions not developing an “5D-island”

5Di MOTIVATION

Page 8:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

8 © Ed. Züblin AG (05/2012)

5Di USE CASE MODEL BASED ESTIMATION

Building Process Integration – Systems Engineering and BIM / Client

Requirements Processing

Manage Change – Change Δ Managed

Design to Fabrication

Model–based Estimation – QTO Processes

Progress Collection, Monitoring and Control

5Di USE CASE

Page 9:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

9 © Ed. Züblin AG (05/2012)

5Di USE CASE MODEL BASED ESTIMATION

The use case is critical to us:

our starting point for usage of 5D as

a standard process: usually a

construction company enters at the

tender phase

horizontal process integration,

covering the whole tender phase

this can only succeed if we

transcend traditional tender

processes. This assures:

model-based vertical integration

holistic process integration

5Di USE CASE

Page 10:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

10 © Ed. Züblin AG (05/2012)

CURRENT SERVICES OF ZÜBLIN – 5D DESIGN

presentation of STRABAG|ZUEBLIN|DYWIDAG solutions in the tender phase

creating a BIM-model on the basis of 2D drawings and/or coordinating external planners

to develop a high-end model suitable for further process integration and decision support

a BIM-model to achieve proper coordination of trades in an early design phase

quality checks and augmentations of external models for follow-up processes

clash detection and the coordination of subsequent resultant amendments

fast and reliable design of complex structures

depicting the construction process by connecting the 3D-model and the schedule

clash detection of moving parts (e.g. cranes)

preparation of site instructions for various construction methods

model-based quantity take-off and cost estimation

model-based quantity take-off for logistics

as-built model for facility management

design to production: 3D-model for “computer-aided manufacturing” (CAM)

We are continuously expanding our services, the following slides will provide some illustrative examples.

Geometry

3D

Sequence

4D

Data/Process

5D

5D SERVICES

Page 11:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

11 © Ed. Züblin AG (05/2012)

EXAMPLES – 5D DESIGN

coordination of trades

logistics planning

assistance for CAM

presentation

model based estimation

(3D) quantity take off

visualizations of scheduling

5D SERVICES

Page 12:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

12 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

multi-storey office building: BIM model provided by client with the explicit request to use this

model in the tender phase

clash

detection

model

issued by

client

3D-

scheduling

site

planning QTO

technical

presentation

Technical

Design

construction

methods

sequencing &

scheduling

construction

site

planning

cost

estimation

technical

presentation

validation of

design concepts &

alternatives

EXAMPLE 1

Page 13:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

13 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

tender documents:

structure

finishes

MEP 63 A0 plans

all drawings derived from BIM model

structure & finishes

MEP

173 A0 plans

also including two BIM models

EXAMPLE 1

Page 14:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

14 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

model-based QTO. Since all drawings were derived from the model, a model-based

QTO was valid by consequence and thus conducted.

structure:

walls, columns…

foundation:

columns…

finishes, façade:

suspended ceilings…

MEP:

ventilation,

electrics…

742 elements 6.000 elements 17.000 elements 73.257 elements

EXAMPLE 1

Page 15:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

15 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

Clash detection. For early coordination and estimation of required work

EXAMPLE 1

Page 16:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

16 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

Scheduling. Structural segmentation of work according to logical scheduling

options. QTO per task

EXAMPLE 1

Page 17:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

17 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

Scheduling. Linking the adapted model to proposed schedule for internal verification and

presentation to the client

EXAMPLE 1

Page 18:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

18 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

Site planning. Use of existing BIM model to efficiently plan and assure site-planning

EXAMPLE 1

Page 19:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

19 © Ed. Züblin AG (05/2012)

EXAMPLE 1: 5D PROCESS USING CLIENT'S MODEL

Presentation for the client. Using all preceding sub-deliverables to show the client the

result of the tender.

EXAMPLE 1

Page 20:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

20 © Ed. Züblin AG (05/2012)

EXAMPLE 2: 5D "FROM SCRATCH"

multi-storey office building: in-house creation of tender model

Technical

Design

construction

methods

cost

estimation

validation of

design concepts &

alternatives

EXAMPLE 2

3D-modeling with

STRABAG templates

model based

scheduling

model-based

estimation

model-based

QTO

construction

site

planning

sequencing &

scheduling

technical

presentation

presen-

tation

Page 21:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

21 © Ed. Züblin AG (05/2012)

EXAMPLE 2: 5D "FROM SCRATCH"

EXAMPLE 2

template library

template-based 3D modeling

standardized QTO recipies and

estimation structure

model-based quantity take-off and estimation

Quality, efficiency and thorough processes enabled by process integration

Page 22:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

22 © Ed. Züblin AG (05/2012)

EXAMPLE 2: 5D "FROM SCRATCH"

3D modeling

EXAMPLE 2

Page 23:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

23 © Ed. Züblin AG (05/2012)

3D scheduling

EXAMPLE 2: 5D "FROM SCRATCH"

EXAMPLE 2

Page 24:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

24 © Ed. Züblin AG (05/2012)

EXAMPLE 2: 5D "FROM SCRATCH"

EXAMPLE 2

Model-based quantity take-off according to STRABAG standards

Page 25:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

25 © Ed. Züblin AG (05/2012)

EXAMPLE 2: 5D "FROM SCRATCH"

EXAMPLE 2

Model-based estimation

Page 26:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

26 © Ed. Züblin AG (05/2012)

EXAMPLE 2

EXAMPLE 2: 5D "FROM SCRATCH"

presentation to the client – on base on „work“ model

Page 27:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

27 © Ed. Züblin AG (05/2012)

THANK YOU.

Page 28:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

28 © Ed. Züblin AG (05/2012)

closing

Page 29:  · multi-storey office building: BIM model provided by client with the explicit request to use this model in the tender phase clash detection model issued by client 3D- scheduling

OVERVIEW 5Di MOTIVATION 5Di USE CASE 5D SERVICES EXAMPLE 1 EXAMPLE 2

29 © Ed. Züblin AG (05/2012)

closing

πάντα ῥεῖ (panta rhei)

- all flowes (Heraklit)