mtacc cpoc esa overview and budget/schedule risk...
TRANSCRIPT
![Page 1: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/1.jpg)
MTA Capital Construction 0
MTACC CPOC
ESA – Overview and Budget/Schedule
Risk Assessment
May 21, 2012
![Page 2: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/2.jpg)
MTA Capital Construction 1
MTA – 2009 MTA - 2012FTA2009
FTA2012
Numbers do not include $463 M for rolling stock which is budgeted separately in Rolling Stock Reserve
$Billions
Low Budget LowHigh Medium High 0
1
2
3
4
5
6
7
8
9
ESA - Budget & Schedule Ranges
7.22
3/16
8.24
9/16 1/17 4/18 9/18 12/18 8/19 9/19
7.32
8.01
7.867.81
7.98 8.24
![Page 3: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/3.jpg)
MTA Capital Construction 2
Risk Informed Budget and Schedule
• FTA independently concurs with budget
• Total Risk Informed Values are consistent with MTA’s current Risk Policy of 80%
probability that the project will be delivered at or below the risk informed budget
of $8.24B and schedule of 8/2019– Following this policy the 2009 rebase-lining would have resulted in a $8.01B budget
• $360M of contingency represents approximately 8% of the remaining $4.6B to
be spent
• Over $1.5B in awards are scheduled for the next 12 months; providing greater
cost certainty
• Efficiency in MTACC Projects and inter-agency program will fund additional
$200M commitment need in current ‘10 to ‘14 Plan
• Balance ($720M) to be addressed in ‘15 to ‘19 Plan with expectation that
additional efficiencies in MTACC Projects can cover some of the increase
2
Basis for Risk Assessment
Risk Informed Base Cost &
Schedule
Contingency Total Risk Informed
Value
Revenue Operation Date
December 2017
August 2018
12 months August 2019
Budget $7.72 B $7.88 B $0.36 B $8.24 B
![Page 4: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/4.jpg)
MTA Capital Construction 3
What Changed?
• By mid-2011, MTACC was reporting significant
construction delays in both Manhattan and
Harold
• Delays in Harold resulted in schedule
compression that placed stress on resources
and outages
• Other critical regional projects have put further
pressure on resources and outages
• Both cost and schedule contingency have been
largely consumed
3
![Page 5: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/5.jpg)
MTA Capital Construction 4
Steps Taken
• Developed a new forecast estimate and schedule
• Used as the Basis for Risk Assessment conducted by
Golder Associates
– Independent facilitator and modeler
• Identified major risks driving cost and schedule
• Produced new Risk Informed Base Cost and Schedule
plus Contingency
• Established New Total Risk Informed Value which
provides 80% probability that the final cost and schedule
will be at or below these levels
4
![Page 6: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/6.jpg)
MTA Capital Construction 5
Potential Risks and Mitigations
![Page 7: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/7.jpg)
MTA Capital Construction 6
Rebuilding and Expansion of Harold
Interlocking
Midday Storage Yard
Sunnyside YardNorthern Blvd
Busiest and most complex passenger railroad interlocking in US
Need for critical track outages and craft personnel timed to ESA needs
![Page 8: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/8.jpg)
MTA Capital Construction 7
Major Rail Projects in the New York
Metropolitan Region
PORTAL BRIDGEHIGH SPEED RAIL
MOYNIHAN STATION
HAROLD INTERLOCKING
EA
ST
R
IV
ER
M A N H A T T A NN E W J E R S E Y
EAST RIVER TUNNELS
NORTH RIVER TUNNELS
RELATEDBROOKFIELD
ESA was originally planned before other projects materialized
![Page 9: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/9.jpg)
MTA Capital Construction 8
Highlights in Harold
• Replacing and adding 92 new switches (231% increase)
• Replacing 11 miles of new track (16% increase)
• Constructing five new railroad bridges
• Replacing and installing 313 new catenary poles and signal
towers (43% increase)
• Constructing 1.25 miles of new retaining wall
• Replacing and installing 12 new Central Instrument Locations
for signal (300%)
• Constructing two (1,000 ft long) new by-pass tunnels
Most of this infrastructure will go on line prior to ESA Revenue Service
and will provide a significant benefit to Amtrak and LIRR operations
8
![Page 10: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/10.jpg)
MTA Capital Construction 9
Shared ESA Tunnel Access and Coordination
Issues
• Limited access paths for major equipment and
material
• Portions of tunnels get blocked when installing
track and a variety of systems
• Multiple contractors working in the same tunnels
in both Manhattan and Queens
9
![Page 11: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/11.jpg)
MTA Capital Construction 10
Procurement Risks
• Limited Competition
– Size of Contracts
– Complexity of Contracts
• Upcoming Major Contracts
– Manhattan Structures
– Two Systems Contracts
– GCT Concourse Fit-out
10
![Page 12: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/12.jpg)
MTA Capital Construction 1111
Risk Delays During Installation and Integration
• Installation of a significant number of system
elements
• Interface and integration of new and legacy
systems
![Page 13: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/13.jpg)
MTA Capital Construction 12
Mitigations
• Continue to monitor actual experience
– Not all risks will materialize
• Need a dynamic and flexible approach to
maintain confidence in meeting or exceeding
targets
• Opportunities fall into three categories
– Engineering
– Contract Interface/Coordination
– Policy
12
![Page 14: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/14.jpg)
MTA Capital Construction 13
Potential Mitigations
• Engineering
– Continue the work of the Operational Readiness group formed
with LIRR to address testing and commissioning
– Re-sequencing of Harold cut-overs
– Creating an Obsolescence Review Committee (during
construction) to evaluate systems elements to determine product
end of life cycle and the system or component version to
implement
• Contract Interface/Coordination
– Continue to create additional access points in Queens, Harold
and Manhattan
– Scope transfers between contracts
• Policy Decisions – Potential Service Reductions
13
![Page 15: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/15.jpg)
MTA Capital Construction 14
Summary
14
Risk Informed Base Cost &
Schedule
Contingency Total Risk Informed
Value
Revenue Operation Date
August2018
12 months August2019
Budget $7.88 B $0.36 B $8.24 B
• Continue to use Risk Model as a management tool
• Need to work with all stakeholders on mitigation
strategies
• Periodic reporting to CPOC on progress and success
with mitigation strategies
![Page 16: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16](https://reader034.vdocuments.site/reader034/viewer/2022042413/5f2d5154e4f03603f7788d54/html5/thumbnails/16.jpg)
MTA Capital Construction 15
IEC Comments
• IEC participated in cost and schedule review and
Risk Assessment and supports the results
• Most significant near-term risk
– Procurement challenges to upcoming large and
complex contracts
15