m/s hll infra tech services ltd. (hites) (subsidiary of...

39
1 | Page M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of HLL Lifecare Ltd, A Government of India Enterprise) As Executing Agency of Central Drugs Standard Control Organization (Under Ministry of Health &Family Welfare, Govt. of India) HITES/IDN/59/CDSCO/IPC-GZB/2017-18/ 01.05.2017 All Bidders, Corrigendum-01 Name of the work: Tender for Construction of Building for CDSCO & its Labs at IPC Complex, Raj Nagar, Ghaziabad, U.P.: Clarifications/ Amendments Ref: Tender No. HITES/IDN/CDSCO/IPC-GZB/ 2017 dated 19.04.2017 Dear Sir, The Corrigendum-01 pertains to request received from bidders & other clarifications/ amendments given below, which shall be treated as part of e-tender to be uploaded online duly signed and stamped along with e-tender: Amendment to Existing e-Tender: S.no. Reference to tender Existing Clause Amended Clause 1 Notice Inviting e-Tender & Instruction to Bidder, Volume- I, Clause 1.4.1, Page 9 1.1.1. Eligibility Criteria The Tenderer should meet the following minimum eligibility criteria: Bidders who fulfill the following requirement shall be eligible to apply. Joint ventures of whatsoever kind 1.1.2. Eligibility Criteria The Tenderer should meet the following minimum eligibility criteria: Bidders who fulfil the following requirement shall be eligible to apply. Joint ventures of whatsoever

Upload: others

Post on 19-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

1 | P a g e

M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of HLL Lifecare Ltd, A Government of India Enterprise)

As Executing Agency of

Central Drugs Standard Control Organization

(Under Ministry of Health &Family Welfare, Govt. of India)

HITES/IDN/59/CDSCO/IPC-GZB/2017-18/ 01.05.2017

All Bidders,

Corrigendum-01

Name of the work: Tender for Construction of Building for CDSCO & its Labs at IPC Complex, Raj Nagar, Ghaziabad, U.P.: Clarifications/

Amendments

Ref: Tender No. HITES/IDN/CDSCO/IPC-GZB/ 2017 dated 19.04.2017

Dear Sir,

The Corrigendum-01 pertains to request received from bidders & other clarifications/ amendments given below, which shall be treated as part of e-tender to be uploaded online duly signed and stamped along with e-tender:

Amendment to Existing e-Tender:

S.no. Reference to tender

Existing Clause Amended Clause

1 Notice Inviting e-Tender & Instruction to Bidder, Volume-I, Clause 1.4.1, Page 9

1.1.1. Eligibility Criteria

The Tenderer should meet the following minimum eligibility criteria:

Bidders who fulfill the following requirement shall be eligible to apply. Joint ventures of whatsoever kind

1.1.2. Eligibility Criteria

The Tenderer should meet the following minimum eligibility criteria:

Bidders who fulfil the following requirement shall be eligible to apply. Joint ventures of whatsoever

Page 2: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

2 | P a g e

are not accepted.

(a) Experience should be in the name of the bidding company and not in subsidiary/ associate company/ Group Company etc.

(b) Experience of having successfully completed works during the last 7 years ending the previous day to the last date of submission of tender.

Three similar completed works each costing not less than the amount equal to Rs.34.09 Crs.

Or

Two similar completed works each costing not less than the amount equal to Rs. 51.14 Crs.

Or

One similar completed work of costing not less than the amount equal to Rs.68.19 Crs.

(c) “Similar Work” shall mean Project comprising construction of a multistoried RCC framed structure having minimum one basement plus Ground Floor plus Five Storeys (machine room and mumty shall not be counted as a storey) including finishing works, internal water supply, sanitary installations and internal electrical installation all composite executed under one agreement. The value of executed works shall be brought to current costing level by enhancing

kind are not accepted.

(a) Experience should be in the name of the bidding company and not in subsidiary/ associate company/ Group Company etc.

(b) i) Experience of having successfully completed works during the last 7 years ending the previous day to the last date of submission of tender.

Three similar completed works each costing not less than the amount equal to Rs.34.09 Crs.

Or

Two similar completed works each costing not less than the amount equal to Rs. 51.14 Crs.

Or

One similar completed work of costing not less than the amount equal to Rs.68.19 Crs.

And

ii) At least one (1) work of part (b)(i) costing not less than the amount equal to 34.09crores should comprise construction of minimum one basement.

(c) “Similar Work” shall mean Project comprising construction of a multi-storeyed RCC framed structure having minimum Five Storeys (Basement, machine room and mumty shall not be counted as a storey) including finishing works, internal water supply, sanitary installations and internal electrical installation

Page 3: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

3 | P a g e

the actual value of work at simple rate of 7% per annum; calculated from the date of completion to last date of receipt of applications for bids.

Own works / work under the same management / own certification of the bidder shall not be considered for pre-qualification.

To become eligible to bid, the bidders shall have to submit an affidavit with their bids and as per Form H and reproduced hereunder.

all composite executed under one agreement. The value of executed works shall be brought to current costing level by enhancing the actual value of work at simple rate of 7% per annum; calculated from the date of completion to last date of receipt of applications for bids.

Own works / work under the same management / own certification of the bidder shall not be considered for pre-qualification.

To become eligible to bid, the bidders shall have to submit an affidavit with their bids and as per Form H and reproduced hereunder.

2 Technical Specification, Volume-IV, Index , Page 2

Index Revised Index, attached as Annexure-I

3 Technical Specification, Volume-IV, Index , Page 552,Sr.no-70 Approved make list (HVAC Works)

Make/Manufacturer VRV/ VRF Outdoor/ Indoor Units/ Refnet Joints/Remote Controllers Mitsubishi Electric/ Daikin/ Toshiba/ Panasonic/ Blue star/ Voltas

Make/Manufacturer VRV/ VRF Outdoor/ Indoor Units/ Refnet Joints/Remote Controllers Mitsubishi Electric/ Daikin/ Toshiba/ Panasonic/ Blue star/ Voltas/Carrier

4 Technical Specification, Volume-IV, Index , Page 545,Sr.no-5

Make/Manufacturer APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB

Stands Deleted.

Page 4: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

4 | P a g e

Approved make list (Electrical Works)

5 BoQ, Vol-V, Mechanized Car Park

“Design, supply, installation, testing and commissioning of Electro-Hydraulic Twin Park Palette Parking System based on lifting mechanism through hydraulic cylinder, to be provided in both the basements (lower basement-106 Nos. approx. & upper basement-54 Nos. approx.). Normal adjustable size will be 4529mm (± 50mm) x 2560mm (±50mm) with the minimum lower level height clearance of 2.1 mtrs. The minimum weighting capacity of lift will be 2.0 tons. Overall parking structure adjustable height of 3700mm. Platform will be of metal framing with GI Corrugated platform profiles. It should be complete with power pack (approx. 1.5 KW or as per OEM, low noise submerged type), operator keys, operator stand. Average retrieval/parking time should not be greater than 120 seconds & the Lifting speed should be min. @ 3 Meter/Minute. System should be height adjustable having safety features as outlined in specifications including cost of required foundation, 3 phase supply to each module, complete with reqd. core & size of electrical cable, control switchgear & necessary earthing etc. complete as per manufacturer's specifications & as per directions of Engineer-in-Charge”.

“Design, supply, installation, testing and commissioning of Hydraulic/Electro-Mechanical Twin Park Palette Parking System to be provided in both the basements (lower basement & upper basement). Normal adjustable size with the minimum lower level height clearance shall be as per OEM standards. The minimum weighting capacity of lift will be 2.0 Tons. Overall parking structure adjustable height as per OEM standard & site requirement. Platform will be of metal framing with GI Corrugated platform profiles with H beam/sheet metal. It should be complete with power pack/motor (approx. 1.5 KW or as per OEM, low noise submerged type (in case of hydraulic)), operator keys, operator stand as per OEM standards. Average retrieval/parking time should not be greater than 120 seconds & the Lifting speed should be min. @ 3 Meter/Minute or best available as per manufacturer’s standard. System should be height adjustable having safety features as outlined in specifications including cost of required foundation, 3-phase supply to each module from electrical panel, complete with suitable core & size of electrical cable, control switchgear & necessary earthing etc. complete as per manufacturer's specifications & as per directions of Engineer-in-Charge”.

Page 5: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

5 | P a g e

6 Technical Specification, Volume-IV, Index , Page 549,Sr.no-4 Approved make list (LV System/ PA System/ CCTV System/ Access Control System/ Door Interlocking System)

Make/Manufacturer CCTV Camera/ DVR/Central Monitoring Software / Other Items Honeywell / Pelco / Vicon /Bosch/ GE/ Axis/ Sony

Make/Manufacturer CCTV Camera/ DVR/Central Monitoring Software / Other Items Honeywell /Bosch/Hikvision/Samsung

7 Technical Specification, Volume-IV, Index, Clause No. 1.5.0, Fire Alarm System-Approvals-Chapter -I)

APPROVALS:

A. The system must have proper listing and/or approval from the following nationally recognized agencies:

UL Underwriters Laboratories Inc

FM Factory Manual

ULC Underwriters Laboratories

Canada

CPWD Central Public Work Department

BIS Bureau of Indian Standards

EN 54 or Equivalent European Standards

APPROVALS:

A. The system must have proper listing and/or approval from the following nationally recognized agencies, as applicable:

UL Underwriters Laboratories Inc

FM Factory Manual

ULC Underwriters Laboratories Canada

CPWD Central Public Work Department

BIS Bureau of Indian Standards

EN 54 or Equivalent European Standards

VdS Verein deutscher Sachversicherer

(German Certifying Body)

Page 6: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

6 | P a g e

Bidders Queries and HITES clarification

Sl. No.

Bidder’s query Clarifications

1 “Soil investigation report Regd.” “Since there is solider pilling & double basement, we request you to kindly share any preliminary soil investigation report / bore log Details.”

The same is available at HITES Office at Noida which can be seen by the Bidder on any working day during office hours.

2 “Land for batching Plant” “We request you to provide free of cost within the site or campus premises for batching plant & other infrastructure like labour camp. The temporary structure will be removed and the land will be handed over after clearing to the satisfaction of the client.”

Terms & Conditions of e-Tender prevails.

3 “Water & Electricity” “We request you to kindly provide water & electricity at a single point at site for construction purpose.”

Terms & Conditions of e-Tender prevails.

4 “Submission date- 11.05.2017” “This being a very prestigious, in order to arrive at very competitive rate for the project we need some more time. We request you to extend the date of submission for 7 days i.e., from 11.05.2017 to 18.05.2017 ”

Terms & Conditions of e-Tender prevails.

Page 7: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

7 | P a g e

5

Section III,3.bids are now invited for following scope of works: Page 28 “The scope of work shall, besides above mentioned works, also include maintenance during defect liability period including & preparation of all detailed shop drawings, obtaining approval from all local authorities, electrical inspector, water sewer, drainage, electricity connection from local bodies, permission /approval for tree cutting etc. As client / HITES aims at getting GRIHA 3-star rating for the building, prospective bidders are required to provide adequate documentation & follow other requirements relevant to enable CLIENT /HITES in achieving these objectives as referred above.”

a. Cost of mentioned works in scope of contractor or client? b. Maintenance charges in case of damage of CP or China

fittings etc.

Terms & Conditions of e-Tender prevails.

6 Special care for existing building & existing institute working: Page 28 “It may be noted that Construction of Building for CDSCO (Central Drugs Standard Control Organisation) and its Labs. At IPC Complex, Raj Nagar, Ghaziabad, (UP). In an existing institute which has to be kept running need special attention and careful planning, so that there is no hindrance to the operation and running of services of the existing IPC complex” Barricading of existing building will be payable or in contractor scope.

Terms & Conditions of e-Tender prevails.

7 Special care for existing building & existing institute working: Page 28 “There may be some services crossing the construction area of the proposed new block. The scope of work includes dismantling of services falling in the construction area and supporting / shifting & making functional existing services / sewerage and water supply

Terms & Conditions of e-Tender prevails.

Page 8: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

8 | P a g e

lines etc. The contractor shall properly take care & safe guard the all the existing services in the area affected by the construction of building for CDSCO and Laboratories. ” If any service etc damage in existing building during work will be payable or in contractor scope.

8 3.5. Approvals required Page29 “The contractor shall obtain all necessary approvals except pre-construction from Municipal and other local bodies including Municipal bodies, water supply agencies concerned, electric supply and inspectorate. Agencies concerned, police and security agencies, Chief controller of Explosive, Fire department, civil Aviation department, concerned in accordance to prevailing rules, building Bye laws, tree cutting etc., as the case may be with related to / required for Construction / completion. All expenditure on this account will be borne by the contractor.” What are other approvals and approx cost of these approvals.”

Terms & Conditions of e-Tender prevails

9 Form-F Page 44 “What is meaning and applicability” Only under taking or else and part of applicability?

Refer Tender Clause 1.29 of Section-I, Vol-I, NIT & ITB (page no 13-14)

10 Other“Availability of land for labour hutment and material entry gate ”Land for labour hutment should be provided in site premises or outside the site, if so then approximate distance between labour hutment area & site.

Refer Tender Clause 38.3 of Section-I, General of SCC, Vol-III (page no 27-28)

11 “The tender document does not mention Basic rate for building materials such as steel, cement, AAC Blocks/ Bricks, Coarse sand and Coarse aggregate. Since the price of raw materials has increased exponentially, please provide basic rate for the same.”

Terms & Conditions of e-Tender prevails.

12 “On the website , only the detailed NIT and BOQ is available, from where we can access Volume II, III, IV, & VI ”

Refer attached Annexure-II

13 “Please confirm if secured advance shall be paid to the contractor for materials brought on site. If yes, please confirm what

Refer tender clause 10B of General Conditions Contract, Vol-II (page 30)

Page 9: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

9 | P a g e

percentage of the total value of material purchased shall be paid.”

14 “Please confirm if Mobilization advance shall be provided. If yes, please confirm what percentage of total contract value that would be. ”

Refer tender clause 10B of General Conditions Contract, Vol-II (page 30)

15 “Please confirm if retention money can be given in the form of bank guarantee”

Refer tender clause 1A of General Conditions Contract, Vol-II (page 14)

16 “Please confirm if escalation clause shall apply on this project” Refer Schedule F of General Conditions Contract Vol-II, (Page 101 & 102)

17 “Please confirm if the insurance, i.e. CAR Policy, will be under the scope of client or contractor. Also, if it will cover general contractor’s staff, labour and material”

Refer tender Clause 46 of General Condition Contract , Vol-II, (Page 66)

18 “Please confirm if workers compensation is in the scope of general contractor”

Refer tender Clause 46 of General Conditions Contract , Vol-II, (Page 66)

19 “Please define/ specify how GST will be applicable during the construction of the project and will it affect the contract value financially.”

Refer tender Clause 38 of General Conditions Contract , Vol-II, (Page 63)

20 “Please define the Mobilization period, since the same is not mentioned in the tender document”

Refer tender Clause 5 of General Conditions Contract , Vol-II, (Page 19)

21 “In U.P. State especially Noida, permission for earth work excavation is to be obtained from the local body. This may please be informed whether the permission is taken by the department.”

The Contractor shall arrange for the permission, if any, required for operation of items related to earth work that is excavation, its disposal and bringing back the earth required for the work. The rates quoted by the contractor shall be all inclusive including royalty etc., if any.

22 “Generally the associate agencies forwarded their rates after the receipt of the minutes of the pre bid which generally take weeks time. It is suggested that submission of tender date may be extended for 15 days.”

Terms & Conditions of e-Tender prevails.

23 “Approximate length of the barricading the construction area be intimated”

Bidders may visit the site.

Page 10: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

10 | P a g e

24 “An item of barricading is available in CPWD schedule of Rates. It is suggested that, the same may be included in the BOQ. ”

Terms & Conditions of e-Tender prevails.

25 “A statutory increase i.e. GST etc which come in force after the submission of tender shall be reimbursed”

Terms & Conditions of e-Tender prevails.

26 “It has been mentioned in the Special Conditions, the batching plant preferably be installed within 50mtr. From the site. This may please be confirmed whether space for installing batching plant & site office /stores is available within the working area. ”

Terms & Conditions of e-Tender prevails.

27 “Minimum interim payment shown in schedule-F as INR.150.00lakh, it is suggested that this provision for first two bills & last two bills be reduced.”

Terms & Conditions of e-Tender prevails.

28 “Provision of technical staff mentioned in the schedule-F is on higher side. This may please be reduced ”

Terms & Conditions of e-Tender prevails.

29 “At S.No. 38 of list of approved makes, Promat& Godrej does not manufacture Metal Fire Door, the name of M/s. Sukri & M/s. Bhawani Fire protection may please be added to get most competitive rates / offers”

Terms & Conditions of e-Tender prevails.

30 “At S.No. 39 of list of approved makes Asahi India safety Glass &Modi does not manufacture Fire rated glass. It is suggested that name of “PYROGUARD & SCHOTT (Germany) “May please be added.”

Terms & Conditions of e-Tender prevails.

31 “For door fixture / fittings for fire rated doors M/s. Marshal & M/s. Assa-Abloy names may please be added.”

Terms & Conditions of e-Tender prevails.

32 “In BOQ Item for Mechanized Car Parking System provision of Hydraulic / Electro-Mechanical car parking system is mentioned whereas the specification attached with the tender are only for Hydraulic system. Out of four manufacture mentioned in the approved list only one company i.e. M/s Klaus is manufacturing the hydraulic system & the specification attached is only suits to M/s. KLAUS. It is suggested that specification for electro-Mechanical system may please also be included”

Please refer Amendment to existing e-Tender(Sl. No.5) for revised BoQ & Annexure-A for Revised Technical Specifications for Mechanized Car Park System.

Page 11: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

11 | P a g e

33 “In FAS, Specs ask for UL listed system whereas BOQ as for both UL/VDS approved system. Kindly confirm what we need to consider.”

The item needs to be executed as specified in BOQ. Refer reply at sl. No. 7 of “Amendment to Existing e-Tender”.

34 “In FAS, all detector & devices asked with inbuilt fault isolator which is a default feature of VDS system not UL approved system. Can we propose external fault isolator after every 20 devices as per UL norms? ”

The item needs to be executed as specified in BOQ. Accordingly, fault Isolators can be considered as per UL/VDS standard.

35 “In FAS & CCTV, Specs & BOQ are not matching. Kindly confirm whether we quote considering specs or BOQ.”

The item needs to be executed as specified in BOQ.

36 “In CCTV, approved makes like Pelco, Sony are of IP based CCTV solution whereas BOQ asks for analog HD solution. Kindly confirm what we need to consider.”

The item needs to be executed as specified in BOQ. As regard make, refer reply at sl. No. 6 of “Amendment to Existing e-Tender”.

37 “At S.no. 70 of approved make for HVAC, LG name may please be added for VRV / VRF outdoor / indoor units/ refnet joints/ Remote controllers works.”

Refer reply at sl. No. 3 of “Amendment to Existing e-Tender”.

38 “Kindly let us know Tax Structure we need to consider as GST implementation is on the way.”

Terms & Conditions of e-Tender prevails.

39 Vol –IV Tech Specs, Approved Makes:- “Request you to consider Voltas make in addition to makes specified in tender for water cooled screw chillers. Please note Voltas hold a Pioneering position and having a more than 40 years experience in manufacturing & supplying Water/ Air Cooled Chillers from India. As per new initiative take by Government regarding promoting "Make in India" policy we request you to please accept Voltas make. Voltas is already been installed and approved in numerous government projects of PWD, CPWD, NBCC ESIC and other government organizations. Voltas is sufficing all the technical parameters and specification mentioned in Tender. If required we can provide NIT copies for the same too.”

Terms & Conditions of e-Tender prevails.

40 HVAC BOQ--Sub Head –A 2), Vertical Inline Chilled Water Pumps:- “As per the approved manufacturers there is only single make who

Terms & Conditions of e-Tender prevails.

Page 12: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

12 | P a g e

could provide vertical inline pump. So, Request you to consider vertical end suction split casing pump instead of vertical inline pump.”

41 HVAC BOQ--Sub Head –A 6): Hot water Pumps- “As per the given parameters of the pump, pump manufacturers are unable to do selection with 65% efficiency. So request you to consider minimum efficiency to be 50 %.”

Hot Water Pumps with minimum 50% efficiency is acceptable.

42 HVAC BOQ--Sub Head –A 18):- Thermostat for FCU:- “Please clarify about the quantity of thermostat whether it is 10 Nos. or we have to consider 2 thermostats per set (one for cooling and one for heating coil).”

Each FCU shall have only one thermostat which shall be suitable for four pipe system for simultaneous cooling & heating as mentioned in BoQ. Terms & Conditions of e-Tender prevails.

43 HVAC BOQ-Sub Head –A 19):- Thermostat for AHU:- “Please clarify about the quantity of thermostat whether it is 47 Nos. or we have to consider 2 thermostats per set (one for cooling and one for heating coil).”

Each AHU shall have only one thermostat which shall be suitable for four pipe system for simultaneous cooling & heating as mentioned in BoQ. Terms & Conditions of e-Tender prevails.

44 HVAC BOQ-Sub Head –A 20):-PICB Valve:- “In the Given Item- 1.For FCU already in item No.15) PICB valve is mentioned, so it should be omitted from this line item to avoid cost doubling. 2. For FMAHU and CSU, total quantity is 47 Nos. and hence total

quantity of PICB valve should be 94 (one for cooling and one for heating coil) but in BOQ total quantity is 110. Please clarify on the same.”

1. It is mentioned in BoQ item description of FCU that quantity of PICB valve have been quantified separately, thus, the cost for the same should not be considered in this line item.

2. Each AHU or FCU shall have cooling coil and heating coil.

So there shall be 02 nos. of PICB control valve for each AHU or FCU, one for cooling coil and second for heating coil & Quantity has been taken accordingly in BoQ.

Terms & Conditions of e-Tender prevails.

45 Vol –IV-Tech Specs-Approved makes:- “Request you to approve following makes in addition to approved makes-

Axial fans Airflow / Humidin

Terms & Conditions of e-Tender prevails.

Page 13: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

13 | P a g e

Centrifugal Fans Airflow / Humidin

Check Valve/ Foot Valve/ Sluice Valve/ NRV

Castle

Thermostat /Humidistat Danfoss

Room Thermostat Danfoss

Fire/smoke Dampers Caryaire

Split AC Units (R-410 A refrigerant /Inverter driven compressor)

VOLTAS

2-Way Pressure Independent Balancing & Control Valve

Flowcon

Butterfly Valves (Water Duty)

Castle

Motorized Butterfly Valves

Castle/Advance

Closed Expansion Tank Emerald

Data / telephone cable (2/4/10/20/50/100 pair cables)

Delton

Digital / Analog Phones / Handsets

Ptel

EPABX machine NEC

Active Components- Core and Edge switch

HP

Ethernet switch/ router Fortinate

Passive components- Horizontal and vertical cabling

R &M

Access control system DDS

Page 14: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

14 | P a g e

CCTV Camera / DVR/ Central Monitoring Software / Other Items

Tyco

46 GCC Clause no. 10 B II, Page no. 30 & 10 B IV Page no. 32 We request you to Interest Free mobilization advance against Bank Guarantee. The mobilization shall be recovered on pro-rata basis from 3rd RA Bill upto completion of 80% of the contract value. Bank guarantee shall be released to us time to time as per the recovery of mobilization advance. (On a minimum amount of Rs.50 Lac). Considered with validity of all Bank Guarantee for a period of one year & shall be extended as per the requirement- Please Clarify

Terms & Conditions of e-Tender prevails.

47 GCC Clause no. 10 B II, Page no. 30 We request you to Secured Advance 90% of the quoted value for materials shall be paid to us within 15 days from the date of submission of bill & shall be recovered from our RA bill payment on actual consumption basis. Recovery of full advance shall be made within 3 months in equal installment from the date of payment- Please Clarify

Terms & Conditions of e-Tender prevails.

48 GCC Clause no. 1 A, Page no. 14 We will provide Corporate Guarantee in lieu of performance guarantee- Please Clarify

Terms & Conditions of e-Tender prevails.

49 GCC Clause no. 1 A, Page no. 14 & 15 Considered with there shall not be any cash retention from our bills and shall be release as per the following: (i) 2.5% to be released during of the course of the project in

tranches against BG valid till DLP (12 months) (ii) Balance 2.5% to be release on virtual completion against BG

of equivalent amount valid till DLP (12 months)- Please Clarify

Terms & Conditions of e-Tender prevails.

Page 15: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

15 | P a g e

50 SCHEDULE ‘F’ 2 (ix) Page 100 Considered with Extra item shall be derived non tender items > For item with material &Labour- Cost of materials + cost of labour + operational / rental charges of tools & plants + 20% overheads & profits. Vat, service tax &labourcess as applicable shall be payable extra.

Terms & Conditions of e-Tender prevails.

51 GCC clause no. 3, Section III Page 28 We have considered that all necessary statutory approvals, permissions, sanctions, NOC from local body, MOEF, state govt., central govt. etc shall be arranged and paid by owner. All the necessary deposits, fees, expenditures for all type of permission/ sanctions etc. including extra water and sewage charge, shall be paid by Clients/ HITES- Please Clarify

Terms & Conditions of e-Tender prevails.

52 SCC clause no. 2.2 d, Page 64 Considered with space for site office, general store, storage of materials, plant & machinery. Batching plant reinforcement yard and for labour accommodation will be provided by client free of cost at site - Please Clarify

Terms & Conditions of e-Tender prevails.

53 Mentioned in List of approved make Page 538 to 554 Considered with rates are quoted based on any make can be use in place of first make from the list of approved or equivalent makes as given in the tender and no deduction will be done on account of using approved make other than first make- Please Clarify

Terms & Conditions of e-Tender prevails.

54 NIT We request you to please extend the date of submission of tender at least Two weeks after the date of reply of pre-bid queries- Please Clarify

Terms & Conditions of e-Tender prevails.

55 Soil Investigation Report We request you to provide the soil investigation report- Please

The same is available at HITES Office at Noida which can be seen by the Bidder on any working day during office hours.

Page 16: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

16 | P a g e

Clarify

56 BOQ We have considered wherever basic rates are given in the tender document shall be considered inclusive of all taxes F.O.R. at site- Please Clarify

Basic Rates given in the tender document are inclusive of all taxes

& are F.O.R at Site.

57 Cement, Reinforcement steel & Structural Steel We request you to provide the basic rate- Please Clarify

Basic Rates of Cement & Reinforcement Steel are given in the

tender document. Refer Schedule F at page no. 102 of GCC of Vol-

II of tender document

58 Basic rates We have considered basic rates are given in the BOQ for flooring stone shall be considered inclusive of all taxes F.O.R. at site in cut to size- Please Clarify

Basic Rates given in the tender document are inclusive of all taxes

& are F.O.R at Site.

59 BOQ item no. 7.23 We request you to provide the basic rate- Please Clarify

Terms & Conditions of e-Tender prevails.

60 Door & window Hardware We request you toad the name M/s Doorset in list of approved make- Please Clarify

Terms & Conditions of e-Tender prevails.

61 BOQ item no. 11.39, 11.41 We request you to provide the basic rate- Please Clarify

Terms & Conditions of e-Tender prevails.

62 BOQ item no. 264 Considered with minimum quantity of elevation area one cubical 4.8 sqm.- Please Clarify

Terms & Conditions of e-Tender prevails.

63 “Soil investigation report may please be provided.” The same is available at HITES Office at Noida which can be seen

by the Bidder on any working day during office hours.

64 “Time period of completion for work of such scope i.e. double basement plus G+5, is too less and this may please be extended to at least 24months.”

Terms & Conditions of e-Tender prevails.

Page 17: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

17 | P a g e

65 “Has Service Tax been considered in the provided estimate or not? The same shall be fully reimbursed or not?”

Refer tender Clause 37 of General Condition Contract , Vol-II,

(Page 62)

66 “Has the project received all the necessary statutory approvals from local authorities like forest department, NGT etc.?”

The required statutory approvals are under process

67 “Has the department received permission for tree cutting or not?” Refer tender Clause 36 (i) of Section –1, General of Special

Condition Contract , Vol-III, (Page 26)

68 “The qualifying criteria may please be relaxed to “one work of similar nature i.e. basement plus ground plus five storey.”

Refer amendment at Sl. no. 1 above on page 1

69 “Clause 38 (i) states that any new taxes, levies or cess that become statutes after the last date of receipt of tender shall be reimbursed, does this include GST?”

Terms & Conditions of e-Tender prevails.

70 “Is there enough security in and around the campus?” Terms & Conditions of e-Tender prevails.

71 “The following vendors may please be approved:-

• 21. Cement: Birla Manglam

• 76. Reinforcement Steel: Rathi (As per Govt. Order as Attached.)

• 90. Tiles : Ceramic Tiles: Orient Bell, Somany

• 92. Tiles: Glazed (Ceramic) Tiles : Orient Bell

• 94.Tiles: Vitrified (Double/ Multi Charged) / Germ Free: Orient Bell, Somany

Terms & Conditions of e-Tender prevails.

Page 18: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

18 | P a g e

71 SUB HEAD A-MACHINERY Water cooled chiller - 300 TR ( BOQ S.NO-1)

A) Chiller shall be equipped with VFD YORK POINT: York WATER COOELD Chiller not comes with VFD for 300 TR capacity. Please confirm.

B) WATER Cooled chilling machine actual capacity 300 TR with COP 5.75 (Min.)

Trane POINT: Actual capacity shall be 297 TR instead of 300 TR and cop shall be 5.58.Please confirm

C) VFD Shall be floor mounted for water cooled chiller. DAIKIN POINT

VFD Shall be Unit mounted.

A) Terms & Conditions of e-Tender prevails. B) Terms & Conditions of e-Tender prevails. C) Floor/ Unit Mounted VFD is acceptable.

72 SUB HEAD A-MACHINERY Variable Hot Water Pump (BOQ S.NO-10) Pump efficiency-65%(Min) ARMSTRONG POINT :Hot water pump efficiency shall be 54 %

Hot Water Pumps shall be with minimum 50% efficiency.

73 SUB HEAD A-MACHINARY- FRP INDUCED DRAFT COOLNG TOWER (S.NO-7) Cooling tower shall be Equipped with statically and dynamically balanced propeller fan. Query: Cooling tower shall be Equipped with Axial flow fan instead of propeller fan as per OEM Standards.

Terms & Conditions of e-Tender prevails.

74 Specification of Cooling Tower, Page No. 291/S.NO 3.8 under Sub Head Cooling Tower-S.NO-3. All tower whose height more than 2.5 mtr. shall have safety cage& HAND RAILING. Query: We request you to remove safety cage& hand railing as per OEM recommendation.(BELL)

Terms & Conditions of e-Tender prevails.

Page 19: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

19 | P a g e

75 Makes of Motor for Cooling Tower (Sub Head- list of approved make page no 550 HVAC ) Electric motor make-ABB/Seimens/Crompton Greaves Query:We request you to approve make of motor as per OEM Standards.

Terms & Conditions of e-Tender prevails.

76 Makes of fans for Air handling units (subhead 11- HVAC MAKE LSIT page no -550 ) Centrifugal /plug fans for AHU-Kruger/Greenheck/Wolter/ comferi/Nicotra Query:a)Please approve VTS make fans for air handling units since VTS is approved in AHU make list. b) Request you to kindly provide us auto cad drawings for fine working.

a)Terms & Conditions of e-Tender prevails. b) GFC Drawings will be provided to successful bidder at an appropriate stage.

77 SUB HEAD C-PRE INSULATED DUCT ( BOQ S.NO -9) Thickness of Duct is not mentioned in BOQ. Query:Kindly confirm thickness of duct.

It is already mentioned in the Technical Specifications. Terms & Conditions of e-Tender prevails.

78 SUB HEAD A-HEPA FILTER WITH HOUSING ( BOQ S.NO -9) TROX POINTS:

1. sizes are 610x610x70 mm deep and 610x455x70 mm deep, depth cannot be common for both filter& housing. Please confirm

2. Quantites are given in sqmt. Not in Numbers. Please confirm quantities in Number.

3. Please confirm Efficiency or rating for filter H13/H14 etc. 4. Which kind of diffuser/ face plate is required with filter box

for air distribution.

1. Size mentioned in BoQ is of HEPA Filters. Housing size shall be selected accordingly.

2. Terms & Conditions of e-Tender prevails 3. It is already mentioned in the Technical Specifications,

Terms & Conditions of e-Tender prevails. 4. Face shall be like 4 way multileaf conventional type

diffusers.

Page 20: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

20 | P a g e

Annexure-A

Technical Specifications for Hydraulic/Electro Mechanical Car Parking

1. General Description:

1.1. Supply, installation, testing and commissioning of Hydraulic/Electro-Mechanical twin park palette parking system in two levels. Normal adjustable size & height clearance, overall parking structure shall be as per site conditions & OEM standards. The minimum weighing capacity of lift will be 2.0 tons.

1.2. Platform should have firm grip of vehicle and therefore should not be smooth finish. Galvanized platform thickness shall be as specified below and palette should terminate with a support/indication for the judgment of parking a car.

1.3. The Vertical moment of platform will be controlled by hydraulics/Electro Mechanical system and motor/power pack suitably designed of 1.5 KW (approx.) powers. System should work on 3 phase connection with 230 v supply. Electrical control box and hydraulic assemble should be mounted on the column of a lift to provide a clearance to the ground.

2. Technical Requirements of Hydraulic System:

• All hydraulic car parking system should be provided with the following features to ensure safety, ease of working and endurance.

• The system will be column based with Z columns per palette.

• Galvanized wave platform with thickness of 2 mm.

• Every column should have at least 6 anchor bolts with wide base plate which gives maximum strength to pole so pole does not require any other support at top and stands alone without bending.

• If the device consists of posts of two sides, carriage of two sides, and wave plate platform, then the left and right post can be used in common. The left and right carriage can form double-linked or multi – linked device with the column at random.

• Individual/ Shared Power pack will be provided with various stackers. (40 liters power pack for 4 nos. of stackers, 60 liters power pack for 6 nos. of stackers, 100 liters power pack for 10 nos. of stackers). Motor, Power pack, oil tank unit and power boxes are mounted onto pole to keep the floor clear of equipment and cables.

• Double cylinders Lift: There are two nos. cylinders to lift one vehicle per platform. Cylinders should be properly sealed to reduce the possibility of leaking of oil.

Page 21: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

21 | P a g e

• Each palette to have any emergency stop button.

• Hydraulic unit should be waterproof to avoid any failure of system due to moist (in case of hydraulic system).

• Each palette should be supported with individual hydraulic drive for individual operation (in case of hydraulic system).

• Photo sensor should be installed to prevent accidental movement of top Pallet.

• Each electrical part, safety devices should have CE certification/TUV standard

3. Technical Requirements of Electro Mechanical System:

o In case of Electro-mechanical system, Single power pack/motor of 1.5 KW for each unit. Individual Motor usage makes lifts can be taken into usage simultaneously which sops queuing of vehicles at the time of use.

o The system will be column based with H beams per palette.

o It should be complete with PCB Card and electrical installation etc. The system shall be designed to accommodate cars of size 5000 mm length and 2000 mm height (SUV) in ground floor, cars of 5000 mm length and 1700/1550 mm height cars of 5000 mm length in 1st floor/on Pallet with average retrieval/parking time not more than as specified in BOQ or best available with the OEM. All the structural work shall be finished and painted as per suitability and requirement. The parking structure will have to be constructed 2 levels above the ground with the electro mechanical technology. The structure will be supported with 4 columns and a middle column sharing two pallets for maximum space utilization. Each column should be anchored into RCC floor by 150 mm anchor bolts of approved make. Platform should have firm grip of vehicle and therefore should not be smooth finish. Galvanized platform with 1.6 mm thickness and pallet should have a wheel stopper for the judgment of parking a car. The Vertical moment of platform will be controlled by Chain & Rope System and fitted with a 3 Phase motor of capacity 1.5 kW. The Clear Pallet width shall be of 2100 mm & Length 3970 mm. In case of Power failure manual retrieval of the car parked on the first level should be possible.

o Photo sensor should be installed to prevent accidental movement of top Pallet. o Each electrical part, safety devices should have CE certification/TUV standard. o Each palette to have any emergency stop button.

▪ It should be with suitable steel structure frame of size H beam -152 x 152 x 7 x 10 -2900 L. ▪ DC magnetic brakes, photo sensors, Cam limit Switch, Pallet Stopper to be provided in case of electro mechanical system. ▪ Motor/ Power pack, power boxes should be mounted onto pole to keep the floor clear of equipment and cables.

4. Steelwork & Civil Works:

4.1. All Structural Steel fabrication, supply and delivery to site, erecting it in place, including painting, making necessary holes, chases in concrete masonry etc., aligning and grouting steel members in Cement Concrete of approved proportion along with other allied works etc. complete as

Page 22: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

22 | P a g e

per manufacturer’s specifications & directions of Engineer-In-Charge is included in the scope of work & nothing extra shall be payable on this account.

4.2. The Structural Steel work shall cover all items necessary for efficient and safe functioning of the car lifts including as applicable machine beams, hoisting beams, guide rails, strut angles at every landings, rail brackets, bearing plates, hitch beams, stretchers, separators, buffer supports, cleats, bolts, etc. All guide rail brackets shall be provided with adequate supports. No claim for extra payment shall be admitted because of missing out any of these aspects while quoting for the work.

4.3. Scaffolding required for the erection of the lift(s) and hoisting of all machinery and equipment to the required heights shall also be arranged within the quoted price.

5. Electrical Connection Requirement:

5.1. In individual power pack unit design, hydraulic units and power boxes are placed on the lift pole. Power unit and the power distribution box can be hung on the upper position of post, which can save installation space.

5.2. In shared power pack power cables to be located near to lift. Shared power pack unit generally mounted near to the pillars in civil be designed and approved with engineers before installation.

6. Variations in Power supply:

All equipment shall be capable of working efficiently under conditions of Voltage and frequency variations. The range of variation is as below:

Voltage : ±10% Frequency : + 5%

7. Drawings & Documents

The drawings provided are for guidelines only. Prior to execution of work the contractor shall submit the required shop drawings as per

requirement showing all the details viz. Layout drawings, Schematic diagrams, Drawings for control panels & any other drawings /details incl. of

controller, control panels in respect of design and metal used for its contact points for approval of same from Engineer-In-Charge. Further the

Contractor should prepare & submit the required Method Statement as per manufacturer’s specifications for each item of work including for

Quality Assurance to Engineer in charge for approval prior to start of work. All work shall be carried out on the basis of approved shop drawings.

8. Quoted Rates

Irrespective of the item description given in the BOQ and/or the specifications given herein, the quoted rates should include cost of all the required

items, components including preparatory works & execution of associated Civil/Electro mechanical works for required functioning of the system as

per manufacturer’s specifications & directions of Engineer-In-Charge.

Page 23: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

23 | P a g e

9. Training

The successful contractor shall fully provide training to Client’s personnel in operation and routine maintenance of the parking lift. Such training

shall be imparted during installation of the system and also after commissioning.

10. Operating Instructions:

The Contractor shall furnish required 4 sets of operation manuals inclusive of the operating instructions which shall include information and

guidance on operating pressures, temperatures, and quantities, etc.. Do's & Don’ts, Safety Measures & Precautions etc. as per requirements. Such

manuals should also include wiring diagrams, manufacturer’s lists of spare parts with part numbers, exploded views with identification of parts etc.

as per manufacturer’s specifications & directions of Engineer-In-Charge.

11. Guarantee of the System:

The materials and workmanship of the Electro Car parking system and its installations shall be guaranteed and the guarantee shall cover making

good of any defects, not due to any ordinary wear and tear or improper use and care, which may develop within One year from the date of handing

over of installations duly tested and commissioned to the Client.

12. Other Conditions

The local statutory Electro Car parking system Rules for Control as applicable shall be complied with. Contractor shall be responsible to obtain

necessary License from the Electrical / electro hydraulic car parking system Inspectorate or any other statutory authorities w.r.t electro hydraulic

car parking system before handing over of the installation(s) by taking timely action in submission of prescribed application form along with other

documents/drawings as per requirements. The statutory fees if any payable on behalf of Client for obtaining such approvals from relevant statutory

authorities shall be reimbursed by the Client on submission of original payment receipts.

12.1. Project information / data:

Design ambient for electrical equipment is 40°C to 45°C

12.2. Test at Site: -

Tests at site shall be carried out as per I.S. 14665 Part 5.

12.3. Approval of Installations and Completion Certificate: -

Approval/ Completion Certificate from the Electrical Inspectorate of Local/ Government, as required for installation and Commissioning of

Parking Lifts shall be obtained and made available to the Employer before handing over Lifts at no extra cost.

Page 24: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

24 | P a g e

Important Note:

1. Max. size of single file for uploading requisite documents in e-tender portal of HLL is 5 MB. 2. For uploading tender in e-tender portal of HLL, Internet explorer 9 & above should be run on compatible mode with full administrator

permission. Also please run the SRM pre-installer before starting the e-tender process for smooth running of the portal. 3. Bidders are advised to send the scanned copy of Tender Fee & EMD in prescribed form as mentioned in NIT & ITB before due date &

time as per e-tender at email address – [email protected]. 4. All other terms & condition of tender document remains unchanged.

Prospective bidders are advised to regularly scan through HLL e-tender portal @https://etender.lifecarehll.com for corrigendum/amendments etc., if any, will be notified on this portal only and separate advertisement will not be made for this.

The Vice President (ID) HLL Infra Tech Services Ltd.

END OF CORRIGENDUM-01

Page 25: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list
Page 26: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

SRM BIDDER HELP

DOCUMENT-ATTACHMENT

BIDDING

Page 27: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

Access theportal through the link: https://etender.lifecarehll.com/irj/portal

Log in with user credentials or as Guest user.

Select the appropriate RFX and click on Display Event

For knowing Tender details- go to RFX information

Page 28: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

For seeing Technical details click on Technical RFX tab

Under C folder-External Area

If required files can be downloaded to your local machine

Page 29: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

For seeing Price bid attachment –go to Items -Details- Notes and attachments

If required files can be downloaded to your local machine

Page 30: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

For participating in Tender

Click on Register button

Fill in the Questionnaire Section & attach valid Digital Signature Certificate (Class 3-B)

User ID & Password will be provided

Bidder has to remit the Tender fee & EMD offline & scan copy of the same should be sent to email id:

[email protected]

Once Tender fee payment is acknowledged, Create Response button will be activated after which

bidders can upload their bid proposal.

For attaching Technical bid documents

Click on Notes & Attachment under Rfx information and click on Add Attachment under C-folder

Browse the document and digitally sign it

Page 31: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

For Price bid Attachment

Go to Items tab, click on details

Page 32: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

Put tick on Is item quoting check box

Go to Notes and attachment tab, click on Add attachment

Page 33: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

Browse the document, digitally sign it and attach it

Attach document with exactly same file name attached by the purchaser

Page 34: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

Check for any errors

click on Submit

Digitally Sign it and Encrypt it

Page 35: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

For editing the document, click on Edit button, for print preview click on Decrypt button

Page 36: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list
Page 37: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

Edit the document and submit it.

Page 38: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of HLL Lifecare Ltd, A Government of India Enterprise)

As Executing Agency of

Central Drugs Standard Control Organization

(Under Ministry of Health &Family Welfare, Govt. of India)

HITES/IDN/59/CDSCO/IPC-GZB/2017-18/ 03.05.2017

All Bidders,

Corrigendum-02

Name of the work: Tender for Construction of Building for CDSCO & its Labs at IPC Complex, Raj Nagar, Ghaziabad, U.P.

Ref: Tender No. HITES/IDN/CDSCO/IPC-GZB/ 2017 dated 19.04.2017

Amendment to Tender Clause

Ref. to tender Existing Clause Amended Clause

Notice Inviting e-Tender (Detailed NIT) Cl. 1.2 S.No. 8 & 9

Last date to fill/ upload the

tender through e-tendering

Date of opening of tender Last date to fill/ upload the

tender through e-tendering

Date of opening of tender

11.05.2017 upto 15.00 Hrs. 12.05.2017 at 11.00 Hrs. 16.05.2017 upto 15.00 Hrs. 17.05.2017 at 11.00 Hrs.

Important Note:

1. All other terms & condition of tender document remains unchanged. Prospective bidders are advised to regularly scan through HITES e-tender portal @https://etender.lifecarehll.com for corrigendum/amendments etc., if any, will be notified on this portal only and separate advertisement will not be made for this.

The Vice President (ID)

M/s HLL Infra Tech Services Ltd. (HITES)

END OF CORRIGENDUM-02

Page 39: M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of ...hllhites.com/uploads/tenders/_541690725.pdf · APFC Panels L&T/ Siemens (Siepan)/ Schneider/ ABB Stands Deleted. ... list

END OF CORRIGENDUM-03

M/s HLL Infra Tech Services Ltd. (HITES) (Subsidiary of HLL Lifecare Ltd, A Government of India Enterprise)

As Executing Agency of

Central Drugs Standard Control Organization

(Under Ministry of Health &Family Welfare, Govt. of India)

HITES/IDN/59/CDSCO/IPC-GZB/2017-18/ 06.05.2017

All Bidders,

Corrigendum-03

Name of the work: Tender for Construction of Building for CDSCO & its Labs at IPC Complex, Raj Nagar, Ghaziabad, U.P.

Ref: Tender No. HITES/IDN/CDSCO/IPC-GZB/ 2017 dated 19.04.2017

Amendment to Tender Clause

Ref. to tender Existing Clause Amended Clause

General Conditions of Contract,, Section - 6 Proforma of Schedules, Page102

Material covered under this clause

Cement & Steel Reinforcement bars, Material covered under this clause

Cement & Steel Reinforcement bars,

Base price of all the materials covered under Clause 10CA

*Cement- Rs. 5400/- Tonne, Base price of all the materials covered under Clause 10CA

*Cement- Rs. 5300/- Tonne,

Reinforcement Steel- Rs. 34070/- Tonne Reinforcement Steel- Rs. 42525/- Tonne

General Conditions of Contract,, Section - 6 Recovery rates for quantities beyond permissible variation, Page104

S. No. Description of item

Rates in figure and words at which recovery shall be made from the contractor

S. No.

Description of item

Rates in figure and words at which recovery shall be made from the contractor

Excess beyond permissible variation

Less used beyond permissible variation

Excess beyond permissible variation

Less used beyond permissible variation

1 Cement Nil Rs. 5940/- per Tonne

1 Cement Nil Rs. 5830/- per Tonne

2 Steel reinforcement

Nil Rs.37477/- per Tonne

2 Steel reinforcement

Nil Rs.46777/- per Tonne

Important Note: All other terms & condition of tender document remains unchanged. Prospective bidders are advised to regularly scan through HITES e-tender portal @https://etender.lifecarehll.com for corrigendum/amendments etc., if any, will be notified on this portal only and separate advertisement will not be made for this.