mrp. question: how do firms actually organize things to turn materials into finished products?

35
MRP MRP

Upload: letitia-jenkins

Post on 22-Dec-2015

220 views

Category:

Documents


1 download

TRANSCRIPT

MRPMRP

Question: how do firms actually organize things to turn materials into finished products?

Master Production Schedule (MPS)

• Time-phased plan specifying how many and when the firm plans to build each end item

Aggregate Plan(Product Groups)

Aggregate Plan(Product Groups)

MPS(Specific End Items)

MPS Example – Maine Woods Toy Co.

41 42 43 44 45 46 47 48 49 50 51 52

Tricycle 300 300 300 300 300 300 300 300 250 250 250 250Wagon 300 300 300 300 250 250Scooter 300 300 300 300 250 250

Totals 2,000

Week

Pro

duct

2,400 2,400

October November DecemberMonth

One possible MPS…

Products are combinations of parts…

Example: Bicycle

Handle bars (1)

Metal Frame (1)

Wheels (2)

Dependent vs Independent Demand

• Dependent Demand

– Demand for a component (raw material, part, sub-assembly) is dependent on the demand for the end-item into which the component goes.

• demand often occurs in batches

• Independent Demand

– Demand for an item is independent of the demand for other items. These demands are typically determined by outside customers and are end-item demands

Bill of Materials (BOM)

• Shows all the assemblies, subassemblies, components, and raw materials required to produce an item

• Shows way a finished product or parent item is put together from individual components

• Parent item shown at highest level or level zero• Parts that go into parent item are called level 1

components and so on• Production planners explode BOM for level zero item

to determine the number, due dates, and order dates of subcomponents

Let’s look at an example BOM...

A

B(2) C(1)

D(3) E(3) D(1)

Question:

How many D’s we need in order to produce 50 A’s?

Schematic of MRP System

Material Requirements Planning (MRP)

• Computer-based information system that schedules and orders dependent-demand inventory components;

• Uses the master production schedule, bills of materials, and inventory records as inputs;

• Outputs recommendations:– When to release new orders– When to reschedule open orders.

Let’s look at an example BOM...

A

B(2) C(1)

D(3) E(3) D(1)

How do we manage order release?

Parts-Product Process Lead Time

A 10

B 15

C 10

D 15

E 10

We need information on delivery times!

Let’s look at an example BOM...

A

B(2) C(1)

D(3) E(3) D(1)

Question:

When do we start producing/ordering each

part?

(10)

(15) (10)

(10)

(15)

(15)

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Delivery date for final product

5 days

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Start assembly for 50 units of A

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Start assembly for 100 units of B

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Start assembly for 50 units of C

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Order 300 units of D for B’s process

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Order 50 units of D for C’s assembly

Let’s assume that we need 50 units of A…

Parts-Products

A

B

C

D

E

Order 50 units of E for C’s assembly

Customer

Assembly

Assembly

Production

Production

Production

Units are PUSHED forward according to the plan!

Summary: How does MRP work?

Material Requirements Planning

Customer

Assembly

Assembly

Production

Production

Production

Units are PULLED forward only when needed!

What about JIT/Lean Production?

Forecast

Hamburger Patties

Chicken Patties

Cheeseburger

Hamburger

Chicken Sandwich

Push/Pull Decoupling Point

Material Requirements Planning

Units are PUSHED forward to a certain point. Final configuration (PULL) occurs only when the actual

customer demand occurs.

Lot Sizing in MRP Systems

• Lot-for-lot (L4L):Produce to cover next period

• EOQ:Apply the EOQ approximation for yearly demand

• Least Unit Cost:Minimize total cost (order + carry) per unit

These are all approximate methods, none is guaranteed to be optimal. We can apply all of them and find the least-cost one to implement.

• MRP generates material orders

• Order sizes/lots can be chosen according to various objectives

Example

Cost per item: $10Order/setup cost: $47Inventory carrying cost/month 2%Starting inventory: 50Production lead time 1 monthMonthly requirements1 2 3 4 5 6100 50 80 120 70 80

For the solution, see file mrp_methods.pdf

MRP Evolution

MRP

Closed Loop MRP

MRP II

ERP

Schedule Materials

Schedule Materials

Incorporate Feedback

Schedule & Purchase Materials

Coordinate w/ Mfg Resources

Closed-Loop MRP

Production PlanningMaster Production SchedulingMaterial Requirements PlanningCapacity Requirements Planning

Realistic?No

Feedback

Execute:Capacity PlansMaterial Plans

Yes

Feedback

Goal: Plan and monitor all resources of a manufacturing firm (closed loop): manufacturing marketing finance engineering

Simulate the manufacturing system

Manufacturing Resource Planning (MRP II)

Enterprise Resource Planning Systems is a computer system that integrates application programs in accounting, sales, manufacturing, and other functions in the firm

This integration is accomplished through a database shared by all the application programs

ERP Systems

Typical ERP System

Video: ERP at Hillerich & Bradsby Notes:

Major ERP Providers

Firm HQ Acquisitions2004 Share of $23.6B Market

SAP Germany 40%

Oracle US People Soft

JD Edwards22%

Sage Group UK 7%

Microsoft US 3%

Infor US SSA

BaanSource: AMR Research

Desire to standardize and improve processes

To improve the level of systems integration

To improve information quality

Reasons to Implement ERP

ERP Drawbacks

Cost $250M+ for a Fortune 100 company

Transition painImplementation resourcesTrainingResistance to change

Summary and Conclusions… Master Production Schedule (MPS) converts

aggregate plan to a detailed schedule Primary inputs to MRP are MPS, BOM’s (for

part relationships) and Inventory Records (for lead times and inventory position)

MRP is a push system but can be used in conjunction with pull systems

MRP grew and evolved to include closed-loop, Manufacturing Resource Planning (MRP II), and eventually ERP