mri/ ct/ urgent care facilityeidsoninc.com/crmcurgentcare2017/division 00 - procurement and... ·...
TRANSCRIPT
PROJECT MANUAL
for
MRI/ CT/ URGENT CARE FACILITY
for the
CULLMAN REGIONAL MEDICAL CENTER 1912 Alabama Highway 157 Cullman, Alabama 35058
ADPH PROJECT NO. B-16-066
ISSUED FOR BIDS
January 23, 2017
Prepared By
2701 1st Avenue South, Suite 100 | Birmingham, AL 35233 Tel 205.879.4462 | GMCNETWORK.COM
GMC PROJECT NUMBER: HBHM160008
MRI /CT /URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. TABLE OF CONTENTS GMC PROJECT NO. HBHM160008 0 - 1/5
Division Section Title
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 002113 INSTRUCTIONS TO BIDDERS 002600 PROCUREMENT SUBSTITUTION PROCEDURES 003132 003132A
GEOTECHNICAL DATA GEOTECHNICAL REPORT
004321 ALLOWANCE FORM 004322 UNIT PRICES FORM 006000 PROJECT FORMS
DIVISION 01 - GENERAL REQUIREMENTS 011000 SUMMARY 012100 ALLOWANCES 012200 UNIT PRICES 012500 SUBSTITUTION PROCEDURES 012600 CONTRACT MODIFICATION PROCEDURES 012900 PAYMENT PROCEDURES 013100 013100.1
PROJECT MANAGEMENT AND COORDINATION ELECTRONIC FILE (CAD) RELEASE
013200 CONSTRUCTION PROGRESS DOCUMENTATION 013300 SUBMITTAL PROCEDURES 014000 QUALITY REQUIREMENTS 014100 STRUCTURAL TESTS AND SPECIAL INSPECTIONS 014200 REFERENCES 015000 TEMPORARY FACILITIES AND CONTROLS 016000 PRODUCT REQUIREMENTS 017300 EXECUTION 017329 CUTTING AND PATCHING 017700 CLOSEOUT PROCEDURES 017823 OPERATION AND MAINTENANCE DATA 017839 PROJECT RECORD DOCUMENTS 017900 DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS 024100 DEMOLITION
DIVISION 03 - CONCRETE 033000 CAST-IN-PLACE CONCRETE
MRI /CT /URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. TABLE OF CONTENTS GMC PROJECT NO. HBHM160008 0 - 2/5
DIVISION 04 - MASONRY 042000 UNIT MASONRY
DIVISION 05 - METALS 051200 STRUCTURAL STEEL 052100 STEEL JOISTS 053100 STEEL DECK 054000 COLD-FORMED METAL FRAMING 055000 METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES 061053 MISCELLANEOUS ROUGH CARPENTRY 061600 SHEATHING 064116 PLASTIC-LAMINATE-FACED ARCHITECTURAL CABINETS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION 071416 COLD FLUID-APPLIED WATERPROOFING 072100 THERMAL INSULATION 072726 FLUID-APPLIED MEMBRANE AIR BARRIERS 074213 METAL COMPOSITE MATERIAL WALL PANELS 075420 PVC (KEE) ROOFING 077100 ROOF SPECIALTIES 077200 ROOF ACCESSORIES 078413 PENETRATION FIRESTOPPING 078443 JOINT FIRESTOPPING 079200 JOINT SEALANTS
DIVISION 08 - OPENINGS 081113 HOLLOW METAL DOORS AND FRAMES 081416 FLUSH WOOD DOORS 083313 COILING COUNTER DOORS 083616 EXAM ROOM SLIDING DOOR ASSEMBLIES 084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS 087100 DOOR HARDWARE 088000 GLAZING 088300 MIRRORS
MRI /CT /URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. TABLE OF CONTENTS GMC PROJECT NO. HBHM160008 0 - 3/5
DIVISION 09 - FINISHES 092216 NON-STRUCTURAL METAL FRAMING 092900 GYPSUM BOARD 095113 ACOUSTICAL PANEL CEILINGS 096513 RESILIENT BASE AND ACCESSORIES 096516 RESILIENT SHEET FLOORING 096519 RESILIENT TILE FLOORING 096543 LINOLEUM FLOORING 099123 INTERIOR PAINTING
DIVISION 10 - SPECIALTIES 102113 PLASTIC-LAMINATE-CLAD TOILET COMPARTMENTS 102123 CUBICLE CURTAINS AND TRACK 102600 WALL PROTECTION 102800 TOILET ACCESSORIES 104413 FIRE PROTECTION CABINETS 104416 FIRE EXTINGUISHERS 105113 METAL LOCKERS 107300 OVERHEAD SUPPORTED ALUMINUM CANOPIES
DIVISION 12 - FURNISHINGS 122413 ROLLER WINDOW SHADES
DIVISION 13 - SPECIAL CONSTRUCTION 134900 RADIATION PROTECTION
DIVISION 21 – FIRE SUPPRESSION 210500 GENERAL PROVISIONS-FIRE SUPPRESSION 211000 MATERIALS AND METHODS-FIRE SUPPRESSION 214000 FIRE PROTECTION
DIVISION 22 - PLUMBING 220500 GENERAL PROVISIONS - PLUMBING 221000 MATERIALS AND METHODS - PLUMBING 221500 THERMAL AND ACOUSTICAL INSULATION FOR PLUMBING SYSTEMS 222000 PLUMBING FIXTURES AND EQUIPMENT
MRI /CT /URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. TABLE OF CONTENTS GMC PROJECT NO. HBHM160008 0 - 4/5
DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING 230500 GENERAL PROVISIONS - HVAC 231000 MATERIALS AND METHODS - HVAC 231500 THERMAL AND ACOUSTICAL INSULATION FOR HVAC SYSTEMS 235000 HEATING AND AIR CONDITIONING EQUIPMENT AND SPECIALTIES 236000 AIR DISTRIBUTION 237000 HVAC TESTING AND BALANCING 238100 BUILDING AUTOMATION SYSTEM (BAS)
DIVISION 26 - ELECTRICAL 260101 ELECTRICAL – GENERAL PROVISIONS 260102 ELECTRICAL – SCOPE OF WORK 260104 BASIC MATERIALS AND METHODS 260519 CONDUCTORS 260526 GROUNDING 260533.1 RACEWAYS - METAL 260533.2 RACEWAYS – NON METALLIC 260533.3 OUTLET AND JUNCTION BOXES 260534 RACEWAY SYSTEMS FOR WONER FURNISHED EQUIPMENT 262213 DRY TYPE TRANSFORMERS 262416.1 PANELBOARDS – LIGHTING RECEPTACLE 262146.2 PANELBOARDS - POWER 262726 BASIC DEVICES 262813 FUSES 262816.1 SAFETY SWITCHES 262816.2 CIRCUIT BREAKERS – INDIVIDUALLY MOUNTED 263623 AUTOMATIC LINE TRANSFER SWITCHES 265000 LIGHTING MATERIALS AND METHODS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY 283100.1 FIRE ALARM SYSTEM
DIVISION 31 - EARTHWORK 312000 EARTH MOVING 312500 EROSION AND SEDIMENTATION CONTROL
MRI /CT /URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. TABLE OF CONTENTS GMC PROJECT NO. HBHM160008 0 - 5/5
313116 TERMITE CONTROL
DIVISION 32 – EXTERIOR IMPROVEMENTS 321216 HOT MIX ASPHALT 321313 PORTLAND CEMENT CONCRETE PAVING 321613 CURBS AND GUTTERS 321723 PAVEMENT MARKING 328423 UNDERGROUND IRRIGATION SYSTEM 329000 PLANTING
DIVISION 33 - UTILITIES 331000 WATER SERVICE PIPING 333000 SANITARY SEWERAGE 334000 STORM DRAINAGE
END OF TABLE OF CONTENTS
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. INSTRUCTIONS TO BIDDERS GMC PROJECT NO. HBHM160008 002113 - 1/1
DOCUMENT 002113 - INSTRUCTIONS TO BIDDERS
1.1 INSTRUCTIONS TO BIDDERS
A. AIA Document A701, "Instructions to Bidders," is hereby incorporated into the Procurement and Contracting Requirements by reference.
1. A copy of AIA Document A701, "Instructions to Bidders," will be provided under separate cover by the Architect.
1.2 RELATED REQUIREMENTS
1. Section 004313 “Bid Security Forms” for Bid Bond requirements.
END OF DOCUMENT 002113
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. PROCUREMENT SUBSTITUTION PROCEDURES GMC PROJECT NO. HBHM160008 002600 - 1/3
SECTION 002600 - PROCUREMENT SUBSTITUTION PROCEDURES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitution requests made prior to receipt of bids.
B. Related Requirements: 1. Section 012500 “Substitution Procedures” for product substitution requirements.
1.3 DEFINITIONS
A. Procurement Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Procurement and Contracting Documents, submitted prior to receipt of bids.
B. Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Contract Documents, submitted following Contract award. See Section 012500 "Substitution Procedures" for conditions under which Substitution requests will be considered following Contract award.
1.4 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.5 PROCUREMENT SUBSTITUTIONS
A. Procurement Substitutions, General: By submitting a bid, the Bidder represents that its bid is based on materials and equipment described in the Procurement and Contracting Documents, including Addenda. Bidders are encouraged to request approval of qualifying substitute materials and equipment when the Specifications Sections list materials and equipment by product or manufacturer name.
B. Procurement Substitution Requests will be received and considered by Owner when the following conditions are satisfied, as determined by Architect; otherwise requests will be returned without action:
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. PROCUREMENT SUBSTITUTION PROCEDURES GMC PROJECT NO. HBHM160008 002600 - 2/3
1. Extensive revisions to the Contract Documents are not required. 2. Proposed changes are in keeping with the general intent of the Contract Documents,
including the level of quality of the Work represented by the requirements therein. 3. The request is fully documented and properly submitted.
1.6 SUBMITTALS
A. Procurement Substitution Request: Submit to Architect. Procurement Substitution Request must be made in writing by prime contract Bidder only in compliance with the following requirements:
1. Requests for substitution of materials and equipment will be considered if received no
later than 10 days prior to date of bid opening.
2. Submittal Format: a. Submit three copies of each Substitution Request, using CSI Form 1.5C,
“Substitution Request (During the Bidding Phase)”.
3. Substitution Request shall include at minimum, the following:
a. Identify the product or the fabrication or installation method to be replaced in each request. Include related Specifications Sections and drawing numbers.
b. Provide complete documentation on both the product specified and the proposed substitute, including the following information as appropriate: 1) Point-by-point comparison of specified and proposed substitute product
data, fabrication drawings, and installation procedures. 2) Copies of current, independent third-party test data of salient product or
system characteristics. 3) Samples where applicable or when requested by Architect. 4) Detailed comparison of significant qualities of the proposed substitute
with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
5) Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
6) Research reports, where applicable, evidencing compliance with building code in effect for Project, from ICC-ES.
7) Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, which will become necessary to accommodate the proposed substitute.
c. Provide certification by manufacturer that the substitute proposed is equal to or superior to that required by the Procurement and Contracting Documents, and
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. PROCUREMENT SUBSTITUTION PROCEDURES GMC PROJECT NO. HBHM160008 002600 - 3/3
that its in-place performance will be equal to or superior to the product or equipment specified in the application indicated.
d. Bidder, in submitting the Procurement Substitution Request, waives the right to additional payment or an extension of Contract Time because of the failure of the substitute to perform as represented in the Procurement Substitution Request.
B. Architect's Action:
1. Architect may request additional information or documentation necessary for evaluation of the Procurement Substitution Request. Architect will notify all bidders of acceptance of the proposed substitute by means of an Addendum to the Procurement and Contracting Documents.
C. Architect's approval of a substitute during bidding does not relieve Contractor of the responsibility to submit required shop drawings and to comply with all other requirements of the Contract Documents.
END OF DOCUMENT 002600
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. GEOTECHNICAL DATA GMC PROJECT NO. HBHM160008 003132 - 1/1
SECTION 003132 - GEOTECHNICAL DATA
1.1 GEOTECHNICAL DATA
A. This Document with its referenced attachments is part of the Procurement and Contracting Requirements for Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of Bidders' own investigations. They are made available for Bidders' convenience and information, but are not a warranty of existing conditions. This Document and its attachments are not part of the Contract Documents.
B. A geotechnical investigation report for Project, prepared by Goodwyn, Mills and Cawood, dated July 29, 2016, is available for viewing as appended to this Document.
C. Related Requirements:
1. Document 002113 "Instructions to Bidders" for the Bidder's responsibilities for examination of Project site and existing conditions.
END OF DOCUMENT 003132
JULY 29, 2016
REPORT OF GEOTECHNICAL EXPLORATION
CULLMAN REGIONAL
MEDICAL CENTER MRI/CT/URGENT CARE FACILITY
CULLMAN, CULLMAN COUNTY
ALABAMA
GM&C PROJECT NO. GBHM160031
TABLE OF CONTENTS
Page
1.0 PROJECT INFORMATION AND SCOPE OF WORK ......................................................................... 1
1.1 Project Information ........................................................................................................................................... 1 1.2 Scope of Work ................................................................................................................................................... 1
2.0 SITE AND SUBSURFACE CONDITIONS ............................................................................................ 2
2.1 General ............................................................................................................................................................... 2 2.2 Site Geology ....................................................................................................................................................... 2 2.3 Subsurface Conditions ..................................................................................................................................... 2 2.4 Groundwater Information ............................................................................................................................... 3 2.5 Laboratory Analyses ........................................................................................................................................ 3
3.0 RECOMMENDATIONS ............................................................................................................................ 4
3.1 Sitework Preparation ........................................................................................................................................ 4 3.2 Weathered Rock/Rock Excavation ................................................................................................................ 4 3.3 Time of Year Site Preparation Considerations .............................................................................................. 5 3.4 Fill Placement .................................................................................................................................................... 6 3.5 Backfilling Utility Trenches ............................................................................................................................. 7 3.6 Foundations ....................................................................................................................................................... 7 3.7 Floor Slabs .......................................................................................................................................................... 8
4.0 PAVEMENTS ............................................................................................................................................. 10
4.1 Pavement Subgrade ........................................................................................................................................ 10 4.2 Rigid Pavement ............................................................................................................................................... 10 4.3 Flexible Pavement ........................................................................................................................................... 11
5.0 OTHER CONSIDERATIONS ................................................................................................................. 12
5.1 Construction Services ..................................................................................................................................... 12
6.0 REPORT LIMITATIONS ......................................................................................................................... 13
APPENDIX: Boring Location Plans Soil Classification Chart Subsurface Diagrams Boring Records Summary of Laboratory Results Field and Laboratory Procedures
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 1 of 14
1.0 PROJECT INFORMATION AND SCOPE OF WORK
1.1 Project Information
A geotechnical exploration and evaluation has been conducted for the proposed Cullman Regional
Medical Center located in Cullman, Alabama. The proposed building will be a 1-story structure with
slab-on-grade and metal stud framing. The building will be approximately 10,000 SF in size and will be
within ±2 feet of existing grades. The existing parking lot will also be reconfigured and regraded. The
existing gravel parking lot north of the proposed building will also be graded and paved. We understand
that cuts up to 5 feet may be required in the gravel parking lot to achieve final grades.
The purpose of the exploration and evaluation is to provide a characterization of the site pertaining to site
preparation issues including earthwork and excavation considerations and recommendations relative to
design and construction of foundations; however no structural loads have been provided at this time.
1.2 Scope of Work
The purpose of this exploration was to perform a general evaluation of the subsurface conditions at the
site and to provide general sitework recommendations, recommended foundation types, and pavement
recommendations. The scope of the exploration and evaluation included a site reconnaissance, field and
laboratory testing, and an engineering evaluation of the foundation materials.
The scope of services for the geotechnical study did not include any environmental assessment for the
presence or absence of wetlands or hazardous or toxic materials in the soil, surface water, groundwater,
or air, on or below or around this site. Any statements in this report or on the boring records regarding
odors, colors, or unusual or suspicious items or conditions are strictly for the information of the client.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 2 of 13
2.0 SITE AND SUBSURFACE CONDITIONS
2.1 General
The proposed new building location is currently in an existing parking lot for the Cullman Medical
Center. The proposed new parking lot north of the proposed new building is currently covered with
gravel.
2.2 Site Geology
Published geologic information and our experience indicates that the site is underlain by the Pottsville
formation. The Pottsville formation consists of alternating beds of sandstone, shale, and siltstone with
coal seams within the shale. The bedrock weathers to form clayey sand and sandy clay soils with varying
amounts of silt. The bedrock surface is relatively level in the formation.
2.3 Subsurface Conditions
Six (6) soil borings were performed at the site; two (2) in the proposed building area (B-1 and B-3) and
four (4) in the planned parking and drive areas. Boring B-4 was drilled in the proposed south parking lot,
B-2 in the proposed west parking lot near the existing cooling towers, and B-5 and B-6 in the north
parking lot across Kress Drive. Borings B-1, B-2, and B-3 were drilled to auger refusal depths of 10, 4, and
11 feet, respectively. The pavement borings were drilled to a boring termination depths ranging from 5.5
to 15.5 feet.
The borings were drilled using a truck mounted drill rig (CME 45) equipped with a rotary head and
hollow stem augers (HSA). Soils were sampled using a two-inch OD split barrel sampler driven with a
manual hammer. The boring locations were selected and staked in the field by GMC. The ground
surface elevations at the boring locations were determined by GMC survey crew.
Borings B-1 through B-4
The borings encountered medium to hard sandy LEAN CLAYS (Unified Soils Classification System CL)
to depths ranging from 4 to 6 feet below grade. Standard penetration tests (SPT) N-values in this soil
ranged from 9 to over 50 blows per foot (bpf). Boring B-1 encountered very dense clayey SAND (SC), or
partially weathered sandstone, from about 6 feet to the auger refusal depth of 10 feet. Standard
penetration tests (SPT) N-values in this soil was over 50 blows per foot (bpf). Boring B-3 encountered
hard SILT (ML), or weathered siltstone, from 3.5 feet to the refusal depth of 11 feet. Standard penetration
tests (SPT) N-values in this soil was over 50 blows per foot (bpf).
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 3 of 13
Borings B-5 and B-6
Material classified as FILL was encountered in borings B-5 and B-6. The fill consisted of medium to very
stiff lean clay (CL) and loose to medium SILTY, CLAYEY SAND with GRAVEL (SC-SM). The depth of
the FILL in borings B-5 extended to approximately 6 feet below existing grade. In boring B-6, the FILL
was present to the boring termination depth of 15.5 feet. Standard penetration tests (SPT) N-values in
this soil ranged from 10 to 20 blows per foot (bpf).
Refusal Material
Auger refusal was encounter in borings B-1 through B-3 at depths ranging from 4 to 11 feet below the
ground’s surface. Auger refusal is likely the less weathered parent bedrock. Rock coring of the material
would be required to confirm the material type and continuity. Rock coring was beyond the scope of this
exploration. However, these shallow refusal depths are common in this geology and the weathering of
the weathering of the parent bedrock gradually decreases with depth.
General
The subsurface descriptions contained herein are of a generalized nature to highlight the major soil
stratification features and soil characteristics. The boring records included in the appendix should be
reviewed for specific information as to individual boring locations. The stratification shown on the
boring records represents conditions only at the actual boring locations. Variations may occur and
should be expected between boring locations. The stratifications represent the approximate boundary
between subsurface materials, and the transition may be gradual.
2.4 Groundwater Information
At the time of our field activities, no groundwater was present in the borings. It is important to note that
the groundwater levels may not have stabilized in the borings. Furthermore, groundwater levels may
vary due to seasonal conditions, runoff, and other factors not evident at the time of drilling.
2.5 Laboratory Analyses
The soil samples collected were visually classified in the field by a geotechnical engineer. Selected
samples were tested in our laboratory. These tests consisted of natural moisture contents, Atterberg
limits, and grain size distribution. The results are shown on the Boring Records and the laboratory data
sheets in the Appendix.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 4 of 13
3.0 RECOMMENDATIONS
3.1 Sitework Preparation
Sitework preparation should consist of the following:
Removal of all existing asphalt, curb and gutter, and tree roots in the proposed new construction
areas.
After the site has been brought to grade and before the placement of any fill material, the
subgrade should be proofrolled using a loaded tandem-axle dump truck or similar approved
equipment. Areas that rut or pump excessively should be undercut and replaced based upon the
geotechnical engineer’s recommendation.
We recommend a GM&C geotechnical engineer or qualified soils technician observe the
undercutting operations.
The amount of undercutting will heavily depend on the season, prevailing weather conditions, and/or
rainfall at or just before sitework takes place. During the wet season, the amount of undercutting may be
greater, whereas in drier weather, lesser amounts of undercutting may be necessary, if recompaction or
stabilization of soils left in place can be achieved. Stabilization using geotextile such as a Mirafi HP270 or
approved equal with stone and/or bridging of marginally suitable soils can be a more flexible option in
pavement areas.
Once the geotechnical engineer has approved the subgrade area, it can be filled following the Fill
Placement recommendations.
3.2 Weathered Rock/Rock Excavation
In this area, typically material that can be augered through can be removed in large excavations by
conventional grading equipment. Weathered rock can normally be removed by ripping in mass
excavations. The hard soil and partially weathered rock (PWR) will likely require loosening with
equipment such as a Caterpillar D8 or larger dozer equipped with a single tooth ripper or other means.
Intact bedrock will likely require blasting to remove. In confined excavations such as for utilities or
foundations, a hydraulic-ram or limited blasting may be required. It is our opinion that it would be
reasonable to have the grading contractors bid the project on the basis of unclassified excavation.
Unclassified excavation is commonly used for bidding excavation work in rock units where there is
gradual change from soil to partially weathered rock to intact bedrock.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 5 of 13
If blasting is required during construction, it will be important to control blasting so that the rock below
the established final grade is not fractured to a high degree. The over-break and disturbance of rock
below the final grade can create voids and “fluffed up” rock that must be removed prior to foundation
construction. Consequently, minimizing rock disturbance beneath structural areas will be an important
item when resistant rock beds are excavated. Exercising strict elevation control when drilling the shot
holes is the first step in controlling overblasting of rock below the final grade. We recommend that the
grading specifications state that the contractor will be responsible for removing any over-blasted rock and
replacing the disturbed rock with lean concrete or compacted engineered fill as appropriate. The grading
contractor should recognize the stratified condition of the rock and the fact that resistant sandstone beds
could be underlain by softer shale beds and thin clay seams, or vice versa. Also, because the rock is
layered, it will tend to break in slab-like pieces.
3.3 Time of Year Site Preparation Considerations
During periods of heavy rain, the near surface soils can become saturated unstable conditions can occur.
The time of the year that the sitework begins can affect the project considerably. In this area, the “wet
season” is generally between the months of November and May, and the “dry season” from June to
October. There are many considerations that need to be addressed prior to bidding a project that could
affect the budget based on the time of year a project starts earthwork activities. The time of the year that
the geotechnical borings were performed can provide a false sense of actual near surface conditions
depending on the time of year and weather conditions. Below are considerations that should be
addressed based on the time of the year earthwork is started.
“Wet” Season
During the wet season, the amount of undercutting may be greater, therefore resulting in greater
excavation costs. The soils are typically proofrolled to determine their suitability for the placement of
new fill or subgrade support. During the wet season, the surface soils have a higher moisture content
and will tend to pump, therefore, hindering the placement of new fill. In addition, the drying time, time
period between rain events, and temperature is not conducive to scarify soils, allow to dry, and
recompact. At this time, the decision should be made by the owner to try either scarify/dry/compact the
in-place soils, which could take time, or undercut and replace with suitable material, which could
increase the sitework costs. Based on our experience, the amount of undercut could be 1 to 2 feet more
(or greater in localized areas), whereas in drier weather, lesser amounts of undercutting may be
necessary, if recompaction or stabilization of soils left in place can be achieved. Stabilization using
geotextile or geogrid with stone and/or bridging of marginally suitable soils can be a more flexible option
in pavement areas.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 6 of 13
Some undercut soils are not always “unsuitable” soil and can be moisture conditioned and reused as fill
in the deep areas, if drying conditions are favorable.
The site contractor shall be responsible for maintaining a firm, unyielding and stable subgrade condition.
Should the near surface soils become wet, the contractor should be prepared to mitigate these conditions
by repeated aeration and exposure to sunlight or by admixture treatment (such as lime).
“Dry” Season
During the dry season, the surface soils have a lower moisture content and will tend to “bridge” or
“crust” softer underlying soils. They will generally allow the placement of new fill, but the crust can
break down if repeated passes with heavily loaded equipment is persistent. In addition, new fill from
cuts or other sources may need to be moisture conditioned prior to compaction. The soils can dry
significantly, requiring the addition of water for proper compaction. Water trucks should be used, as
required, by the contractor to condition the soils within the required specifications.
Contractor Responsibility
The grading contractors have the option of performing their own evaluation of the site conditions to
assess the excavation considerations based on the time of year a project is bid. We strongly suggest that
the grading contractors conduct their own exploration and evaluation of the site conditions and material
management requirements to cost effectively develop the site.
Typically, due to the movement of heavy equipment and weather conditions, the subgrade becomes
disturbed during construction. As a result, fine grained (clayey and silty) soils have a tendency to lose
shear strength and support capability. Therefore, additional effort on the Contractor’s part will be
required to reduce traffic and limit disturbance of soils. It is essential that the subgrade be restored to a
properly compacted condition based on optimum moisture and density requirements. Restoration of the
subgrade should be addressed in the project specifications.
3.4 Fill Placement
Select fill material in the building area and 5 feet beyond the building perimeter and in pavement areas
should be compacted to at least 98 percent of the standard Proctor (ASTM D-698) maximum dry density with
moisture requirements of minus 3 to plus 3 percentage points of the optimum moisture content.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 7 of 13
Fill material should meet the following characteristics:
Material Property Specification
Liquid Limit (LL) < 50%
Plasticity Index (PI) < 25%
Maximum Dry Density (ASTM D-698) 100 pcf
Particle Size 3 inches or less
The on-site LEAN CLAY (CL) and CLAYEY SAND (SC) should be acceptable as fill material; however,
they will likely need to be moisture conditioned prior to use to achieve compaction. Samples of the
proposed fill materials should be provided to the geotechnical engineer for Proctor testing and evaluation
prior to placement. Density tests should be performed to document compaction and moisture content of
any earthwork involving soils and other applicable materials. Density tests should be performed
frequently, with a recommended minimum of one test per lift of fill under all structures and one test per
5,000 square feet per lift in other areas.
3.5 Backfilling Utility Trenches
Backfilling of storm drain and utility trenches must be performed in a controlled manner to reduce
settlement of the fill and cracking of overlying floor slabs and pavements. We recommend that utility
trenches be backfilled with acceptable borrow or dense-graded crushed stone in 6-inch loose lifts
compacted with mechanical piston tampers to the project requirements. Should seepage occur in utility
trenches, it may be necessary to “floor” the trench with dense-graded gravel to provide a working
surface. If crushed stone is used to backfill utility trenches, we recommend that dense graded
aggregate (DGA, compacted in lifts) be used. Open-graded crushed stone, such as ALDOT #57, can
serve as a channel for seepage toward structures and therefore is not recommended for use as utility
trench backfill within 10 feet of the building perimeter.
3.6 Foundations
Although no structural loads have been provided at this time, we believe that the building can be
supported on conventional shallow foundations designed for a net allowable bearing pressure of 3,000
psf for individual column footings and 2,500 pounds per square foot (psf) for continuous or wall
footings. This assumes the footings bear on stiff naturally occurring soil or compacted fill as
recommended. Assuming relatively light loads, we anticipate settlements of approximately 1 inch, total
for columns and ½ inch differential between adjacent columns and along 40-foot lengths of the walls.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 8 of 13
Footings should bear on naturally occurring stiff soils or fill compacted to at least 98% standard Proctor
density. Exterior foundations should bear at a minimum of 18 inches below exterior adjacent grade;
interior foundations should bear at a minimum of 12 inches. All foundation excavations should be
cleared of all loose soil prior to concrete placement.
Even though computed footing dimensions may be less, column footings and continuous footings should
have minimum dimensions of 24 inches and 18 inches, respectively. This allows for hand cleaning of
materials disturbed during the excavation process and reduces the potential for punching shear failure.
The geotechnical engineer or his representative should observe all foundation excavations. The
engineer can provide geotechnical guidance to the owner’s design team should any unforeseen
foundation problems develop during construction. If any areas of foundation surfaces prove to be
unsuitable, the foundation excavation should be over-excavated. The over-excavated area can be
backfilled with “lean” concrete up to the planned foundation bearing depth.
Foundation concrete should be placed the same day as soon as possible so that the foundation bearing soils
can remain near the existing moisture content. Foundation bearing surfaces should not be disturbed or left
exposed during inclement weather. Saturation of the on-site soils can cause a loss of strength and
increased compressibility. Excavations for footings should be hand cleaned to remove any loose soil or
mud from the foundation bearing surface. If concreting is not possible immediately after excavation, we
recommend that a thin layer (approximately 2 inches) of lean concrete or CLSM be placed on the bearing
surface for protection after we have observed and evaluated the exposed bearing surfaces. Exposed
bearing soils should be compacted prior to placement of reinforcing.
3.7 Floor Slabs
It is our opinion that floor slabs can be built on-grade achieving support from properly compacted fills as
outlined in the Site Preparation section of this report. Ground supported slabs should be founded on a
minimum of 4 inches of compacted, material such as an open graded crushed stone or gravel such as
ALDOT #57, or a clean sand or dense graded aggregate (DGA) with less than 10% passing the #200 sieve.
Granular material and DGA should be compacted to at least 95% of the standard Proctor density. This
layer should provide uniform and immediate support for the slab and act as a capillary break. A vapor
retarder should be used on top of the granular layer, as required by the building use.
Care should be taken so that fines from the subgrade are not allowed to contaminate the granular layer.
If fines do contaminate this layer, capillary rise and subsequent damage to moisture sensitive floor
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 9 of 13
coverings could occur. On most projects, there is some time lag between initial grading and the time
when the contractor is ready to place concrete for the slab-on-grade. Inclement weather just prior to
placement of concrete for the slab-on-grade can result in trapped water in the granular layer.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 10 of 13
4.0 PAVEMENTS
4.1 Pavement Subgrade
Typically, during construction, the pavement subgrade becomes disturbed because of traffic and
environmental conditions. Prior to construction of pavements, it is essential that the subgrade be restored
to a properly compacted condition. The specifications should include notes pertaining to subgrade
restoration immediately prior to pavement construction. The on-site soils will have a tendency to lose
shear strength (and consequently pavement support capability) if they are exposed to excessive moisture.
Thus, proper moisture conditioning of the subgrade prior to placement of the pavement base course will
result in better pavement performance. Subgrade soils should be compacted to at least 98 percent of the
materials standard Proctor maximum dry density.
4.2 Rigid Pavement
All Portland cement concrete pavements should contain 4 to 6 percent entrained air assuming the mix will
contain ¾ -inch to 1-inch nominal maximum size aggregate. Concrete slump should be no more than 2
inches when placed by slip forming and no more than 4 inches for non-slip formed concrete. Minimum 28-
day concrete compressive strength should be 4,000 psi and minimum flexural strength 550 psi.
RIGID PAVEMENT MINIMUM THICKNESS
Pavement Materials Light Duty (inches) Heavy Duty (inches)
Portland Cement Concrete 5 7
Crushed Aggregate Base Course 4 4
Pavement joints, reinforcing, and details should be designed in accordance with the applicable American
Concrete Institute (ACI) standards.
Areas to be paved should be prepared as recommended in Site Preparation section of this report.
Portland cement concrete pavement should meet the requirements of ALDOT Section 450 and the
crushed aggregate base course should meet the requirements of Section 825 Type B.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 11 of 13
4.3 Flexible Pavement
No traffic information has been provided; however, we assume that typical traffic will include
automobiles and occasional trucks in parking areas and drives. If this traffic information changes, it
should be provided to Goodwyn, Mills and Cawood, Inc. so that we can review the pavement
recommendations and make any necessary changes to the pavement sections.
Typical minimum recommended pavement sections for this project site are as follows:
FLEXIBLE PAVEMENT MINIMUM THICKNESS
Pavement Materials Standard Duty (inches) Heavy Duty (inches)
Asphaltic Concrete Surface Course 1 1.5
Asphaltic Concrete Binder Course 2 3
Crushed Aggregate Base Course 6 8
The pavement sections represent minimum recommended thickness for a pavement section designed for
a 20-year life. However, periodic maintenance should be anticipated over the pavement design life. All
pavement materials and construction procedures should conform to the State of Alabama Department of
Transportation Standard Specifications for Highway Construction, 2012 Edition. The crushed aggregate base
stone should be an aggregate as outlined in Section 825, Type B, and should be compacted to at least 98
percent of the modified Proctor (AASHTO T-180) maximum dry density. The hot-mix asphalt should
conform to Section 424.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 12 of 13
5.0 OTHER CONSIDERATIONS
5.1 Construction Services
Field observations, monitoring, and quality assurance testing during earthwork and foundation
installation are an extension of the geotechnical design. We recommend that Goodwyn, Mills, and
Cawood, Inc. be allowed to continue our involvement in the project through these phases of construction.
Quality assurance observations and testing related to earthwork should be performed by competent
personnel under the general administrative supervision of a geotechnical engineer familiar with the
design requirements and considerations of this project. We recommend that qualified geotechnical
personnel observe proofrolling and associated undercutting, as required, foundation excavations and
subgrades, evaluate the materials to be used as fill, and test the compaction of all fill and backfill.
________________________________________________________________________________________________________ Proposed Cullman Regional Medical Center July 29, 2016 GM&C Project No. GBHM160031 Page 13 of 13
6.0 REPORT LIMITATIONS
The recommendations submitted are based on the available soil information obtained by GM&C and
design details furnished by GM&C for the proposed project. If there are any revisions to the plans for
this project or if deviations from the subsurface conditions noted in this report are encountered during
construction, we should be notified immediately to determine if changes in the foundation, or other,
recommendations are required. If GM&C is not retained to perform these functions, GM&C cannot be
responsible for the impact of those conditions on the performance of the project.
The geotechnical engineer warrants that the findings, recommendations, specifications, or professional
advice contained herein have been made in accordance with generally accepted professional geotechnical
engineering practices in the local area. No other warranties are implied or expressed.
After the plans and specifications are more complete, the geotechnical engineer should be provided the
opportunity to review the final design plans and specifications to check that our engineering
recommendations have been properly incorporated into the design documents. At that time, it may be
necessary to submit supplementary recommendations.
We emphasize that this report was prepared for design and informational purposes only and may not be
sufficient to prepare an accurate construction budget. Contractors reviewing this report should
acknowledge that the recommendations contained herein are for design and informational purposes only.
A more comprehensive exploration and testing program would be required to assist the contractor in
preparing the final building pad preparation, grading, and foundation construction budgets. In no case
should this report be utilized as a substitute for development of specific earthwork specifications.
The information contained in this report is not intended, nor is sufficient, to aid in the design of
segmental or mechanically stabilized earth (MSE) retaining walls. Segmental or MSE wall designers and
builders should not rely on this report and should perform independent analysis to determine all
necessary soil characteristics for use in their wall design, including but not limited to, soil shear strengths,
bearing capacities, global stability, etc.
APPENDIX
Boring Location Plans
Soil Classification Chart
Subsurface Diagram
Boring Records
Summary of Laboratory Results
Field and Laboratory Procedures
GBHM1600317.28.16
Boring Location PlanCullman MOBCullman, Alabama
B‐1
B‐4
B‐3
B‐2
BORING LOCATIONS APPROXIMATED IN THE FIELD BY REFERENCING SITE FEATURES
NOT TO SCALE
APPROXIMATE BORING LOCATIONSN
GBHM1600317.28.16
Boring Location PlanCullman MOBCullman, Alabama
B‐5
B‐6
BORING LOCATIONS APPROXIMATED IN THE FIELD BY REFERENCING SITE FEATURES
NOT TO SCALE
APPROXIMATE BORING LOCATIONSN
GRAVELAND
GRAVELLYSOILS
CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES
WELL-GRADED SANDS, GRAVELLYSANDS, LITTLE OR NO FINES
POORLY-GRADED SANDS,GRAVELLY SAND, LITTLE OR NOFINES
PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTS
LETTERGRAPH
SYMBOLSMAJOR DIVISIONS
COARSEGRAINED
SOILS
TYPICAL
DESCRIPTIONS
WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES, LITTLE OR NOFINES
POORLY-GRADED GRAVELS,GRAVEL - SAND MIXTURES, LITTLEOR NO FINES
SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES
CLEANGRAVELS
GRAVELS WITHFINES
CLEAN SANDS
(LITTLE OR NO FINES)
SANDS WITHFINES
LIQUID LIMITLESS THAN 50
LIQUID LIMITGREATER THAN 50
HIGHLY ORGANIC SOILS
NOTE: DUAL SYMBOLS ARE USED TO INDICATE BORDERLINE SOIL CLASSIFICATIONS
GW
GP
GM
GC
SW
SP
SM
SC
ML
CL
OL
MH
CH
OH
PT
SILTY SANDS, SAND - SILTMIXTURES
CLAYEY SANDS, SAND - CLAYMIXTURES
INORGANIC SILTS AND VERY FINESANDS, ROCK FLOUR, SILTY ORCLAYEY FINE SANDS OR CLAYEYSILTS WITH SLIGHT PLASTICITY
INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTYCLAYS, LEAN CLAYS
ORGANIC SILTS AND ORGANICSILTY CLAYS OF LOW PLASTICITY
INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS FINE SAND ORSILTY SOILS
INORGANIC CLAYS OF HIGHPLASTICITY
SILTSAND
CLAYS
MORE THAN 50%OF MATERIAL ISLARGER THANNO. 200 SIEVE
SIZE
MORE THAN 50%OF MATERIAL ISSMALLER THANNO. 200 SIEVE
SIZE
MORE THAN 50%OF COARSEFRACTION
PASSING ON NO.4 SIEVE
MORE THAN 50%OF COARSEFRACTION
RETAINED ON NO.4 SIEVE
SOIL CLASSIFICATION CHART
(APPRECIABLEAMOUNT OF FINES)
(APPRECIABLEAMOUNT OF FINES)
(LITTLE OR NO FINES)
FINEGRAINED
SOILS
SANDAND
SANDYSOILS
SILTSAND
CLAYS
ORGANIC CLAYS OF MEDIUM TOHIGH PLASTICITY, ORGANIC SILTS
800
805
810
815
820
825
830
0 20 40 60 80 100 120 140 160 180 200800
805
810
815
820
825
830
0 20 40 60 80 100 120 140 160 180 200
AR9.1'
EL 816.6'
30
19
13
50/5"
50/1"
4.5
4.5
AR4'
EL 824.5'
19 3.5
AR11'
EL 812.5'
16
24
50/5"
50/5"
50/1"
BT5.5'
EL 821.5'
12
50/3"
26
CLIENT Cullman Regional Medical Center
PROJECT LOCATION Cullman, AL
PROJECT NAME MRI/CT/Urgent Care Facility
SUBSURFACE DIAGRAMBuilding and Parking
CL SC Asphalt
GP ML
Distance Along Baseline (ft)BT - Boring TerminationAR - Auger Refusal
Ele
vatio
n (f
t)
PROJECT NUMBER GBHM160031
BT
-AR
DE
PT
H+
ELE
V L
OG
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T 7
/29/
16
B-1PPV(tsf)
N-Value(%REC/%RQD)
B-2PPV(tsf)
N-Value(%REC/%RQD)
B-3PPV(tsf)
N-Value(%REC/%RQD)
B-4PPV(tsf)
N-Value(%REC/%RQD)
810
815
820
825
830
835
840
0 10 20 30 40 50 60 70 80 90810
815
820
825
830
835
840
0 10 20 30 40 50 60 70 80 90
BT10.5'
EL 819'
17
26
7
9
50/5"
4.5
3.5
2.25
4.5
BT15.5'
EL 813.9'
10
20
10
20
20
4.5
CLIENT Cullman Regional Medical Center
PROJECT LOCATION Cullman, AL
PROJECT NAME MRI/CT/Urgent Care Facility
SUBSURFACE DIAGRAMNorth Parking Lot
FILL CL
Distance Along Baseline (ft)BT - Boring TerminationAR - Auger Refusal
Ele
vatio
n (f
t)
PROJECT NUMBER GBHM160031
BT
-AR
DE
PT
H+
ELE
V L
OG
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T 7
/29/
16
B-5PPV(tsf)
N-Value(%REC/%RQD) B-6
PPV(tsf)
N-Value(%REC/%RQD)
SS
SS
SS
SS
SS
63
16-17-13(30)
10-10-9(19)
6-6-7(13)
25-50/5"
50/1"
4.5
4.5
13 27 15 1212
SANDY LEAN CLAY (CL), brown, very stiff, moist
SANDY LEAN CLAY (CL), brown, very stiff, moist
SANDY LEAN CLAY (CL), red, stiff, moist
CLAYEY SAND (SC), red, very dense, medium to fine,moist - partially weathered sandstone
CLAYEY SAND (SC), brown, very dense, medium tofine, moist - partially weathered sandstoneAuger refusal was encountered at 9.1 feet.
NOTES
GROUND ELEVATION 825.7 ft
LOGGED BY J. Shaddix
DRILLING METHOD CME 45, Manual-Hammer, HSA w/SPT AT TIME OF DRILLING None Encountered
AT END OF DRILLING ---
AFTER DRILLING ---
HOLE SIZE 5"
DRILLING CONTRACTOR Smith Drilling GROUND WATER LEVELS:
CHECKED BY K. Wales
DATE STARTED 7/15/16 COMPLETED 7/15/16
ATTERBERGLIMITS
SA
MP
LE T
YP
EN
UM
BE
R
FIN
ES
CO
NT
EN
T(%
)
RE
CO
VE
RY
%(R
QD
)
BLO
WC
OU
NT
S(N
VA
LUE
)
PO
CK
ET
PE
N.
(tsf
)
DE
PT
H(f
t)
0
5
10
15
20
25
30
35
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PLA
ST
ICLI
MIT
PLA
ST
ICIT
YIN
DE
XP
LAS
TIC
ITY
IND
EX
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
GR
AP
HIC
LOG
MATERIAL DESCRIPTION
PAGE 1 OF 1BORING NUMBER B-1
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.G
MC
BO
RIN
GS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T
7/29
/16
SS 6-12-7(19) 3.5
2" Asphalt6" Base StoneSANDY LEAN CLAY (CL), red, very stiff, moist
Auger refusal was encountered at 4.0 feet.
NOTES
GROUND ELEVATION 828.5 ft
LOGGED BY J. Shaddix
DRILLING METHOD CME 45, Manual-Hammer, HSA w/SPT AT TIME OF DRILLING None Encountered
AT END OF DRILLING ---
AFTER DRILLING ---
HOLE SIZE 5"
DRILLING CONTRACTOR Smith Drilling GROUND WATER LEVELS:
CHECKED BY K. Wales
DATE STARTED 7/15/16 COMPLETED 7/15/16
ATTERBERGLIMITS
SA
MP
LE T
YP
EN
UM
BE
R
FIN
ES
CO
NT
EN
T(%
)
RE
CO
VE
RY
%(R
QD
)
BLO
WC
OU
NT
S(N
VA
LUE
)
PO
CK
ET
PE
N.
(tsf
)
DE
PT
H(f
t)
0
5
10
15
20
25
30
35
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PLA
ST
ICLI
MIT
PLA
ST
ICIT
YIN
DE
XP
LAS
TIC
ITY
IND
EX
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
GR
AP
HIC
LOG
MATERIAL DESCRIPTION
PAGE 1 OF 1BORING NUMBER B-2
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.G
MC
BO
RIN
GS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T
7/29
/16
SS
SS
SS
SS
SS
62
8-8-8(16)
14-11-13(24)
50/5"
50/5"
50/1"
10 28 20 88
SANDY LEAN CLAY (CL), brown, very stiff, moist
SANDY LEAN CLAY (CL), red, medium, moist
SILT (ML), reddish-brown, hard, moist - weatheredsiltstone
Auger refusal was encountered at 11.0 feet.
NOTES
GROUND ELEVATION 823.5 ft
LOGGED BY J. Shaddix
DRILLING METHOD CME 45, Manual-Hammer, HSA w/SPT AT TIME OF DRILLING None Encountered
AT END OF DRILLING ---
AFTER DRILLING ---
HOLE SIZE 5"
DRILLING CONTRACTOR Smith Drilling GROUND WATER LEVELS:
CHECKED BY K. Wales
DATE STARTED 7/15/16 COMPLETED 7/15/16
ATTERBERGLIMITS
SA
MP
LE T
YP
EN
UM
BE
R
FIN
ES
CO
NT
EN
T(%
)
RE
CO
VE
RY
%(R
QD
)
BLO
WC
OU
NT
S(N
VA
LUE
)
PO
CK
ET
PE
N.
(tsf
)
DE
PT
H(f
t)
0
5
10
15
20
25
30
35
ELE
VA
TIO
N(f
t)
820
815
810
805
800
795
790
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PLA
ST
ICLI
MIT
PLA
ST
ICIT
YIN
DE
XP
LAS
TIC
ITY
IND
EX
ELE
VA
TIO
N(f
t)
820
815
810
805
800
795
790
GR
AP
HIC
LOG
MATERIAL DESCRIPTION
PAGE 1 OF 1BORING NUMBER B-3
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.G
MC
BO
RIN
GS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T
7/29
/16
SS
SS
SS
8-6-6(12)
30-50/3"
14-15-11(26)
11
9
SANDY LEAN CLAY (CL), light red, medium, fine,moist
SANDY LEAN CLAY (CL), light red, hard, fine, moist -weathered siltstone
SANDY LEAN CLAY (CL), red, very stiff, moist -weathered siltstone
Boring was terminated at 5.5 feet.
NOTES
GROUND ELEVATION 827 ft
LOGGED BY J. Shaddix
DRILLING METHOD CME 45, Manual-Hammer, HSA w/SPT AT TIME OF DRILLING None Encountered
AT END OF DRILLING ---
AFTER DRILLING ---
HOLE SIZE 5"
DRILLING CONTRACTOR Smith Drilling GROUND WATER LEVELS:
CHECKED BY K. Wales
DATE STARTED 7/15/16 COMPLETED 7/15/16
ATTERBERGLIMITS
SA
MP
LE T
YP
EN
UM
BE
R
FIN
ES
CO
NT
EN
T(%
)
RE
CO
VE
RY
%(R
QD
)
BLO
WC
OU
NT
S(N
VA
LUE
)
PO
CK
ET
PE
N.
(tsf
)
DE
PT
H(f
t)
0
5
10
15
20
25
30
35
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PLA
ST
ICLI
MIT
PLA
ST
ICIT
YIN
DE
XP
LAS
TIC
ITY
IND
EX
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
GR
AP
HIC
LOG
MATERIAL DESCRIPTION
PAGE 1 OF 1BORING NUMBER B-4
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.G
MC
BO
RIN
GS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T
7/29
/16
SS
SS
SS
SS
SS
7-8-9(17)
8-12-14(26)
6-3-4(7)
5-5-4(9)
25-50/5"
4.5
3.5
2.25
4.5
14
14
SANDY LEAN CLAY (CL), brown, very stiff - FILL,moist
SILT (ML), dark brown, gray, medium - FILL, moist,with trace of organics
SANDY LEAN CLAY (CL), yellowish-brown, stiff, moist
SANDY LEAN CLAY (CL), reddish-brown, hard, moist -weathered siltstone
Boring was terminated at 10.5 feet.
NOTES
GROUND ELEVATION 829.5 ft
LOGGED BY J. Shaddix
DRILLING METHOD CME 45, Manual-Hammer, HSA w/SPT AT TIME OF DRILLING None Encountered
AT END OF DRILLING ---
AFTER DRILLING ---
HOLE SIZE 5"
DRILLING CONTRACTOR Smith Drilling GROUND WATER LEVELS:
CHECKED BY K. Wales
DATE STARTED 7/15/16 COMPLETED 7/15/16
ATTERBERGLIMITS
SA
MP
LE T
YP
EN
UM
BE
R
FIN
ES
CO
NT
EN
T(%
)
RE
CO
VE
RY
%(R
QD
)
BLO
WC
OU
NT
S(N
VA
LUE
)
PO
CK
ET
PE
N.
(tsf
)
DE
PT
H(f
t)
0
5
10
15
20
25
30
35
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PLA
ST
ICLI
MIT
PLA
ST
ICIT
YIN
DE
XP
LAS
TIC
ITY
IND
EX
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
GR
AP
HIC
LOG
MATERIAL DESCRIPTION
PAGE 1 OF 1BORING NUMBER B-5
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.G
MC
BO
RIN
GS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T
7/29
/16
SS
SS
SS
SS
SS
36
5-5-5(10)
8-10-10(20)
6-6-4(10)
10-10-10(20)
10-10-10(20)
4.5 13
7 19 14 55
SANDY LEAN CLAY (CL), red, stiff - FILL, moist
SILTY CLAYEY SAND with GRAVEL (SC-SM), brown,medium, coarse to fine- FILL, moist
SILTY CLAYEY SAND with GRAVEL (SC-SM), brown,loose, coarse to fine- FILL, moist
SILTY CLAYEY SAND with GRAVEL (SC-SM), darkgray, medium, coarse to fine- FILL, moist
Boring was terminated at 15.5 feet.
NOTES
GROUND ELEVATION 829.4 ft
LOGGED BY J. Shaddix
DRILLING METHOD CME 45, Manual-Hammer, HSA w/SPT AT TIME OF DRILLING None Encountered
AT END OF DRILLING ---
AFTER DRILLING ---
HOLE SIZE 5"
DRILLING CONTRACTOR Smith Drilling GROUND WATER LEVELS:
CHECKED BY K. Wales
DATE STARTED 7/15/16 COMPLETED 7/15/16
ATTERBERGLIMITS
SA
MP
LE T
YP
EN
UM
BE
R
FIN
ES
CO
NT
EN
T(%
)
RE
CO
VE
RY
%(R
QD
)
BLO
WC
OU
NT
S(N
VA
LUE
)
PO
CK
ET
PE
N.
(tsf
)
DE
PT
H(f
t)
0
5
10
15
20
25
30
35
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PLA
ST
ICLI
MIT
PLA
ST
ICIT
YIN
DE
XP
LAS
TIC
ITY
IND
EX
ELE
VA
TIO
N(f
t)
825
820
815
810
805
800
795
GR
AP
HIC
LOG
MATERIAL DESCRIPTION
PAGE 1 OF 1BORING NUMBER B-6
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.G
MC
BO
RIN
GS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T
7/29
/16
B-1 1.5-3 27 15 12 12.5 63 12.9 CL
B-3 1.5-3 28 20 8 9.5 62 10.1 CL
B-4 0-1.5 10.7
B-4 1.5-3 8.8
B-5 0-1.5 14.3
B-5 1.5-3 14.1
B-6 1.5-3 12.6
B-6 4-5.5 19 14 5 19 36 7.3 SC-SM
SpecificGravity
PAGE 1 OF 1
PlasticLimit
PlasticityIndex
%<#200Sieve
LiquidLimitDepth
NaturalMoisture
(%)Borehole
Max. SieveSize Tested
(mm)
SUMMARY OF LABORATORY RESULTS
Class-ification
Opt.MoistureContent
(%)
Max DryDensity
(pcf)
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
1.U
SC
S S
UM
MA
RY
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T 7
/29/
16
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.0010.010.1110100
coarse fine
ClassificationSpecimen Identification
Specimen Identification D100 D60 D30 D10 %Gravel
0.955
1.5-3.0
1.5-3.0
4.0-5.5
B-1
B-3
B-6
coarseSILT OR CLAY
2006
SANDY LEAN CLAY(CL)
SANDY LEAN CLAY(CL)
SILTY, CLAYEY SAND with GRAVEL(SC-SM)
PI Cc
15
20
14
27
28
19
CuLL PL
finemedium
10 501/2HYDROMETERU.S. SIEVE OPENING IN INCHES U.S. SIEVE NUMBERS
1403 4 20 406 601.5 8 143/4 3/8
GRAIN SIZE DISTRIBUTION
COBBLESGRAVEL
62.8
61.7
36.3
12.5
9.5
19
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
SAND
GRAIN SIZE IN MILLIMETERS
12
8
5
%Sand %Silt %Clay
8.6
1.1
29.4
28.6
37.2
34.3
3 100
B-1
B-3
B-6
24 16 301
1.5-3.0
1.5-3.0
4.0-5.5
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
7.G
RA
IN S
IZE
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T 7
/29/
16
0
10
20
30
40
50
60
0 20 40 60 80 100
LL PL PI
1.5-3.0
1.5-3.0
4.0-5.5
12
8
5
ATTERBERG LIMITS' RESULTS
SANDY LEAN CLAY(CL)
SANDY LEAN CLAY(CL)
SILTY, CLAYEY SAND with GRAVEL(SC-SM)
B-1
B-3
B-6
ML
CL
MH
CH
63
62
36
Specimen Identification
CL-ML
PLASTICITY
INDEX
LIQUID LIMIT
Fines Classification
27
28
19
15
20
14
CLIENT Cullman Regional Medical Center
PROJECT NUMBER GBHM160031
PROJECT NAME MRI/CT/Urgent Care Facility
PROJECT LOCATION Cullman, AL
2.A
TT
ER
BE
RG
LIM
ITS
GB
HM
1600
31 C
ULL
MA
N M
ED
ICA
L C
EN
TE
R.G
PJ
GM
C D
AT
A T
EM
PLA
TE
.GD
T 7
/29/
16
FIELD TEST PROCEDURES General The general field procedures employed by Goodwyn, Mills and Cawood, Inc. (GM&C), are summarized in the American Society for Testing and Materials (ASTM) Standard D420 which is entitled "Investigating and Sampling Soil and Rock". This recommended practice lists recognized methods for determining soil and rock distribution and groundwater conditions. These methods include geophysical and in-situ methods as well as borings. The detailed collection methods used during this exploration are presented in the following paragraphs. Standard Drilling Techniques General: To obtain subsurface samples, borings are drilled using one of several alternate techniques depending upon the subsurface conditions. These techniques are: In Soils: a) Continuous hollow stem augers. b) Rotary borings using roller cone bits or drag bits, and water or drilling mud to flush the hole. c) "Hand" augers. In Rock: a) Core drilling with diamond-faced, double or triple tube core barrels. b) Core boring with roller cone bits. Hollow Stem Auger: A hollow stem augers consists of a hollow steel tube with a continuous exterior spiral flange termed a flight. The auger is turned into the ground, returning the cuttings along the flights. The hollow center permits a variety of sampling and testing tools to be used without removing the auger. Rotary Borings: Rotary drilling involves the use of roller cone or drag type drill bits attached to the end of drill rods. A flushing medium, normally water or bentonite slurry, is pumped through the rods to clear the cuttings from the bit face and flush them to the surface. Casing is sometimes set behind the advancing bit to prevent the hole from collapsing and to restrict the penetration of the drilling fluid into the surrounding soils. Cuttings returned to the surface by the drilling fluid are typically collected in a settling tank, to allow the fluid to be recirculated. Hand Auger Boring: Hand auger borings are advanced by manually twisting a 4” diameter steel bucket auger into the ground and withdrawing it when filled to observe the sample collected. Posthole diggers are sometimes used in lieu of augers to obtain shallow soil samples. Occasionally these hand auger borings are used for driving 3-inch diameter steel tubes to obtain intact soil samples. Core Drilling: Soil drilling methods are not normally capable of penetrating through hard cemeted soil, weathered rock, coarse gravel or boulders, thin rock seams, or the upper surface of sound, continuous rock. Material that cannot be penetrated by auger or rotary soil-drilling methods at a reasonable rate is designated as “refusal material”. Core drilling procedures are required to penetrate and sample refusal materials. Prior to coring, casing may be set in the drilled hole through the overburden soils, to keep the hole from caving and to prevent excessive water loss. The refusal materials are then cored according to ASTM D2113 using a diamond studded bit fastened to the end of a hollow, double or triple tube core barrel. This device is rotated at high speeds, and the cuttings are brought to the surface by circulating water. Core samples of the material penetrated are protected and retained in the swivel-mounted inner tube. Upon completion of each drill run, the core barrel is brought to the surface, the core recovery is measured, and the core is placed, in sequence, in boxes for storage and transported to our laboratory.
Sampling and Testing in Boreholes General: Several techniques are used to obtain samples and data in soils; however the most common methods in this area are: a) Standard Penetrating Testing b) Water Level Readings These procedures are presented below. Any additional testing techniques employed during this exploration are contained in other sections of the Appendix. Standard Penetration Testing: At regular intervals, the drilling tools are removed and soil samples obtained with a standard 2 inch diameter split tube sampler connected to an A or N-size rod. The sampler is first seated 6 inches to penetrate any loose cuttings, and then driven an additional 12 inches with blows of a 140-pound safety hammer falling 30 inches. Generally, the number of hammer blows required to drive the sampler the final 12 inches is designated the "penetration resistance" or "N" value, in blows per foot (bpf). The split barrel sampler is designed to retain the soil penetrated, so that it may be returned to the surface for observation. Representative portions of the soil samples obtained from each split barrel sample are placed in jars, sealed and transported to our laboratory. The standard penetration test, when properly evaluated, provides an indication of the soil strength and compressibility. The tests are conducted according to ASTM Standard D1586. The depths and N-values of standard penetration tests are shown on the Boring Records. Split barrel samples are suitable for visual observation and classification tests but are not sufficiently intact for quantitative laboratory testing. Water Level Readings: Water table readings are normally taken in the borings and are recorded on the Boring Records. In sandy soils, these readings indicate the approximate location of the hydrostatic water table at the time of our field exploration. In clayey soils, the rate of water seepage into the borings is low and it is generally not possible to establish the location of the hydrostatic water table through short-term water level readings. Also, fluctuation in the water table should be expected with variations in precipitation, surface run-off, evaporation, and other factors. For long-term monitoring of water levels, it is necessary to install piezometers. The water levels reported on the Boring Records are determined by field crews immediately after the drilling tools are removed, and several hours after the borings are completed, if possible. The time lag is intended to permit stabilization of the groundwater table, which may have been disrupted by the drilling operation. Occasionally the borings will cave-in, preventing water level readings from being obtained or trapping drilling water above the cave-in zone. The cave-in depth is measured and recorded on the Boring Records. Boring Records The subsurface conditions encountered during drilling are reported on a field boring record prepared by the Driller. The record contains information concerning the boring method, samples attempted and recovered, indications of the presence of coarse gravel, cobbles, etc., and observations of ground water. It also contains the driller's interpretation of the soil conditions between samples. Therefore, these boring records contain both factual and interpretive information. The field boring records are kept on file in our office. After the drilling is completed, a geotechnical professional classifies the soil samples and prepares the final Boring Records, which are the basis for all evaluations and recommendations. The following terms are taken from ASTM D2487 or Deere's Technical Description of Rock Cores for Engineering Purposes, Rock Mechanical Engineering Geology 1, pp. 18-22.
Relative Density of Cohesionless Soils From Standard Penetration Test
Consistency of Cohesive Soils
Very Loose < 4 bpf Loose 5 - 10 bpf Medium 11 - 30 bpf Dense 31 - 50 bpf Very Dense > 50 bpf (bpf = blows per foot, ASTM D 1586)
Very Soft < 2 bpf Soft 3 - 4 bpf Medium 5 - 8 bpf Stiff 9 - 15 bpf Very Stiff 16 - 30 bpf Hard > 30 bpf
Relative Hardness of Rock Particle Size Identification Very Soft Rock disintegrates or easily compresses to touch; can be hard to very hard soil. Soft Rock may be broken with fingers. Moderately Soft Rock may be scratched with a nail, corners and edges may be broken with fingers. Moderately Hard Rock a light blow of hammer is required to break samples. Hard Rock a hard blow of hammer is required to break sample.
Boulders Larger than 12" Cobbles 3" - 12" Gravel Coarse 3/4" - 3" Fine 4.76mm - 3/4" Sand Coarse 2.0 - 4.76 mm Medium 0.42 - 2.00 mm Fine 0.42 - 0.074 mm Fines (Silt or Clay) Smaller than 0.074 mm
Rock Continuity Relative Quality of Rocks
RECOVERY = Total Length of Core x 100 % Length of Core Run
RQD = Total core, counting only pieces > 4" long x 100 % Length of Core Run
Description Core Recovery % Incompetent Less than 40 Competent 40 - 70 Fairly Continuous 71 - 90 Continuous 91 - 100
Description RQD % Very Poor 0 - 25 % Poor 25 - 50 % Fair 50 - 75 % Good 75 - 90 % Excellent 90 - 100 %
LABORATORY TESTING GENERAL The laboratory testing procedures employed by Goodwyn, Mills and Cawood, Inc. (GM&C) are in general accordance with ASTM standard methods and other applicable specifications. Several test methods, described together with others in this Appendix, were used during the course of this exploration. The Laboratory Data Summary sheet indicates the specific tests performed. SOIL CLASSIFICATION Soil classifications provide a general guide to the engineering properties of various soil types and enable the engineer to apply his past experience to current problems. In our investigations, samples obtained during drilling operations are examined in our laboratory and visually classified by an engineer. The soils are classified according to consistency (based on number of blows from standard penetration tests), color and texture. These classification descriptions are included on our "Boring Records". The classification system discussed above is primarily qualitative and for detailed soil classification two laboratory tests are necessary; grain size tests and plasticity tests. Using these test results the soil can be classified according to the AASHTO or Unified Classification Systems (ASTM D-2487). Each of these classification systems and the in-place physical soil properties provides an index for estimating the soil's behavior. The soil classification and physical properties obtained are presented in this report. POCKET PENETROMETER TEST A pocket penetrometer test is performed by pressing the tip of a small, spring-loaded penetrometer with even pressure to a prescribed depth into a soil sample. This test yields a value for unconfined compressive strength, which may be correlated with unconfined compressive strengths obtained by other laboratory methods. MOISTURE CONTENT Moisture contents are determined from representative portions of the specimen. The soil is dried to a constant weight in an oven at 100o C and the loss of moisture during the drying process is measured. From this data, the moisture content is computed. PARTICLE SIZE DISTRIBUTION The distribution of soils coarser than the No. 200 (75-mm) sieve is determined by passing a representative specimen through a standard set of nested sieves. The weight of material retained on each sieve is determined and the percentage retained (or passing) is calculated. A specimen may be washed through only the No. 200 sieve, if the full range of particle sizes is not required. The percentage of material passing the No. 200 sieve is reported. The distribution of materials finer than the No. 200 sieve is determined by use of a hydrometer. The particle sizes and distribution are computed from the time rate of settlement of the different size particles while suspended in water. These tests are performed in accordance with ASTM D-421, D-422 and D-1140. ATTERBERG LIMITS Liquid Limit (LL), Plastic Limit (PL) and Shrinkage Limit (SL) tests are performed to aid in the classification of soils and to determine the plasticity and volume change characteristics of the materials. The Liquid Limit is the minimum moisture content at which a soil will flow as a heavy viscous fluid. The Plastic Limit is the minimum moisture content at which the soil behaves as a plastic material. The Shrinkage Limit is the moisture content below which o further volume change will take place with continued drying. The Plasticity Index (PI) is the numeric difference of Liquid Limit and Plastic Limit and indicates the range of moisture content over which a soil remains plastic. These tests are performed in accordance with ASTM D-4318, D-4943 and D-427.
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. ALLOWANCE FORM GMC PROJECT NO. HBHM160008 004321 - 1/1
FORM OF PROPOSAL – ATTACHMENT 2
SECTION 004321 - ALLOWANCE FORM
1.1 BID INFORMATION
A. Bidder: __________________________________________________________________________________________________________________________________________
B. Project Identification: MRI /CT /Urgent Care Facility
C. Project Location: Cullman Regional 1912 Alabama Highway 157 Cullman, Alabama 35058
D. Owner: The Healthcare Authority of Cullman County d/b/a Cullman Regional
1912 Alabama Highway 157 Cullman, Alabama 35058
E. Architect: Goodwyn, Mills and Cawood
F. Architect Project Number: HBHM160008
1.2 BID FORM SUPPLEMENT
A. This form is required to be attached to the Bid Form.
B. The undersigned Bidder certifies that Base Bid submission to which this Bid Supplement is attached includes those allowances described in the Contract Documents and scheduled in Section 012100 "Allowances."
1.3 SUBMISSION OF BID SUPPLEMENT
A. Respectfully submitted this 15th day of February, 2017.
B. Submitted By :______________________________________________________( Insert name of bidding firm or corporation).
C. Authorized Signature: _________________________________________________________________________ (Handwritten signature).
D. Signed By: _________________________________________________________________________________________________ (Type or print name).
E. Title: _____________________________________________________________________ (Owner/Partner/President/Vice President).
END OF DOCUMENT 004321
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. UNIT PRICES FORM GMC PROJECT NO. HBHM160008 004322 - 1/2
FORM OF PROPOSAL – ATTACHMENT 1
DOCUMENT 004322 - UNIT PRICES FORM
1.1 BID INFORMATION
A. Bidder: __________________________________________________________________________________________________________________________________________
B. Project Identification: MRI /CT /Urgent Care Facility
C. Project Location: Cullman Regional 1912 Alabama Highway 157 Cullman, Alabama 35058
D. Owner: The Healthcare Authority of Cullman County d/b/a Cullman Regional
1912 Alabama Highway 157 Cullman, Alabama 35058
E. Architect: Goodwyn, Mills and Cawood
F. Architect Project Number: HBHM160008
1.2 BID FORM SUPPLEMENT
A. This form is required to be attached to the Bid Form.
B. The cost of Unit Prices itemized below, in the quantities noted to be included in base bid, shall be included in the bid amount entered on the Form of Proposal
C. The undersigned Bidder proposes the amounts below be added to or deducted from the Contract Sum on performance and measurement of the individual items of Work and for adjustment of the quantity given in the Unit-Price Allowance for the actual measurement of individual items of the Work.
D. If the unit price does not affect the Work of this Contract, the Bidder shall indicate "NOT APPLICABLE."
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. UNIT PRICES FORM GMC PROJECT NO. HBHM160008 004322 - 2/2
1.3 UNIT PRICES
A. Unit-Price No. 1: Removal of unsatisfactory soil and replacement with satisfactory soil material.
1. ___________________________________________________________________________ Dollars ($_______________________________) per unit.
B. Unit-Price No. 2: Rock excavation and replacement with satisfactory soil material.
1. ___________________________________________________________________________ Dollars ($_______________________________) per unit.
C. Unit-Price No. 3: Off-site disposal of excess soil in lieu of stockpiling at a designated on-site location.
1. ___________________________________________________________________________ Dollars ($_______________________________) per unit.
1.4 UNIT PRICES SHALL BE INCLUDED IN BASE BID
A. The cost of Unit Prices itemized above, in the quantities noted to be included in base bid, shall be included in the bid amount entered on the Form of Proposal.
1.5 SUBMISSION OF BID SUPPLEMENT
A. Respectfully submitted this 15th day of February 2017.
B. Submitted By :______________________________________________________( Insert name of bidding firm or corporation).
C. Authorized Signature: _________________________________________________________________________ (Handwritten signature).
D. Signed By: _________________________________________________________________________________________________ (Type or print name).
E. Title: _____________________________________________________________________ (Owner/Partner/President/Vice President).
END OF DOCUMENT 004322
MRI / CT / URGENT CARE FACILITY ADPH PROJECT #B-16-066 for CULLMAN REGIONAL CULLMAN, ALABAMA
GOODWYN, MILLS & CAWOOD, INC. PROJECT FORMS GMC PROJECT NO. HBHM160008 006000 - 1/1
SECTION 006000 – PROJECT FORMS
1.1 FORM OF AGREEMENT AND GENERAL CONDITIONS
A. Owner/Contractor Agreement and General Conditions:
1. AIA Document A101, "Standard Form of Agreement between Owner and Contractor, Stipulated Sum" and,
2. AIA Document A201, "General Conditions of the Contract for Construction."
3. Copies of AIA Documents A101 and A201 will be provided under separate cover by the Architect.
1.2 ADMINISTRATIVE FORMS
A. Administrative Forms: Additional administrative forms are specified in Division 01 General Requirements.
B. Preconstruction Forms:
1. AIA Document A312, "Performance Bond and Payment Bond." 2. AIA Document G715, "Supplemental Attachment for ACORD Certificate of
Insurance 25-S."
C. Information and Modification Forms:
1. AIA Document G716, "Request for Information (RFI)." 2. AIA Document G709, "Work Changes Proposal Request." 3. AIA Document G701, “Change Order." 4. AIA Document G707, "Architect's Supplemental Instructions." 5. AIA Document G714, "Construction Change Directive."
D. Payment Forms:
1. AIA Document G702, "Application and Certificate for Payment." 2. AIA Document G703, “Continuation Sheet” 3. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims." 4. AIA Document G706A, "Contractor's Affidavit of Payment of Release of Liens." 5. AIA Document G707, "Consent of Surety to Final Payment."
END OF DOCUMENT 006000