Design-Build for Small Projects

NAVFAC Hawaii Capital ImprovementsDesign Division

Page 2: Mr. Garrett Lee

2

PRESENTATION OVERVIEW

•Design-Build (DB) in NAVFAC What is Design-Build?

Why Design-Build?

• Contract Vehicles for Small Project DB Multiple Award Construction Contract (MACC)

Single Source Negotiated Scope

Small Project

• 6 Part Request for Proposal (RFP) Format

Page 3: Mr. Garrett Lee

3

What is Design-Build?

• FAR 36.102 defines Design-Build as combining design and construction in a single contract with one Contractor

• Utilizes the standard 6 part NAVFAC Design-Build RFP process

• Design-Build RFP tells the Contractor what is needed and not how to accomplish the project

• Design-Build projects are projects that require design by a licensed professional architect or engineer

Page 4: Mr. Garrett Lee

4

Why Design-Build in NAVFAC ?

• Better quality facilities in less time and for less overall cost

Independent Study Confirms DB as a Better Method

• NAVFAC has declining resources and funds

• Design-Build is NAVFAC’s preferred execution method

Page 5: Mr. Garrett Lee

5

Requirements

RFP

Design-Build Contract

Design-Build Process

Completed Facility

Page 6: Mr. Garrett Lee

6

NAVFACIPT Staff

ACQ / PM / DM

NAVFACIPT Staff

ACQ / PM / DM

ClientProject Sponsor

ClientProject Sponsor

The EntireDesign-BuildProject Team

Design-BuildPrime

Contractor

Design-BuildPrime

Contractor

Design-Build Project Team

DB Contractor’sA-E DOR

DB Contractor’sA-E DOR

DB Contractor’sMajor

Subcontractors

DB Contractor’sMajor

Subcontractors

DB Contractor’sMajor Suppliers

DB Contractor’sMajor Suppliers

NAVFACCIBL Tech Staff

NAVFACCIBL Tech Staff

NAVFACFEAD Staff

NAVFACFEAD Staff

ClientEnd User

ClientEnd User

Page 7: Mr. Garrett Lee

7

DESIGN-BUILD PROCESSES

There are four DB processes, each with a specific applicability:

•Standard – This process competes several contractors in a single source selection. Suited for large projects.

•MACC – This process competes within a defined pool of contractors and is for projects that are suitable for follow-on task orders to an existing MACC (Multiple Award Construction Contract).

•Single Source Negotiated Scope – This process allows the Government and client to develop the scope of work with a single contractor. It takes advantage of the set-aside programs, often 8(a), and is usually used for smaller, low risk projects.

•Small Project – This process is designed for the single source negotiated and is specifically for small, low risk projects.

Page 8: Mr. Garrett Lee

8

KTR Design

Standard DB

RFP Development

RFP Development

8(a)/ JOC

Typical Contract Vehicle

Follow-on Task Order

Basic Award

NotionalEffort

&Timeline

Build8(a)/ JOC

Con

trac

t

Aw

ard

MACC DB

Single Source Neg Scope DB

Small Project DB

Contractor Design & Build

Contractor Design & Build

Contractor Design & Build

Contractor Design & Build

KTR Proposal Level of Design

5%-15% Design

~0% Design

~15% Design

~15% Design

RFP Development –Scope, Budget,

Schedule

Page 9: Mr. Garrett Lee

9

WHICH CONTRACT VEHICLE?

Single Source Negotiated / Small Project

8(a) MACC

Project SizeSSN < $3,000,000

Small Proj < $1,000,000 Usually < $3,000,000

Example Type Projects

A/C Replacement, Fire Sprinkler, Office Alteration, Toilet Renovation

Whole Building Renovation, Construct PEB, Install Elevator, Seismic Upgrade of Building

Design / Engineering Effort

Limited engineering

Tailored design

Plans & limited specs (supplemented by shop drawings & submittals)

Page 10: Mr. Garrett Lee

10

NAVFAC DESIGN-BUILD REQUEST FOR PROPOSAL WEBSITE

RFP Parts 1 through 6RFP Parts 1 through 6RFP Parts 1 through 6RFP Parts 1 through 6

www.wbdg .org/ndbm

Page 11: Mr. Garrett Lee

11

NAVFAC Design-Build Master Format

NAVFAC DB RFP WEBSITE: www.wbdg.org/ndbm/

PART 6

PART 5

PART 4

PART 3

PART 2

PART 1

Proposal Forms & Documents

Performance Technical Specifications

Prescriptive Specifications

Attachments

Project Program

General Requirements

Statement of w

ork

Page 12: Mr. Garrett Lee

12

SMALL PROJECT TEMPLATE

PART 1

Proposal Forms & Documents

Performance Technical Specifications

Prescriptive Specifications

Attachments

Project Program

General Requirements

Statement of

work

Small Project PART 2

Small Project PART 3

Small Project PART 4

PART 5

(Typically not

required)Small

Project PART 6

Parts 2 thru 6 are scaled down versions of the DB Master Format

Page 13: Mr. Garrett Lee

13

Questions?