mps proiect 2014
TRANSCRIPT
Software projectmanagement
Android game development
- 3 D Adventure
Short description
The project reflects the development of a 3D game.
The phases of the game include the creation of the game and the story and characters definition
Being an android application, time is also an issue. The whole process should not take longer than a few months
Resources (1) We have a team of nine competent people.
=> A few team member swill have multiple roles.
Software Roles:
Project manager: Indy
Game designers: Garry, Gwen
Artist: Ariana
Programmers: Peter, Penny, Perry, Garry
Technical director: Gwen
Testers: Tweak, Peter, Penny
Animator: Andrew
Resources (2)
Work hour costs in normal conditions:
Wages: 7-9$ / hr
The project manager and Game designers earn more
Work hour costs in case of overtime:
For everyone: 9$ / hr
Constrains & Risks There are two major constrains:
most important: money
constrain: time
The planning will be done by the project manager. He will try to reduce the cost to a minimum.
=> No overtime!
• Overtime is only for special situations and it has to be agreed by the project manager and person in issue.
Project phases:
Concept
Planning and design
Development (pre-alpha)
Testing (alpha)
Release
Maintenance and bug fixes
General Overview
ConceptPlanning and Design
Development and Testing
ReleaseMaintenance and bug fixes
Project cost
Conclusions We have used Microsoft Project to manage
our android application.
We chose it because it allowed us to enter the tasks in a list, to schedule them, to assign resources to these tasks, and to enter costs for all the phases and resources while tracking the changes.
Microsoft Project is useful from the very first step since it supplies some templates that we can use for a specific kind of project