motorway maintenance and renewals contract (mmarc) · atkins appointed as technical adviser in...

31
Motorway Maintenance and Renewals Contract (MMaRC) Progress to Date & Consideration of Future Developments Kevin O’Rourke Head of Network Operations, TII. Sean McDonnell MCAAS Commission Manager, Associate Director, Atkins. September 28th 2016

Upload: others

Post on 05-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Motorway Maintenance and Renewals Contract (MMaRC)

Progress to Date & Consideration of Future Developments Kevin O’Rourke Head of Network Operations, TII. Sean McDonnell MCAAS Commission Manager, Associate Director, Atkins.

September 28th 2016

Page 2: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years

(winter 2018/2019) + 1 + 1 years 2nd generation contracts expected in

Spring 2019 Consultation with CCMA/LAs during

2017.

Current Status Motorway Maintenance and Renewals Contracts (MMaRC)

Page 3: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Transition: from LA MMaRC Liaison: 21 Local Authority areas + 10

PPPs. Scale: Breaking into lots. Duration: Economy vs flexibility. Depots: Provision & ownership,

restrictions on access. Contract Type / Risk Transfer: Winter

Services, Incident Response, Asset Damage. Procurement: Quality (70%) / Price (30%)

Key Issues / Decisions

Page 4: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

MMaRC Network Operator Length

A Heavy traffic urban Globalvia Sacyr Jons [GSJ] 160 km

B Lighter traffic rural Colas Roadbridge JV [CRJV] 256 km

C Mixed urban/rural Egis Lagan Services [ELS] 328 km

Total 744 km

Motorway / Dual carriageway network Length

Total Length of Dual & motorway network 1,210 km

- PPP 374 km

- PPP under construction 94 km

- MMaRC 744 km

- Local Authority 92 km

Scale of Contracts

Entire MMaRC equivalent to one UK maintenance area. Division into lots. Subdivision of network. Restrictions on tenderers.

Page 5: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Duration Longer duration – more economic Shorter duration allows quicker

contract evolution Balance with maximum flexibility

for TII: 5 years +1 +1

Page 6: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Depots

NRA Strategic Salt Barn – 15,000 tonnes

Operational Salt Barn with Lean-to structure

Fuel Tank Location

Brine Tank location

Depot Office & Car Park

Ennis Depot

TII owned – leased to MMaRC Contractor Strategic Salt storage (NDFEM)

Depot Area Salt Storage

Strategic Operational

Balbriggan A 20,000t 6,500t

Athlone B 9,000t

Ennis B 15,000t

Kinnegad B 12,000t

Nenagh B

Cahir C 30,000t 11,500t

Kilkenny C

Total 77,000t 27,000t

Reduces barrier to future entrants

Depot Weighbridge

Page 7: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Contract Type Bespoke Contract agreed with GCCC as no equivalent available; Lump Sum for defined works / responsibilities; Tendered rates for renewal works (1,550 items in Schedule of

Rates);

Minimum contract value of approx. €20M per annum.

Page 8: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Routine Maintenance

Incident Response

Winter Operations

Capital Renewals andImprovements

(based on a schedule of rates)

Lump Sum

Risk Transfer

EIWO

EIWO = Employer Instructed Works Order

Page 9: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Risk Transfer Winter Services - Full risk transfer, performance specification

with specified minimum resource levels. Incident Response - Full risk transfer for Initial Response, Support

Response as instructed. Response times ½ hour to 2 hours. Asset Damage – Full risk transfer up to €12,500. Incentive to

pursue insurers where liable. Problem with fire damage (Accidental Fires Act 1943). TII claims / IPB.

Page 10: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

European Comparison (CEDR 2010)

200.1

220.7

34.6 25.6

105.8

45.8

16.9 13.7 27.3 29.8

182.1

32.9 24

86.3

Motorway Maintenance Expenditure €1,000s/year/km (ex VAT)

Page 11: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Routine Maintenance

Incident Response

Winter Operations

Capital Renewals andImprovements

(based on a schedule of rates)

Lump Sum

MMaRC Contract Overview

EIWO

EIWO = Employer Instructed Works Order

Page 12: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – Lump Sum Activities Routine Maintenance

Page 13: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – Lump Sum Activities

Incident Response – 2015 5,312 incidents

Incident Categories - 2015

Page 14: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – Lump Sum Activities

Winter Activities – 2015/2016 Season

Page 15: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – Issues / Opportunities Historic underfunding led to significant legacy issues. Baseline Survey carried out – legacy defects identified & now

substantially advanced. The MMaRC Contract was identified as an appropriate

mechanism to deal with: Additional funding Environmental issues Safety works identified in RSI’s & HD15’s.

Page 16: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – EIWOs Completed Filter Drain Remediation Works

Page 17: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – EIWOs Completed Marker Plates

Page 18: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – EIWOs Completed

M50 Diversion Routes

M50 Emergency Diversion Routes

Page 19: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – EIWOs Completed

Rolling Crown Works

Flooding M11

Flooding

Page 20: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – Pavement Schemes Rolling crowns. HD 28 sites. Junction & mainline

improvements.

Page 21: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Progress to Date – Environmental Monitoring

Page 22: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Japanese Knotweed

Progress to Date – Environmental Monitoring

Page 23: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Drainage Improvements - Vibro Line removal for drainage gaps.

Progress to Date – Other Works

Before After

Page 24: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Clear Zone Provision

Progress to Date – Other Works

Page 25: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Visibility Provision

Progress to Date – Other Works

Page 26: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Drainage Upgrades

Progress to Date – Other Works

Page 27: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Election Poster Removal

Progress to Date – Other Works

Page 28: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Next Generation - Timeline • 5 year contracts; • Contract period expires winter 2018/2019; • Option to extend 1 + 1 years; • Expected MMaRC Generation 2 start date to be Spring 2019.

Page 29: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Next Generation – Items for Consideration Aspect Issue

Procurement Levelling of Pitch Duration of Contract Restriction on Award Lots Quality / Price

Funding Implications Risk Transfer Extent of Services / Technical Requirements Winter Service Plant Specification

TII & National Policy Extent of MMaRC Areas Incident Response Services Relationship with Local Authority Fire Services

Administration TII hosted Asset Management Database Interface with Local Authorities Technical Supervision

Page 30: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Summary Contracts working well Significant positive impact on network Additional funding Many ‘legacy’ issues addressed Now planning towards next generation contract.

Page 31: Motorway Maintenance and Renewals Contract (MMaRC) · Atkins appointed as Technical Adviser in 2010. Contract start dates Nov/Dec 2013. Envisaged contract term 5 years (winter 2018/2019)

Thank You