More than an idea not yet a project

1

Meeting Issues & Goals

CFS-ADI Tokyo 2014 Mike Harrison

Page 2: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

2

Timeline

Atsuto Suzuki @ the P5 meeting in Chicago

LCC working timeline

Page 3: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

Planning Basic Design Detailed Design Tendering

2014 2015 2016 2017 2018

Basic Survey

Geological Survey

Detailed Survey

Detailed

Cost Estimate

   Land NegotiationSite Decision

  Land Acquisition Acquisition

Compensation

Environmental Impact Survey

Environmental Impact Study

Permission

Topographical Survey

Basic

Const

ruct

ion w

ork

s

Preparation

Additional.

2014 2015 2016 2017 2018

Schedule – Pre-project CFS work (LCWS13)

Page 4: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

Planning Basic Design Detailed Design Tendering

2014 2015 2016 2017 2018

Const

ruct

ion

work

s  Ground facility planning

Basic plan and placement

Installation planEquipment

layout drawingEquipment layout

Ground facility layout drawing

  Experimental equipment layout

Schedule – Machine Input to CFS Design

CFS-ADI Tokyo 2014 Mike Harrison

Page 5: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

5

Energy Phasing - Which ILC ?

CFS-ADI Tokyo 2014 Mike Harrison

Page 6: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

6

Energy Phasing – Concept (LCC)

A multiple staged energy implementation, while technically feasible, will require several stop-start cycles with associated complications: thus the LCC Directorate has interpreted the JAHEP statement to mean a project with a first stage of 250 GeV. A pause in installation would then ensue to allow for a period of commissioning (~1 year) and physics operation of approximately 4 years after which time a single shutdown of ~1 year would be used to complete the project to 500 GeV.

This has many implications for the construction planning including the CFS activities.

We have established a joint parameters WG to advise the LCB/LCC on these issues – Nick, Kaoru, Jie + Jim Brau et al

CFS-ADI Tokyo 2014 Mike Harrison

Page 7: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

7

IP Concept

Can we decide which approach to follow ?

CFS-ADI Tokyo 2014 Mike Harrison

Page 8: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

8

Layout

08.02.2013 Windsor, UK N. Walker - ILC Cost Review

accelerator cryomodules

CFS-ADI Tokyo 2014 Mike Harrison

Is the cryostring length stable ?Does Q-enhancing flash cooling change the cryolooplength ?

Page 9: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

Tunnel Layout & Access Halls

“Mountainous” Topography site-dependent design

“Kamaboko” tunnel

Most infrastructure underground.

9CFS-ADI Tokyo 2014 Mike Harrison

Page 10: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

10

Site Utilities & Central Campus

The site utilities we understand, the central campus is less well defined

Page 11: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

• Can we back-end load the pre-project CFS activities to reduce funding needs pre-2016 without impacting the schedule ?

• Can we determine the ADI requirements for the next 2-to-3 years which at a minimum provides the necessary information for the CFS work? 12 months ?

• Can we agree on the optimal energy phasing implementation scheme

• Can we agree on the preferred IP concept• Are the tunnel X-section & penetrations OK• How do the lab/campus facilities interact with the project –

equipment testing, engineering support, equipment staging and storage, offices, power & water infrastructure, etc…

• Any significant site-specific impact to the TDR design

• Cost vulnerability – can we identify any potential significant cost risk hidden in the post-TDR environment ?

11

Goals & Questions

CFS-ADI Tokyo 2014 Mike Harrison

Page 12: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

12

Agenda

Session 1, 9.00; Meeting Kick-off, Chair Akira YamamotoGoals – Mike Harrison,CFS Status – Atsushi EnomotoADI Status – Nick WalkerThe first session will outline the meeting goals as well as the status of the CFS and ADI work to date. Session 2, 11.00; CFS pre-project activities, Chair – Vic KuchlerPre-project scope of work (long & medium term plan), Timeline, Required resources, Profile – Masanobu Miyahara

DiscussionThe CFS pre-project work scope will determine the readiness for a construction project hence we need to understand the elements of the work scope and their individual schedules. Can any items be delayed with compromising the effort ? Can the 5-year estimate for this work be shortened in any way ? Since non trivial funding will be needed to complete this work then this implies some kind of budget before the anticipated GO-NOGO decision in 2016. How much money is needed and when, if we try and minimise a pre-project request

CFS-ADI Tokyo 2014 Mike Harrison

Page 13: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

13

Agenda

Session 3 14.00; ADI Support of CFS, Chair – Nikolay SolyakIssues pertaining to CFS for each system – Nick Walker

DiscussionThere remains” loose ends” in several systems in regard to CFS requirements. Ascertaining these issues will help determine the systems groups work scope and remaining CFS uncertainty. Session 4, 16.00; Technology Support & CFS Impact, Chair – Hitoshi Hayano

Cryomodule & Waveguide installation, LHe inventory control, Radiation shielding, Safety - Tomoyuki Sanuki & Masanobu Miyahara

DiscussionThis session will examine issues related to the tunnel and access-tunnel X-sections and input penetration layout. Is the generic tunnel layout including accessibility and safety now stable ?

CFS-ADI Tokyo 2014 Mike Harrison

Page 14: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

14

Agenda

Session 5, 9.00, MD(1), Chair – Ewan PatersonDetector Requirements both SiD and ILD minimum needs – Karsten Buesser DiscussionDo we understand the Detector design well enough to determine the CFS Detector Hall requirements ? Is there risk that significant Detector changes could still remain ? Can we identify the major technical cost drivers arising from the Detectors in terms of the CFS, including comparisons of effects with vertical shaft and horizontal access? Session 6, 11.00; MDI (2), Chair – Yasuchika YamamotoInteraction Region Solutions including Hybrid, Detector Hall impact on Overall Construction schedule – Yoshinobu Nishimoto ARUP Study Status – John OsborneDiscussionCan we conclude the horizontal – vertical access debate ( at least conceptually) ? Hybrid model – positives/negatives. When do we need to resolve this ? What needs to be done in the near term to facilitate this decision ?

CFS-ADI Tokyo 2014 Mike Harrison

Page 15: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

15

Agenda

Session 7 14.00; Energy Phasing, Chair – Nick WalkerGeneral Scheme, parameters, CFS impact – Benno ListDiscussion

The proposal to implement the project in stages has implications for the CFS approach and scope. What are these features (transfer lines, cryogenics, installation, storage, test facilities ……) ? There may be a request for energies in excess of 500 GeV as part of the project baseline. How do we approach this ? Session 8 16.00; Site Infrastructure, Chair Nobuhiro Terunuma

Power Usage, Site requirements (water etc..) Vic Kuchler & Atsuchi EnomotoEnergy Issues – Marc Ross (Alt., Ewan Paterson)Discussion Further information will be required soon on the outside-the-TDR site needs (power, water, roads etc….). How well do we know these requirements ? Are there any significant energy efficiency opportunities ? Power reduction on demand ?

CFS-ADI Tokyo 2014 Mike Harrison

Page 16: More than an idea not yet a project 1 Meeting Issues & Goals CFS-ADI Tokyo 2014 Mike Harrison

16

Agenda

Session 9, 09.00; CFS near term & Required ADI input, Chair – Atsushi Enomoto6-12 month activities, required ADI information - Masanobu

Miyahara Discussion

The CFS pre-project work scope will need to have aspects of the accelerator design to be finalised at certain points in the timeline. We need to define when this ADI input is needed and what aspects needed to be defined. What near-term aspects of the CFS work will need to be addressed and what resources will be available. Session 10, 11.00; Wrap-Up, Chair – Brian FosterWhat have we learned ?

We will use this session to document the conclusions and map out a plan for the next few years: the LCC phase. We will also discuss how we may well prepare for the ALCW-14, to be held at Fermilab in May.

CFS-ADI Tokyo 2014 Mike Harrison