MONTHLY STATUS REPORT September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23, 2014 Los Alamitos, California

Upload: others

Post on 04-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

Title Slide

MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT

Weaver Elementary School Modernization Project

September 23, 2014

Los Alamitos, California

Page 2: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASING

Progress 13

Phase 5/5A – Complete

All Buildings Modernized & In Use

ON TIME AND ON

BUDGET!

Page 3: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

Executive Summary

Classroom Building P2

• Classrooms modernized and in use since August 11th

Building A – Media Center, Kitchen, Classrooms

• Media Center moved back in September 15th

• Kitchen modernization and updates complete and serving

students

• Kid’s Korner and Music Classrooms complete and in use

Site Work

• Asphalt and Irrigation work completed over the summer

• Final site clean up in progress

• Final asphalt work in laydown area to be scheduled

• Demobilization in progress

PHASE 5 and 5A– Complete and Moved-In

Page 4: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5 - SUMMARY OF PROGRESS

Progress 13

Classroom Building ‘P2’ Typical Classroom Prior to Modernization

Page 5: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5 - SUMMARY OF PROGRESS

Progress 13

Classroom Building ‘P2’ Typical Classroom During Construction

Page 6: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5 - SUMMARY OF PROGRESS

Progress 13

Classroom Building ‘P2’ Modernization Complete

Page 7: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5 - SUMMARY OF PROGRESS

Progress 13

Summer Sitework Asphalt Repair Work and Slurry Seal

Page 8: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5 - SUMMARY OF PROGRESS

Progress 13

Summer Sitework New Irrigation System Installed

Page 9: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Media Center - Building ‘A’ Prior to Modernization

Page 10: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Media Center - Building ‘A’ Modernization Complete

Page 11: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Media Center - Building ‘A’ Prior to Modernization

Page 12: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Media Center - Building ‘A’ Modernization Complete

Page 13: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Kitchen and Office- Building ‘A’ Prior to Modernization

Page 14: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Kitchen and Office- Building ‘A’ Modernization Complete

Page 15: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Staff/Parent Workroom – Building ‘A’ Prior to Modernization

Page 16: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Staff/Parent Workroom – Building ‘A’ Prior to Modernization

Page 17: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Classrooms – Building ‘A’ Prior to Modernization

Page 18: MONTHLY STATUS REPORT September 2014 · MONTHLY STATUS REPORT – September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Weaver Elementary School Modernization Project September 23,

PHASE 5A - SUMMARY OF PROGRESS

Progress 13

Classrooms– Building ‘A’ Modernization Complete