MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
CONTENTS
1.0 Project Background 2
2.0 Major Activities and Review Meetings of the Month 3
3.0 Out Line Tasks to be carried out 3
4.0 Activities of Third Party Quality Audit Consultant 5
-
7/27/2019 Monthly Progress Report for July 2013
3/131
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1. Project Background
Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road
network in the state, the nine coastal districts cover 26,000 km of road length. Every year during the
period of April-May and September-December, cyclonic situations set in to the Bay of Bengal. With
the recent changes in climatic conditions, the catastrophic events are increasing resulting in very
devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from 1892
to 1989, there were as many as 67 cyclones within the State.
It is essential to provide safe residential accommodation to the vulnerable population during any
eventuality or disaster due to natural calamities such as cyclones and associated tidal waves and
storm surges. The project is formulated based on experiences of Government of Andhra Pradesh in
mitigating such disasters during the past and also keeping in view the existing facilities available in
the project area in Andhra Pradesh.
The Government of India has applied for a credit of US$ 255 Million equivalent from the International
Development Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP),
and it intends to apply the proceeds to payments for goods, works, related services and consulting
services under this Project.
National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra
P d h h d t d t H d b d h i it d th lt t t b it l f idi
-
7/27/2019 Monthly Progress Report for July 2013
4/131
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2. Major Activities and Review Meetings of the Month
S.No Place Date Activity
1 Prakasam 18.07.2013Conducted workshop for Engineers and Contractors on QualityAssurance on NCRMP works at Chief Planning office, Ongole
2 Hyderabad 29.07.2013Attended NCRMP Review meeting at 'H' Block, AP Secretariat,Hyderabad
3. Outline of tasks to be carried out
The scopes of services for the Third Party Quality Audit (TPQA) assignment are
A. The consultant will prepare an inception report within 30 days from signing of the contract that
details the method agreed during negotiations to be employed in performing the services.
B. Assist SPIU in resolving issues related to Non compliances.
C. The field testing being conducted by the implementation staff will be observed and when doubts
arise in such observations another sample will be taken and will be tested independently to verify
whether it is as per the standards or not.
D The consultant will review civil work components of the cyclone shelters and related roads &
-
7/27/2019 Monthly Progress Report for July 2013
5/131
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
compliances of the works, the remedial measured suggested & taken up for non-compliances and
the modifications needed in the work plan basing on the experiences in the lapsed quarter.
H. The consultant will assist SPIU in ensuring the works, by way of reporting, are carried out as per
specifications, quality & quantity and towards achieving the desired results. Any defective work
noticed by the consultant shall be reported immediately and suggest corrective measures to the
field engineers, for immediate rectification and give feedback to SPIU with regards to compliance
of suggested corrective measures. Wherever compliances are not happening, a report will be
submitted to the SPIU& line department.
I. The consultant will participate in the workshops / trainings administrated by the PIUs / line
departments, quarterly and also as and when called for to give their inputs and also to act as
resource persons as and when needed.
J. The competency of the implementation staff will be verified and reported to SPIU and suitable
suggestions will be made.
K. The work plans of the implementation agency will be observed and suitable modifications will be
suggested basing on the past experiences in the sites.
L. The consultant will prescribe suitable formats for progress reporting and the same formats will be
used to report regularly.
M. The consultant will advise on the required site audit procedures for individual duties and
responsibilities including detailed inspection schedules and check lists
-
7/27/2019 Monthly Progress Report for July 2013
6/131
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
S. At the end of every week the Consultant will submit a report containing the details of field visits
undertaken during the week indicating the date of visit. In addition to the site level reports and
weekly report, consolidated reports would be submitted every month and quarter, compiling the
findings in the site reports, summary audit opinion, corrective actions, progress of works and
issues etc. The Consultant will also make presentations on audit findings at the designated forums
as and when required by the client.
4. Activities of Third Party Quality Audit Consultant.
All the activities of TPQA consultant, such as status of TPQA visits, Quality Audit reports, NCR status
reports, status of Quality Control tests and other reports are summarized in the tables and furnished
in this Monthly Progress Report as detailed below.
Status of NCRMP Year-1 works are given in Table-1
Final QCRs to be submitted for the Year-1 works statement is given in Table-2
Spillover works statement for the Year-1 works are given in Table-3
Details of Spillover works for the year-1 works are given in Table-4
Agreements communicated for NCRMP Year-2 works statement given in Table-5
O e all statement of Ag eements comm nicated Yea 2 o ks + Spillo e Yea 1 o ks
-
7/27/2019 Monthly Progress Report for July 2013
7/131
RHB
RCS
MPCS
B
ridges
Roa
ds(R&B)
Total
RHB
RCS
MPCS
B
ridges
Roa
ds(R&B)
Total
RHB
RCS
MPCS
B
ridges
Roa
ds(R&B)
Total
1 Srikakulam 6 8 2 4 1 21 3 8 0 3 1 15 12 3 0 2 1 0 6 0
2 Vizianagaram - - - 2 1 3 0 0 0 2 1 3 3 0 0 0 0 0 0 0
3 Visakhapatnam 8 6 7 - - 21 8 6 5 0 0 19 14 0 0 1 0 0 1 1
4 East Godavari 2 8 3 - - 13 2 7 2 0 0 11 8 0 0 1 0 0 1 1
5 West Godavari 10 - - - - 10 10 0 0 0 0 10 10 0 0 0 0 0 0 0
6 Krishna 5 3 - - - 8 5 3 0 0 0 8 8 0 0 0 0 0 0 0
7 Guntur 3 12 - 2 - 17 3 11 0 1 0 15 9 0 1 0 1 0 2 0
8 Prakasham 14 7 2 1 - 24 14 7 2 1 0 24 24 0 0 0 0 0 0 0
9 Nellore 16 10 - - - 26 16 8 0 0 0 24 24 0 2 0 0 0 2 0
Total 64 54 14 9 2 143 61 50 9 7 2 129 112 3 3 4 2 0 12 2
Total No. of works entrusted in Year-1 = 143 nos No. of works deleted = 2 nos
No. of works completed by 14.04.2013 = 129 nos Spillover works in to Year 2 = 143 2 129 = 12 nos
No. of works for which Final QCRs submitted = 112 nos No. of works for which Final QCRs to be submitted = 17 nos
S.no
District
No. of works(Under Concluded
Agreements)No. of works Completed No. of works under Progress
No
.ofworksnot
started
No.
ofFinalReports
Submitted
Status of NCRMP Year-1 works up to 14.04.2013 TABLE - 1
Page 6 of 130
-
7/27/2019 Monthly Progress Report for July 2013
8/131
Sl.
No
Dist
rict
Categ
ory
Packages allotted under
Phase - 1s.no Names of works under each package Work Status Remarks
1 1 Road from DPN R&B road to Uddandapalem Work completedEOAT and Approval of working estimate
awaited
2 2 Road from K. Umilada Junction to Koduru (Link Road) Work completedEOAT and Approval of working estimate
awaited
3 3
Road from Borubhadra, Malagam to Kollipadu via
Seepuram, Gantapeta Work completed
EOAT and Approval of working estimate
awaited
4 1 Construction of CS at Gajapathinagaram Work completed Approval of working estimate awaited
5 2 Construction of CS at Ratnayampeta Work completed Approval of working estimate awaited
6 3 Construction of CS at Patimeeda Work completed working estimate approval not received
7 4 Construction of CS at Mullaparra Work completed working estimate approval not received
8 5 Construction of CS at Bangarampeta Work completed working estimate approval not received
9 RCSNCRMP/B-W/AP/RCS/PRED/
04/Uppalaguptam/0031 Road from R&B Road to Chinaraghavulapeta CS Work completed
Approval of working estimate awaited &
ATRs not received
10NCRMP/B-W/AP/MPCS/PRED/
04/Thondangi/0012 Construction of CS at Lakshmanudipeta in Thondangi Work completed working estimate approval not received
11NCRMP/B-W/AP/MPCS/PRED/
04/Thondangi/0013 Construction of CS at Avulamanda Work completed working estimate approval not received
12NCRMP/B-W/AP/RCS/PRED/
07/PV Palem/0011 Road from R&B road to Mandevaripalem Work completed Approval of working estimate awaited
13 2Road from Ganapavaram R&B Road to
PedamarpuvaripalemWork completed
Approval of working estimate awaited &
ATR not received
14 3 Road from R&B Road to Chinapuluguvaripalem Work completed
Approval of working estimate awaited &
ATR not received
15 4 From R&B road to Yaramvaripalem Work completedApproval of working estimate awaited &
ATR not received
16 5 Road from R&B Road to Pedagollapalem CS Work completedApproval of working estimate awaited &
ATR not received
17 6 Pedagollapalem PR road to Bonthagoralapalem Work completedApproval of working estimate awaited &
ATR not received
RCS
RHBNCRMP/B-W/AP/RHB/PRED/
01/Santhabommali/003
List of Works which are completed and final QCRs to be submitted by TPQA (awaiting approval of W.E/R.E) TABLE - 2
Srikakulam
NCRMP/B-W/AP/RCS/PRED/
07/Karlapalem/002
NCRMP/B-W/AP/MPCS/PRED
/03/Payakaraopeta/003
Guntur
NCRMP/B-W/AP/MPCS/PRED
/03/Nakkapalli/002Visakhapatnam
MPCS
MPCS
EastGodavari
Page 7 of 130
-
7/27/2019 Monthly Progress Report for July 2013
9/131
Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works
1 Srikakulam 1 2 0 0 2 3 3 5 1 1 0 0 4 6
2 Vizianagaram 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Visakhapatnam 1 1 0 0 0 0 1 1 0 0 0 0 1 1
4 East Godavari 1 1 0 0 0 0 1 1 0 0 0 0 1 1
5 West Godavari 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6 Krishna 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Guntur 0 0 1 1 0 0 1 1 1 1 0 0 2 2
8 Prakasam 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Nellore 0 0 1 2 0 0 1 2 0 0 0 0 1 2
3 4 2 3 2 3 7 10 2 2 0 0 9 12Total
Details of Spill over (NCRMP Year-1) works which are not completed by 14.04.2013 TABLE - 3
Sl.
No.District
PR R&B I & CADTOTAL
MPCS RCS RHB TOTAL Bridges Saline Embankment
Page 8 of 130
-
7/27/2019 Monthly Progress Report for July 2013
10/131
Sl.
NoDistrict
Categ
ory
Packages allotted under
Phase - 1s.no Names of works under each package
Agreement
No. / Date
Work
StatusRemarks
1 1Road from R&B road Mobagam to
Duubakavanipeta via Gajapathinagaram
/2010-11, Dt.
30.04.2011Completed
2 2Road from Talasamudram to Dola
Regulator
/2010-11, Dt.
30.04.2011Completed
3 NCRMP/B-W/AP/RHB/PRED/01/Polaki/005
3 Road from R&B road Edulavalasa - Killamto Jonnam via Talasamudram
/2011-12, Dt.30.04.2011
Completed
4R&B
bridge
NCRMP/B-W/AP/Br/R&B/
01/Uppugedda/0024
Construction of High level bridge across
Uppugedda at KM 7/6 of Srikakulam
muncipal limits to Pukkalapeta via
Killipalem in Srikakulam Dt, A.P.
47/2010-2011,
Dt17.12.2010
Work in
Progress
Bridge hand rails and finishing work is in
progress, Approach road earth work completed
5 5 Construction of CS at KollipaduG.o rt No 451
dt 06.04.2010
Work in
Progress
Finishings is in progress, & compound wall work
is in progress
6 6 Construction of CS at RunkuG.o rt No 451
dt 06.04.2010
Work in
Progress
Finishings is in progress, & Sump, Septic tank
anfd compound wall execavation is in progress.
7Visakhapa
tnamMPCS
NCRMP/B-W/AP/MPCS/PRED
/03/Rambilli/0041 Construction of CS at Venkayyapalem
/2011-12, Dt.
03.10.2011
work in
progress
All slabs, brick work, plastering, wood
joinery, flooring, plumbing, painting
completed. One side compound wall is to be
construct.
8East
GodavariMPCS
NCRMP/B-W/AP/MPCS/PRED/
04/ Uppalaguptam/0021
Construction of CS at Pedaraghavulapeta
of Uppalaguptam Mandal
78/2011-12
Dt:17.10.2011Completed
9 BridgesNCRMP/B-W/AP/Br/R&B/
07/Bapatla/0114
Reconstruction of HLB @Km2/4 of Bapatla -
Pandurangapuram Road across perali drain
78/2010-11
1.12.2010
work in
progress
Bridge completed Approaches Pending due to LA
problem
10 RCSNCRMP/B-W/AP/RCS/PRED/
07/PV Palem/0016
Road from R&B Road Alluru to
Yadavapalem
2011-2012
1.11.2011Completed
11 3Road from @ 56/8 to C.K road to
Periyavettu kuppam CS14.09.2012
work in
progressWBM Gr-II progress
12 2Providing BT road to Pedapannamgadu in
Tada Mandal14.09.2012
Work
completedRoad furniture is balance
NCRMP/B-W/AP/RCS/PRED/09/TADA/009
RCSSPSRNellore
Guntur
SPILL OVER (NCRMP YEAR-1) WORKS STATUS TABLE - 4
Srikaulam
RHB
NCRMP/B-W/AP/RHB/PRED/
01/Polaki/006
MPCSNCRMP/B_W/AP/MPCS/PRED/
01/Santhabommalli/005
Page 9 of 130
-
7/27/2019 Monthly Progress Report for July 2013
11/131
Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works
1 Srikakulam 11 22 4 11 4 10 19 43 0 0 0 0 19 43
2 Vizianagaram 1 1 1 5 0 0 2 6 0 0 0 0 2 6
3 Visakhapatnam 1 1 3 4 3 5 7 10 0 0 0 0 7 10
4 East Godavari 3 5 6 9 5 8 14 22 2 2 0 0 16 24
5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33
6 Krishna 0 0 8 26 8 23 16 49 0 0 0 0 16 49
7 Guntur 2 2 2 3 1 1 5 6 1 1 0 0 6 7
8 Prakasam 0 0 3 11 8 23 11 34 1 1 0 0 12 35
9 Nellore 0 0 10 18 9 19 19 37 0 0 0 0 19 37
18 31 41 96 46 113 105 240 4 4 0 0 109 244Total
Details of Agreements Communicated by SPIU to TPQA Consultant during Quarter 1 ending with June 2013 TABLE - 5
R&B I & CADTOTAL
MPCS RCS RHB
PR
TOTAL Bridges Saline EmbankmentDistrictSl.
No.
Page 10 of 130
-
7/27/2019 Monthly Progress Report for July 2013
12/131
TABLE - 6
Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works
1 Srikakulam 12 24 4 11 6 13 22 48 1 1 0 0 23 49
2 Vizianagaram 1 1 1 5 0 0 2 6 0 0 0 0 2 6
3 Visakhapatnam 2 2 3 4 3 5 8 11 0 0 0 0 8 11
4 East Godavari 4 6 6 9 5 8 15 23 2 2 0 0 17 25
5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33
6 Krishna 0 0 8 26 8 23 16 49 0 0 0 0 16 49
7 Guntur 2 2 3 4 1 1 6 7 2 2 0 0 8 9
8 Prakasam 0 0 3 11 8 23 11 34 1 1 0 0 12 35
9 Nellore 0 0 11 20 9 19 20 39 0 0 0 0 20 39
21 35 43 99 48 116 112 250 6 6 0 0 118 256Total
RCS RHB
Details of Agreements Communicated by SPIU to TPQA Consultant during Quarter 1 ending with June 2013 + Spill over works of Year-1
Sl.
No.District
PR I & CAD
TOTALMPCS
Saline
Embankment
R&B
TOTAL Bridges
Page 11 of 130
-
7/27/2019 Monthly Progress Report for July 2013
13/131
PR
R&B-Brid
ges
I&CAD
D
Started
Notstart
ed
Progres
s
Completed
Stopped
/
Deleted
CivilEngineers
visits
Env&Social
visits
ElectricalE
ngg
visits
TotalVisits
Issued
Closed
Pending
CivilAud
it
Reports
Social&E
nv
Auditrepo
rts
ElectricalA
udit
reports
1 Srikakulam 48 1 0 49 40 5 40 0 4 192 32 2 226 168 15 1 14 17 23 2
2 Vizianagaram 6 0 0 6 6 0 6 0 0 28 5 0 33 48 0 0 0 5 0 -
3 Visakhapatnam 11 0 0 11 11 0 11 0 0 122 18 13 153 528 10 1 9 20 9 17
4 East Godavari 23 2 0 25 17 8 17 1 0 114 1 5 120 135 1 1 0 4 0 3
5 West Godavari 33 0 0 33 31 2 31 0 0 164 1 0 165 229 16 16 0 8 0 -
6 Krishna 49 0 0 45 38 11 38 0 0 59 11 0 70 57 5 2 3 4 8 -
7 Guntur 7 2 0 9 6 3 5 1 0 70 2 0 72 26 0 0 0 1 0 -
8 Prakasam 34 1 0 35 35 0 35 0 0 187 36 0 223 654 19 10 9 29 18 -
9 Nellore 39 0 0 39 39 0 39 0 0 150 46 0 196 1030 15 9 6 27 24 -
250 6 0 252 223 29 222 2 4 1086 152 20 1258 2875 81 40 41 115 82 22Total
ABSTRACT OF NCRMP WORKS PROGRESS STATUS UP TO JULY 2013 TABLE - 7
Cummulative Visits of TPQA
Cummulative Audit
Reports submitted
by TPQA
Sl.
No.
District
Work Entrusted Status of Works
TotalNo.ofQCtests
conducted
NCRs By TPQA
Review
ofContract
Doc
ument
Page 12 of 130
-
7/27/2019 Monthly Progress Report for July 2013
14/131
Annexure - A
Status of Works
-
7/27/2019 Monthly Progress Report for July 2013
15/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 92
11 to 40% 78
41 to 70% 19
71 to 100% 34
Works Not Started 29
Deleted 4
Total No of Works 256
Consolidated Abstract Status of NCRMP Works to the end of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
16/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 20
11 to 40% 13
41 to 70% 0
71 to 100% 7
works Deleted 4
Works Not Started 5
Completed 3
Total No of works 49
Abstract Status of NCRMP Works in Srikakulam District to the
end of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
17/131
MPCS 1 Y2-001Construction of CS in
Kollipadu110.00 7.10.2011 19.10.2011 5.07.13
Finishings is in progress,
& compound wall work is
in progress
95% _ Sand Material is not available
for 6 months.
MPCS 2 Y2-002Construction of CS in
Runku109.42
Decebmer
2012Dec-12 5.07.13
Finishings is in progress,& Sump, Septic tank anfd
compound wall
execavation is in
progress.
90% _
Site handed over to contractor
in december 2012, Sand not
available for 6 Months.
MPCS 3 Y2-005Construction of CS in
Amalpadu
MPCS 4 Y2-006Construction of CS in
Angavanipeta82.50 _ _ 18.04.14 Not started
PR engineers took position of
the requuired land in
Gramkantam.The villagers
wanted to cinstruct the cyclone
shelter at Amalapadu. PR
officers informed that it will be
resolved after elections.
MPCS 5 Y2-007Construction of CS in
Ch.Batsalavanipeta
MPCS 6 Y2-008Construction of CS in
Chintavanipeta
MPCS 7 Y2-009Construction of CS in
U.Narasingupalli85.00 _ _ 18.09.14 Not started
PR engineers took position of
the requuired land in
Gramkantam.The villagers
wanted to cinstruct the cyclone
shelter at Amalapadu. PR
officers informed that it will be
resolved after elections.
MPCS 8 Y2-010Construction of CS in
Bypalli85.00 25.03.2013 18.04.13 18.09.14
Reinforcement for
footings is in progress15% _
MPCS 9 Y2-011Construction of CS in
Chinavanka85.00 25.03.2013 20.04.13 18.09.14 PCC completed 15% _
MPCS 10 Y2-012Construction of CS in
Chinnakothuru74.20 25.03.2013 20.05.13 18.09.14 Earth work completed 10% _
MPCS 11 Y2-013
Construction of CS in
Chinnajittuvani palam
4
NCRMP/B-
W/AP/MPCS/PRED/
01/Ranasthalam/008
MPCS 12 Y2-018
Construction of A type
CS in Kommaravanipeta,
Ranasthalam mandal
74.20 20.3.13 _ 14.03.14 Not started
Contractor has informed that the
work will be started before 15-
08-2013
5NCRMP/B-W/AP/MPCS/
PRED/ 01/Kaviti/011MPCS 13 Y2-023
Construction of MPCS in
Ch. Karrivanipalem
(Type B), Kaviti mandal
85.00 23.05.2013 _ 19.03.14 Not started
Contractor has informed that the
work will be started before 15-
08-2013
Deleted
1
NCRMP/B-
W/AP/MPCS/PRED
/01/Santhabommali/005
2
NCRMP/B-
W/AP/MPCS/PRED/
01/V.Kotturu/003
3
NCRMP/B-
W/AP/MPCS/PRED/
01/V.Kotturu/004
Deleted
Deleted
Deleted
Date of
commencem
ent of work
DFC Stage of work
% of
work
done
Reasons for non-started
worksRemarks
Status of NCRMP works in Srikakulam District to the end of July 2013
Sl.
No
.
Package Nos.Catag
ory
S.n
o
Projec
t codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
Page 16 of 130
-
7/27/2019 Monthly Progress Report for July 2013
18/131
Date of
commencem
ent of work
DFC Stage of work
% of
work
done
Reasons for non-started
worksRemarks
Status of NCRMP works in Srikakulam District to the end of July 2013
Sl.
No
.
Package Nos.Catag
ory
S.n
o
Projec
t codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
6NCRMP/B-W/AP/MPCS/
PRED/ 01/Sompeta/012MPCS 14 Y2-024
Construction of MPCS in
Ramayyapatnam (Type
B)
85.00 23.05.2013 19.06.13 14.03.14 Earth work is in progress 5% _
MPCS 15 Y2-025Construction of MPCS in
Metturu (Type D)
82.50 20.03.13 4.05.13 14.06.14Foundation concrete is in
progress
10% _ With in the mile stone
MPCS 16 Y2-026Construction of MPCS in
Nuvvalarevu (Type D)82.50 20.03.13 _ 14.06.14 Not started
Contractor has informed that the
work will be started before 15-
08-2013
8
NCRMP/B-
W/AP/MPCS/PRED/
01/Santhabommali/014
MPCS 17 Y2-027
Construction of MPCS in
Reddica Sunnapalli
(Type C)
74.20 03.04.13 28.06.13 02.04.14 Earth work is in progress 5% _
MPCS 18 Y2-028Construction of MPCS in
Calingapatnam (Type D)110.00 20.03.13 15.04.13 14.06.14
Foundation completed,
Back filling is in progress20% With in the mile stone
MPCS 19 Y2-029
Construction of MPCS in
Bandravanipeta (Type
D)
110.00 20.3.13 05.05.13 14.06.14Foundation concrete is in
progress15% With in the mile stone
10
NCRMP/B-
W/AP/MPCS/PRED/
01/Polaki/018
MPCS 20 Y2-030Construction of MPCS in
Akkuvaram (Type B)85.00 15.03.13 10.04.13 14.03.14 PCC work is in progress 10% within milestones
MPCS 21 Y2-031
Construction of MPCS in
Jaganadhapuram (Type
B)
82.50 20.03.13 28.06.13 14.06.13 PCC completed 10%
Progress slow. Some problem
in availability of materials. Site
is located in interior area.
MPCS 22 Y2-032Construction of MPCS in
Kothamukkam (Type A)82.50 20.03.13 30.07.13 14.06.13 Earth work is in progress 5%
Progress slow. Some problem
in availabilit of materials. Site
is located in interior area.
MPCS 23 Y2-036
Construction of MPCS in
Bonthalakoduru (Type
B)
82.50 15.04.13 10.07.13 2.07.14 Earth work is in progress 5%
Progress slow. Some problem
in availability of materials. Site
is located in interior area.
MPCS 24 Y2-037
Construction of MPCS in
Pathadibbalapalem
(Type A)
82.50 15.04.13 26.06.13 2.07.14 Earth work completed 5%
Progress slow. Some problem
in availability of materials. Site
is located in interior area.
RCS 25 Y2-145 Road from Chinnavankato Gopaladavooru
3675 62.00 25.03.13 18.04.13 14.03.14 Road widening is inprogress
10% With in the mile stones
RCS 26 Y2-146
Road from MN peta
Road to Kondavooru and
to CS
500 23.00 25.03.13 18.04.13 14.03.14Road widening is in
progress10% With in the mile stones
RCS 27 Y2-147Road from R&B Road to
S.J. Puram265 18.00 25.03.13 18.04.13 14.03.14 GSB layer completed 20% With in the mile stones
RCS 28 Y2-148Road from Kothapeta
Road to Sainooru CS785 27.00 25.03.13 18.04.13 14.03.14
Road widening is in
progress10% With in the mile stones
12
NCRMP/B-
W/AP/MPCS/PRED/
01/Etcherla/017A
13
NCRMP/B-
W/AP/RCS/PRED/
01/V.Kottoru/001
7 NCRMP/B-W/AP/MPCS/PRED/
01/V.Kothuru/013
11
NCRMP/B-
W/AP/MPCS/PRED/
01/Ranasthalam/016
9
NCRMP/B-
W/AP/MPCS/PRED/
01/Gara/015
Page 17 of 130
-
7/27/2019 Monthly Progress Report for July 2013
19/131
Date of
commencem
ent of work
DFC Stage of work
% of
work
done
Reasons for non-started
worksRemarks
Status of NCRMP works in Srikakulam District to the end of July 2013
Sl.
No
.
Package Nos.Catag
ory
S.n
o
Projec
t codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
14
NCRMP/B-W/AP
/RCS/PRED/01/
Santhabommali/008
RCS 29 Y2-150
Borubhadra -
Meghavaram Road to M.
Maruvada
2000 82.00 03.04.13 20.05.13 14.01.14
Road widening work is in
progress and culverts
completed.
20% With in mile stones
RCS 30 Y2-154
Road from
Yeeramukkam Rati
R&B road to
Dunnavooru
350 15.75 18.03.13 29.04.13 14.03.14Road widening is in
progress 10% With in mile stones
RCS 31 Y2-155
Road from
Yeeramukkam Rati
R&B road Geddavooru
600 27.75 18.03.13 29.04.13 14.03.14Road widening is in
progress10% With in mile stones
RCS 32 Y2-156
Road from R&B road
Ganguwada to ro ad to
Sigalaputtuga
875 31.43 18.03.13 29.04.13 14.03.14Road widening is in
progress10% With in mile stones
RCS 33 Y2-157Road from R&B road to
Akkuvaram585 25.76 18.03.13 17.04.13 14.03.14
CC road completed,
Shoulders work is in
progress.
90% With in mile stones
RCS 34 Y2-158Road from R&B road to
Pathadibbalapalem3500 100.00 20.03.13 5.04.13 14.03.14
Road widening is in
progress and culverts
completed.
10% With in mile stones
RCS 35 Y2-159 Road from R & B road toPothayyapeta CS 1300 54.00 20.03.13 15.04.13 14.03.14 Road widening is inprogress 5% With in mile stones
17NCRMP/B-W/AP/RHB/
PRED/01/Polaki/005RHB 36 Y1-096
Road from R&B road
Edulavalasa - Killam to
Jonnam via
Talasamudram
2700 76.10 30.04.2011 11.10.2011 31.05.13 Completed 100%
RHB 37 Y1-097
Road from R&B road
Mobagam to
Duubakavanipeta via
Gajapathinagaram
2750 100.40 30.04.2011 11.10.2011 31.05.13 Completed 100%
RHB 38 Y1-098
Road from
Talasamudram to Dola
Regulator
1600 43.00 30.04.2011 11.10.2011 31.05.13 Completed 100%
RHB 39 Y2-265Road from B.M (R&B)
Road to Simmayyapeta1350 30.03.13 10.05.13 24.06.14
Road widening is in
progress10% With in mile stones
RHB 40 Y2-266Road from R&B road to
Marripadu400 30.03.13 7.05.13 24.06.14 GSB laying is in progress 20% With in mile stones
RHB 41 Y2-267Road from R&B Road to
Kakarapalli1200 30.03.13 1.05.13 24.06.14
Road widening is in
progress10% With in mile stones
RHB 42 Y2-268Road from R&B road to
Marripadu700 30.03.13 7.05.13 24.06.14 GSB laying is in progress 20% With in mile stones
107.50
15
NCRMP/B-
W/AP/RCS/PRED/
01/Mandasa/010
16
NCRMP/B-
W/AP/RCS/PRED/
01/Etcherla &
Ranasathalam/012
18NCRMP/B-W/AP/RHB/
PRED/01/Polaki/006
19
NCRMP/B-W/AP
/RHB/PRED/01/
Santhabommali/001A
Page 18 of 130
-
7/27/2019 Monthly Progress Report for July 2013
20/131
Date of
commencem
ent of work
DFC Stage of work
% of
work
done
Reasons for non-started
worksRemarks
Status of NCRMP works in Srikakulam District to the end of July 2013
Sl.
No
.
Package Nos.Catag
ory
S.n
o
Projec
t codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
RHB 43 Y2-269Road from R&B road to
Pathalingudu500 _ _ 24.06.14
Jungle clearence is in
progress
Adjoining land oweners(Paddy
fields) are objecting to earthwork
widening, Department officers
are trying to reslove the issue.
20
NCRMP/B-
W/AP/RHB/PRED/
01/Santhabommali/001
B
RHB 44 Y2-270
Road from DPN road to
Gangaram Village via
Palatalagam,
Srikrishnapuram
3700 204.00 03.04.13 5.04.13 22.09.14
Sub grade layer
completed from km 0/000
to Km 3/200, Bridge earth
work completed.
25%
Bridge designs are under
revision due to short fall in
number of spans
RHB 45 Y2-273
DPN road to D.L.Puram
jn. via Koduru,
Magathapadu,
Guppidipeta
2350 100.00 25.03.13 18.04.2013 19.03.14
Road widening and
culverts work completed,
WBM gr-II collection is in
progress
30% With in mile stones
RHB 46 Y2-274Guppidipeta road to
Chinnakoviripeta1340 54.00 25.03.13 18.04.2013 19.03.14
WBM GR-II laying is in
progress30% With in mile stones
RHB 47 Y2-275
K.C. Road to
Rajarampuram via
Ampalem Revuamplam
900 44.00 29.03.13 18.04.13 24.03.14Road widening and
culverts work completed.20% With in mile stones
RHB 48 Y2-276KC road to Amplam
(via) Urjam, Nandigam1.6 54.00 29.03.13 18.04.13 24.03.14
Road widening and
culverts work completed.20% With in mile stones
23
NCRMP/B-
W/AP/Br/R&B/
01/Uppugedda/002
R&B-
Br49 Y2-438
Construction of High
level bridge across
Uppugedda at KM 7/6 of
Srikakulam muncipal
limits to Pukkalapeta via
Killipalem
128.00 17.12.2010 25.08.12 31.07.13
Bridge hand rails and
finishing work is in
progress, Approach road
earth work completed
90%
Delayed due to revision of
Drawings. EOAT shall be
obtained
21
NCRMP/B-
W/AP/RHB/PRED/
01/Polaki/007
22NCRMP/B-W/AP/RHB/
PRED/ 01/Polaki/008
l
Page 19 of 130
-
7/27/2019 Monthly Progress Report for July 2013
21/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 6
11 to 40% 0
41 to 70% 0
71 to 100% 0
Works Not Started 0
Total No of works 6
Abstract Status of NCRMP Works in Vizianagaram District to theend of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
22/131
1
NCRMP/B-
W/AP/MPCS/
PRED/02/Pusapatir
ega/003
MPCS 1 Y2-041Construction of MPCS inBoddugurayyapeta (Type A)
80 14.03.2013 12.06.2013 13.03.2014
Earthwork Excavation, PCC
for footings, RCC footings,
pedestals and columns uptobottom of plinth beam work
completed. Back filling infoundation completed.
20%
RCS 2 Y2-160Road from R & B Road to
Gudepuvalasa CS440 14 14.03.2013 14.03.2013 13.03.2014
Earth work for widening is
in progress.2%
Progress of work is
slow
RCS 3 Y2-161Road from R&B road toKavulawada CS
150 16 14.03.2013 14.03.2013 13.03.2014Earth work for widening is
in progress.2%
Progress of work isslow
RCS 4 Y2-162Road from R & B Road to
Roluchappidi CS550 18.5 14.03.2013 14.03.2013 13.03.2014
Earth work for widning, GSB
work completed.12%
RCS 5 Y2-163Road from R&B road to
Chinapathiwada CS60 4.5 14.03.2013 14.03.2013 13.03.2014
Earth work for widning, GSB
work completed.7%
Progress of work is
slow
RCS 6 Y2-164Road from R&B road to BV
peta770 28 14.03.2013 14.03.2013 13.03.2014
Earth work for widning, GSB
work completed.7%
progress of work is
slow
% of
work
done
Reasons
for non-
started
works
Remarks
Status of NCRMP works in Vizianagaram District to the end of July 2013
Sl.
No.
Package
Nos.
catag
ory
S.
no
Project
codeWork Name
Length
(Mts)
Estimate
Value in
(Rs.Lakh
s)
DHS
2
NCRMP/B-
W/AP/RCS/PRED/
02/Bhogapur
am/001
Date of
commence
ment of
work
DFC Stage of work
Page 21 of 130
-
7/27/2019 Monthly Progress Report for July 2013
23/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 1
11 to 40% 1
41 to 70% 2
71 to 100% 7
Works Not Started 0
Total No of works 11
Abstract Status of NCRMP Works in Visakhapatnam District tothe end of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
24/131
1
NCRMP/B-W/
AP/MPCS/
PRED/03/Rambillii/004
MPCS 1 Y2-048
Construction of
cyclone shelter at
Venkayyapalem
70 03.10.11
Re startafter getting
approval of
foundationre design on29.06.2012
02.07.2012EOAT
approved
up to17.06.2013
All slabs, brick work,plastering, wood joinery,
flooring,plumbing, painting
completed. One sidecompound wall is to beconstruct.
97%
EOAT shall be
obtained from
competentauthority
2
NCRMP/B-W/AP/MPCS/
PRED/03/ S.
Rayavaram/009
MPCS 2 Y2-057
Construction of CS
at Bangarampalem I
& II H/o Vakadu.
(Type D)
110 20.04.13 20.04.2013 19.04.13
Earthwork excavationstarted and stop due to site
dispute. Alternate site is
identified and approval ispending.
0
Initially Contractor
started earthwork on asite handed over to
him. The site belongsto forest department.
Revenue officialspromised to hand over
a revenue site
adjacent to the forestsite. The site is likely
to be handed overafter elections.
RCS 3 Y2-165
Road from R & Broad to
Chinanagamayyapal
em CS
1525
Meters73 11.03.13 11.03.2013 10.12.13
WBM Gr-II From KM 0.000
to Km 0.800 completed.
Three nos. CD workscompleted.
WBM Gr-III From KM 0.000
to Km 0.800 spreadingcompleted, compaction
work is in progress.
35%
From KM 0.800to KM 1.525 is
not started.
(This stretchfalls under
forest land.).
PIU pursuingthe mater with
forest
department.
RCS 4 Y2-166Road from R & Broad to Annavaram
CS
1100
Meters73 11.03.13 11.03.2013 10.12.13
WBM Gr-II ( From km0.00to 1.057 ) and CC Road
work ( From km 1.057 toKM 1.107 ) completed .
WBM Gr-III From KM 0.000
to Km 0.800 spreading
completed, compactionwork is in progress.
51%
Status of NCRMP works in Visakhapatnam District to the end of July 2013
Sl.
No.Package Nos.
catago
ryS.no
Project
codeWork name
Length
(Mts)
Estimate
Value in
Lakhs
(Rs.lakhs)
DHS DFC Stage of work
% of
work
done
Reasons for non-
started worksRemarks
3
NCRMP/B-W/
AP/RCS/PRED/
03/Bheemili/00
5
Date of
commence
ment of
work
Page 23 of 130
-
7/27/2019 Monthly Progress Report for July 2013
25/131
Status of NCRMP works in Visakhapatnam District to the end of July 2013
Sl.
No.Package Nos.
catago
ryS.no
Project
codeWork name
Length
(Mts)
Estimate
Value in
Lakhs
(Rs.lakhs)
DHS DFC Stage of work
% of
work
done
Reasons for non-
started worksRemarks
Date of
commence
ment of
work
4
NCRMP/B-W/
AP/RCS/PRED/03/S.Rayavara
am/006
RCS 5 Y2-167
Road from R & B
road to
Revupolavaram CS
1065Meters
56.46 07.03.13 07.03.2013 06.12.13
Earth work for widening, CC
Road work completed fromKM 0.000 to KM 0.8538 and
from KM 0.8845 KM 1.072
98%
5
NCRMP/B-W/
AP/RCS/PRED/
03/Rambilli/007
RCS 6 Y2-168
Road from R & B
road toKothapatnam CS
650
Meters37 11.03.13 11.03.2013 10.09.13
Earth work, sub grade,GSB
and CC Road work
completed from KM 0.000to KM 0.610
98%
RHB 7 Y2-280Road from R & B
road to Rajavaram
425
Meters168 07.03.13 07.03.2013 06.06.14
One pipe culvert, WBM Gr-
II, Gr-III and OGPC seal
coat Work is completedFrom KM 0.0 to KM 0.425
95%
RHB 8 Y2-281Road from Rajala R& B Road to
Rajaraidupalem
1764Meters
168 07.03.13 07.03.2013 06.06.14
Sub grade with selectedearth(Gravel): From km 0.640to 0.750, from KM 1.190 to Km
1.764 completed. Earth workand WBM Gr-II completed
From KM 0.000 to KM 0.012,from KM 0.030 to KM 1.764.
GSB : 1488 Meters From KM
0.030 to KM 0.094, from KM0.340 to KM 1.764 completed.
45%
RHB 9 Y2-282
Road from R & B
road toGajareddipalem via
Venkaypalem
2614Meters
168 07.03.13 07.03.2013 06.06.14
4 Nos pipe culverts completed.
From Km 0/106 to Km 1/600and from km 2/0 to km 2/620GSB,WBM Gr-II,Grade-III and
OGPC + Seal coat completed.
From KM 1.600 to Km 2.0 andFrom KM 2.620 to KM 2.720
GSB work completed.
85%
From KM 1.600
to Km 2.000and in KM
2.620 to KM2.720, The
local peoplestopped the
work by
demandingshifting of
electrical poles.
6
NCRMP/B-W/
AP/RHB/PRED/03/Payakaraop
eta/005
Page 24 of 130
-
7/27/2019 Monthly Progress Report for July 2013
26/131
Status of NCRMP works in Visakhapatnam District to the end of July 2013
Sl.
No.Package Nos.
catago
ryS.no
Project
codeWork name
Length
(Mts)
Estimate
Value in
Lakhs
(Rs.lakhs)
DHS DFC Stage of work
% of
work
done
Reasons for non-
started worksRemarks
Date of
commence
ment of
work
7NCRMP/B-W/AP/RHB/PRED/
03/Payakaraop
eta/008
RHB 10 Y2-283Road from Z.P RoadPalmanpeta to
Korlayyapeta
1110
Meters58 07.03.13 07.03.2013 06.12.13
One single row and one tworow pipe culvert works
completed.
Retaining wall work completed
for 62.55 Meters ( 62.55m inkm 0/600 ).Earth work, GSB and CC
pavement From Km 0/0323to Km 0/4021, from Km 0/689
to 0/9294 and Cross Road
from Km 0/328 to 0/498Completed
93%
8
NCRMP/B-W/
AP/RHB/PRED/
03/Atchutapuram/009
RHB 11 Y2-284Road from R & B
Road to Vadapalem
450
Meters23 07.03.13 07.03.2013 06.09.13
CC Road completed from
KM 0.000 to KM 0.424495%
Page 25 of 130
-
7/27/2019 Monthly Progress Report for July 2013
27/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 12
11 to 40% 3
41 to 70% 1
71 to 100% 1
Works Not Started 8
Total No of works 25
Abstract Status of NCRMP Works in East Godavari District to the
end of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
28/131
1
NCRMP/B-
W/AP/MPCS/PRED/
04/
Uppalaguptam/002
MPCS 1 Y2-062
Construction of Cyclone Shelter
at Pedaraghavulapeta of
Uppalaguptam Mandal
105.65 17.10.11 24.02.12 16.07.13 Completed 100% _
MPCS 2 Y2-074Construction of CS at
Kesavadasupalem (Type D) 120 23.04.13 22.07.14 Nil Nil
site handed over on 29-
06-2013. Contractor is
making arrangements to
commence the work
MPCS 3 Y2-075Construction of CS at Pallipalem
(Type D)120 23.04.13 12.07.2013 22.07.14
Gravel collected for
Cattle Ramp0.1 _
MPCS 4 Y2-076Construction of CS at
Padamatapalem (Type D)106.94 22.04.13 21.06.13 21.07.14
Footings and Columns
completed ( F1, F4,CF2,
CF1, F3, SF2, CF3, SF1
)up to Plinth beam.
5% _
MPCS 5 Y2-077Construction of CS at
Kesanapalli (Type D)106.94 22.04.13 No 21.07.14 Nil Nil
4
NCRMP/B-
W/AP/MPCS/PRED/
04/Mamidikuduru/01
2
MPCS 6 Y2-078Construction of CS at Karavaka
(Type B)94 22.04.13 No 21.04.14 Nil Nil
5
NCRMP/B-
W/AP/RCS/PRED/
04/U. Kothapalli/002
RCS 7 Y2-169Road from R&B road to
Samanthkurru Pallepalem CS120 9 26.03.13 06.07.13 25.12.13
Carting Earth
Completed.12% _
RCS 8 Y2-170Approach Road from R & B
Road to Turupupalem CS100 7.5 04.04.13 No 03.03.14 Nil Nil
Contractor has Not not
yet startedNot started
RCS 9 Y2-171Road from R & B Road to
Kesanapalli (New) CS100 7 04.04.13 No 03.03.14 Nil Nil
Contractor has Not not
yet startedNot started
RCS 10 Y2-172Road from R & B Road to
Padamatipalem CS1880 70.5 04.04.13 14.06.13 03.03.14
Widening with Earth
work Completed.5%
RCS 11 Y2-173
Road from R & B Road to
Katrenipadu Lanka CS 640 20.5 29.04.13 08.06.13 30.10.13
OGPC + Seal coat
completed from Km.0.000 to Km 0.500.
55%
RCS 12 Y2-174Road from R & B road to
Kesavadasupalem (New) CS430 29.5 29.04.13 16.07.13 30.10.13
Widening and Carting
Earth work Completed.5%
8
NCRMP/B-
W/AP/RCS/PRED/
04/Mamidikuduru/01
3
RCS 13 Y2-175Road from R&B road to
Karavaka CS800 33 08.03.13 18.06.13 07.09.13
2no. Pipe Culvert
Completed3%
2NCRMP/B-W/AP/MPCS/PRED/
04/Sakhinetipally/01
0
Villge people abjected
on the location and
Contractor has Not yet
started. Departmentalofficers wanted to resole
the issue after elections.
7NCRMP/B-W/AP/RCS/PRED/
04/Razole &
Sakhinetipalli/010
6
NCRMP/B-
W/AP/RCS/PRED/
04/Malikipuram/009
3
NCRMP/B-
W/AP/MPCS/PRED/
04/Malikipuram/011
% of
work
done
Reasons for non-started
worksRemarks
Status of NCRMP works in East Godavari District to the end of July 2013
Sl.
No.Package Nos.
categor
yS.no
Project
codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
Date of
commencem
ent of work
DFC Stage of work
Page 27 of 130
-
7/27/2019 Monthly Progress Report for July 2013
29/131
% of
work
done
Reasons for non-started
worksRemarks
Status of NCRMP works in East Godavari District to the end of July 2013
Sl.
No.Package Nos.
categor
yS.no
Project
codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
Date of
commencem
ent of work
DFC Stage of work
9
NCRMP/B-
W/AP/RCS/PRED/
04/Katrenikona/015
RCS 14 Y2-176
CC Road from main proposed
road to Neellarevu II CS in
Neellarevu
540 29 08.03.13 06.07.13 07.02.14Widening and Carting
Earth work Completed.5%
10
NCRMP/B-
W/AP/RCS/PRED/
04/Allavaram/016
RCS 15 Y2-177Road from R&B road to
Samanthakurru CS380 41 29.04.13 02.06.13 30.10.13
Retaining wall
Completed.11%
RHB 16 Y2-289Road from R&B road to
Korukondavari Group1000 44.5 30.03.13 06.06.13 29.02.14
Widening and Carting
Earth work Completed.6%
RHB 17 Y2-290Road from R&B road to Gondi
Kodapa830 49.5 30.03.13 12.06.13 29.02.14
Widening and Carting
Earth work Completed.7%
RHB 18 Y2-293BT road fr om Komaragiripatnam
to Kadadari and to CS3500 93 30.03.13 09.07.13 29.03.14
Widening and Carting
Earth work Completed.6%
RHB 19 Y2-294
Road from R&B road
Samanthakurru to
Chakkavaripeta Rameswaram
880 55 30.03.13 14.07.13 29.03.14Widening work
Completed.7%
RHB 20 Y2-295Road from Guthena deevi to
Gogullanka1920 105 27.04.13 No 26.04.14 Nil _
Contractor has Not not
yet startedNot started
RHB 21 Y2-296Road from R&B road to
Ramalayampeta Pallamkurru (v)1350 105 27.04.13 No 26.04.14 Nil _
Contractor has Not not
yet startedNot started
14
NCRMP/B-
W/AP/RHB/PRED/
04/Katrenikona/016
RHB 22 Y2-297Road from N. Kothapalli to
G.Pora in Katrenikone (v)3500 157 30.03.13 No 29.03.14 Nil _
Contractor has Not not
yet startedNot started
15
NCRMP/B-
W/AP/RHB/PRED/
04/Razole/020
RHB 23 Y2-298Road from R&B road to
Aravapalem740 13 25.03.13 04.07.13 24.09.13
WBM Grade III
Spreding completed for
200m.
7%
16
NCRMP/B-
W/AP/Br/R&B/
04/Pampa Yeru-
1/015
Bridge 24 Y2-444
Construction of Bridge at Km
43/10 of Vakalapudi - Edatam
road across Pampa Yeru in EG
District.
8374 505 26.03.13 13.04.13 25.09.14
Pier 1,2,3 and 4 Wells
concrete and shinking
in progress.
18%
17
NCRMP/B-
W/AP/Br/R&B/
04/Pampa Yeru-
2/016
Bridge 25 Y2-445
Construction of Bridge at Km
43/6 of Vakalapudi - Edatam
road across Pampa Yeru in EG
District.
5054 355 25.03.13 20.05.13 24.09.14
Pier 2 cutting Edge and
Kerb completed and
Pier 2 cutting Edge and
Kerb Reinforcement is
in Progress.
8%
13
NCRMP/B-
W/AP/RHB/PRED/
04/Katrenikona/014
11
NCRMP/B-
W/AP/RHB/PRED/
04/Sakhinetipalli/00
8
12
NCRMP/B-
W/AP/RHB/PRED/
04/Allavaram/012
Page 28 of 130
-
7/27/2019 Monthly Progress Report for July 2013
30/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 7
11 to 40% 21
41 to 70% 2
71 to 100% 1
Works Not Started 2
Total No of works 33
Abstract Status of NCRMP Works in West Godavari District to theend of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
31/131
1
NCRMP/B-
W/AP/RCS/PRED/
05/Achanta/002
RCS 1 Y2-178Road from R&B road to Ayodya
lanka Marrimula CS. (CC Road)2500 136.00 30.03.2013 05.04.2013 29.03.2014 Sub grade completed. 6.00
2
NCRMP/B-
W/AP/RCS/PRED/
05/Bhimavaram/004
RCS 2 Y2-181
Construction of approach road to
CS in Losari of Bhimavaram
Mandal.
100 7.00 08.03.2014 16.05.2013 07.09.2013Sub grade, GSB
completed.14.00
RCS 3 Y2-182Road from R&B road to
Kothakayalathippa CS1200 51.70 02.04.2013
Sub grade, GSB, CD Works
completed.27.00
RCS 4 Y2-183Road from Narsapur Perupalem
R&B road to Mandavarithota1500 59.35 02.04.2013
Sub grade, GSB, CD Works
completed.33.70
RCS 5 Y2-184Road from Mollaparru R & B road
to Mollaparru Patha Colony850 58.80 02.04.2013
Sub grade,GSB completed.
CD works is in Progress.13.35
RCS 6 Y2-185
oa rom K . al em ( )
Panchayat office to Metturevu Palli
palem
880 36.15 02.04.2013 Scarifying is in progress. 10.09
RCS 7 Y2-186 R&B road to Chinamynavanilanka 1300 58.70 02.07.2013 Sub grade completed. 5.23
RCS 8 Y2-187 PR road to Ramanujapuram 1200 61.30 02.07.2013 Sub grade completed. 10.16
RCS 9 Y2-188Road from P.R road to
Prakasapuram750 30.00 02.07.2013 Sub grade completed. 10.45
5
NCRMP/B-
W/AP/RHB/PRED/
05/Kalla/004
RHB 10 Y2-299K.G. R&B Road to Mamidipudi of
Kalawapudi.2080 91.00 08.03.2013 15.04.2013 07.12.2013 GSB Material collection. 5.09
6
NCRMP/B-
W/AP/RHB/PRED/
05/Mogaltur/006
RHB 11 Y2-302Khalipatnam R&B Road to
Khalipatnam ferry1800 77.00 21.03.2013 12.04.2013 20.12.2013
Scarifying completed.
Earth Work is in Progress.6.54
RHB 12 Y2-306
oa rom arsapur erupalem
R&B Road to Melamvaripalem
Peru alem S
800 41.00 15.04.2013Sub grade,GSB completed.
CD works is in Progress.30.41
RHB 13 Y2-307
Road from Perupalem Mollaparru
R&B road via Sattinenivarimeraka
to K.D. Pallavapalem
730 34.20 15.04.2013Sub grade,GSB completed.
CD works is in Progress.22.45
RHB 14 Y2-308oa rom erupalem
Dibbalapallipalem R&B road to
Mellapallavapalem
1860 77.25 15.04.2013Sub grade & CD Works is in
Progress.6.06
RHB 15 Y2-309
Road from Perupalem beach R&B
Road to Challavarimeraka via
Mucherlavarimeraka
1760 76.55 15.04.2013Sub grade 950 m
Completed.4.14
7
NCRMP/B-
W/AP/RHB/PRED/
05/Mogaltur/008
06.03.2013 05.06.2014
3
NCRMP/B-
W/AP/RCS/PRED/
05/Mogaltur/005
20.03.2013 29.06.14
4
NCRMP/B-
W/AP/RCS/PRED/
05/Narsapur/006
21.03.2013 20.03.2014
Remarks
Status of NCRMP works in West Godavari District to the end of July 2013
Sl.
No.Package Nos.
catago
ry
S.
no
Project
codeWork Name
Length
(Mts)
Estimate
Value Rs. in
Rs.lakhs
DHS
Date of
commenceme
nt of work
DFC Stage of work
% of
work
done
Reasons for non-
started works
Page 30 of 130
-
7/27/2019 Monthly Progress Report for July 2013
32/131
Remarks
Status of NCRMP works in West Godavari District to the end of July 2013
Sl.
No.Package Nos.
catago
ry
S.
no
Project
codeWork Name
Length
(Mts)
Estimate
Value Rs. in
Rs.lakhs
DHS
Date of
commenceme
nt of work
DFC Stage of work
% of
work
done
Reasons for non-
started works
RHB 16 Y2-310Road from Perupalem R&B road to
Dindla1600 62.25 15.04.2013
Sub grade completed. CD
works is in Progress.19.00
RHB 17 Y2-311
Road from Narsapur Perupalem
R&B road to Nellipallipalem via
Ambedkar colony Harijanapeta
4600 175.35 15.04.2013
Sub grade, GSB 1.000 KM
completed. CD works is in
Progress.
19.36
RHB 18 Y2-312Road from Perupalem R&B Road to
Kouruvaripalem1800 82.15 15.04.2013
Sub grade completed. CD
works is in Progress.10.32
RHB 19 Y2-313Road from SP R&B road to
Pasaladeevi2650 140.00 20.03.2013
Sub grade & CD works
completed.26.51
RHB 20 Y2-314 LT R&B road to Modi 800 34.53 20.03.2013 Sub grade completed.. 12.63
RHB 21 Y2-315SP R&B road to Gannabathulavari
palem of Chamakuripalem3750 149.47 20.03.2013
Sub grade & CD works
completed.22.53
RHB 22 Y2-316Road from R&B road to SC Colony
of Pedalanka750 47.60 Not Started 0.00
Villagers are objected.
Now the problem is
resolved. Work will
commence shortly
RHB 23 Y2-317R&B road to Rajeev Nagar of
Darbharevu1600 76.20 Not Started 0.00
Some villagers went tocourt not to proceed with
work.
RHB 24 Y2-318SP R&B road to Pedathota of
Turputallu250 18.10 01.04.2013
Sub grade, GSB, WMM, CD
Works completed.
Shoulders Work is in
pro ress.
52.92
RHB 25 Y2-319 R&B road to Peta of Turputallu 920 45.70 01.04.2013
Scarifying completed.
Earth Work & Sub grade
work is in Progress.
12.14
RHB 26 Y2-320R&B road to Pedathota of
Turputallu380 19.40 01.04.2013
Sub grade, GSB, WMM, CD
Works completed.
Shoulders Work is in
pro ress.
54.28
RHB 27 Y2-321 R&B road to Guttulavar imeraka 970 40.80 01.04.2013Sub grade & GSB
completed.14.00
RHB 28 Y2-322Road from R & B Road to
Pulaparthivaripalem2000 85.65 01.04.2013 Sub grade completed. 20.12
RHB 29 Y2-323 R&B road to Pedaedigapa lem 630 39.50 01.04.2013Sub grade, GSB, CD Works
completed.22.07
RHB 30 Y2-324 R&B road to Evanivarimeraka 190 14.05 01.04.2013 GSB Material collection. 5.16
11
NCRMP/B-
W/AP/RHB/PRED/
05/Narsapur/013
25.03.2013 24.03.2014
8
NCRMP/B-
W/AP/RHB/PRED/
05/Mogaltur/009
18.03.2013 17.06.2014
9
NCRMP/B-
W/AP/RHB/PRED/
05/Narsapur/010
14.03.2013 13.06.2014
10
NCRMP/B-
W/AP/RHB/PRED/
05/Narsapur/012
27.03.2013 26.06.2014
Page 31 of 130
-
7/27/2019 Monthly Progress Report for July 2013
33/131
-
7/27/2019 Monthly Progress Report for July 2013
34/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 31
11 to 40% 6
41 to 70% 1
71 to 100% 0
Works Not Started 11
Total No of works 49
Abstract Status of NCRMP Works in Krishna District to the end of
July 2013
35
-
7/27/2019 Monthly Progress Report for July 2013
35/131
RCS 1 Y2-189Road from R&B road to CS @
Ullipalem690 43.25 21.03.13 28.05.13 20.06.14
CD work, GSB
completed. WMM is in
progress
40
RCS 2 Y2-190Road from R & B Road to CS
at Jaruguvanipalem500 31.08 21.03.13 22.07.13 20.06.14 sub grade is in progress 9
RCS 3 Y2-191
Road from R&B road to CS @
Utagundam 290 16.16 21.03.13 22.07.13 20.06.14
Earth work and
scrarifying completed 3
RCS 4 Y2-192Road from R&B road to CS @
Ramakrishna puram390 21.39 21.03.13 28.05.13 20.06.14
GSB completed,wmm is
in progess40
RCS 5 Y2-193Road from R&B road to CS @
Chintakolla1950 95.16 21.03.13 20.07.13 20.06.14 GSB work in progress 20
RCS 6 Y2-194Road from R&B road to CS @
Padalavaripalem510 30.15 21.03.13 04.06.13 20.06.14
Earth work completed
and material collected
for CD works
4.8
RCS 7 Y2-195Road from R&B road to CS @
Mandapakala590 34.55 21.03.13 04.06.13 20.06.14
Widening completed
GSB collection is in
progress.
5.3
RCS 8 Y2-196
Road from R&B road to
Ramakrishna puram R & B
Road via Pathaupakali
3300 179.04 21.03.13 29.07.13 20.03.14Jungle clearance, earth
work completed1
RCS 9 Y2-197R & B Road to CS at
Kothaupakali510 32.26 21.03.13 29.07.13 20.03.14
jungle clearance, earth
work in progress1
RCS 10 Y2-198Road from Uppu Canal drain to
CS at Nali630 33.90 25.03.13 29.07.13 24.06.14
Jungle clearance is in
progress1
RCS 11 Y2-199Road from Nali R & B Road to
Barrankula CS2430 99.78 25.03.13 29.07.13 24.06.14
Jungle clearance
,Scarifying earth work
excavation is in
progress
3
RCS 12 Y2-200From R&B road to
Bhavadevarapalli230 29.85 25.03.13 29.07.13 24.06.14
Jungle clearance is in
progress1
RCS 13 Y2-201Road from R&B road to CS at
Pedapalem570 37.23 20.03.13 29.07 .13 19 .06.14
Jungle clearance
,Scarifying earth work
excavation is in
progress
3.5
RCS 14 Y2-202 Road from Gullalamoda R&Broad to Etimoga
183 19.65 20.03.13 27.07 .13 19 .06.14 Material collected forCD works
1
RCS 15 Y2-203Road from R&B to CS at China
Etimoga210 33.79 20.03.13 25.05 .13 19 .06.14
RCC slab compled,
earth work excavation
complted
2
RCS 16 Y2-204Road from R & B Road to CS
at China Kammavaripalem300 26.51 20.03.13 27.07 .13 19 .06.14
Jungle clearance work
is in progress1
NCRMP/B-
W/AP/RCS/P
RED/
06/koduru/00
2
3
NCRMP/B-
W/AP/RCS/P
RED/
06/Nagayala
nka/003
Reasons for
non-started
works
4
NCRMP/B-
W/AP/RCS/P
RED/
06/Nagayala
nka/004
5
NCRMP/B-
W/AP/RCS/PRED/
06/Nagayala
nka/005
1
NCRMP/B-
W/AP/RCS/P
RED/
06/koduru/001
2
Remarks
Status of NCRMP works in Krishna District to the end of July 2013
Sl.
No.
Package
Nos.
catago
ryS.no
Project
codeWork Name
Length
of Road
(Mts)
Estimate
Value
(Rs.Lakh
s)
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
Page 34 of 130
-
7/27/2019 Monthly Progress Report for July 2013
36/131
Reasons for
non-started
works
Remarks
Status of NCRMP works in Krishna District to the end of July 2013
Sl.
No.
Package
Nos.
catago
ryS.no
Project
codeWork Name
Length
of Road
(Mts)
Estimate
Value
(Rs.Lakh
s)
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
RCS 17 Y2-205
Road from China Zinkapalem
to Gollamanda via Peda
Zinkapalem
2030 103.90 22.03.13 21.06.14 Work not started
RCS 18 Y2-206Road from R&B road to CS at
Gollamanda900 47.92 22.03.13 21.06.14 Work not started
RCS 19 Y2-207Road from ZP Road to CS at
Natchugunta300 17.31 22.03.13 21.06.14 Work not started
RCS 20 Y2-208Road from Krishna River to
Elichetladibba CS720 58.85 22.03.13 21.06.14 Work not started
RCS 21 Y2-211
Road from
Kammavanicheruvu R&B road
to Venkata durgambapuram in
Machilipatnam Mandal
4100 203.77 22.03.13 13.04.13 21.04.14
Earth work started and
GSB material collection
in progress
19.5
RCS 22 Y2-212Road from R&B Road
Pedayadara to Harijanawada1100 66.33 22.03.13 02.07.13 21.04.14
Material collected for
CD works1
RCS 23 Y2-215Road from R&B Road
Karagraharam to Pallipalem630 41.49 04.06.13 01.09.14 Work not started
RCS 24 Y2-216 Road from R&B RoadKammavaricheruvu to KPT
palem
820 62.74 04.06.13 01.09.14 Work not started
RCS 25 Y2-217
Road from R&B Road
Kammavaricheruvu to
Malakayalanka
450 32.50 04.06.13 01.09.14 Work not started
RCS 26 Y2-218
Road from R&B Road
Pallithumalapalem to
Nelithippa
245 17.48 04.06.13 01.09.14 Work not started
Materials are to
transported
across salt creek
using punts. Due
to the problem ofapproach roads
during rainy
season, the works
can be taken up
after the rainy
season only. Prior
to the onset of
monsoon some
work should have
been done.
Contractor has
now informed
that the works
would be
completed before
agreement time.
7
NCRMP/B-
W/AP/RCS/P
RED/
06/Machilipat
nam/008
8
NCRMP/B-W/AP/RCS/P
RED/
06/Machilipat
nam/010
Contractor is
making
arrangements to
commence thework. He has
informed the
works would be
completed well
before agreement
time.
6
NCRMP/B-
W/AP/RCS/P
RED/
06/Nagayala
nka/006
Page 35 of 130
-
7/27/2019 Monthly Progress Report for July 2013
37/131
Reasons for
non-started
works
Remarks
Status of NCRMP works in Krishna District to the end of July 2013
Sl.
No.
Package
Nos.
catago
ryS.no
Project
codeWork Name
Length
of Road
(Mts)
Estimate
Value
(Rs.Lakh
s)
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
9
-
W/AP/RHB/
PRED/
06/Koduru/0
04
RHB 27 Y2-328Road from R&B Road to
Narsimhapuram3550 155.10 22.03.13 19.04.13 21.03.14
CD work& GSB, WMM
completed.58.06
RHB 28 Y2-329Road from R&B Road to
Krishnapuram2530 118.60 22.03.13 25.07.13 21.03.14
Material collected for
CD works1
RHB 29 Y2-330Road from R&B road to
Pedagudumotu1850 87.40 22.03.13 17.05.13 21.03.14 CD work is in progress. 2
RHB 30 Y2-335Road from R&B Road to Parra
chivara800 51.58 25.03.13 17.07.13 24.06.14
Jungle clearance work
is in progress1
RHB 31 Y2-336Road from R&B road to
Pedagowdapalem810 54.90 25.03.13 17.07.13 24.06.14
jungle clearance
completed & road
widening is in progress
2
RHB 32 Y2-337Road from R & B Road to
Mulapalem660 36.05 25.03.13 17.07.13 24.06.14
Jungle clearance work
is in progress1
RHB 33 Y2-338Road from Ganapeswaram
R&B Road to Pullaiahgaridibba1810 132.16 25.03.13 17.07.13 24.06.14
jungle clearance
completed & road
widening is in progress
4
RHB 34 Y2-343Road from R & B Road toIndiramma Tank in
Gullalamoda
1600 114.24 22.03.13 29.07.13 21.06.14Jungle clearance work
is in progress0.1
RHB 35 Y2-344Construction of road from ST
colony to Uppu drain in Dindi.1260 104.43 22.03.13 29.07.13 21.06.14
Jungle clearance work
is in progress0.1
RHB 36 Y2-345Road from Z.P.road to
Sorlagondi1380 110.23 22.03.13 29.07.13 21.06.14
Jungle clearance work
is in progress0.1
RHB 37 Y2-346Road from R & B road toMPUP School in
Sangameswaram
610 44.21 22.03.13 29.07.13 21.06.14Jungle clearance work
is in progress0.1
10
-
W/AP/RHB/PRED/
06/Koduru/0
11
NCRMP/B-
W/AP/RHB/P
RED/
06/Nagayala
nka/008
Just startrd
Contractor has
received
mobilization
advance on
19.07.13.
Contractor has
informed that
he was making
arrangements
commence
other items of
work and
complete theseworks well
before
agreement time.
12
NCRMP/B-
W/AP/RHB/P
RED/
06/Nagayala
nka/010
Page 36 of 130
-
7/27/2019 Monthly Progress Report for July 2013
38/131
Reasons for
non-started
works
Remarks
Status of NCRMP works in Krishna District to the end of July 2013
Sl.
No.
Package
Nos.
catago
ryS.no
Project
codeWork Name
Length
of Road
(Mts)
Estimate
Value
(Rs.Lakh
s)
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
RHB 38 Y2-347
Road from Matlam Z.P road to
Govindarajuladibba in
Kruthivennu mandal
1320 72.94 14.03.13 20.05.13 13.02.14
jungle clearance
completed & road
widening is in progress
10
RHB 39 Y2-348
Road from R&B road to
Amudalapalli (Pennamdibba)
in Kruthivennu mandal
2000 118.63 14.03.13 01.04.13 13.02.14
CD works completed
&.road widening is in
progress
11
RHB 40 Y2-349
Road from Seethannapalli
R&B Road to Gollagudem in
Kruthivennu mandal
720 51.83 14.03.13 01.04.13 13.02.14
CD works completed
&.road widening is in
pro ress
9
RHB 41 Y2-350
Road from R&B Road to
Bolugondi in Kruthivennu
mandal
1200 77.44 14.03.13 01.04.13 13.02.14
CD works completed
&.road widening is in
progress
12
RHB 42 Y2-351Road from R&B Road to
Ramapuram1370 96.05 18.03.13 17.06.14 Work not started
RHB 43 Y2-352Road from Chinapandraka R&B
Road to Uppuluru 3920 271.11 18.03.13 17.06.14 Work not started
RHB 44 Y2-353 Road from B.L road to Matlam 1950 152.00 26.03.13 17.06.13 25.06.14Gravel collection is in
progress for Sub Base5
RHB 45 Y2-354Road from Interu R&B road to
Parvathipuram3054 309.90 26.03.13 25.06.14 Work not started
Contractor
making
arrangements to
commence the
work
RHB 46 Y2-366Road from Gokavaram R & B
road to Vodarevupalem1060 50.90 18.03.13 25.07.13 16.04.14
Jungle clearance
completed & road
widening is in progress
1
RHB 47 Y2-367Road from Gokavaram R & B
road to Baduguvaripalem 470 35.07 18.03.13 25.07.13 16.04.14
Jungle clearance
completed & roadwidening is in progress
1
RHB 48 Y2-368Road from R&B Road
Thallapalem to Rayapalli470 29.49 18.03.13 25.07.13 16.04.14
Jungle clearance
completed & road
widening is in progress
1
RHB 49 Y2-369Road from Manginapudi R & B
Road to Pathareddypalem515 39.55 18.03.13 25.07.13 16.04.14
Jungle clearance
completed & road
widening is in progress
1
15
NCRMP/B-
W/AP/RHB/P
RED/
06/Kruthiven
nu/014
16
NCRMP/B-
W/AP/RHB/P
RED/
06/Machilipat
nam/020
13
NCRMP/B-
W/AP/RHB/P
RED/
06/Kruthiven
nu/011
14
NCRMP/B-
W/AP/RHB/P
RED/
06/Kruthiven
nu/013
Contractor is
making
arrangements to
commence the
work. He has
informed the
works would be
completed wellbefore agreement
time.
Page 37 of 130
-
7/27/2019 Monthly Progress Report for July 2013
39/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 3
11 to 40% 1
41 to 70% 0
71 to 100% 2
Works Not Started 3
Total No of works 9
Abstract Status of NCRMP Works in Guntur District to the end ofJuly 2013
Status of NCRMP works in Guntur District to the end of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
40/131
1
NCRMP/B-W/
AP/MPCS/
PRED/07/
Nizampatham/00
3
MPCS 1 Y2-097Construction of CS in Sanjeevanagar
of Kothapalem (Type B)35x40 85 22.3.2013 - 21.3.2014 Work not Started 0%
Contractor sick.
Deprtment issued
notice. Praposed
to start the work in
August.
2
NCRMP/B-
W/AP/MPCS/PRED/
07/Repalle/005
MPCS 2 Y2-101 Construction of CS inLankavanidibba (Type D)
35x40 110 22.3.2013 - 21.3.2014 Work not Started 0%
Contractor sick.
Department issued
notice. Proposed
start the work in
August
3
NCRMP/B-
W/AP/RCS/PRED
/
07/Nizampatnam
/005
RCS 3 Y2-225
Road from R&B
Koosureiyuvaripalem Road to
Marakavaripalem
1050 54 21.3.2013 3.6.2013 20.12.2013 GSB is in progress 15%
4
NCRMP/B-
W/AP/RCS/PRED
/ 07/PV
Palem/001
RCS 4 Y2-219Road from R&B Road Alluru to
Yadavapalem1033 51 1.11.2011 15.5.2012 30.4.2013 Work completed 100%
-
RCS 5 Y2-226
Road from Adavipallipalem R& B
road to New Tsunami colony (via)
Krupanagar Colony, Adavi Village
751 52 1.4.2013 - 20.12.2013 Work not Started 0%
Contractor has
informed that the
work would be
started before 15-
08-2013
RCS 6 Y2-227Road from R & B road to
Pattapupalem750 46 1.4.2013 18.6.2013 31.3.2014 Earth work is in progress 5% -
6
NCRMP/B-W
/AP/RHB/
PRED/07/
Nagaram/007
RHB 7 Y2-379Road from R&B road to
Gattuvaripalem2175 124 21.3.2013 3.6.2013 20.3.2014 Earth work is in progress 10% -
7
NCRMP/B-W
/AP/Br/ R&B/07/
Bapatla/011
Bridge 8 Y2-450
Reconstruction of HLB @Km2/4 of
Bapatla-Pandurangapuram Road
across perali drain
355 370 1.12.2010 7.7.2011 31.8.2012
Bridge completed
Approaches Pending due
to LA problem
90%
-
8
NCRMP/B-W/
AP/Br/R&B/07/
Peddapalli/022
Bridge 9 Y2-453
Reconstruction of bridge across
Peddapalli drain at km 14/6 of
Chandole bridge to Nizampatnam
road
193 145 12.3.2012 9.5.2013 11.3.2014 Earth work is in progress 5% -
% of
work
done
Reasons for non-
started worksRemarks
Status of NCRMP works in Guntur District to the end of July 2013
Sl.
No.Package Nos.
catagor
yS.no
Project
codeWork Name
Length
(Mts)
Estimate
Value
(Rs.lakhs)
DHS
5
NCRMP/B-
W/AP/RCS/PRED
/ 07/Bapatla/006
Date of
commence
ment of
work
DFC Stage of work
Page 39 of 130
-
7/27/2019 Monthly Progress Report for July 2013
41/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 9
11 to 40% 13
41 to 70% 4
71 to 100% 9
Works Not Started 0
Total No of works 35
Abstract Status of NCRMP Works in Prakasam District to the endof July 2013
-
7/27/2019 Monthly Progress Report for July 2013
42/131
RCS 1 Y2-228Road from R&B road to
Motupalli CS870 49 25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress 10%
RCS 2 Y2-229
Roa rom Km1 2+186 o
Chinaganjam Railway gate-
Bapaianagar ZP Road to
Ramachandranagar H/o
Kotha alem
836 39.1 25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress 10%
RCS 3 Y2-230
Roa rom Motupa i R&B Roa
to Nirikshanagiri (via)
Rudramambapuram CS in
Motupalli G.P.
2276 88.4 25.03.2013 15.05.2013 25.05.2014 GSB in progress 15%
RCS 4 Y2-231Road from R&B road to
Mattigunta CS363 12.47 25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress 10%
RCS 5 Y2-232Vedullapalli Vodarevu R&B road
to CS at Vijayalakshmipuram482 19 25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress 10%
RCS 6 Y2-233Road from Pakala PR Road to
Chellammagaripattapupalem CS1200 55 14.03.2013 02.04.2013 14.05.2014
1) GSB Work completed.
2) C.C Work progress.
3) WBM Grade-II, Spreading in
progress.
30%
RCS 7 Y2-234
Road from Pakala PR road to
Potthaiahgaripalem CS,
Kranthinagar Revu.
2150 102 14.03.2013 02.04.2013 14.05.2014 GSB work in progress. 20%
RCS 8 Y2-235Road from Woollapalem R&B
road to Devalampallipalem CS1200 47 14.03.2013 02.04.2013 14.05.2014 GSB work in progress. 20%
RCS 9 Y2-236Road from Tangutur to
Ananthavaram640 42 14.03.2013 02.04.2013 14.05.2014 GSB work in progress. 20%
RCS 10 Y2-238Road from Z.P. road to
Srirampattapupalem2040 108 11.03.2013 15.03.2013 10.03.2014
1)GSB & C.C Work completed
2) Shoulders to be done.95%
RCS 11 Y2-239Road from ZP road to
Pallipalem of Chakicharala800 47.79 11.03.2013 15.03.2013 10.03.2014
GSB Comp ete , CC Comp ete CD
Completed & WBM Gr-II Completed.
WBM Gr-III Completed, OGPC + SC
Completed, CD Works Completed
Shoulders in Progress.
98%
3
% of
work
done
1NCRMP/B-W/AP/RCS/PRED/
08/Chinaganjam
& Chirala/006
2
NCRMP/B-W/AP
/RCS/PRED/08/S.Konda &
Tangutur/010
Reasons for
non-started
works
NCRMP/B-W/AP
/RCS/PRED/08/
Ulavapadu/009
Remarks
Status of NCRMP works in Prakasam District to the end of July 2013
Sl.
No.Package Nos.
catago
ryS.no
Project
codeWork Name
Length
(Mts)
Estimate
Value in
Lakhs
DHS
Date o
commenc
ement of
work
DFC Stage of work
Page 41 of 130
-
7/27/2019 Monthly Progress Report for July 2013
43/131
RATE OF PROGRESS OF WORKS No of works
up to 10% 3
11 to 40% 20
41 to 70% 9
71 to 100% 7
Works Not Started 0
Total No of works 39
Abstract Status of NCRMP Works in SPSR Nellore District to the
end of July 2013
-
7/27/2019 Monthly Progress Report for July 2013
44/131
RCS 1 Y2-240
Road from @ 56/8 to C.K
road to Periyavettu kuppam
cyclone shelter
2000 85 14.09.2012 15.09.2012 13.09.2013WBM Gr-II
progress55% NIL
RCS 2 Y2-241
Providing BT road to
Pedapannamgadu in TadaMandal
1015 37.5 14.09.2012 15.09.2012 13.09.2013 BT completed 90% NIL
2NCRMP/B-W/AP/RCS/
PRED/09/Alluru/012RCS 3 Y2-242
Approach road to
Labbipalem420 21.97 ` 1.05.2013 17.09.13
CC pavement is
progress85% NIL
3NCRMP/B-W/AP/RCS/
PRED/09/Bogole/013RCS 4 Y2-243
Road from R & B road to
Pathakadapalem1400 52.37 20.03.13 1.05.2013 19.09.13
Earth work is
progress20% NIL
RCS 5 Y2-244Road from Ramudupalem
on R&B road to Pallipalem3600 203 20.03.13 10.04.2013 19.06.14 GSB is progress 50% NIL
RCS 6 Y2-245Road from Korutur to
Pattapupalem2250 148 20.03.13 1.06.2013 19.06.14
CD works
complete Gsb
progress,
34% NIL
5 NCRMP/B-W/AP/RCS/PRED/09/Kavali/020 RCS 7 Y2-246 Road from 230/6 Km of M.CRaod to Pedapattapupalem 6200 197.92 28.02.13 1.03.2013 27.02.14 GSB completed. 41% NIL
RCS 8 Y2-247Road from R&B road to
Utukuru Pallipalem3800 138 20.03.13 1.04.13 19.06.14 GSB is progress 24% NIL
RCS 9 Y2-248Road Ponnapudi R&B Road
to Ramachendrapuram.2000 114 20.03.13 1.04.13 19.06.14 GSB completed 40% NIL
RCS 10 Y2-249Ponnapudi R&B road to
Busagadipalem1900 92 20.03.13 1.04.13 19.06.14 GSB progress 25% NIL
RCS 11 Y2-250Road from Ponnapudi R&B
Road to Lakshimipuram1000 51.5 20.03.13 12.04.2013 19.06.14
su gra e
completed. CC
road in progress
20% NIL
RCS 12 Y2-251 Road from R&B Road toRamalingapuram
1700 75.5 20.03.13 12.04.2013 19.06.14 Eath work inprogress
20% NIL
7NCRMP/B-W/AP/RCS/PRED/
09/Chillakur/ 014RCS 13 Y2-252
Road from R&B Road
Lingavaram to
Narravaripalem
6808 338.86 21.03.13 22.03.2013 20.03.14 GSB progress 25% NIL
8NCRMP/B-W/AP/RCS/PRED/
09/Chillakur/015RCS 14 Y2-253
Road from R&B road (via)
Narravaripalrm to Srinivasa
Satram
2260 100.72
21.03.13
1.04.2013 20.03.14GSB is
completed.30% NIL
Remarks
Status of NCRMP works in SPSR Nellore District to the end of July 2013
Sl.
No.Package Nos.
Catagor
yS.no
Project
codeWork Name
Length
Mts
Estimate
Value in
lakhs
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
Reasons
for non-
started
works
1NCRMP/B-W/AP/RCS/PRED/
09/TADA/009
4NCRMP/B-W/AP/RCS/PRED/
09/I. Pet/018
6NCRMP/B-W/AP/RCS/PRED/
09/Vidavaluru/ 021
Page 43 of 130
-
7/27/2019 Monthly Progress Report for July 2013
45/131
Remarks
Status of NCRMP works in SPSR Nellore District to the end of July 2013
Sl.
No.Package Nos.
Catagor
yS.no
Project
codeWork Name
Length
Mts
Estimate
Value in
lakhs
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
Reasons
for non-
started
works
9NCRMP/B-W/AP/RCS/PRED/
09/Kota/016RCS 15 Y2-254
Road from R&B Road to
Doruvukatta road (via)
Allmpadu, Deyyaladibba
4320 181.32 20.03.13
21.03.13
19.03.14 BT completed 90% NIL
RCS 16 Y2-255
Road from Kotha Kudur
Katepalli road to PathaPattapupalem
600 35 15.03.13 1.07.2013 14.06.14Eath work in
progress 10% NIL
RCS 17 Y2-256Road from C.S. Puram to
Edurupalem2200 96 15.03.13 1.05.2013 14.06.14 GSB progress 25% NIL
RCS 18 Y2-257
Road from Mahlakshmi
puram to Sagara
Sangamam (via)
Muthyalathopu
Pattapupalem
2600 81 15.03.13 1.05.2013 14.06.14 B.T.completed 90% NIL
RCS 19 Y2-258
Road from R&B road
Nelaturu to Ananthavaram
CS
100 11 15.03.13 1.07.2013 14.06.14Eath work in
progress5% NIL
11 NCRMP/B-W/AP/RCS/PRED/09/Tada/024
RCS 20 Y2-259
Road from @ Km 65/4 of
CK Road to Tada Kuppam
CS
1900 83.63 22.03.13 23.03.2013 21.03.14
Gsb
completed,WMM
is progress
54% NIL
12NCRMP/B-W/AP/RHB/PRED/
09/Allur/018RHB 21 Y2-419
Road from R.I Road to C.R.
Palem (via) Sambhunipalem4000 110.01 18.03.13 1.06.2013 17.03.14
Vented road dam
is progress10% NIL
RHB 22 Y2-420
Salt Road from Iskapalli to
Salt fields at Kotha
Kurrupattapupalem
3000 131 18.03.13 19.03.2013 17.03.14
Gsb
completed,WMM
progress
55% NIL
RHB 23 Y2-421Road from R&B road to
Zuvvagu Lakshmipuram1800 81 18.03.13 19.03.2013 17.03.14 GSB progress 12% NIL
RHB 24 Y2-422Road from R&B Road to
Zuvvagu
2100 28 18.03.13 19.03.2013 17.03.14
Gsb
completed,WMM
progress
58% NIL
RHB 25 Y2-423
Road from Annagaripalem
R&B road to Pedanattu
Pattapupalem
2100 71 04.03.13 1.06.2013 03.03.14Eath work in
progress23% NIL
RHB 26 Y2-424
Roa rom
Pedapattapupalem to
Nandempuram
2800 94 04.03.13 4.3.2013 03.03.14
Gs
completed,WMM
progress
40.00% NIL
10
NCRMP/B-W/AP/RCS/PRED/
09/T.P.Gudur&
Muthukur/019
13NCRMP/B-W/AP/RHB/PRED/
09/Allur/019
14NCRMP/B-W/AP/RHB/PRED/
09/Kavali/024
Page 44 of 130
-
7/27/2019 Monthly Progress Report for July 2013
46/131
Remarks
Status of NCRMP works in SPSR Nellore District to the end of July 2013
Sl.
No.Package Nos.
Catagor
yS.no
Project
codeWork Name
Length
Mts
Estimate
Value in
lakhs
DHS
Date of
commence
ment of
work
DFC Stage of work
% of
work
done
Reasons
for non-
started
works
RHB 27 Y2-425Ponnapudi-Utukur road to
Pattapupalem2800 133.5 20.03.13 21.3.2013 19.03.14
Eath work in
progress25% NIL
RHB 28 Y2-426Road from R&B road to
Venkatareddypalem1100 54.5 20.03.13 21.3.2013 19.03.14
Eath work in
progress45% NIL
RHB 29 Y2-427Ponnapudi R&B road to
Anjanayapuram950 49 20.03.13 21.3.2013 19.03.14
sub grade is in
progress25% NIL
RHB 30 Y2-428Ponnapudi Utukur road to
Srigowripuram1100 64 20.03.13 21.3.2013 19.06.14
sub grade is in
progress20% NIL
RHB 31 Y2-429
Road from Ponnapudi
Utukur R&B road To
Kothuru
800 59 20.03.13 21.3.2013 19.06.14 GSB Completed. 25% NIL
RHB 32 Y2-430
Road from Ponnapud i
Utukur R&B road to
Prasanthi giri colony
1200 64.5 20.03.13 21.3.2013 19.06.14
Gsb
completed,WMM
in progress
45% NIL
RHB 33 Y2-431Ponnapudi R & B road to
Venkatanarayanapuram
1200 64.5 20.03.13 21.3.2013 19.06.14
GSB
Completed,WMM
in progress
40% NIL
RHB 34 Y2-432Road from Ponnapudi R &
B road to Ponnapudi500 35 20.03.13 21.3.2013 19.06.14
CC pavement
completd90% NIL
RHB 35 Y2-433Road from Mypadu R&B
Road to Kollimittapalem2350 123.5 20.03.13 21.03.2013 19.03.14
GSB
completed,WMM
is in ro ress
45% NIL
RHB 36 Y2-434
Road from Nellore
Mypadu R&B Road to West
Pattapupalem
900 56.5 20.03.13 20.06.2013 19.03.14GSB is in
progress20% NIL
18NCRMP/B-W/AP/RHB/PRED/
09/V.Chalam/021RHB 37 Y2-435
Road from
Thirumalammapalem R&B
Road to Gajulapalli Koneru
2400 95.88 08.02.13 9.2.2013 07.11.13 BT completed 90% NIL
19NCRMP/B-W/AP/RHB/PRED/
09/Kota/022RHB 38 Y2-436
Road from R&B road
Kothapatnam to
Yamadinnepalem (via)
Srinivasasatram
6100 267.31 19.03.13 20.03.2013 18.06.14 GSB completed 25% NIL
20NCRMP/B-W/AP/RHB/PRED/
09/Kota/023RHB 39 Y2-437
Road from at km 22/5 of
Yamadinne palem road to
Gunnampadia
1320 71.78 08.02.13 9.2.2013 07.11.13 BT completed 90% NIL
17NCRMP/B-W/AP/RHB/PRED/
09/I.Peta/027
15NCRMP/B-W/AP/RHB/PRED/
09/Vidavaluru/025
16NCRMP/B-W/AP/RHB/PRED/
09/Vidavaluru/026
Page 45 of 130
-
7/27/2019 Monthly Progress Report for July 2013
47/131
Annexure - B
NCR Status of Works
-
7/27/2019 Monthly Progress Report for July 2013
48/131
-
7/27/2019 Monthly Progress Report for July 2013
49/131
Sl.
No.Package No.
catag
ory
Project
codeWork name
Date of
Issued
NCR
No.Observations Remedial meassures Present status of NCR
SRIKAKULAM DISTRICT NCR STATUS AS ON 31.07.2013
13NCRMP/B-W/AP/RCS/PRED/
01/V.Kotturu/001.RCS Y2-148
Road from Kotharoad to
Sainoore6.7.13 12
At some locations, Raingullies are observed,
insists to rectify the same.
NCR no-12 Issued to the contractor/Line
department is requested to take suitable
remedial action.
Pending
14NCRMP/B-W/AP/MPCS/PRED/
01/Gara/015.MPCS Y2-028
Construction of Cyclone
shelter at Calingapatnam8.7.13 13
Saftey equipment was not provided to
concrete workers,insists to provide the safety
euipment to workers.
NCR no-13 Issued to the contractor/Line
department is requested to take suitable
remedial action.
Pending
15NCRMP/B-W/AP/MPCS/PRED/
01/Santhabommali/005.MPCS Y2-001
Construction of Cyclone
shelter at Kollipadu8.7.13 14
Saftey equipment was not provided to
concrete workers,insists to provide the safety
euipment to workers.
NCR no-14 Issued to the contractor/Line
department is requested to take suitable
remedial action.
Pending
Page 48 of 130
-
7/27/2019 Monthly Progress Report for July 2013
50/131
Sl.
No.Package No.
catago
ry
Project
codeWork name
Date of
Issued
NCR
No.Observations Remedial meassures Present status of NCR
VIZIANAGARAM DISTRICT NCR STATUS AS ON 31.07.2013
Page 49 of 130
-
7/27/2019 Monthly Progress Report for July 2013
51/131
Sl.
No.Package No.
catago
ry
Project
codeWork name
Date of
Issued
NCR
No.Observations Remedial meassures Present status of NCR
1 NCRMP/B-W/AP/RCS/PRED/
03/Bheemili/005
RCS Y2-165 Road from R&B road to
Chinanagamayyapalem
cyclone shelter
20.05.2013 1 WBM Gr-III sample collected and condut the
sive analysis test .The test results are IS sieve
45mm size at percentage of 96.13 as agaist of
60% to 90%. The mateial is under size in IS
sieve 45mm size.
NCR-1 Issued to take suitable remedial action
before proceding with further work. The rejected
material to be removed from the site and
replaced with suitable material
NCR pending
2 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005
RHB Y2-282 Road from R&B road toGajareddypalem
25.05.13 2 Right side compound wall is in obstructionKm2/652 to 2/658 approximaty 1mt.leftside
formers place is there.no contractor and line
department are tackling the land acqusition
issue at Km1/6 to