module n° 3icao state safety programme (ssp) implementation course 1 module n° 3 icao sarps...

40
Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5 ICAO State Safety Programme (SSP) Implementation Course 25/02/10

Upload: madeline-boyle

Post on 27-Mar-2015

232 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 1

Module N° 3 ICAO SARPs related to safety

management

Revision N° 5 ICAO State Safety Programme (SSP) Implementation Course 25/02/10

Page 2: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 2

SSP – A structured approach

Module 2Basic safety management

concepts

Module 3 ICAO SARPs related

to safety management

Module 4 ICAO SSP framework

Module 5ALoS related to an

SSP

Module 6 Prescription / Performance

Module 8SSP implementation plan

Module 1 Introduction to the

SSP implementation course

Module 7 SSP training programme

Module 3 ICAO SARPs related

to safety management

Page 3: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 3

At the end of this module, participants will be able to explain

the ICAO SARPs concerning safety management

Objective

Page 4: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 4

ICAO SARPs

State safety accountabilities

Questions and answers

Points to remember

Exercise N° 1 – Safety risk assessment – Airport construction project (See Handout N°1)

Contents

Page 5: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 5

Two audience groups

StatesService providers

Three distinct requirementsState safety programme (SSP)

Acceptable level of safety (ALoS) Safety management System (SMS)

Safety performance of the SMSManagement accountability

ICAO safety management SARPs – The big picture

Page 6: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 6

States shall establish a State safety programme (SSP), in

order to achieve an acceptable level of safety (ALoS) in civil

aviation

The ICAO SSP framework (Module 4)

Basic safety management SARPs – Part I

Page 7: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 7

An integrated set of regulations and activities aimed at improving safety

An SSP is a management system for the administration of safety by the State

What is an SSP?

Page 8: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 8

The implementation of an SSP must be commensurate with the size and complexity of the State’s aviation system

SSP in context

Page 9: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 9

The implementation of an SSP may require coordination among multiples authorities responsible for individual element functions in the State

SSP in context

Page 10: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 10

The acceptable level of safety (ALoS) to be achieved shall

be established by the State

Further discussed in Module 5

Basic safety management SARPs – Part I

Page 11: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 11

States shall require, as part of their SSP, that a [service provider] implement an SMS acceptable to the State that, as a minimum:

a) identifies safety hazards

b) ensures the implementation of remedial action necessary to maintain agreed safety performance

c) provides for continuous monitoring and regular assessment of the safety performance

d) aims at a continuous improvement of the overall performance of the safety management system

Basic safety management SARPs – Part II

Page 12: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 12

1. Approved training organizations that are exposed to safety risks during the provision of their services

2. Aircraft operators3. Approved maintenance

organizations4. Organizations responsible for

design and/or manufacture of aircraft

5. Air traffic services providers6. Certified aerodromes

Service providers required to implement an SMS

Page 13: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 13

A systematic approach to managing safety, including the necessary organizational structures, accountabilities, policies and procedures

Service providers are responsible for establishing an SMS

States are responsible, under the SSP, for the acceptance and oversight of service providers’ SMS

What is an SMS?

Page 14: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 14

A safety management system (SMS) shall clearly define lines of safety accountability throughout a service provider organization, including a direct accountability for safety on the part of senior management

(Accountability

Obligation or

willingness

to account for

one’s actions)

Basic safety management SARPs – Part III

Page 15: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 15

Safety responsibilities within an SSP are functions and duties which describe the safety purpose of what an individual is required to do, with regard to the operation of the SSP

Safety accountabilities within an SSP are statements of what an individual is required to deliver, either directly or through supervision and management of others, including those to whom the individual has delegated responsibility, with regard to the operation of the SSP

Further discussed in Module 4

State safety responsibilities and accountabilities

Page 16: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 16

Basic safety management SARPs in summary

StateState Service providerService provider

States shall establish a State safety programme (SSP), in order to achieve an acceptable level of safety (ALoS) in civil aviation

ALoS to be achieved shall be established by the State

States shall establish a State safety programme (SSP), in order to achieve an acceptable level of safety (ALoS) in civil aviation

ALoS to be achieved shall be established by the State

States shall require, as part of their SSP, that a [service provider] implement an SMS acceptable to the State that, as a minimum: identifies safety hazards ensures the implementation of

remedial action necessary to maintain agreed safety performance

provides for continuous monitoring and regular assessment of the safety performance

aims at a continuous improvement of the overall performance of the safety management system

States shall require, as part of their SSP, that a [service provider] implement an SMS acceptable to the State that, as a minimum: identifies safety hazards ensures the implementation of

remedial action necessary to maintain agreed safety performance

provides for continuous monitoring and regular assessment of the safety performance

aims at a continuous improvement of the overall performance of the safety management system

Page 17: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 17

Questions and answers

ICAO SARPs related to safety management

Page 18: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 18

Q: What is an SSP?A: ?

Questions and answers

Slide number:

Page 19: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 19

Q: What are the service providers included in the ICAO SARPs on SMS?

A: ?

Questions and answers

Slide number:

Page 20: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 20

Q: What is a safety management system (SMS)?

A: ?

Questions and answers

Slide number:

Page 21: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 21

1. Definition of SSP

2. Definition of SMS

3. State safety responsibilities and accountabilities

Points to remember

Page 22: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 22

Practical exercise N° 1 – Safety risk assessment - Airport construction project (Handout N° 1)

ICAO SARPs related to safety management

Page 23: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 23

Participants will be divided into separate groups

A facilitator will be appointed, who will coordinate the discussions and activities of each group

A summary of discussions will be written on electronic forms

A draft report, using the appropriate electronic form, will be prepared for its presentation in the plenary sessions and a member of the group (assisted by other members of the group) will brief on the results

International airport construction project

Page 24: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 24

Objective of the exercise

Conduct a safety risk assessment of a three-phase airport construction project (relocation of the control tower, construction of a parallel runway and construction of a new international terminal south of the airport)

Time allocated

03:00 hours

International airport construction project

Page 25: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 25

Scenario

International airport extension project in three phases (150,000 movements a year with a forecast of 10% traffic increase yearly)

Phase 1 – Relocation of the control tower south of the airport

Phase 2 – Construction of a parallel runway 10R-28 L, including all taxiways

Phase 3 – Construction of an international passenger terminal south of the airport

International airport construction project

Page 26: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 26

Current aerodrome layout

Page 27: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 27

Relocation of the control tower The control tower will be relocated south of the airport

(see aerodrome layout) and its height will be 15 m (50 feet) Duration: 12 months

Airport operationThe airport will continue to operate day and night (H24)

during the time of the constructionHazard identification and safety risk management

Identify the hazards, their consequences and assess the safety risks during the construction period

Phase 1 – Relocation of the control tower

Page 28: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 28

Phase 1 – Aerodrome layout

Phase 1

Page 29: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 29

Your task1. Review the aerodrome scenario for Phase 1 and

corresponding instructions2. List the type of operation or activity3. State the generic hazard(s)4. State the specific components of the hazard(s) 5. State the hazard-related consequences and assess the

safety related risk(s)6. Assess existing defences to control the safety risk(s) and

resulting safety risk index7. Propose further action to reduce the safety risk(s) and

resulting safety risk index8. Complete the following log (Table 03/01)

Phase 1 – Relocation of the control tower

Page 30: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 30

Table 03/01 – Hazard identification and safety risk management

Existing defencesto control safety risk(s) and safety

risk index

Further action to reduce safety risk(s) and resulting safety

risk index

Generic hazard

Type of operationor activity

1

2

3

4

5

Hazard-related consequences

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Specificcomponents of the hazard

Page 31: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 31

Construction of a parallel runwayIt is a new parallel runway (10R-28L) 4.200 m long and 60

m wide, including its corresponding taxiways (see aerodrome layout). Duration: 24 months

Airport operationThe airport will continue to operate day and night (H24)

during the time of the constructionHazard identification and safety risk management

Identify the hazards, their consequences and assess the safety risks during the construction period

Phase 2 – Construction of a parallel runway 10R-28 L

Page 32: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 32

Phase 2 – Aerodrome layout

Phase 2

Page 33: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 33

Your task1. Review the aerodrome scenario for Phase 2 and

corresponding instructions2. List the type of operation or activity3. State the generic hazard(s)4. State the specific components of the hazard(s) 5. State the hazard-related consequences and assess the

safety related risk(s)6. Assess existing defences to control the safety risk(s) and

resulting safety risk index7. Propose further action to reduce the safety risk(s) and

resulting safety risk index8. Complete the following log (Table 03/02)

Phase 2 – Construction of a parallel runway 10R-28 L

Page 34: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 34

Table 03/02 – Hazard identification and safety risk management

Existing defencesto control safety risk(s) and safety

risk index

Further action to reduce safety risk(s) and resulting safety

risk index

Generic hazard

Type of operationor activity

1

2

3

4

5

Hazard-related consequences

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Specificcomponents of the hazard

Page 35: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 35

Construction of a new international terminalIt is a new international terminal south of the airport,

including its corresponding access road and taxiways (see aerodrome layout). Duration: 36 months

Airport operationThe airport will continue to operate day and night (H24)

during the time of the constructionHazard identification and safety risk management

Identify the hazards, their consequences and assess the safety risks during the construction period

Phase 3 – Construction of a new international terminal

Page 36: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 36

Phase 3 – Aerodrome layout

Phase 3

Page 37: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 37

Your task1. Review the aerodrome scenario for Phase 3 and

corresponding instructions2. List the type of operation or activity3. State the generic hazard(s)4. State the specific components of the hazard(s) 5. State the hazard-related consequences and assess the

safety related risk(s)6. Assess existing defences to control the safety risk(s) and

resulting safety risk index7. Propose further action to reduce the safety risk(s) and

resulting safety risk index8. Complete the following log (Table 03/03)

Phase 3 – Construction of a new international terminal

Page 38: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 38

Table 03/03 – Hazard identification and safety risk management

Existing defencesto control safety risk(s) and safety

risk index

Further action to reduce safety risk(s) and resulting safety

risk index

Generic hazard

Type of operationor activity

1

2

3

4

5

Hazard-related consequences

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Safety risk index:Safety risk tolerability:

Specificcomponents of the hazard

Page 39: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Module N° 3 ICAO State Safety Programme (SSP) Implementation Course 39

Elect a facilitator

Start with a general discussion on the objective of the task and the material available for this exercise (no more than 10 minutes)

Select one of the participants of the group for preparing the final report on the laptop

Be prepared to deliver the results of the exercises (in a pen drive) to the course instructor at least five minutes before the time allocated

Useful tips

Page 40: Module N° 3ICAO State Safety Programme (SSP) Implementation Course 1 Module N° 3 ICAO SARPs related to safety management Revision N° 5ICAO State Safety

Revision N° 5 ICAO State Safety Programme (SSP) Implementation Course 25/02/10

Module N° 3 ICAO SARPs related to safety

management