Page 1: Module 12 - Workshare for PMs Facilitator Guide

Workshare for Project Managers

Facilitator Guide

Page 2: Module 12 - Workshare for PMs Facilitator Guide

© Copyright 2009 WorleyParsons Services Pty Ltd This document has been prepared on behalf and for the exclusive use of WorleyParsons. This document may not be reproduced without the express permission of the Business Process Owner

Workshare Training – Workshare for Project Managers

Rev Description Orig Review WorleyParsons Approval

Date

A Issued for review Neil Grunwell

----

25-Aug-09

B Revised and reissued for use Stella Durdin Suren Thurairajah

Suren Thurairajah

26-Sept-12

Page 3: Module 12 - Workshare for PMs Facilitator Guide

Rev A 25-Aug-09 12 Page i

Workshare for Project Managers

Introduction .................................................................................................................. 1

Workshare Overview ................................................................................................... 1 A WorleyParsons Definition of Workshare .................................................................... 2 The Importance of Workshare – a business imperative ................................................ 3

The Role of the Project Integration Engineer ........................................................... 5 Why the PIE role is so important ................................................................................... 6 Major Accountabilities of the PIE ................................................................................... 7 The ‘Human’ attributes of a PIE ..................................................................................... 7 The Career Opportunities the PIE role can create ........................................................ 8

Workshare Methodology Overview ............................................................................ 9

Initiating a Workshare Opportunity ......................................................................... 10 Engaging the Supporting Office ................................................................................... 10 Defining the Work Split between the HO and SO ........................................................ 11

Undertaking a Gap Analysis .............................................................................. 11 Scoping the Work Split ...................................................................................... 13 Developing an Estimate of Hours (and Cost) .................................................... 15 Selection of Key Personnel ............................................................................... 16

Project Kick-off .......................................................................................................... 16 Are you really ready to kick-off Workshare? ................................................................ 16 Managing the initial start-up (the first 30 days) ............................................................ 17 Inter-Entity Work Orders .............................................................................................. 17 PAAF Process ............................................................................................................. 17 Workshare Kick-off Meeting ......................................................................................... 19 Team Induction(s) ........................................................................................................ 20

Project Execution ...................................................................................................... 21 Work Release Package (WRP) development & maintenance .................................... 21

Collaboration Tools ................................................................................................... 24 Utilizing SharePoint as a Project Workshare Portal .................................................... 24 Web Conferencing Tools ............................................................................................. 25

Cultural Awareness – An Introduction .................................................................... 27 What is Culture? .......................................................................................................... 27 Examples of Cultural Differences in Behaviours and Gestures ................................... 29 Key Competencies for Managing across the Globe .................................................... 30

Self Awareness .................................................................................................. 31 Communicating Effectively – Developing the Knowledge and Skills ................ 32

Module Summary ....................................................................................................... 34

Exercise / Questionnaire ............................................................................................. 1

Page 4: Module 12 - Workshare for PMs Facilitator Guide

Rev A 25-Aug-09 12 Page ii

ABOUT THIS FACILITATOR GUIDE This Facilitator Guide has been designed to assist facilitators effectively deliver the training module. Other course material includes:

PowerPoint slides

Participant Guide Participants should be provided with a printed Participant Guide which they will use to take notes and /or answer questions and activities where necessary This Facilitaor Guide guide matches the Participant guide in layout but also includes the following extra assistance for facilitators:

Copies of the slides that correspond with the content

Colour-coded boxes with additional information and/or guidance for the facilitator

“Facilitator Resource” section at the back of the guide with question sheets to be printed.

Prior to Facilitating To adequately oprepare for facilitating the course the facilitator should:

Read the presentation slides and course content. Ther are additional notes on the slides to help you prepare.

Print “Facilitator Resources section at the back ofthis guide to use for a wrap up and review activity.

Timing Guide

Start Finish Topic

09:00 09:30 Course Intro &Workshare definition in the WorleyParsons context

09:15 09:30 EMS Workshare process overview

09:30 09:45 Initiating a Workshare Opportunity

09:45 10:15 Project Kick-off and Execution

10:15 10:30 Communication and Collaboration Tools

10:30 10:45 Cultural Awareness – a brief introduction

10:45 11:00 Wrap up & Review exercise

Information for

facilitator in

boxes like this.

Page 5: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 1

INTRODUCTION

Workshare is no longer an option but is now a business imperative to both assist in

overall growth and to maintain WorleyParsons’ competitive edge.

Even as market conditions change between times of high resource requirements

and lower workloads in some regions, Workshare is still important to balance short

term resource needs and to provide attractive delivery options in terms of both

schedule and cost.

Course Objectives: The desired outcome of this module is that you will be able to demonstrate understanding of:

the Workshare philosophy and work processes and their importance to WorleyParsons

the role of a Project Manager, Project Integration Engineer (PIE) and Discipline Lead in Workshare set-up and execution

the Project Manager’s role in contributing to the Workshare scope split definition and Work Release Package (WRP) development

the concepts of Cultural Awareness introduced in this module.

Introduce self

and explain the

objectives of

the session.

Before continuing on, get people to do a basic introduction

including:

Name

Role

Any experience with Workshare

Expectations for the course

Note their expectations on a flipchart/whiteboard so you can

refer basck to them later.

Page 6: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 2

WORKSHARE OVERVIEW

A WorleyParsons Definition of Workshare

Workshare occurs when one office packages a portion of the project scope for

execution by another WorleyParsons office. The Home Office (HO) retains

accountability for overall project performance.

A sometimes heard misconception is that Workshare involves a High Value

Execution (HVE) component. HVE is just one type of Workshare opportunity. All

WorleyParsons offices globally can be Workshare locations – either in a Home

Office or Supporting Office role.

There are a number of variances in the process to accommodate the scenarios that

we encounter in such a diverse business but the key elements required to

successfully deliver are consistent.

If a proposal is bid by one office and then fully executed by another office, it is not considered to be Workshare – the executing office becomes the contract holder.

Page 7: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 3

The Importance of Workshare – a business imperative

Workshare is no longer an option but is now a business imperative to assist in both

the overall growth and to maintain WorleyParsons’ competitive edge.

Why Workshare?

The Benefits of Workshare

Resources – optimize the use of our global resource pool and assist in maintaining workloads across offices, aid retention and improve stability of key personnel.

Specialist Skills – optimize the use of our extensive and diverse specialist skills across the organization.

Market Position – remain competitive or improve competitive position in an increasingly internationalized market by demonstrating the ability to adapt to the needs of global delivery maximizing skill usage, minimizing cost and maintaining quality of output.

Profitability – has the potential to maximize profitability of opportunity.

New Opportunities – using Workshare opens up new opportunities for locations and for WorleyParsons as a whole.

Schedule improvement – utilizing Workshare provides access to an increased resource base increasing schedule improvement opportunities.

Slide only has a

list of these

points. Refer

the group to

detailed

information in

their book.

This slide is

animated so

that only the

heading shows

at first.

Before

revealing

answers get

suggestions

from the group

for these points.

Reveal answer

and allow time

for them to

document.

We work in a globally competitive arena

Our competitors have embraced Workshare and the use of

low cost centres

Customers have ‘commoditised’ the design market and we

need to adapt to a new environment:

Customers consider it acceptable to shop around for the

lowest cost

We need to be able to compete on both quality and price

We need to leverage the global execution capabilities within

the organisation

some project opportunities are of such a large size that a

single office could not execute them to an acceptable

schedule

Successful Workshare delivery enables WorleyParsons to

sell a ‘one WorleyParsons’ global solution – a potentially

marketable differentiator

Page 8: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 4

Impacts of Workshare on our Staff

Workshare can be perceived as taking work from the location to go to a ‘cheaper’

location. This is not the intent. It is about bidding and winning more work,

maintaining our competitive position and improving employment stability in the long

term, enabling us to execute larger projects using multiple offices and resource

leveling. As we are able to bid and win larger projects, for individuals, there is

greater opportunity to work on diverse, world scale projects.

Any office can be the receiver of Workshare projects (ie. the SO) resulting in new

opportunities and generating work during local ‘lulls’.

Also at an individual level, there are new roles and new skills to develop to adjust to

this changing industry and potentially gain exposure to different offices and cultures.

How Workshare is implemented

1. Planning at the early stages of a project (even at the bid strategy stage) including early engagement of the SO.

2. Proven Methodology – corporate procedures, guides and templates.

3. Assigning of key resources (including the PIE).

4. Regional Workshare Manager and Coordinators (for location support).

Tools used

1. Collaboration Tools – to facilitate communications.

2. Global coordination and resource planning.

3. Knowledge Management – capture of ‘go-bys’ and lessons learnt.

4. Alignment of global systems and procedures to better leverage technology.

5. Ongoing training.

Page 9: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 5

Key Success Factors for successful Workshare Execution

There are a numbers of key success factors that will significantly influence

Workshare delivery so you must ensure:

While a number of the above tasks and processes will be not necessarily beer4

undertaken by the Project Manager directly, the Project Manager still has

responsibility for ensure that these tasks and processes are undertaken in

accordance with our EMS work processes.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

Answers are as follows:

1. Scope definition is accurate and clear

2. SO is able to deliver the agreed scope, any capability gaps

are understood, level of HO support is agreed and provided

where required

3. Communication Plan is well defined

4. All HO and SO responsibilities are clear

5. A clearly defined budget estimate and schedule is in place

and agreed

6. Progress Measurement method is defined

7. Risk assessment and mitigations are in place

8. Deliverables (and expected content) are clear – use ‘go-bys’

as needed

9. Focal points at both HO and SO are in place and trained

10. All other stakeholders are clearly identified

11. All procedures and standards are listed and made available

to the SO

This slide is

animated so only

the heading shows

at first. Before

showing details

get them to work

in pairs and write

down their own

list of what they

think the KSFs

are.

Get them to share

their responses

before showing the

slide.

Page 10: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 6

THE ROLE OF THE PROJECT INTEGRATION ENGINEER

Why the PIE role is so important

Having executed Workshare projects across the company for several years now, we

can say with great certainty that there is a requirement to put sufficient effort into the

coordination of work and information flow between the HO and SO to ensure a

successful Workshare outcome.

There are instances where the Project Manager or Project Engineering Manager

decides to take on the role of the PIE themselves. In almost every instance this

does not work because they:

1. Normally have many diverse issues to deal with.

2. Do not have the time to prioritize Workshare issues over other project activities.

3. Do not have enough time (at the right time) to deal with the day-to-day queries, meetings, conference calls, emails and other communications necessary to ensure Workshare activities run smoothly.

Importantly also, this is not the best use of a Project Manager’s or Project

Engineering Manager’s time. Their focus should be on the overall project delivery

and Customer relationship management.

Having a clear and effective focal point in the form of a PIE in the HO (as well as an

equivalent in the SO) immediately creates a positive impact on the project. Hence

we have now recognized this is a specialist role that is the key HO focal point.

The PIE will be the main ‘go-to’ person for the discipline leads in relation to any

Workshare related issues.

Page 11: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 7

Major Accountabilities of the PIE

On a project, the PIE would normally report to the Project Manager or on a mega-

project the Project Engineering Manager. For functional reporting (training,

development, performance reviews, etc.) the PIE would normally report to the

Location Engineering Manager or Manager of Projects.

The role of the PIE is quite diverse and incorporates elements of engineering

management, project management, project controls, systems and document

management. The chart below indicates the major areas of work effort for the PIE.

The ‘Human’ attributes of a PIE While a good understanding of the key work elements of the PIE role is important, unless the PIE has good communication skills and puts the appropriate level of effort into driving those communications for the team, there will still be significant interface issues for the project. The PIE can succeed in this area by:

Acting as a mediator when required.

Proactively expediting late documents and answers to queries.

Ensure regular discussions are taking place between the HO and SO teams – facilitating where required.

Communicating, communicating and communicating more – better to ‘over-communicate’ than ‘under-communicate’.

Ask the group for suggestions for any additional points

for this list of “human attributes” – discuss suggestions

Page 12: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 8

The selection criteria for persons wanting to take on a PIE role will be heavily weighted towards strong interpersonal skills including:

The selection criteria for persons wanting to take on a PIE role will be heavily weighted towards strong interpersonal skills including:

Where required, additional specific training in these areas can be arranged through our HR groups.

Career Opportunities the PIE role can create

The PIE position is an excellent development position for both existing Project

Engineers and discipline engineers looking to gain broader project delivery

experience and a potential move to a Project Management career path.

As the role covers such a broad range of project delivery activities across

engineering, project management and cost / schedule management, the experience

gained in this position can be an excellent stepping stone into Engineering

Management, Project Management or General Management career paths.

In addition, exposure to other locations, countries and cultures will provide a broader

range of experience than can be gained from working within a single office project

environment.

Specific industry experience relating to the project being undertaken is generally not

a prerequisite, as it is the interpersonal / communication skills and understanding of

the overall work processes that are most important to the successful execution of

the role.

This detail is not on any slide. Ask the who group for suggestions and list on a

whiteboard/flipchart. Suggested responses are:

Collaboration

Diplomacy

Persuasion

Sensitivity

Conflict Resolution

Cultural Awareness

Page 13: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 9

WORKSHARE METHODOLOGY OVERVIEW

The WorleyParsons Workshare methodology is described via the ‘Workshare

Procedure’ in EMS (document ref. EPP-0041).

This outlines the steps involved in the process and the available tools to support the

process. In summary this covers:

Project Award Where we want to make sure Workshare is considered from day 1 and included in the overall Project Execution Plan (PEP). Also note that it is important to let the SO know as soon as possible that the project is awarded (in case they have other preparatory work).

Project Kick-off Meeting This is where the overall Workshare Execution Plan should initially be discussed with the team and the role of the PIE and other key project roles are clarified to the key members of the project team. You can raise this if not raised directly by other project team members.

Workshare Planning This is where we undertake detailed planning, gap analysis of the SO, scope definition, cost control / progress measurement set-up and schedule development.

Workshare Execution Commemcing with a Workshare kick-off meeting and readiness review (we want to make sure both HO and SO are really ready to start!) followed by any training of team members in the Workshare process if required. Then, moving into monitoring and issue resolution.

Workshare Closeout Making sure we have addressed all elements of the Workshare Execution Plan (if in place) and individual Work Release Packages.

Go to the

‘Workshare

Procedure’ in

EMS by

selecting the

‘Engineering

Delivery’

workflow and

click on the

‘Documents’

tab.

Point out the

other

Workshare

supporting

documents here

and in the

‘Forms’ tab.

Open up the

‘Workshare

Procedure’ –

EMS no. EPP-

0041 and start

stepping

through the

process at a

high level.

Hightlight the

points listed in

the table on this

page.

Page 14: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 10

INITIATING A WORKSHARE OPPORTUNITY

Workshare opportunities are normally initiated in two basic ways (with several

variants).

Planned The project is bid on the basis that a portion of the work will be executed by a SO.

Unplanned The project was originally based on a single office execution but a change in circumstances has resulted in the need to engage a SO. This could be due to:

In either situation there is a requirement to scope the work and estimate the hours

and costs associated with the SO work package(s) and most likely seek approval

from the Customer prior to proceeding.

Engaging the Supporting Office

The importance of engaging the SO at the earliest opportunity cannot be over-

emphasized.

It promotes buy-in to the project from the SO.

The SO can assist in scoping the work split and can start planning resource allocations and recruitment if required.

The SO will most likely have ideas and execution options that will assist in ‘selling’ the proposal to the Customer.

It ensures that the HO has an early clear and accurate understanding of the cost of work to be executed by the SO.

Answers are as follows:

Scope increase – resulting in the project being too large for the HO to

execute on their own.

Schedule acceleration – requiring a larger resource pool for a short

duration making it impractical to recruit in the HO.

Cost saving opportunity – particularly the incorporation of a HVE

centre into the execution.

Specialist skills of the Support Office – there may be an area of the

project requiring specialist skills that the HO may not have but another

WorleyParsons office does.

Page 15: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 11

In the ‘heat of battle’ the Home Office project team may sometimes have priority

conflicts and in the lead up to committing the work to the SO, barely engage or in

rare instances, not engage the Support Office at all prior to committing the work to

that office. This obviously does not provide the ideal kick-off to a sound working

relationship and can result in ongoing conflict between the groups.

This is where the Project Manager with support from the PIE can assist the Location

Workshare Coordinators (where they are in place) and Regional Workshare

Managers in raising the flag for the SOs and pushing for that early engagement.

Defining the Work Split between the HO and SO

Undertaking a Gap Analysis

When looking to engage another office for a Workshare opportunity, it is important

that the HO clearly understands the capabilities and resource levels of the proposed

SO so that there is no misalignment of expectations in terms of what can be

delivered and especially the quality expected as part of that delivery.

If the SO capability is not clearly understood, a good methodical way of determining

this is to undertake a gap analysis looking at areas such as:

Have the SO team undertaken similar projects before? Perhaps they have done something similar in another industry sector.

Is the team familiar with the required codes and standards?

For each software system that must be used, does the team have local expertise and support?

Does the current ICT platform support the required software? This applies to EDS, document & data management, project controls, collaboration tools, etc.

A discipline by discipline review of the skill sets that the project Workshare scope requires to verify that suitable expertise is available in the SO.

The gap analysis can be performed at two levels depending on the circumstances:

Page 16: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 12

Organizational Level Gap Analysis

Where it is intended to develop an ongoing long term relationship with a SO to

execute a series of similar size / industry projects, a gap analysis may be

undertaken at the organizational level to determine the areas of expertise and hence

the most appropriate activities for the SO to execute on those projects. This can

then create efficiencies in bidding, scoping and reduce the risk of execution issues

across the range of projects.

An example of this would be to undertake a gap analysis with a HVE centre (such as

Beijing or Bangkok) prior to commencing a series of projects for a specific

Customer, a particular CSG or for an Improve contract.

Project Specific Gap Analysis

A project specific gap analysis should be considered when a suitable organizational

gap analysis is not available or where you are

Looking to work with a new SO where skills are not clearly understood.

Looking to work with an SO that you have previously worked with but on work that is now significantly larger or more complex in nature than undertaken previously or work in an industry sector in which work has not previously been undertaken in conjunction with that SO.

Looking to work with an SO in an industry sector outside of the SO’s normal operating field.

For example, a number of offices initially started through working within a single

Customer Sector Group (CSG) but are encouraged to develop skills across all

CSGs where possible. Workshare provides an opportunity to support this by

enabling the SO to work under the direction of an experienced HO in an industry

area where they may otherwise find it difficult to get ‘a foot in’ on their own.

It is worth remembering that many of our technical skills are transportable across

industries when supplemented by experienced industry professionals.

Page 17: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 13

Managing the ‘Gaps’

It is the project management team’s responsibility to ensure that if required, a gap

analysis is undertaken. It is highly likely when conducting this assessment that

there will be gaps in industry specific knowledge and / or skills. It should not be

instantly assumed that the HO should not give work to a SO that includes these gap

areas. Consideration needs to be given to:

Assisting the SO team to undertake training in the gap areas (particularly around software and systems).

Bringing key members of the SO team in to the HO team during the early phases of a project to gain experience and understanding of the specific project issues.

Seconding experienced key personnel from the HO team into the SO to provide on-site guidance and support.

Using the Gap Analysis for planning HVE Skills Development

Gap Analysis, particular Organization Gap Analysis should form the basis of forward

planning for skills development in HVEs. The Gap Analysis form, once complete,

clearly identifies gap areas and the type/level of those gaps. This information should

be used to develop training programs, recruitment initiatives and expat involvement

in looking at filling those gaps over time. Priorities for gap filling should reflect

regional and global HO strategies and potential up coming projects.

Looking for opportunities to fill gaps on projects is encouraged as a way to minimize

overhead costs.

Scoping the Work Split

Probably the number one consideration and starting point in developing the scope

split is to ‘keep it simple – minimize the interfaces’. If a gap analysis has been

completed, use this in establishing the scope split. Both the HO and the SO should

be involved in the development of the scope split and sign-off on the final agreed

split. It is the responsibility of the HO to ensure that all scope allocated to the SO

can be effectively undertaken by the SO with support and training requirements

considered and included. Generally, packages fall into one of these main

categories:

Horizontal Running across plant areas / facilities. Common examples being P&IDs or civil works – normally single discipline packages.

Vertical Portion(s) or area of the plant is packaged and will likely include all disciplines work within the agreed boundaries.

Phased Work is completed to a defined milestone in the HO (eg. 30% complete) and then transferred to the SO for completion.

Page 18: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 14

The ideal situation for a vertical package split is a very clear set of boundaries (as diagrammatically represented below):

Unless the capability does not exist within the SO it is not recommended that

elements of the vertical package (eg. structural design) are removed and

undertaken by the HO, even if the HO has the available resources. This creates

many complex interfaces that will put significant strain on both the HO and SO

design teams.

Where this is unavoidable, be prepared to devote additional time and resources to

managing the information flow and query resolution.

The agreed scope split is documented in the Workshare Execution Plan (WEP) and

subsequent Work Release Packages (WRPs).

SO

HO

SO HO

HO HO

Tip/‘Go-by’: To remember the difference between horizontal and vertical packaging, use the “one for all – all for one” approach.

Horizontal = one discipline in all areas

Vertical = all disciplines in one area

Don’t under-estimate the effort required to define clear scope boundaries.

Page 19: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 15

Developing an Estimate of Hours (and Cost)

When considering the costs associated with estimating Workshare projects, there

are three additional elements to consider over and above the estimating of a single

office execution project.

From a Discipline Lead’s perspective, we want them to make sure that the additional

coordination hours are considered when developing the estimate of hours.

SO estimate of hours / cost

Based on the agreed scope split.

Note – SO provides cost to HO which the HO may then mark-up to pass on to the customer.

Covers engineering, design, procurement, etc.

Management, coordination and support

HO engineering discipline coord. hours

Additional coordination hours. These would normally be captured as listed tasks on the discipline estimating forms.

Kick-off meetings

Regular progress meetings

Design Reviews

WRP input

Query resolution

Review of deliverables

HO Workshare support hours / costs

This needs to cover the cost of the PIE, visits to SO for HO team, placement costs for HO personnel seconded to SO, additional ICT Hardware and software, etc.

These hours / costs are captured on the HO Workshare Coordination estimate template.

PIE hours

Support services (eg. EDS, ICT, BSG)

Orientation visit to SO

HO personnel assignment costs in SO

SO visits to HO (non-labor only)

Visa and additional taxation costs

ICT hardware and software

Page 20: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 16

Selection of Key Personnel

While we have discussed in previous sections the importance that needs to be

placed on candidate selection for the PIE role, the selection of other key team

members will also influence the success of a Workshare project. These include:

Project Manager

Discipline Lead Engineers

Discipline Lead Designers

Where possible nominate personnel with previous workshare experience. Whilst

technical ability is important, there are traits that are equally important when filling

these roles on a workshare project.

Look to find personnel which have the following:

Excellent communications skills

Open minded

Open to the concept of workshare

Culturally sensitive

Willing to find solutions to new problems – virtual teams come with a new set of issues

In some cases, the focal point of a discipline may not be the ‘lead’ or manager but

one of their subordinates who could be better placed to undertake the coordination /

interface role for their area.

PROJECT KICK-OFF

Are you really ready to kick-off Workshare?

Thorough planning and preparation prior to kicking off a Workshare project is

essential. It is recommended that prior to kicking off the work, a ‘health check’ be

undertaken to assess the readiness of the project to commence its Workshare

activities. This should include items such as:

Is an Inter-Entity Work Order (IEWO) in place and a Personnel Assignment Authorization Form (PAAF) and process operational?

Are all systems operational (including Timesheets, CAD, etc.)?

If required, has the Workshare Execution Plan (WEP) been prepared and issued?

Have timesheet codes been set-up and published?

Ask – what the potential issues could be if you don’t have

these things in place.

Page 21: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 17

Managing the initial start-up (the first 30 days)

Generally, when a project kicks off (whether Workshare or not), there are a number

of tasks and actions that have to be completed in a short period of time for the

project to reach its full running speed. Without a method of tracking these tasks /

actions it is likely that a number will be missed or delayed affecting the efficiency of

the project team.

While a project schedule will highlight the major activities, there is still a need to

manage the detailed tasks, issues and actions.

Inter-Entity Work Orders

The Inter-Entity Work Order (IEWO) is the key document used to record the

agreement between offices where inter-entity invoicing is required. From a

Workshare perspective it is meant to capture the agreed budget, hourly rates (or

lump sum values) and payment terms for work carried out by the Support Office –

work should not commence without a signed IEWO.

The general guidelines for setting up an IEWO are:

Conditions should be fair and agreed by both parties. The IEWO should be signed by both parties.

If the risk is passed on to the SO, so should the associated rewards.

Unless there are special reasons, the WorleyParsons Standard Conditions of Contract should apply between entities.

The currency of the IEWO should normally be in the currency specified by the SO.

Handling of taxes should be clearly defined.

An IEWO is not required for offices in the same region operating on the same finance

system. For example, for the Perth office to engage the Melbourne office (both in ANZ

and on Oracle), an IEWO is not required to facilitate the transfer of costs between

entities within the finance system. However, some projects within the regions still

choose to use the IEWO as a way to document the commercial agreement plus T&Cs.

Page 22: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 18

PAAF Process

A Personnel Assignment Authorization Form (PAAF) is often required by projects to

provide a mechanism for gaining approval for start of work by an individual and their

assignment conditions by the Customer. The PAAF generally covers:

Position Details & nominated candidates details

Employment Type & associated Sell Rate build-up – wwe generally do not show the HVE cost rates to the Customer.

Additional Assignment Costs – mobilization, ongoing living expenses and demobilization costs.

Whether a retention bonus is applicable to the position.

Length of assignment.

The process may vary from project to project and the PAAF form may be project

specific. In general, the corporate process for issuing the PAAF to a customer

should be as follows:

1. Initial PAAFs and any revisions will be originated by the project’s nominated Rates Schedule custodian. This is normally either a project controls or finance representative (eg. Project Accountant).

o HR should then review and sign-off the PAAF to verify:

o Position Title

2. Salary and assignment conditions are correctly represented

3. The Project Manager (or their nominated delegate) is then required to review and approve the PAAF for:

o Salary and Sell Rate build-up

o Position Title

o Assignment conditions correctly represented.

4. The PAAF can then be issued to the Customer for approval / sign-off.

5. Once approved, the details are entered in the finance system so that the correct rates are applied to an individual’s timesheet hours.

6. The hard copy filing (including any revisions) is securely maintained by the project.

Page 23: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 19

Workshare Kick-off Meeting

The Workshare kick-off meeting is the first major opportunity to:

Introduce the key team members from both offices.

Review as a team the content of the WEP.

Review key schedule milestones.

Review schedule for input data required to get work underway.

Review the 30-day look ahead.

Agree on protocols for communications and future meetings.

Ideally if the project budget can support it, the kick-off meeting should be a face-to-

face meeting as this is the most effective forum and can also be used as a way of

introducing some team building. Cultural awareness training can be run at the same

time as the kick-off meeting and is recommended particularly for large projects and

where offices have not previously worked together – this reiterates the need to

consider these costs in the overall project estimate.

The PIE should arrange and facilitate the meeting with the attendees generally

being as follows (depending on the scope):

HO PIE and SO Coordinator

Discipline Leads – HO and SO

EDS Coordinators – HO and SO

Project Controls – HO and SO

Document Control – HO and SO

Project Manager (and Project Engineering Manager if in place)

Note: A separate EDS kick-off meeting is held between the EDS teams from each

office.

Page 24: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 20

Team Induction(s)

For Workshare to be successful the HO team needs to understand what it means to

them. While a project specific Workshare induction should be undertaken for the

key team members such as discipline leads, project control, etc. it is recommended

that all personnel on the projects go through this induction as even if they have no

direct interface with the SO it is likely that what they produce is either an influence

on or influenced by the deliverables from the SO.

The PIE should prepare and facilitate this induction and may also run the induction.

It is valuable for the Project Manager to attend at least at the start to reinforce the

importance of the points covered.

The Workshare Induction should cover:

Why the project is using Workshare.

An overview of the SO and their capabilities.

Team responsibilities, key activities and overview of work split (including timesheet and document approvals).

Workshare enablers to be used (eg. Project Portal) and how to access them.

Any specific milestones or execution issues that the team should be aware of.

Workshare key success factors.

Page 25: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 21

PROJECT EXECUTION

Work Release Package (WRP) development & maintenance

General Purpose of the WRP

The WorleyParsons Work Release Methodology is the overarching vehicle for

scoping and coordination of the Workshare elements of project delivery. At the core

of this methodology is the Work Release Package (WRP) which describes in detail

the scope of work to be performed by the SO.

When a project has a number of WRPs, a Workshare Execution Plan (WEP) can be

used to collect the common information so that it is not repeated in each package.

The WRP then generally contains information specific to the package and

references the WEP.

Responsibility for development and maintenance

The WRP is developed jointly by the lead personnel from both the HO and the SO.

It is a good idea for the PIE to take a coordinating role in pulling the WRP(s)

together to ensure the content is appropriate and there is consistency across WRPs.

Generally, the HO will develop the first draft for review by all stakeholders (including

the SO). Early involvement of all stakeholders in both offices is a key to

successfully completing the WRP. The PIE will also be required to ensure that the

documents are updated to reflect any scope changes. Both the HO and SO must

sign-off the WRP prior to formal issue.

Page 26: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 22

WRP Content Overview

Completed WRPs will generally cover the following topics (although topics may vary

depending on the scope of work and which EMS WRP template is used):

Scope of Work Objective Statement

List of expected deliverables

Completion status of any work to be transferred from HO

Specific exclusions

Home Office responsibilities Role & responsibilities prior to WRP execution

Role & responsibilities during the course of WRP execution

Identification of key stakeholders (including the PIE)

Supporting Office responsibilities Role & responsibilities of SO personnel

Identification of key stakeholders (including SO Coordinator)

Specification & Standards If a WEP is in place, only list those over and above those listed in the WEP.

Input Information List of information (data / models / documents, etc.) to be supplied by HO for the SO to start work.

Estimate Breakdown of estimate and hours by task and deliverable type / group

Schedule Key milestones and interface points with the overall project master schedule.

Engineering Design Systems If a WEP is in place, only list any deviations or additions to those listed in the WEP.

ICT If a WEP is in place, only list any additional requirements associated with the WRP.

Page 27: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 23

Scalability of the WRP

As we undertake a broad range of Workshare projects from small relatively simple

single discipline packages (eg. P&ID drafting) to large complex multi-discipline

packages across all four CSGs, three WRP templates have been created and are

available in EMS:

EPF-0050 – WRP Template (Small Projects) – also known as a ‘Quick Release

Package (QRP)’ and is meant to cater for small once through type packages of work

documenting only the minimum required to define the work scope either as a stand

alone document or under the umbrella of a WEP. Part A covers the general

information you would expect to see while Part B provides a simplified format for

describing the scope of work and execution parameters.

EPF-0049 – WRP Template (Medium Projects) – this is used when a WEP is not

planned and there is only one or two WRPs on the project. This effectively becomes

a combined WEP and WRP for these scenarios.

EPF-0048 – WRP Template (Large Projects) – is used under the umbrella of a

WEP to detail the scope of work and execution requirements for large complex

packages. It is very important that the scope is expressed in sufficient detail that

there will be no misunderstanding of the requirements by either HO or SO

personnel. It should also be made very clear what if anything is explicitly excluded

from the work scope.

Page 28: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 24

COLLABORATION TOOLS

The use of communication and collaborations tools is critical to the success of a

Workshare project. Having the tools in place and the skills available to set-up and

maintain them will make a big difference to the successful delivery of the work

scope.

While it is not expected that a Discipline Lead will need to be an expert in setting

these tools up, you should understand what they do, how to use them and where to

go for support.

Utilizing SharePoint as a Project Workshare Portal

All employees should be familiar with the fact that WorleyParsons has been utilizing

SharePoint as its main tool for intranet services and for project portals. We have

found this to be an effective tool that is relatively easy to set-up and has the ability to

be configured to an acceptable degree to suit project needs without the use of

HTML programming resources (it is menu driven).

This is the most commonly used tool for sharing information and documents across

groups and disparate project teams.

Ensures that all project participants have access to the current information at all times.

Maximizes the efficiency of the team and other participants across a range of locations.

Provides facilities for team news boards, discussions and sub-group sites.

Provides a document upload / download facility with check-in / check-out capability if required.

Access to areas of the project portal on SharePoint can be provided to Customers, vendors or sub-contractors with secure access control.

Useful tips on using a SharePoint Workshare Portal

Create a folder for each WRP.

For multi-discipline WRPs, create discipline sub-folders under the WRP folder.

Create two sub-folders under each WRP / discipline – one for ‘HO to SO’ documents and one for ‘SO to HO’ documents.

There isn’t a limit on the number of documents or files that can be uploaded to a folder but there is a limit of 50Mb per file.

You can create sub-folders with restricted access for confidential information (default access is all WorleyParsons personnel).

Get your team members to subscribe to the pages that they are involved with using the ‘Alert Me’ function so that they do not miss new items posted.

Page 29: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 25

Sample Workshare Portal

A sample site has been generated so that you can get a feel for the type of content

and layout that will work for most scenarios (refer screen shot below).

Tip: A SharePoint Information site is available on the NOW! Providing tips and guides on setting up and using a SharePoint page NOW! - Share Point Information Page

Page 30: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 26

Web Conferencing Tools

There are two main web conferencing tools that are available across the majority of

our business and can be used for:

Conference calls – most locations can dial-in using a local number (cost effective)

Web Conferences – using telephone conference call and web services to sharing of presentations, user’s desktop, on-line marking up of documents, etc.

The available tools are:

Genesys – an external provider and requires a user account. This is useful in particular if any participants are not connected to the WorleyParsons network – if you do not have a Genesys account you will need your Project Manager’s permission to get one (charged to the project) or you will need call on the PIE to set the session going for you.

MS communicator – requires connection to the WorleyParsons network by all participants (can be via VPN). This is a useful tool also for one-on-one ‘chat’, calls and desktop sharing.

From a Workshare perspective this is a very valuable tool for managing your

Workshare Coordination Meetings where issues can be discussed and documents

shared on the screen to assist in getting information and issues across to all

participants. As it is fairly quick to set-up, it can easily be used for adhoc meetings

and discussions.

Additional Information: A SharePoint site has been set-up providing user guides and information about how to get a Genesys account set-up at the following link:

Genesys Conferencing Support Page

Page 31: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 27

CULTURAL AWARENESS – AN INTRODUCTION

In both our professional and home environments we meet and interact with a

diverse range of people with differing social backgrounds, different priorities on what

is important to them and from diverse cultural backgrounds.

If we expect everyone we interact with to have the same ideals, beliefs and values

as ourselves, we are being both unrealistic and misguided. We are all ‘built’

differently and it is this diversity that provides the innovation, inspiration and

challenge that our societies need to learn, grow and develop.

As the majority of us grow up and start our working careers in the same country, we

develop an inherent general understanding of the people around us and what is

generally assumed ‘acceptable’ behavior in our interactions with others. Without

examining the values that drive how we think, feel and live, it is easy to assume that

people from other countries and cultures should understand those things that you

take for granted.

This is an incorrect assumption. Unless a person has been exposed to your culture;

it is more than likely that they will have been raised in an environment with different

values and beliefs which will result in different social behaviors.

By being aware of these cultural differences, we can better communicate, better

read situations and experience rewarding working and social relationships with our

colleagues in other offices.

This is particularly important for a PIE as it is highly likely that you will be

coordinating work between offices in different countries and hence different cultures.

Note: It is worth iterating that this is about cultural awareness – not trying to force one set of cultural values onto another group.

Experience proves that merely crossing cultural boundaries can be considered threatening, while positive attempts to interact may provoke defensive responses. Misunderstandings may be compounded by either an exaggerated sensitivity to possible slights, or an exaggerated and over-protective fear of giving offence.

Page 32: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 28

What is Culture?

“The values, beliefs, norms and traditions within an organization that influence the

behavior of its members” – The Oxford University Press Dictionary of Business

“By dealing with cultural differences up-front one can avoid some of the surprises” –

Tryggve Sthen, CEO Volvo Global Trucks

Our values and beliefs, which cannot be seen by either ourselves or others, drive

our behaviours which can be seen.

For example: if it is important to maintain harmony or ‘save face’ then you are likely

to see an individual or groups who do not reject the ideas of others and who remain

quiet in order to avoid criticizing or rejecting an idea or presenting bad news.

Imagine that group interacting with an individual or group who believes in being

forthright. People in that group are likely to be blunt in rejecting an idea that they

think will not work and will express their feeling directly rather than glossing them

over with politeness.

Page 33: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 29

Examples of Cultural Differences in Behaviours and Gestures

Different groups can have quite different perceptions of the same behaviors and

gestures. Here are some common examples:

Showing the thumb up in certain parts of the world means “Everything’s o.k.”. However, in some Islamic countries (as well as Sardinia and Greece) it is interpreted as a rude sexual sign.

In western European countries (especially between pilots or divers), “Everything’s OK.” is shown with the sign of the thumb and forefinger forming an “O”. In Japan this sign, especially with the fingers curled means “now we may talk about money”, In France it means “nothing” or “without any value” and in Eastern Europe and Russia, it is an indecent sexual sign.

In some countries silence and reflection is valued. In the Americas as well as in Arabic countries the pause between words are usually not too long, while in Japan pauses can give a contradictory sense to spoken words. Enduring silence is perceived as comfortable in Japan, while in India, many European countries and North America it may cause insecurity and embarrassment.

In some Asian countries, if you are invited to dinner, it is well-mannered to leave right after the dinner. If you don’t then it may indicate that you have not eaten enough. In the Indian sub-continent, ,most of Europe, South America and North America, to leave immediately after dinner is considered rude because there is an expectation that you will stay on and enjoy the company of the hosts an not just ‘eat it and beat it’.

In Africa, avoiding eye contact or looking at the ground when talking to elders or someone considered of higher social status is considered a sign of respect. In contrast, these same actions are often interpreted by Europeans, American, Canadians and Australians as signals of deception, shame or guilt

Different cultures maintain different amounts of personal space when meeting and conversing with one another. Northern Europeans leave each other more space that Southern Europeans. By understanding the difference, someone use to more personal space will not interpret someone standing close as threatening or aggressive. and someone use to less personal space will not interpret someone standing far away as remote, aloof or scared

Page 34: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 30

Key Competencies for Managing across the Globe

Organizationally, WorleyParsons has a corporate culture that is underpinned by

guiding values and principles. These have been turned into management practices

and systems and one practice that underpins WorleyParsons strategy is the

promotion of effective cross-culture worksharing. It is, however, at an individual level

that you can make the most difference.

The key competencies for managing globally are:

1) Self Awareness

2) Communicating Effectively – developing the knowledge and skills

3) Managing the processes and tasks.

We will now look at items 1 and 2 above (as item 3 is being covered by our EMS /

WPMP work processes and associated training).

Our Vision and Values

Our VisionWorleyParsons will be the

preferred global provider of

technical, project and operational

support services to our customers, using

the distinctive WorleyParsons culture to

create value for our customers and

prosperity for our people.

RELATIONSHIPS

• Rapport with all stakeholders

• Open and Respectful

• Collaborative approach to

business

AGILITY

• Smallest assignment to world

scale developments

• Local capability with global

leverage

• Responsive to our team’s

preferences

• Optimum solutions

customised to needs

PERFORMANCE

• Zero harm

• Results for the projects

we work on and our

internal stakeholders

• World class capability

and experience

LEADERSHIP

• Committed, empowered and

rewarded people

• Integrity in all aspects of

business

• Energy and excitement

• Minimum bureaucracy

Page 35: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 31

Self Awareness

Self awareness in this context could be defined as being aware of your own

“personal reactions to people who are from a different culture”. Being self aware

also assists in understanding the feelings and needs of other people (being

empathetic).

Very few people have inherent cultural awareness which means that all of us have

to put in considerable effort to develop (and maintain) it. This means that we need

to examine our own biases and prejudices, develop cross-cultural skills and promote

an environment for others to become more culturally aware.

Beware of Stereotyping and Typecasting

“Once formed they tend to persist; they tend to perpetuate by various selective

processes: selective recall, selective interpretation, selective retention and selective

replay… One has to make a conscious and deliberate attempt to overcome these

selective processes” – Samover, Porter, Jain 1981).

While we need to understand how different cultures may perceive our behaviors and

actions, we also need to consciously and deliberately think about how we might be

stereotyping or typecasting individuals or group of individuals in to overcome our

tendencies to-do so.

Understand the Perceptions of your own Culture

It helps greatly in communicating with other cultures for you to understand the way

other cultures may view your own culture. As people from different cultures encode

and decode messages differently, recognizing how your own behaviors and actions

can be interpreted by other cultures can help you to adjust the way a message is

delivered so that it has the best chance of being clearly understood.

Page 36: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 32

Communicating Effectively – Developing the Knowledge and Skills

The ‘tyranny of distance’ can make communicating across locations difficult at the

best of times. Adding different cultural mixes can amplify what would otherwise be

minor issues into significant issues. These issues can most often be attributed to:

Language (speaking) Even if you have learned the vocabulary of the other party’s language, the selection of the most appropriate words and the intonation of delivery can have an impact on the message received.

Language (understanding) Even though the other party may speak your language quite well, their understanding of everything you say at your normal speaking pace may be limited.

Assumptions It is easy to assume understanding and knowledge of areas that you take for granted. This can lead to frustration for both parties if instructions are not crystal clear.

The Situation More often than not, project timelines can create pressures that can result in meetings or conference calls being colored by emotions which can create even more frustration and misunderstanding between the parties.

Page 37: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 33

What can you do to improve communication across cultures?

When coordinating multi-cultural teams and even more so when language skills are

unequal, there are a number of ways that you can effect improvements in the

communications:

1) A relatively easy step you can take to reduce the risk of making some elementary mistakes is to research in advance the culture and communication conventions of the groups that you are going to be working with.

2) Write up roles, responsibilities, agendas, records of discussions and actions agreed to, because often the written word is easier to understand than the spoken word.

3) gives the participants (and yourself) more time to prepare questions / responses and reduce the risk of unintentional ‘emotive’ responses.

4) When writing, the choice of words is very important – more care should be invested in preparing (and reviewing) text prior to issuing as it is likely to be thoroughly analyzed by the recipient.

5) Avoid using slang and idioms – chose words that will convey the most specific meaning.

6) Listen carefully – if in doubt, ask for confirmation of understanding (particularly important if different languages or local accents / pronunciation could be a problem).

7) Respect the difference in other culture’s communication formalities and styles – watch for changes in body language or unintentional silences in conference calls). Remember that the outcome of any communication is to gain rapport in order to get agreement and to deliver a result.

8) It may not be possible to learn the other party’s language but it is a sign of respect to learn a few words and the gestures of greeting someone.

9) In specific circumstances, a translator should be considered to convey important messages.

Page 38: Module 12 - Workshare for PMs Facilitator Guide

Rev B 25-Sep-12 Page 34

MODULE SUMMARY

There are a number of key areas that Project Managers and their teams can

positively contribute and influence the successful delivery of a Workshare project.

1. Understand the capabilities of the Supporting Office (use ‘Gap Analysis’ methods if required).

2. Make sure your estimate of hours reflects any additional coordination effort required.

3. Keep the scope split as simple as possible – even if it means releasing work to the SO that you could do yourselves.

4. Ensure information is handed to the SO on time and review documents in the agreed timeframes.

5. Review the status of the Work Release Packages regularly.

6. View the Supporting Office as part of the team – work with them to resolve any issues – no “us and them” or “it’s their problem now”.

7. Communication! Communication! Communication! Make the time to do it, make it clear and do it regularly!

8. Use the support services available – Workshare Coordinators, EDS team and IT Services.

Page 39: Module 12 - Workshare for PMs Facilitator Guide

Wrap Up Exercice – Facilitator Resources

To wrap up the session and review information covered, use the questions on

the following pages to do an activity as follows.

Stick the question sheets face down on a wall or table and choose people to

pick one up.

They then have to read out the question and try to answer it.

Page 40: Module 12 - Workshare for PMs Facilitator Guide

1 – What is the WorleyParsons definition of Workshare?

Page 41: Module 12 - Workshare for PMs Facilitator Guide
Page 42: Module 12 - Workshare for PMs Facilitator Guide

2 – List three reasons why we undertake Workshare.

Page 43: Module 12 - Workshare for PMs Facilitator Guide
Page 44: Module 12 - Workshare for PMs Facilitator Guide

3 – Name our Supporting Offices.

Page 45: Module 12 - Workshare for PMs Facilitator Guide
Page 46: Module 12 - Workshare for PMs Facilitator Guide

4 – List three advantages of early SO engagement.

Page 47: Module 12 - Workshare for PMs Facilitator Guide
Page 48: Module 12 - Workshare for PMs Facilitator Guide

5 – Why is it important to consider a Gap Analysis?

Page 49: Module 12 - Workshare for PMs Facilitator Guide
Page 50: Module 12 - Workshare for PMs Facilitator Guide

6 – What are the main types of work split (with brief description)?

Page 51: Module 12 - Workshare for PMs Facilitator Guide
Page 52: Module 12 - Workshare for PMs Facilitator Guide

7 – List five key elements of a Work Release Package.

Page 53: Module 12 - Workshare for PMs Facilitator Guide