modul 1 process planning and standard time calculation

20
MODULE 1 Process Planning and Standard Time Calculation

Post on 12-Sep-2014

705 views

Category:

Technology


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Modul 1 process planning and standard time calculation

MODULE 1

Process Planning and Standard Time Calculation

Page 2: Modul 1 process planning and standard time calculation

Production System

Production system is a set of interacting subsystems with the purpose of transforming production inputs into production outputs.

Page 3: Modul 1 process planning and standard time calculation

Production System

Page 4: Modul 1 process planning and standard time calculation

Production System Parameter

• Production• Productivity• Efficiency• Effectiveness• Utilitie• Quality• Capacity

Page 5: Modul 1 process planning and standard time calculation

MRP II (Manufacturing Resource Planning)

Page 6: Modul 1 process planning and standard time calculation

Relationship Between MRP and MRP II

Page 7: Modul 1 process planning and standard time calculation

Just In Time (JIT)

• Just In Time is a production system or a modern fabrication management system developed by Japanese – American named Taichi Ohno of Toyota motor vehicles companies.

• JIT is a concept in which the raw materials used for production activity brought from the supplier of the material was right on time needed by the production process, so it will greatly save even eliminate the cost of inventory.

• The tool that is used in the JIT called Kanban

Page 8: Modul 1 process planning and standard time calculation

Kanban

• JIT production system using a flow of information in the form of a Kanban card-shaped or other equipment such as flags, lights, and others

Page 9: Modul 1 process planning and standard time calculation

7 types of waste

• Over production• Waiting• Transporting• Unnecessary process• Inventory• Unnecessary movement• Rejection

Page 10: Modul 1 process planning and standard time calculation

5 S

Page 11: Modul 1 process planning and standard time calculation

Bill Of Material (BOM)

• BOM (Bill of Material) is a list of the number of components, material and the ingredients

Page 12: Modul 1 process planning and standard time calculation

Operation Process Chart• Operation Process Chart is a chart performs the

process of raw material into a product which the operation steps and inspection belongs.

Page 13: Modul 1 process planning and standard time calculation

OPC

• The Benefit of OPC: To know the production costs and machineTo know raw material spent (efficiency

consideration in each step and inspection) A tool for layout and facilities design. A tool to diagnose work method. A tool for work experience

Page 14: Modul 1 process planning and standard time calculation

OPC sign

•Operation

•Inspection

•Storage

•Double Activities

Page 15: Modul 1 process planning and standard time calculation

Standard Time

• Standard time is the time needed by the worker on average to do the assignment without pressure in a workstation.

• Methods to calculating:a. Directly

b. Indirectly

Page 16: Modul 1 process planning and standard time calculation

Directly Methods

a. Stopwatch

The steps are:– Measure the initial time per activity – Uniformity test – Sufficiency test – Standard time decision

Page 17: Modul 1 process planning and standard time calculation

Directly Methods using Stopwatch

• Uniform Test

• Sufficiency test:

If N’>N, then need more data

Page 18: Modul 1 process planning and standard time calculation

Standard Time Calculation

pWsWn

NWs xi

)1( kWnWb

Calculate the cycle time (Ws)

Calculate the standard time(Wb)

Calculate the normal time (Wn)

Page 19: Modul 1 process planning and standard time calculation

Standard time calculation(notes)

= total measurements times

N = Number of measurements

P (adjustment factors) = 1+∑operator performance level

k = allowance

xi

Page 20: Modul 1 process planning and standard time calculation

Indirectly Calculation

a. Standard Time Data

Standard time data is an indirectly time measurement, by tables, curves and formulas gained by direct measurement. It is about the historical data of time needed. In addition, the standard time is known

b. Motion Time Data

It is different with company’s standard time which has been developed. Motion time data uses developed table by some institute