MODULE 1
Process Planning and Standard Time Calculation
![Page 2: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/2.jpg)
Production System
Production system is a set of interacting subsystems with the purpose of transforming production inputs into production outputs.
![Page 3: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/3.jpg)
Production System
![Page 4: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/4.jpg)
Production System Parameter
• Production• Productivity• Efficiency• Effectiveness• Utilitie• Quality• Capacity
![Page 5: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/5.jpg)
MRP II (Manufacturing Resource Planning)
![Page 6: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/6.jpg)
Relationship Between MRP and MRP II
![Page 7: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/7.jpg)
Just In Time (JIT)
• Just In Time is a production system or a modern fabrication management system developed by Japanese – American named Taichi Ohno of Toyota motor vehicles companies.
• JIT is a concept in which the raw materials used for production activity brought from the supplier of the material was right on time needed by the production process, so it will greatly save even eliminate the cost of inventory.
• The tool that is used in the JIT called Kanban
![Page 8: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/8.jpg)
Kanban
• JIT production system using a flow of information in the form of a Kanban card-shaped or other equipment such as flags, lights, and others
![Page 9: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/9.jpg)
7 types of waste
• Over production• Waiting• Transporting• Unnecessary process• Inventory• Unnecessary movement• Rejection
![Page 10: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/10.jpg)
5 S
![Page 11: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/11.jpg)
Bill Of Material (BOM)
• BOM (Bill of Material) is a list of the number of components, material and the ingredients
![Page 12: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/12.jpg)
Operation Process Chart• Operation Process Chart is a chart performs the
process of raw material into a product which the operation steps and inspection belongs.
![Page 13: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/13.jpg)
OPC
• The Benefit of OPC: To know the production costs and machineTo know raw material spent (efficiency
consideration in each step and inspection) A tool for layout and facilities design. A tool to diagnose work method. A tool for work experience
![Page 14: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/14.jpg)
OPC sign
•Operation
•Inspection
•Storage
•Double Activities
![Page 15: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/15.jpg)
Standard Time
• Standard time is the time needed by the worker on average to do the assignment without pressure in a workstation.
• Methods to calculating:a. Directly
b. Indirectly
![Page 16: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/16.jpg)
Directly Methods
a. Stopwatch
The steps are:– Measure the initial time per activity – Uniformity test – Sufficiency test – Standard time decision
![Page 17: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/17.jpg)
Directly Methods using Stopwatch
• Uniform Test
• Sufficiency test:
If N’>N, then need more data
![Page 18: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/18.jpg)
Standard Time Calculation
pWsWn
NWs xi
)1( kWnWb
Calculate the cycle time (Ws)
Calculate the standard time(Wb)
Calculate the normal time (Wn)
![Page 19: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/19.jpg)
Standard time calculation(notes)
= total measurements times
N = Number of measurements
P (adjustment factors) = 1+∑operator performance level
k = allowance
xi
![Page 20: Modul 1 process planning and standard time calculation](https://reader033.vdocuments.site/reader033/viewer/2022052303/54122aff7bef0a6a098b723f/html5/thumbnails/20.jpg)
Indirectly Calculation
a. Standard Time Data
Standard time data is an indirectly time measurement, by tables, curves and formulas gained by direct measurement. It is about the historical data of time needed. In addition, the standard time is known
b. Motion Time Data
It is different with company’s standard time which has been developed. Motion time data uses developed table by some institute