modot’s approach to program management kathy harvey state design engineer missouri department of...

20
MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Upload: julian-parrish

Post on 22-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

MoDOT’s Approach to Program Management

Kathy HarveyState Design EngineerMissouri Department of Transportation

Page 2: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Current Climate

Example: ’05 concrete is 56% higher than in ’03!

Page 3: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Mill

ion

s

Fiscal Year

Motor Fuel MV Licenses & FeesMV Sales & Use Tax Interest & Misc.Federal (Available to Obligate)

Total Revenue

3

Page 4: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Results

• $5.7 billion program over 6 years(FY02-07) delivered within 0.013 percent of estimate.

• FY 2007 project awards were 7.4 percent ($89.8m) under budget.

Page 5: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

A Change in Culture

• Radically control cost

• Maximize competition

• Seek innovation

Page 7: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

What we used to do

BRIDGE TO BE REPLACED

Page 8: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Practical Design

BEFOREBEFORE

AFTERAFTER

Saved $139,000

Farmers elated with ability to cross with large equipment.

Page 9: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Practical Design

BEFOREBEFORE

AFTERAFTER

Saved $95,000

Page 10: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Value Engineering

Page 11: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

• Employee incentive for delivering projects within 1 percent (or less) of contract award

• Individual incentive up to $2,000 per year

Page 12: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Maximize Competition

Alternate bidding• Concrete or asphalt? Let the marketplace

decide.

Page 13: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Alternate bidding• Not just pavements – pipes, structures,

bridges.

Maximize Competition

Page 14: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Number of Bidders

3.7

4.24

5.54

0

1

2

3

4

5

6

2005 2006 2007 Thru May Alt. Paving ProjectsOct 03 to Present

Bid

s/C

all

• 25 percent more bidders.• 9-10 percent decrease in costs.

Page 15: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Innovation

Performance specificationsEliminate method specifications where possible.

Page 16: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Design-Build

Page 17: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

We’re Producing Results!Smooth Roads Initiative• Now, 74% of major roads in good condition!

Page 18: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

• 161 lives saved in ‘06 – 13 percent drop• Biggest decrease in fatalities in U.S.

• 83 percent of ’07 newspaper editorials positive

• 85 percent of customers believe projects are right transportation solution

Success by the Numbers

• 16 percent reduction in run-off-the-road accidents

Page 19: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

Rave Reviews

MOST IMPROVED ROADS

1. I-40 Arkansas

2. I-44 MISSOURI I-80 Pennsylvania

3. I-70 MISSOURI

4. I-30 Arkansas

5. I-10 Texas

Page 20: MoDOT’s Approach to Program Management Kathy Harvey State Design Engineer Missouri Department of Transportation

• Missouri jumped from 39th to 17th in overall performance of the state highway system. – Reason Foundation

• MoDOT has nation’s 3rd-lowest administrative costs.

“… Missouri has been able to address many needed projects to improve road and bridge conditions, enhance highway safety and ease congestion.” – TRIP report, June 2007