Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 • Intermediate Body: Ministry of Transport • Employer: Latvian Railway - LDZ • Contractor: Consortium Thales Rail Signalling Solution Gmbh and Thales Rail Signalling Solution Baltics • Engineer: Systra

Upload: evangeline-gaines

Post on 12-Jan-2016

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

Modernisation of signalling system (2001/LV/16/P/PT/006)

Stage 1

• Intermediate Body: Ministry of Transport• Employer: Latvian Railway - LDZ• Contractor: Consortium Thales Rail

Signalling Solution Gmbh and Thales Rail Signalling Solution Baltics

• Engineer: Systra

Page 2: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

1. General information of contract:

• Type of project: Plant and Design-Build (FIDIC)• Commencement date: 10.01.2005• Contract price: 47.597.197 EURO• Scope of works (7 stages):

– interlocking systems: 32 stations– Lineblock system, including cable laying: 350 km– Level Crossing systems: 83– Reconstruction of 10 kV power supply line: 182 km– 2 CTC central offices– Point heating system: 21 stations– Refurbishment or installation of buildings (depends on situation):

32 stations• Time for completion:

– Initial: 09.01.2009– Adjusted in Addendum No.3: 31.12.2009

Page 3: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

2. Payments• Basis for payment:

– FIDIC Sub-Clauses 14.2, 14.4, Particular Conditions: BPQPW– Performance of a milestone (FAT, Delivery, Installation, Testing,

Commissioning) for any of 12 types of equipment– Invoice reaching 1% of contract Price.

• Payments made:– Advance payment: 4759719,7 EUR (29.06.2005)– Interim payments:

• 1-st: 2 863 610,29 EUR (Cable FAT) (27.12.2006/30.07.2007)• 2-nd: 897 499,41 EUR (Cable FAT and delivery) (30.07.2007)• 3-d: 484 215,21 EUR (Cable FAT and delivery) (30.07.2007)• 4-th: 2 082 213,5 EUR (FAT of interlocking, CTC hardware, UPS;

cable delivery) (21.12.2007)– Totally paid: 11 087 258,11 EUR (23,3 %)

• Next payments:– Probably for equipment/cable delivery– No more reasons: no further FAT performed, no completed installation,

no test is foreseen, no commissioning planning soon

Page 4: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

3. Cumulative Contractor “Completed Task" Performance

0

500

1000

1500

2000

2500

3000

3500

4000

Jan.

05

Mar

.05

Mai.

05

Jūl.0

5

Sep.0

5

Nov.0

5

Jan.

06

Mar

.06

Mai.

06

Jūl.0

6

Sep.0

6

Nov.0

6

Jan.

07

Mar

.07

Mai.

07

Jūl.0

7

Sep.0

7

Nov.0

7

Jan.

08

Mar

.08

Mai.

08

Jūl.0

8

Sep.0

8

Nov.0

8

Jan.

09

Mar

.09

Mai.

09

Jūl.0

9

Sep.0

9

Nov.0

9

Date

Qu

an

tity

of

Ta

sk

s

Planned to be Completed

Actually Completed Work Programme of 24.08.2007

Work Programme of 05.05.2006

Page 5: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

4. On-going Contractor Task Performance

0

50

100

150

200

250

300

Septe

mbe

r 200

6

Octobe

r 200

6

Novem

ber 2

006

Decem

ber 2

006

Janu

ary 2

007

Febru

ary 2

007

Mar

ch 2

007

April 2

007

May

200

7

June

200

7

July

2007

Augus

t 200

7

Septe

mbe

r 200

7

Octobe

r 200

7

Novem

ber 2

007

Decem

ber 2

007

Janu

ary 2

008

Febru

ary 2

008

Date

Nu

mb

er

of

Ta

sk

s Tasks which did not Progress from Previous Month

Tasks which progressed from Previous Month

Revised Work Programme

Page 6: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

5. Delays in project implementation*• Submission of FRS documents for approval: up to 180

days• Submission of Subsystem Technical Specifications for

approval: up to 200 days• Submission of detailed design for approval:

– Construction part: • Stage 1: up to 170 days• Stage 2: up to 170 days• Stage 3: up to 45 days

– Technological part:• Stage 1: up to 160 days• Stage 2: up to 170 days• Stage 3: up to 45 days

• Construction activity: – Stage 1: up to 180 days– Stage 2: to be started April, 2008, not ready.

* Based on the Detailed Work Programme, document 3CR 74510 0001 UHAFA, Edition 05, dated 24.08.2007

Page 7: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

6. Reason for delays• Insufficiency of Contractor’s human

resources (quality and quantity)

7. Consequences of current delays• Probable delay of project completion

• Application of conditional Delay Damages (currently about 157.200 EUR)

• Probable delay of project Stage 2 (Contractor: Consortium Bombardier/Belam Riga): CTC Jelgava, CTC Daugavpils

Page 8: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

8. Measures already taken

• Contract execution extended for 1 year (Addendum No.3)

• Discussions during monthly progress meetings• High level management meeting with

involvement of president of Thales Rail Signalling Solutions, held on 02.02.2008

• “Hot” management meetings with LDZ Technical Management Director and Contractor – weekly.

Page 9: Modernisation of signalling system (2001/LV/16/P/PT/006) Stage 1 Intermediate Body: Ministry of Transport Employer: Latvian Railway - LDZ Contractor: Consortium

9. Measures to be taken (Contractor)

• Involve more appropriate experienced experts for respective design areas

• Complete remaining technical solutions (CTC, Buildings/containers, Level Crossings, Diesel generators, 10 kV line, etc.)

• Issue documentation for approval without further delays

• Hire many more subcontractors, especially for performance of cable laying activities in parallel