modelling dc - european commission...modelling dc erc starting grant, 2011-2015 february 2020 dragan...
TRANSCRIPT
Modelling DC
ERC Starting Grant, 2011-2015
February 2020
Dragan [email protected]
School of EngineeringUniversity of Aberdeen
While AC power transmission was dominant in 20th century, DC transmission will be prevailing in the 21st.
Motivation1.DC transmission networks are required for large-scale offshore energy evacuation,2. DC grids will be fundamentally different from AC transmission systems. Technical challenges include:
• DC voltage stepping • DC fault isolation• DC grid control and dynamics
3. Typical (mid-size) DC grid shown in Figure 1:• How many DC/DC are required and where should they be located?• Is it better to use many DC CBs or few DC/DC?• Takes 4 hours of simulation on PSCAD for 1s of real time,• Not possible to determine eigenvalues,• Takes a PhD project to tune controls for stable operation,
Goals of Modelling DC project:1.Analyse role and topologies for DC/DC in large DC grids. 2. Analyse role and topologies for DC hubs in large DC grids.3. Develop Models for DC/DC and DC hubs, 4. Understand DC grid Control/stability challenges,
1. Background
2
=
Ba-A0
Ba-B0
= AC/DC Converter Station
SA0
SB0
Ba-A1
Ba-B1
Ba-B3
Bm-A1
Bb-B2
Bm-B2 Bm-B3
Bm-F1
Bm-E1
Bb-B1-1
Bb-B4
Bm-C1
Bb-C2
Bb1-D1-1
Cm-A1
Cb1-A1-1
Cb-B2Cm-B2
Cm-B3
Cm-F1
Cm-E1
Cb1-D1-1
Cb-C2
Cm-C1
Bo-C2
Bo-D1
Bo-E1
Bo-F1
800MVA
800MVA
800MVA
800MVA
200MVA
800MVA1200MVA
800MVA
1200MVA
50km
200km
200km
200k
m
200k
m
200km
200km
200km 50km
800M
W
210km
800MW
DC/DC Converter
300k
m80
0MW
280km200
MW
200km800MW
200km1400MW
300k
m12
00MW
300k
m12
00MW
200km1200MW/200km
1200
MW
447k
m
M
DC CableDC Overhead line
=DC DC=
1200MW
450km
1200
MW73
0km
790
175
324
0
89
86
392
971
324
500
188
103
1200
1200
450
100
4970
750
100
1300
900
618107
0
800MW
500
309
309
1000500
1000
500497
100
500
600
392
800
±400kV ±400kV
±400kV±400kV
±400kV
±400kV
±200kV
±200kV±200kV
±200kV
±400kV
971
447km
1200
MW
=
=
=
=DC DC
=
±400kV
=DCDC=
=
=
=
=1200MVA
1200MVA
790
=
=
800MVA=500
=DC DC
=
300k
m80
0MW
500
=
=
=
1200MW/200km750
750
7501200MVA
=
971
1200MVA
1200MVA
971
±400kV
448
783
783
Bb-B2-1 Bb-B2-2
Bb-B1-2
Bb1-D1-2
Cb1-D1-2
Cb1-A1-2
Bb1-A1-1 Bb1-A1-2
Hybrid DC CB
Figure 1. 11 terminal DC grid (based on CIGRE DC grid) with 3 DC/DC converters.
2. DC/DC converters
3Figure 2. Connecting two existing DC systems using a DC/DC converter.
Using DC/DC converter in DC grids
• Power trading between two DC systems of different voltage levels,• Improved operating flexibility,• Two protection zones, DC faults are not transferred across DC/DC,• Two HVDC of different manufacturers. DC/DC resolves multivendor issues,• DC/DC becomes:
• transformer (DC voltage stepping) ,• power flow regulator,• DC Circuit Breaker.
DC/DC
+/-400kV
+/-300kV
DC cable (200km)
DC cable (20-100km)
500MW
DC cable (500km)
+/-300kV
DC cable (300km) DC cable (200km)
• Interconnect multiple DC systems of different DC voltages,• Power flow in possible on each port. Any port is readily disconnected,• DC faults are not propagated to other ports,• No need for DC circuit Breakers,• Any phase is readily disconnected in case of an internal fault, (graceful
degradation),• Use redundant phase to meet N-1 criterion (substitute faulted phase with
a stand-by phase),
4
V1dc
Port 1
C1
L1 CB1
Port 3
C3
L3CB3
Bus_A
Bus_B
Bus_C
Bus_D
Bus_G
vcA
Port 2
C2
L2 CB2
Port 4ignd
vcB
vcC
vcD
Inner LCL circuit
V1dc
V4dc
V4dc
V3dc
V3dcC4
L4CB4V2dc
V2dc
Fig.3. 4-port, 4-phase DC hub. Phase D is in stand by.
3. DC Hubs
-4-3-2-101234
0.9 0.95 1 1.05 1.1 1.15 1.2
P idc
(pu)
Time(s)
P1dc
P2dc
P3dc
P4dc
-6
-4
-2
0
2
4
6
0.45 0.5 0.55 0.6 0.65
P idc
(pu)
Time(s)
P1dc
P2dc
P3dc
P4dc
5
Advantages:•DC fault is only a local disturbance •DC hub inherently reduces fault current,•DC fault is readily isolated•No need for DC CBs or fast protection, reliability is high•Each DC line can have different voltage level •Each DC line can have different HVDC technologies
3. DC Hubs
Fig.4. North Sea DC grid with 4 DC hubs
6
4. DC Grid demonstrators
Fig.5. 5-terminal, 900V, DC Grid demonstrator at Aberdeen HVDC research centre
7
5. DC Grid modelling
Average value, simulation based, DC Grid modeling: • Average value (type 5) model for each converter is fastest approach with reasonable accuracy,• CIGRE 10 terminal DC grid model, 20s of real time takes 4 hours simulation using average model (20µs).• Standard simulation platforms (PSCAD,EMTP) support only trial and error study in time domain,
Small-signal, linearized, state space, analytical models:• Multiple DQ frames are required at different frequencies and harmonics,• Non-linear elements can not be directly transferred to DQ frame,• Requires manual modeling with elementary equations for each converter, • Medium frequency (300Hz-1000Hz) circuits in the dc/dc converter complicate modeling,• Eigenvalue studies or frequency domain studies are possible, • Parametric studies are fast even for very complex DC grids.
Key eigenvalues original system -14.56 ± j313.2
-17.82± j129.5
Key eigenvalues with increased
PLL gains
-6.98 ± j317-33.74± j101.3
Fig. 6. MMC 10th order DQ analytical model validation, and eigenvalue study example.
8
6. DC Grid control
Fig. 8. DC Grid Dispatcher Controller
Primary/secondary response is decentralised:•DC grid dynamics are 2 orders of magnitude faster than AC grid dynamics.•No inertia. GW powers should be balanced within 1-2ms.•Each converter contributes to DC voltage control.•Control interactions within and between converters are a challenge.
DC Grid central controller:•Secondary response ensures power balance (automatic),•Optimisation of secondary response requires communication and a dispatcher.•Slow, Average DC voltage regulation is proposed, •Tertiary response (human intervention),
Fig. 7. 3-level controller for DC grid terminals
Further research/development work:
1. DC/DC converters as multifunctional DC grid components,• Have not been developed for GW powers.• DC grid planning with DC/DC (architecture, location, flexibility, security),• Complementary/interaction with DC Circuit Breakers, • Optimisation of losses, cost, size, reliability, ...• Adoption of MMC approach,
2. DC Hubs (electronics DC substations), • Have not been developed for GW powers.• DC grid planning with DC/DC (architecture, location, flexibility, security),• Optimisation of losses, cost, size, reliability ...• Control, modelling,
3. Simulation/Modelling of DC grids,• Simulation is very slow and model is too complex if number of converters is high (over 10),• Eigenvalue and parametric study capability is needed.• Faster analytical modeling is required for complex systems.
4. DC grid Control/stability challenges, • Generic control framework does not exist. • Grid control layers and interactions,• Bandwidth segmentation. Temporal and spatial interactions. Distributed fast, and centralized slow control, • Robustness, flexibility, interoperability, interaction with AC grids,
5. Hardware (low power) demonstrations, • De-risking of new converters and grid topologies,
7. Conclusion – further research
9