Mirasol Village Redevelopment Project Update Report to SHRC August 5,2020

Upload: others

Post on 26-Sep-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in

Mirasol Village Redevelopment Project Update Report to SHRC

A u g u s t 5 , 2 0 2 0

Page 2: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in
Page 3: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in

Mirasol Village – 1200 Richards

Rendering of Block A.

Page 4: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in

Recent Accomplishments and Looking Forward

Achievements

• February 2020 –Infrastructure contract start

• April 2020 – Tax credit and bond award for Block A

• April 2020 – Convert to Zoom meeting format

• May 2020 - Execute Green Infrastructure Grant for Mirasol Village Park; execute TCC Grant Agreement

• June 2020 – Close financing; start Blocks B/E construction

• July 2020 – MHP award for Block C

The Year Ahead

• September 2020 – Virtual Groundbreaking

• October 2020 – Start Block A

• November 2020 – Complete infrastructure construction

• February 2021 – Start park and garden construction

• January 2021 – Apply for bonds and tax credits for Block C

• Late 2021

- First set of residents move-in Blocks B and E

- Park & garden completion

- Start Block C construction

Page 5: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in

Neighborhood Updates

TCC funded projects

• RT station design 65% complete and Construction start (track realignment) 2021

• NeighborWoods tree location plan underway; added 566 more leverage trees

• Community Garden site plan approved by City; construction drawings 50%

• Block A housing development and Solar Installation start

• Workforce Development MOU finalized with SacRT

City projects

• Salvation Army site improvements completed

• 12th Street ‘Complete Streets’ in pre-development, new fence at overpass, sidewalk and bike lane construction 2021

• 12th Street Mural and Art project planning underway

• D Street basketball and multi-sports court in 2021

• Bus shelter, Route 11 service expansion in 2022

Page 6: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in

• Major area of focus for resident stability: economic mobility.

• Reached the 60% mark at the beginning of 2020 and the pandemic came in March.

• Why is the 60% mark important?

People Strategy –Economic Mobility

36%

48%

54%

59%60% 60%

57% 57%58%

57%

55%

30%

35%

40%

45%

50%

55%

60%

65%

2016 2017 2018 2019 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20

Employment Rate

Page 7: Mirasol Village Redevelopment Project Update Report to SHRC · 8/5/2020  · •12th Street Mural and Art project planning underway •D Street basketball and multi-sports court in

People Strategy – COVID 19 Survey Results

Basic Needs• Households with enough food to last 7 days:

• 80% March 2020 – 97% June 2020• Households with antibacterial soap or other disinfectants:

• 66% March 2020 – 87% June 2020• Households with a 2-week supply of prescriptions:

• 90% March 2020 – 100% June 2020

Households with School–Age Youth• Households with access to broadband internet at home:

• 87% March 2020 – 100% June 2020• Households with access to a computer or tablet with internet

connectivity: • 73% March 2020 – 100% June 2020

• Head of households &/or school-aged children required to do remote learning: • 26% March 2020 – 96% June 2020