Minutes of the 110th meeting of State Environment Impact Assessment Authority
held on. 2nd February, 2018 under the Chairmanship Sh. Bharat Bhushan IAS
(Retd.), Chairman, SEIAA held in the meeting room of office of SEIAA Haryana,
Sector-2 Panchkula, regarding Environmental Clearance under EIA Notification
dated 14.9.2006.
All the members are present. The project proposals as recommended by SEAC for
Environmental Clearance or otherwise and listed in the Agenda item circulated vide letter
No. 43 to 45 dated 16.01.2018 were discussed following decisions were taken:-
Item No.[1] Environmental Clearance for construction of Lalit Suri Education &
Charitable Trust, Food craft complex, Badkhal road, Faridabad,
Haryana by The Lalit Suri Education & Charitable Trust.
The case was lastly taken up in the 109th meeting of the SEIAA held on
22.12.2017 and the Authority unanimously opinion that it needs more time to study and
analyze the case, therefore it has been deferred for the next meeting.
In the today’s meeting after detailed deliberations the Authority
unanimously decided that it needs more time to study and analyse the case, therefore it
has been deferred for the next meeting.
Item No.[2] Environmental Clearance for the development of Group Housing
Colony “Rudco Golf Greens”located at Revenue Estates of Village
Palwal, Sector-7, Palwal, Haryana M/s Rurban Development
Corporation Pvt. Ltd.
The case lastly considered in the 101st meeting of SEIAA held on
22.03.2017 and the Authority decided to defer this case with the decision that Sh. G. R.
Goyat Chairman SEAC and Sh. A. K. Bhatia, Member SEAC shall visit the site for
inspection and shall submit the report on the point as indicated above within 15 days
period.
The case has been taken up in the today’s meeting and as per the site
inspection report submitted by the sub-committee dated 14.12.2017 the authority decided
to go with recommendations of SEAC to de-list this case. It was also decided that the
decision of the Authority should be conveyed to the Project Proponent and copy of the
same be forwarded to the Haryana State Pollution Control Board, DGTCP, Haryana &
R.O. MOEF, GOI for information and necessary action.
Item No.[3] Environmental Clearance for proposed Common Bio Medical Waste
Treatment Facility (CBWTF) located at Khatoni No. 157, Village
BazidaJatan, near railway crossing, Tehsil & District-Karnal, Haryana
by M/s. Haat Supreme Wastech Pvt. Ltd..
The case was lastly considered in the 106th meeting held on 07.09.2017 and
the Authority decided that the said project being the “Existing” may be exempted from
“Public Consultation/Hearing” as per the para 7(ii) dated 23rd Nov., 2016 of the MoEF
notification, 2006 subject to:
2
The above unit is already existing and operational and has obtained the
Consent to Operate from the State Pollution control Board.
The State pollution control board has not taken adverse action against the unit
on the pretext of any public complaint or not keeping the pollution under the
permissible levels in the past.
The unit will obtain “No increase in Pollution load” Certificate/permission
from the State/central pollution Control Board.
In the today’s meeting the representative of the project proponent has
submitted the letter dated 30.01.2018 issued by RO, HSPCB Yamunanagar No.
HSPCB/YMN/2018/4865 stating.
Unit is existing, operational and the accorded CTO is valid up to 30.09.2020.
HSPCB has not taken any adverse action and no complaint has been received
against the unit and unit is complying with the prescribed limits in past.
There is no increase in the pollution load and the unit has submitted the no
increase the pollution load in the prescribed format of MoEF& CC, GoI. There
is no expansion proposed by the unit in its existing capacity.
In view of the above the Authority decided to refer back this case to SEAC
for appraisal.
Item No.[4] Environmental Clearance for proposed Common Bio-Medical Waste
Treatment Facility (CBWTF) located at Khewat no 1, Khatoni no 1
kite. No 50, Tadadi No 314, village VPO Bagwala, Tehsil Barwala,
District Panchkula, Haryana by M/s Esskay Hygienic Services.
The case was lastly taken up in the 109th meeting of the SEIAA held on
22.12.2017 and the Authority decided another opportunity is given to project proponent
to appear before authority for further clarification.
In the today’s meeting the Authority observed that no communication or
representation has been received from the project proponent, therefore, authority was of
the unanimous opinion that the case may be deferred and another chance be given to the
project proponent to submit the needed documents/presentation.
Item No.[5] Environmental Clearance for proposed Common Bio-Medical Waste
Treatment Facility (CBWTF), at Plot no. 66, Roz Ka Meo Industrial
area, Sohna, Mewat, Haryana by Synergy Waste Management Pvt.
Ltd.
The case was lastly taken up in the 109th meeting of the SEIAA held on
22.12.2017 and the Authority unanimously decided that it needs more time to study the
direction issued by CPCB through its letter no. B-31011/BMW (42.25)/2017/WMD-
1/13215 dated 03.11.2017 as well as OA no. 620 of 2017 filled before Hon’ble National
Green Tribunal, therefore it has been decided to defer to the next meeting.
3
In the today’s meeting the representative of the project proponent submitted
MOEF & CC, GOI, New Delhi letter F.No. 20/1/2017-HSMD dated 05.01.2018
addressed to Member Secretary HSPCB, Panchkula under point 6.0 clearly stating that
“Guidelines issued by CPCB do not have any provisions restricting the establishment of a
new facility within the radial proximity of an existing facility”.
The project being new in nature, therefore, authority asked the PP to get the
“Public hearing (if required)” conducted as per EIA Notification dated 04.04.2016.
In view of the above the Authority decided to refer back this case to SEAC
along with the cited letter for appraisal.
Item No.[6] Environmental Clearance of expansion of Residential Plotted Colony
namely “Vatika India Next” on total land measuring 477.206 acres at
Sector-81, 82, 82A, 83, & 85, Village Sihi, Sikhopur & Sikanderpur
Badha District Gurgaon, Haryana by M/s Vatika Limited.
The case was lastly taken up in the 109th meeting of the SEIAA held on
22.12.2017 and the Authority unanimously decided that it needs more time to study the
finer points and to look deeper in the case, therefore it has been decided to defer the next
meeting.
The authority has gone through all the necessary documents pertaining to the
present case and observed that SEAC during its 161st meeting held on 29.11.2017 has
recommended the case as:
“The Committee after detailed discussion is of the unanimous view that this is a case of
violation based on report submitted by the Sub-Committee. The Committee, therefore, decided
that the case may accordingly be recommended to the SEIAA for taking action accordingly and
the Committee is of the unanimous view that this case may be referred to SEIAA for
sending it to the concerned authority for deciding the Environment Clearance case as per
latest notification dated 14.03.2017. SEIAA may take a final view in the matter”
In the today’s meeting after detailed discussions & deliberations Authority felt that
it needs more time to study the case pertaining to violations in light of the latest
notification dated 14.03.2017.
Item No.[7] Environmental Clearance for construction of warehouse (Non
Agricultural Produce) in the revenue estate of village Pathredi, Tehsil
Manesar, Dist. Gurugram, Haryana by M/s Embassy Industrial Park
Pvt. Ltd.
The case was taken up in the 109th meeting of the SEIAA held on 22.12.2017 and
the Authority decided to defer this case with the decision that the project proponent may
be asked to submit reply to the above raised observation within 15 days period.
The project proponent has submitted the reply on 16.01.2018 and the same has
been taken up in the today’s meeting.
The project proponent has submitted that the “Green area” maximally can be
extended upto 17.4% & submitted an affidavit in this regard along with the latest lay-out
plan and the “Area Statement” depicting Ground Coverage 53412.76 sqmt (54.99%),
4
Roads 12213.53 sqmt (12.58%), Parking 14586.84 sqmt (15.02%), Green area 16910.13
sqmt (17.41%) of the project area. However this is a warehouse project, where pollution
would be less in comparison of group housing project. The replies to the queries raised
earlier were found to be satisfactory.
In view of the above the Authority decided to agree with the recommendations of
SEAC to accord Environment Clearance to this project.
Item No.[8] Environmental Clearance for proposed Terms of Reference of
“Mounded Storage Vessels at Bharat Petroleum Corporation Ltd” at
Village Dhansu, District Hisar, Haryana by Bharat Petroleum
Corporation Ltd,
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the construction
of “Mounded Storage Vessels at Bharat Petroleum Corporation Ltd” at Village Dhansu,
District Hisar, Haryana on a area of existing LPG plant is 14.925 Acres and no additional
land will be used for installation of three mounded storage vessels (3x300 MT) at existing
LPG Plant. For installation of mounded vessels, existing above ground vessels will be
dismantled accordingly in phased manner after stabilization of proposed mounded
vessels. The proposed project has green belt on 33.5 % (20234.36 sqm out of 60399.57
sqm of area of the plant. The number of existing trees 325 numbers and proposed trees
925 numbers. The water required for domestic and washing of cylinders is 10 KLD. The
source of water is bore well and canal water. Fire water storage is 5100 kl fire
emergencies and ETP of 10 KLD is already in operation at the existing plant to treat the
effluent generated through washing of tested cylinders. The existing LPG Plant is Zero
discharge unit and treated waste water is used for green belt purpose. Demand of
electricity is 190 KW. At the existing LPG Plant, 55 m x 21 m (1155 sqm) area has been
earmarked for parking of tank/LPG lorries. The parking area is sufficient for 20 Trucks.
However, maximum 7 to 8 trucks are required to be parked at one point of time at
existing LPG Plant. No truck/vehicle is allowed to park out site the LPG plant on the
road. Two rain water harvesting pits of size 3.4 m x 2.3 m and 4.2 m x 4.5 m have been
provided at existing LPG Plant to recharge the ground water aquifers. Total 10 numbers
of rainwater harvesting pits will be provided at existing LPG Plant of BPCL. Before the
desilting tank of rainwater recharge pits, oil interceptor shall be provided. Necessary
safety measures including two safety relief valves at, (SRV), two independent level
indicators, a high-level switch, pressure gauge, high level alarms, remote operated valves
Deluge/water sprinkling system, automatic fire protection (fixed) system, etc have been
provided at each LPG storage vessels.
The above recommendation of SEAC was taken up for consideration in the
today’s meeting. Detailed discussions were held regarding water requirement, quality of
water, green belt development plan etc.
5
In view of the above the Authority decided to agree with the
recommendations of SEAC to accord Environment Clearance to this project.
Item No.[9] Environmental Clearance for construction of Corporate Office
Building located at Plot No. C-11 in City Center, Sector-29 at Urban
Estate-II, Gurugram-122002, Haryana by M/s Hyundai Moter India
Ltd.
The SEAC has recommended this project for Environmental Clearance subject to
stipulation stated therein. The Project Proponent has proposed the construction of
Corporate Office Building located at Plot No. C-11 in City Center, Sector-29 at Urban
Estate-II, Gurugram-122002, Haryanaon a total plot area of 7820.80 sqm (1.93 Acres).
The total built up area shall be 28334.42 sqm. The project proposed shall comprise of 4
Basements + GF + 05 Floor. The proposed project shall have Office blocks, Showrooms,
Kitchen, Employee Gymnasium etc. The maximum height of the building shall be 39.3
meter. The total water requirement shall be 104 KLD. The fresh water requirement shall
be 34 KLD. The waste water generation shall be 67.5 KLD which will be treated in the
STP of 100 KLD capacity. The total power requirement shall be 1145 KVA which will
be supplied by DHBVN. The Project Proponent has proposed to develop green belt on
1955.70 sqm (25%) of project area (506.14sqm green belt plantations + 460.06sqm Lawn
area + 894.09 sqm Avenue Plantation + 95.41 sqm Peripheral Plantation). The Project
Proponent proposed to construct 02 rain water harvesting pits. The solid waste generation
will be 405 kg/day. The bio-degradable waste will be treated in the project area by
adopting appropriate technology. The total parking spaces proposed are 289 ECS.
In the today’s meeting the recommendation of SEAC and the project details were
taken up for consideration in the presence of representative of the project proponent and
consultant. Detailed discussions were held regarding existence of revenue rasta, water
requirement, quality of water, green belt development plan, Ambient Air Quality, NOC
regarding non-involvement of Aravalli Notification dated 07.05.1992, recycle and reuse
of water, parking plan, traffic circulation etc. The representatives of the project proponent
submitted the documents showing the necessary amendment for the treatment of the
residual water in the cooling towers and have submitted the calculations for the
requirement of treated water in HVAC along with the mitigation measures needed to take
care of the ambient air.
In view of the above the Authority decided to agree with the recommendations of
SEAC to accord Environment Clearance to this project.
Item No.[10] Environmental Clearance for proposed expansion of Existing “Artemis
Hospital” at Sector-51, Gurgaon, Haryana by M/s Artemis Medicare
Services Ltd.
The SEAC was considered this case in its 162nd meeting held on 14.12.2017.
6
During discussion, it was revealed from the Site Inspection Report dated
23.08.2017 of Advisor, Northern Zonal Officer, Ministry of Environment, Forest &
Climate Change, Government of India wherein it is clearly mentioned in the conclusion
that the area proposed for expansion was under development. In the above said inspection
report there are 3 photographs which is showing construction in the proposed expansion
area. This is a clear case of violation of EIA Notification, 2006 since PP has started
construction in proposed expansion area prior to obtaining environment clearance.
In the today’s meeting after detailed deliberations the Authority was of the
unanimous opinion that it needs more time to study and analyse the case, therefore it has
been deferred for the next meeting.
Item No.[11] Environmental Clearance for the development of Industrial Estate and
CETP at I.E. Barhi, Phase-III near Gannaur, District – Sonepat,
Haryana (under Cateogory 8(b) project by HSIIDC.
The case was taken up in the 83rd meeting held on 28.09.2015 and it was
observed that the project proponent has failed to submit the permission for withdrawal of
Ground water and the Authority decided to refer back this case to SEAC with the advice
to re-appraise the project proposal in terms of deficiencies pointed out above and send its
recommendations within stipulated period as prescribed in the Notification.
In the today’s meeting it was found that the PP has submitted the
permission for withdrawal of Ground water from CGWA.
In view of the above the Authority decided to agree with the
recommendations of SEAC to accord Environment Clearance to this project.
Item No.[12] Environmental Clearance for expansion of “Commercial Complex” at
Village Badshahpur, Sector-66, Gurgaon, Haryana by M/s Emaar
MGF Land Limited,
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the expansion of
“Commercial Complex” at Village Badshahpur, Sector-66, Gurgaon, Haryanaon a total
plot area of 9105.464 sqm (2.25 Acres). The total built up area shall be 41007.6 sqm
(existing 36439.033 sqm + expansion 4568.567 sqm). The project proposed shall
comprise of 1 Tower 4 Basement G + 18 Floors, Retail shops. The proposed project shall
have 153 Service apartment room (keys). The maximum height of the building shall be
83.55 meter. The total water requirement shall be 170 KLD. The fresh water requirement
shall be 102 KLD. The waste water generation shall be 106 KLD which will be treated in
the STP of 130 KLD capacity. The total power requirement shall be 3277.9 KW which
will be supplied by DHBVN. The Project Proponent has proposed to develop green belt
on 1859.84 sqm (25.50%) of project area (658.11 sqm Green Belt Plantations + 886.1
sqm Lawn + 201.22 sqm Peripheral Plantation + 109.72 sqm Avenue Plantation). The
Project Proponent proposed to construct 03 rain water harvesting pits. The solid waste
7
generation will be 546 kg/day. The bio-degradable waste will be treated in the project
area by adopting appropriate technology. The total parking spaces proposed are 408 ECS.
The above recommendation of SEAC was taken up for consideration in the
today’s meeting. Detailed discussions were held regarding water requirement, quality of
water, green belt development plan, Ambient Air Quality, NOC regarding non-
involvement of Forest land, recycle and reuse of water, parking plan, traffic circulation
etc.
It was observed by the Authority that:
[1] Volume of water (given), volume of every recharge pit (given), on the basis of
these two numbers of pit has been calculated. But how much should be the
diameter of bore meant for recharging?
Water Balance chart
[2] 10 KLD fresh water for pool; the water required is for replenishment. Evaporation
losses depend upon the surface area of pool and cannot be 10,000lts/day.
[3] Please explain the process of Filter back-wash requiring 5000 lts that too on daily
basis.
[4] Water is very scarce resource, one should implement the best practices &
technologies available to conserve it. 500 KVA DG sets can be air cooled & water
requirement for HVAC can be reduced also. Secondly, provide the schematic plan
to treat the residual water present in cooling-tower circuit & how to handle/dispose
off the rejects?
Form 1-A
[5] Provide the assumed energy consumption per square foot of built-up area under pt.
9.1.
[6] Provide the required details under pt. 9.5 & 9.9 and specifications under pt. 9.7 as
asked.
In view of the above discussions the Authority decided to defer this case
with the decision that the project proponent may be asked to submit reply to the above
raised observation within 15 days period.
Item No.[13] Environmental Clearance for proposed POL Depot at Village-
BirHisar, Disttrict- Hisar, Haryana by M/s Bharat Petroleum
corporation Limited.
The SEAC has recommended this project for approval of TOR subject to
stipulation stated therein. The Project Proponent has proposed POL Depot at Village-
BirHisar, Disttrict- Hisar, Haryana.
In the today’s meeting the SEIAA approved the “Terms of Reference” and
it was decided that the project proponent will prepare the EIA by using Model Terms of
Reference of MoEF& CC along with the following additional terms of reference:
Specific condition:
8
1. The PP should submit the NOC from Airport Authority of India.
2. The PP should submit the permission of District Magistrate.
3. The PP should submit the nearest distance from the water bodies.
4. The PP should submit the report of ground water quality and monitoring.
5. The PP should submit the safety standard proposal as per OISD Standard 244.
6. The PP should submit the traffic circulation study alongwith mitigation measures.
7. The PP should submit permission from Forest Department .
8. The PP should submit permission from Wildlife.
9. The PP should submit the CLU.
10. The PP should conduct public hearing.
11. The PP should submit the resolution of Panchayat.
12. The PP should submit the NOC of Petroleum and Explosive Safety Organisation
(PESO).
Item No.[14] Environmental Clearance for “Expansion cum Modification” of I.T.
Park project located at Village-Ghatta, Sector-61, Gurugram,
Haryanaby M/s Active Promoters Pvt. Ltd.
The SEAC has recommended this project for approval of TOR subject to
stipulation stated therein. The Project Proponent has proposed “Expansion cum
Modification” of I.T. Park project located at Village-Ghatta, Sector-61,
Gurugram,Haryana.
In the today’s meeting the SEIAA approved the “Terms of Reference” and
it was decided that the project proponent will prepare the EIA by using Model Terms of
Reference of MoEF& CC along with the following additional terms of reference:
Specific condition:
1. The PP should submit the NOC from the Deputy Commissioner concerned for Aravali.
2. The PP should submit the 3 Months study report i.e. November, December & January.
3. The PP should submit the contour plan and the bandh level.
4. The PP should submit the ground water level and quantity monitoring around 5 KM
radius of the site.
5. The PP should conduct public hearing.
Item No.[15] Environmental Clearance for construction of “Affordable Group
Housing scheme” at Sector-67-A, Gurugram, Haryana by M/s Shri
Colonizers & Developer Pvt. Ltd.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the construction
of “Affordale Group Housing scheme” at Sector-67-A, Gurugram, Haryana on a total plot
area of 39785.69 sqm (9.83125 Acres). The total built up area shall be 92549.791 sqm.
The project proposed shall comprise of Group Housing, Commercial, Community Centre
and Anganwari. The proposed project shall have 1330 Dwelling Unit. The maximum
9
height of the building shall be 47.96 meter. The total water requirement shall be 617
KLD. The fresh water requirement shall be 439 KLD. The waste water generation shall
be 499 KLD which will be treated in the STP of 610 KLD capacity. The total power
requirement shall be 7000 KW which will be supplied by DHBVN. The Project
Proponent has proposed to develop green belt on 8567.669 sqm (22.97%) of project area
(1698.762sqm Green belt Plantation + 2874.387sqm Avenue plantation + 775.005 sqm
Peripheral Green area + 3219.515 sqm Lawn area). The Project Proponent proposed to
construct 10 rain water harvesting pits. The solid waste generation will be 3213 kg/day.
The bio-degradable waste will be treated in the project area by adopting appropriate
technology. The total parking spaces proposed are 672 ECS Car parking and 658 no. of
two wheeler parking.
In the today’s meeting the recommendation of SEAC and the project details
were taken up for consideration in the presence of representative of the project proponent
and consultant. Detailed discussions were held regarding existence of revenue rasta,
water requirement, quality of water, green belt development plan, Ambient Air Quality,
NOC regarding non-involvement of Aravalli Notification dated 07.05.1992, recycle and
reuse of water, parking plan, traffic circulation etc.
In view of the above the Authority decided to agree with the
recommendations of SEAC to accord Environment Clearance to this project.
Item No.[16] Environmental Clearance for proposed Affordable Group Housing
Colony on an area measuring 5.08339 acres at Village Taraf Insar &
Rajputan, Sector 1-A, Panipat, Haryanaby M/s Emperium Realty Pvt.
Ltd.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the construction
of Affordable Group Housing Colony on an area measuring 5.08339 acres at Village
Taraf Insar & Rajputan, Sector 1-A, Panipat, Haryana on a total plot area of 20571.717
sqm (5.08339 Acres). The total built up area shall be 48558.497 sqm. The project
proposed shall comprise of 7 Towers + GF + 13 Floor, Aaganwadi cum Creche,
Community hall, Balconies. The maximum height of the building shall be 49.15 meter.
The total water requirement shall be 368 KLD. The fresh water requirement shall be 255
KLD. The waste water generation shall be 294 KLD which will be treated in the STP of
355 KLD capacity. The total power requirement shall be 5424 KW which will be
supplied by UHBVN. The Project Proponent has proposed to develop green belt on
4240.865 sqm (20.615%) of project area (114.024sqm Green belt plantation +
3242.906sqm Lawn area + 863.935 sqm Peripheral Plantation). The Project Proponent
proposed to construct 05 rain water harvesting pits. The solid waste generation will be
1826 kg/day. The bio-degradable waste will be treated in the project area by adopting
appropriate technology. The total parking spaces proposed are 383 ECS.
10
In the today’s meeting the recommendation of SEAC and the project details
were taken up for consideration in the presence of representative of the project proponent
and consultant. Detailed discussions were held regarding existence of revenue rasta,
water requirement, quality of water, green belt development plan, Ambient Air Quality,
NOC regarding non-involvement of Aravalli Notification dated 07.05.1992, recycle and
reuse of water, parking plan, traffic circulation etc. The Authority asked the project
proponent to elaborate point 9.1, 9.5, 9.6 and 9.13 and the project proponent submitted all
the necessary details under the asked points of Form-1A.
In view of the above the Authority decided to agree with the
recommendations of SEAC to accord Environment Clearance to this project.
Item No.[17] Environmental Clearance expansion of Affordable Group Housing
Colony in the revenue estate of village Budena, Sector-86, Faridabad,
Haryana by M/s Adore Realtech Pvt. Ltd.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the Expansion of
Affordable Group Housing Colony in the revenue estate of village Budena, Sector-86,
Faridabad, Haryana on a total plot area of 36927.51 sqm (9.125 Acres) (existing
20234.60 sqmt + Expansion 16692.91 sqm). The total built up area shall be 107441.94
sqm (Existing 50219.52 sqm + Expansion 57222.42 sqm). The project proposed shall
comprise of Basement + 20 Residential Towers (T1-T20) S + Maximum 14 Floors,
Aanganwaadi&Creche area, Community hall and Commercial block. The proposed
project shall have 1335 Dwelling Units. The maximum height of the building shall be
44.98 meter. The total water requirement shall be 965 KLD. The fresh water requirement
shall be 605 KLD. The waste water generation shall be 793 KLD which will be treated in
the STP of 1100 KLD capacity. The total power requirement shall be 6803.26 KVA
which will be supplied by DHBVN. The Project Proponent has proposed to develop
green belt on 7379.998 sqm (20%) of project area (1419.89sqm Peripheral Area + 5960.1
sqm Lawn area). The Project Proponent proposed to construct 12 rain water harvesting
pits. The solid waste generation will be 3451.19 kg/day. The bio-degradable waste will be
treated in the project area by adopting appropriate technology. The total parking spaces
proposed are 670 ECS and 1335 ESS for Two wheeler.
The above recommendation of SEAC was taken up for consideration in the
today’s meeting. Detailed discussions were held regarding water requirement, quality of
water, green belt development plan, Ambient Air Quality, NOC regarding non-
involvement of Forest land, recycle and reuse of water, parking plan, traffic circulation
etc. It was observed by the Authority that:
Water balance Diagram
[1] Presentation shows Water Consumption 135 LPCD & Form1A shows 86 lpcd;
why does anomaly exist?
11
[2] Pg. no.38; Base line concentration value for PM10& PM2.5 is 302.6 & 125.2 µg/m3
respectively & incremental concentration value 2.2 µg/m3 in both cases. The
values are very much on higher side. Suggest the mitigation measures.
[3] Reply & provide details as asked & required under pt. 8.1/9.3/9.7/9.9
[4] Reproducing the comments given in review w.r. to MoEF’s letter dtd. 30.05.12 in
the site visit report dtd. 22/12/17
[5] “It is evident from the above review that: CTE has been obtained which is valid
upto 1.03.2021. majority of conditions of construction phase was compiled
whereas a few such as RWH pits, green belt, facilities for composting, green
development, piezometers* for ground quality monitoring , approval of structural
safety etc., needs sincere efforts. Further, living conditions of the labor camp
require improvement.”
[6] Has PP obtained permission from CGWB for drawing ground-water through
bore-well?
In view of the above, the Authority decided to agree with the
recommendations of SEAC and EC would be accorded to project proponent provided
they submits the satisfactory clarification to the above raised observations within 15 days.
It was also decided that the project proponent shall supply the copies of information to all
the members of SEIAA and after their approval the EC letter shall be issued.
Item No.[18] Environmental Clearance for proposed Affordable Housing Project at
Sector-75, Faridabad, Haryana by M/s Iris Plaza Pvt. Ltd.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the construction
of Affordable Group Housing Colony in the revenue estate of village Budena, Sector-86,
Faridabad, Haryana on a total plot area of 24129.381 sqm. The total built up area shall be
52466.65 sqm. The project proposed shall comprise of Commercial/Convenient shopping
(Staff), Aaganwadi cum Creche, Community hall, Mumty& Machine room, Podium. The
proposed project shall have 765 Dwelling Units. The maximum height of the building
shall be 44.6 meter. The total water requirement shall be 374 KLD. The fresh water
requirement shall be 256 KLD. The waste water generation shall be 307 KLD which will
be treated in the STP of 355 KLD capacity. The total power requirement shall be 3341
KW which will be supplied by DHBVN. The Project Proponent has proposed to develop
green belt on 4769.510 sqm (22%) of project area (687.85 sqm Green belt plantations +
2923.71 sqm Lawn area + 1157.95 sqm Peripheral Plantation). The Project Proponent
proposed to construct 05 rain water harvesting pits. The solid waste generation will be
2029 kg/day. The bio-degradable waste will be treated in the project area by adopting
appropriate technology. The total parking spaces proposed are 394 ECS or 765 Scooter.
12
In the today’s meeting the recommendation of SEAC and the project details
were taken up for consideration in the presence of representative of the project proponent
and consultant. Detailed discussions were held regarding existence of revenue rasta,
water requirement, quality of water, green belt development plan, Ambient Air Quality,
NOC regarding non-involvement of forest land, recycle and reuse of water, parking plan,
traffic circulation etc. The Authority asked the project proponent to submitt the
documents along with the revised water balance diagram and made the necessary
amendments under point 9.1, 9.13 of form-1A. The representative of the project
proponent submitted the same.
In view of the above the Authority decided to agree with the
recommendations of SEAC to accord Environment Clearance to this project.
Item No.[19] Environmental Clearance for Commercial Colony located at Village-
Dhankot, Sector-102, Gurugram, Haryanaby M/s Aristocrate Home
Developers Pvt. Ltd.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the construction
of Commercial Colony located at Village-Dhankot, Sector-102, Gurugram, Haryanaon a
total plot area of 8093.70 sqm (2 Acres). The total built up area shall be 33775.046 sqm.
The project proposed shall comprise of 4 Basements + UGF + 4 Floor, Retails/shops,
Restaurant/Food court and Multiplex. The maximum height of the building shall be 28.90
meter. The total water requirement shall be 162 KLD. The fresh water requirement shall
be 64 KLD. The waste water generation shall be 94 KLD which will be treated in the
STP of 115 KLD capacity. The total power requirement shall be 2055 KW which will be
supplied by DHBVN. The Project Proponent has proposed to develop green belt on
2165.985 sqm (26.76%) of project area (1285.602 sqm Avenue plantations + 880.383
sqm Peripheral Plantation). The Project Proponent proposed to construct 02 rain water
harvesting pits. The solid waste generation will be 974 kg/day. The bio-degradable waste
will be treated in the project area by adopting appropriate technology. The total parking
spaces proposed are 374 ECS.
The above recommendation of SEAC was taken up for consideration in the
today’s meeting. Detailed discussions were held regarding water requirement, quality of
water, green belt development plan, Ambient Air Quality, NOC regarding non-
involvement of Forest land, NOC from the Deputy Commissioner concerned for Aravali,
recycle and reuse of water, parking plan, traffic circulation etc. It was observed by the
Authority that:
Water Balance Chart
13
[1] Water is a very scarce resource; one should be very judicious in consuming. The
proposed installed capacity of DG sets can be Oil/Air Cooled instead of Water-
cooled to serve the purpose of Water Conservation.
[2] Water in “Cooling tower Circuit” whether of DG sets or of HVAC would not be
completely evaporated or utilized in cooling, the water remaining in the circuit
would be having higher concentration of salts etc. How this water will be treated
& how the rejects would be handled? Submit the schematic diagram
Form 1-A
[3] Pt 5.1; provide details of background air quality levels with predicted values based
on dispersion models taking into account the increased traffic generation as a
result of construction.
[4] Pt.5.4; Provide details of the movement patterns of internal roads, bicycle tracks,
pedestrian pathways, footpaths etc. with areas under each category
[5] Provide the assumed energy consumption per square foot of built-up area under pt.
9.1.
[6] Provide the required details under pt. 9.5, Have you considered the use of street
lighting, emergency lighting and solar hot water systems for use in the building
complexes? Substantiate with details.
[7] Provide the details of transformers & motor efficiencies, lightening intensity & air
conditioning load assumption. Provide the technical details as asked under pt. 9.7
[8] Provide the required details “To what extent the non-conventional energy
technologies are utilized in the overall energy consumption?” under pt. 9.13.
In view of the above, the Authority decided to agree with the
recommendations of SEAC and EC would be accorded to project proponent provided
they submits the satisfactory clarification to the above raised observations within 15 days.
It was also decided that the project proponent shall supply the copies of information to all
the members of SEIAA and after their approval the EC letter shall be issued.
Item No.[20] Environmental Clearance for Expansion of project Residential Plotted
Colony cum Group Housing project “RahejaAranya” area measuring
165.5375 acres located at Sector-11 & 14, Village Sohna& Raipur,
District Gurgaon, Haryana by M/s Raheja Developers Ltd.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the Expansion of
project “Residential Plotted Colony” located at Sector-11 & 14, Village Sohna& Raipur,
District Gurgaon, Haryana on a total plot area of 669876.14 sqm. The total built up area
shall be 254526.299 sqm. The project proposed shall comprise of Nursery School,
Primary School, High School, Creche, Dispensary, Religious Building, Community
Centre, Taxi-stand, Nursing Home, ATM, Clinic, Beauty parlor, Multipurpose Booth,
sub-post office, Milk & Veg. booth. The maximum height of the building shall be 150
14
meter. The total water requirement shall be 2692 KLD. The fresh water requirement shall
be 1437 KLD. The waste water generation shall be 1500 KLD which will be treated in
the STP of 1986 KLD capacity. The total power requirement shall be 17.3 MW which
will be supplied by DHBVN. The Project Proponent has proposed to develop green belt
on 194117 sqm (32%) of project area (37813.172 sqm Avenue Plantations + 57109.160
sqm Green Belt + 16662 sqm Peripheral Plantation + 82533.948 sqm Lawn area). The
Project Proponent proposed to construct 100 rain water harvesting pits. The solid waste
generation will be 11433.5 kg/day. The bio-degradable waste will be treated in the
project area by adopting appropriate technology. The total parking spaces proposed are
1229 ECS.
The above recommendation of SEAC was taken up for consideration in the
today’s meeting. Detailed discussions were held regarding water requirement, quality of
water, green belt development plan, Ambient Air Quality, NOC regarding non-
involvement of Forest land, recycle and reuse of water, parking plan, traffic circulation
etc. It was observed by the Authority that the proposal is for the expansion of project and
while going through the documents lots many ambiguities have been found and the six
monthly compliance report of MoEF& CC, GoI states that many of the conditions of EC
has not been complied for in the existing project.
After detailed deliberations, the Authority unanimously opinion that it
needs more time to study and analyze the case, therefore it has been deferred for the next
meeting.
Item No.[21] Environmental Clearance for Warehousing & Transport Hub (243.89
Acres) in Village Babra-Bakipur, PatliHazipur, Tehsil Farrukhnagar
and VillDhana, Tehsil Gurgian in Industrial Model Township (IMT) of
Manesar, Gurgaon, Haryana by HSIIDC, Industrial Estate, C 13-14,
Sector-6, Panchkula.
The SEAC has recommended this project for Environmental Clearance
subject to stipulation stated therein. The Project Proponent has proposed the Warehousing
& Transport Hub (243.89 Acres) in Village Babra-Bakipur, PatliHazipur, Tehsil
Farrukhnagar and VillDhana, Tehsil Gurgian in Industrial Model Township (IMT) of
Manesar, Gurgaon, Haryana on a total plot area of 986987.81 sqm (243.89 Acres). The
total built up area shall be 740240.865 sqm. The project proposed shall comprise of
Nursery School, Primary School, High School, Creche, Dispensary, Religious Building,
Community Centre, Taxi-stand, Nursing Home, ATM, Clinic, Beauty parlor,
Multipurpose Booth, sub-post office, Milk & Veg. booth. The maximum height of the
building shall be 150 meter. The total water requirement shall be 2658 KLD. The fresh
water requirement shall be 1315 KLD. The waste water generation shall be 1334 KLD
which will be treated in the STP of 1986 KLD capacity. The total power requirement
shall be 22 MVA which will be supplied by DHBVN. The Project Proponent has
15
proposed to develop green belt on 296477 sqm (30.04%) of project area (62128 sqm
Avenue Plantations + 43748 sqm Green Belt + 164332 sqm Lawn area + 26269 sqm
Peripheral Plantation). The Project Proponent proposed to construct 154 rain water
harvesting pits. The solid waste generation will be 20738.02 kg/day. The bio-degradable
waste will be treated in the project area by adopting appropriate technology. The total
parking spaces proposed are 105906.23 sqm.
The above recommendation of SEAC was taken up for consideration in the
today’s meeting. Detailed discussions were held regarding water requirement, quality of
water, green belt development plan, Ambient Air Quality, NOC regarding non-
involvement of Forest land, NOC from the Deputy Commissioner concerned for Aravali,
recycle and reuse of water, parking plan, traffic circulation etc.
In view of the above the Authority decided to agree with the
recommendations of SEAC to accord Environment Clearance to this project.
*********