PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE GOVT. OF INDIA Indira Paryavaran Bhavan, JorBagh Road New Delhi 110003 KARIVANE BAUXITE MINE Village- Karivane Tehsil- Shriwardhan , Dist- Raigad, State- Maharashtra Applied area in Block No.01:-In Survey Nos. 58, 61 TO 66, AREA:-51.15 Ha and Block No.2:- In Survey Nos. 50, 51, 52 & 53, AREA:- 26.22 Ha Total Area:- 77.37 Ha Private Non Forest and Revenue Waste Land (Proposed Production Capacity of Bauxite Ore : 1,15,000 TPA) PROJECT PROPONENT M/S ALATGE STONE CRUSHING INDUSTRIES H. No. 148, Near Madasra, At- Arathi, Post & Taluka- Shriwardhan, Dist. Raigad. Maharashtra EIA CONSULTANT SRUSHTI SEVA PRIVATE LTD. NABET Accreditated EIA Consultant Certificate No NABET/EIA/1518/RA027 Valid upto 02.12.2018 May 2017

Upload: others

Post on 18-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

PRE FEASIBILITY REPORT

Submitted to

MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE GOVT. OF INDIA

Indira Paryavaran Bhavan, JorBagh Road New Delhi 110003

KARIVANE BAUXITE MINE

Village- Karivane Tehsil- Shriwardhan , Dist- Raigad, State- Maharashtra

Applied area in

Block No.01:-In Survey Nos. 58, 61 TO 66, AREA:-51.15 Ha and

Block No.2:- In Survey Nos. 50, 51, 52 & 53, AREA:- 26.22 Ha Total Area:- 77.37 Ha

Private Non Forest and Revenue Waste Land

(Proposed Production Capacity of Bauxite Ore : 1,15,000 TPA)

PROJECT PROPONENT

M/S ALATGE STONE CRUSHING INDUSTRIES H. No. 148, Near Madasra, At- Arathi, Post & Taluka- Shriwardhan,

Dist. Raigad. Maharashtra

EIA CONSULTANT

SRUSHTI SEVA PRIVATE LTD. NABET Accreditated EIA Consultant

Certificate No NABET/EIA/1518/RA027 Valid upto 02.12.2018

May 2017

Page 2: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

i

TABLE OF CONTENTS

1. EXECUTIVE SUMMARY 1-2

2. INTRODUCTION OF THE PROJECT 3

i Identification of project & project proponent

ii Brief description of nature of the project

iii Need for the project

iv Employment generation (direct & indirect)

3. PROJECT DESCRIPTION 4-9

i Type of project

ii Location

iii Alternate site

iv Size of magnitude of operation

v Project description

vi Raw materials sources & transportation

vii Resource recycling.

viii Water requirement & supply

ix Waste generation and waste management

4. SITE ANALYSIS 10-11

i Connectivity

ii Proposed plant land detail

iii Topography

iv Existing infrastructure

v Soil classification

vi Climate

vii Social infrastructure

Page 3: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

ii

5. PLANNING BRIEF 12

i Planning concept

ii Population projection

iii Land use planning

iv Infrastructure demand

v Amenities

6. PROPOSED INFRASTRUCTURE 13

i Industrial area

ii Residential area

iii Green belt

iv Social infrastructure

v Connectivity

vi Drinking water

vii Sewerage system

viii Industrial waste management

ix Solid waste management

x Power requirement & supply

7. REHABILITATION AND RESETTLEMENT (R&R PLAN)

14

8. PROJECT SCHEDULE & COST ESTIMATES 14

9. ANALYSIS OF PROPOSAL FINAL RECOMMENDATIONS 15

ANNEXURE

I MINE BOUNDARY PILLAR LOCATION STATEMENT 16

II ENVIRONMENT MANAGEMENT PLAN 17-18

III ESTIMATED PROJECT CAPITAL COST & PRODUCTION COST 19-20

MAPS

1 CADASTRAL MAP 21

2 SURFACE PLAN 22

3 KEY PLAN 23

Page 4: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

1

1. EXECUTIVE SUMMARY

M/S Alatge Stone Crushing Industries has got grant for Mining Lease vide Letter

No. MMN/1098/42461/75102/Desk-4 dated 03/06/2000 over an area of 77.37

Ha in Karivane Village, Shriwardhan Taluka of Raigad District of Maharashtra

State to mine the Bauxite.

M/S Alatge Stone Crushing Industries the project proponent is a Partnership

firm having registered office in Raigad District.

The Karivane Deposit is located towards ESE of Shriwardhan town of Raigad

District of Maharashtra State. The bauxite zone is usually occurs sandwiched

between the overlying Laterite and underlying Basalt. Bauxite in the area occurs

in the forms of small pockets, thin lenses and tabular bodies in the Laterite

capping.

The geological reserves established in the proposed Mining Lease Area is 5,65,242

tonnes and the extractable reserves of Bauxite are 5,35,904 tonnes.

The area has been earlier explored on a Regional Scale by the Geological Survey of

India and Directorate of Geology and Mining, Government of Maharashtra, Nagpur

during the year 1970-71 and 1972-73, it is seen from the analysis results that

Bauxite from the area is quite suitable for alumina and alumina metal.

It is proposed to extract Bauxite with the annual production capacity of 1,15,000

tonnes/annum.

The proposed method of mining is Opencast fully Mechanized mine with drilling

and blasting.

The Life of the Mine anticipated to be five years. However during proposed

exploration the reserves are likely to increase and as subsequently life of the mine

will be enhanced.

Average depth of the Pits will be 8 to 10 Meters; hence two benches of 4 to 5

meters will be formed for safety factor. Bench will have a slope of 650angle.

Access road will be developed to the Pit area.

The Overburden is in the form of intercalated clay which is considered as 20 % of

the Total ROM handling. The intercalated waste will be concurrently filled in the

mined out area.

Page 5: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

2

Total Lease area is 77.37 Ha, of which 50.19 Ha areas is mineable during the

Conceptual Period. And rest area is proposed under the safety barrier of Road,

Electric line, nallas, Green Belts are approximately 25.43 Ha.

The transport from mine head to the consumer is through hired tippers / trucks /

by road.

The minimum depth of water table is 25 m bgl. Maximum depth of the working is

10mts hence ground water will not be intercepted.

There is no possibility for encountering any ground water source during the plan

period thus no pumping is required.

The Savitri river is flowing 1.5 Km at the South of the Lease area. The dendritic to

sub dendritic drainage Pattern is commonly observed in the study area.

The climate of the area is categorized as tropical monsoon. Typical coastal climate

is experienced in the area . The monsoon prevails from June to September and

the average Rainfall varies from 2500 to 3000 mm. The seasonal variation of

temperature and moisture prevailing in the area is mainly responsible for the

process of Bauxitization/Lateritization.

The study area consisting of 77.37 Ha mining lease as core zone and 10 Km

radius around core zone is identified as buffer zone.

Bauxite produced from mine will be crushed and screened to give 0-100 mm

size. After suitable blending the same will be sold.

Man power requirement will be 110 Nos for Statutory Purposes, Supervisory

requirement and also required for loading, hauling, drilling and blasting

operations.

The Environment Impact Assessment and Environment Management Plan for

the proposed project shall be prepared as per the guidelines provided in the EIA

Notification 2006.

The power requirement will be met from MSEB grid. The quantity of water

required for mining in this mine is 80 m3/day. Water will be purchased from

nearby villages with prior consent & permission of the owner.

There is no National Park, Wildlife Sanctuary, Archeological site, Historical

places located within 10 Km from the proposed mine.

The total project cost for the Karivane Bauxite Mining Project has been

estimated at Rs. 3.9 Crores.

Page 6: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

3

2. INTRODUCTION OF THE PROJECT / BACKGROUND FORMATION

i) Identification of Project and Project Proponent

The proposal under consideration is for Karivane Bauxite Mine 77.37 Ha

situated in Private land at-Village: Karivane, Tahsil-_Shriwardhan, Dist: Raigad,

Maharashtra for the production of 1,15,000 Tonnes /Annum of Bauxite ore.

The proposed project is categorized as 'A' under EIA notification 2006.

Address of Project Proponent is as under:

M/S ALATGE STONE CRUSHING INDUSTRIES

H. No. 148, Near Madasra,

At-Arathi, Post &Taluka- Shriwardhan,

Dist. Raigad.

Maharashtra

ii) Brief description of nature of the project

The area falls under Raigad District of Maharashtra State at Karivane , Tahsil-

Shriwardhan indicated as potential source of Bauxite ore Deposit.

iii) Need for the project and it’s important to the country and or region.

Maharashtra is one of the major producers of bauxite in the country. Bauxite is

found at few places near the coast at village Moolvelas, Kurvade, Danda, Khujare,

Saigaon, Harvit, udgaon, etc. of Tal. Shriwardhan, Dist. Raigad. The bauxite

mined out will be consumed by Aluminum and Calcined alumina producing

industries.

iv) Employment Generation (Direct and Indirect) due to the project.

The mine will directly employ about 110 workers. There will be employment

generation of double this number in secondary and tertiary sectors. It is

proposed to employ the local population wherever possible in the proposed

project activities.

Page 7: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

4

3. PROJECT DESCRIPTION

i) Type of project including interlinked and Interdependent project, if any.

The proposed Karivane Bauxite Mine (77.37Ha.) will be developed by opencast

fully mechanized mine (1,15,000 TPA). There is no interlinked project.

ii) Location (map showing general location, specific location, and project

boundary & project site layout) with coordinates.

Figure 1 gives the general and specific location of Karivane Bauxite Mine. The

nearest railway station is at Mangaon which is at a distance of 86 Kms. The

Lease area is located in jurisdiction of Village Karivane in District Raigad

(Maharashtra). The area can be approached from district headquarters, Alibag

to Wadkhal Naka which is 22 Km. From wadkhal Naka to Mumbai Goa National

Highway up Mangaon and the distance is 44km. From Mangaon there is

diversion towards Shriwardhan Tahsil which is 45 Km and connected by tar

Road.

iii) Details of alternate sites considered and the basis of selecting the proposed

site, particularly the environmental consideration gone into should be

highlighted.

Mining is a site specific and has to be undertaken at the place of the occurrence of

the mineral and hence no alternative sites explored.

iv) Size or magnitude of operation.

The proposed mining Lease Area is 77.37 Ha with proposed production capacity

of Bauxite Ore 1,15,000 TPA.

Page 8: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

5

Figure 1. Location Map

Latitude: 18°0'49.17.9"

Longitude: 73°6'8.8.78"

Toposheet: 47F/4 &G/1

Near Village- Karivane

Taluka- Shriwardhan

District- Raigad, Maharashtra

The area is covered under Toposheet No 47F/4 &G/1 on 1:50,000 scale

Survey No. Lease Area Ha. Ownership/ Occupancy

58, 61, 62, 63, 64, 65, 66, 50,

51, 52, 53

77.37 Ha Private Land

The cadastral plan and surface plan of the mining lease are given in Map 1 and

Map 2 respectively.

The coordinates of the boundary are given in Annexure I.

Location of Mine

Page 9: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

6

v) Project description with process details (a schematic diagram/ flow chart showing the project layout, components of the project etc. should be given).

The Karivane Deposit is located towards ESE of Shriwardhan town of Raigad

District of Maharashtra State. The bauxite zone is usually occurs sandwiched

between the overlying Laterite and underlying Basalt. Bauxite in the area occurs

in the forms of small pockets, thin lenses and tabular bodies in the Laterite

capping.

Sequences of lava flows capped by Laterite constitute the geological formation in

the area. Laterite capping contains Bauxite zones with lithomarge Clays at the

base of the Laterite profile. The Deccan Traps which are almost horizontal, are

generally massive and compact. Enrichment of Bauxite is conspicuous but it is

very erratic and irregular. bauxite occurs in-situ under Laterite capping in the

forms of Pockets, thin lenses and as a float Ore on the Slopes of the plateau.

Bauxite occurs both as insitu under the laterite Capping and as a Float Ore on the

Slopes of the Plateau. Bauxite deposit occurs as Pockets, irregular masses, thin

lenses and tabular bodies in the Laterite Capping and is not confined to

continuous horizons. The mode of occurrence of the deposit is generally reflected

in the Scarp Section.

The above generalized profile is not visible in any slope sections. Bauxite also

occurs in the form of Float ore at the base of the Scarp-Sections and one the slopes

of the Plateau. The bauxite deposits in the area occur in the form of Blanket type

in the ferruginous or aluminous laterite. Thickness of bauxite ore is varying and

ranging from 3 to 4 m. The deposit is extending from eastern end to western end

in the form of blanket type and in Places it is having large voids. It is observed that

very often an impressive thickness of Bauxite dwindles to almost nothing within

short distances, converse by Outcrops which to be minor thickness may develop

into thick and massive lenticles of Bauxite.

Reserves :

Reserves Tonnes

Mineable Category 5,35,904

Blocked out Category 29,338

Total 5,65,242

Mining Method: The mining method identified as fully opencast mechanized.

Page 10: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

7

The Proposed Production Programme: The summary of development work and

production of Bauxite ore during 5 years period is—

Year Ore Volume

(m3)

ROM (Tonnes)

Saleable Ore in

(Tonnes)

Inter- calated waste

(Tonnes)

Ore to waste ratio

1st 46846 93692 75000 18692 1:0.25 2nd 71875 143749 114999 28750 1:0.25 3rd 71915 143830 115000 28830 1:0.25 4th 71873 143746 115000 28746 1:0.25 5 th 72422 144844 115000 29844 1:026

Source: Mining Plan

Dump re-handling (for the purpose of recovery of mineral):

It is proposed to handle about 1,43,700 tonnes of ROM every year. The excavated

land will be back-filled concurrently with about 20% Intercalated waste, to

convert waste land into cultivable agricultural land. The waste generated will be

backfilled in the worked out pits concurrently.

Conceptual plan: The mining operation by means of opencast fully mechanized

method will be continued till conceptual period.

Conceptual Mine Development: As the area is not been explored completely, on

the basis of an evaluation of various parameters, such as the distribution and

nature of occurrence of bauxite deposit, structural features, topography, pit

design, geo-hydrological conditions, etc, and ultimate Pit limit has been

tentatively delineate for the exposures in the applied area. However, after the

completion of the proposed Exploration, the Reserves will be re estimated and

accordingly conceptual Plan will be modified.

The lease area is divided in two blocks. Both blocks are having the Public Road

and nallas. Thus a safety barrier of 50 meter will be maintained along the Public

road, nallas. A Green belt of 7.5 enter all along the periphery of the lease is to be

mention as the part of statutory requirement.

At the end of the lease period of the mine an area of 50.19 Ha and average 6-10

mts depth will be formed. This will be reclaimed concurrently by year-wise

refilling to convert waste land into plantation area. The entire worked out pit will

be reclaimed by plantations. Total Lease area is 77.37 Ha, of which 50.19Ha areas

is mineable during the Conceptual Period and rest area is under the safety barrier

Page 11: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

8

of road, electric line, green belt will be approximately 25.43 Ha. The Pits will be of

rectangular in Shape and systematic mining will be done to exhaust the mineral

reserve.

Waste Generation and Management: Intercalated waste of about 1,34,862

tonnes will be generated during five year proposal. The excavated land will be

refilled by intercalated waste which will be later on convert into cultivable land.

Processing: Bauxite produced from mine will be crushed and screened to give0-

100m size. After suitable blending, the same will be sold in the market.

Marketing /End Use: Bauxite available in the area is acceptable to Aluminium

manufacturing , calcined alumina industries. Lower grade bauxite will be used for

blending and for cement industries also.

Mine Drainage: There are three seasonal nallahs passing through the mining lease

area (Block 01) (Map 2). As reported earlier the mining operations are not likely to

intersect ground water table which is lying at 25 m bgl and mining operation will

be confined to 10m from the surface. Rain water accumulated in the pit during

monsoon will be naturally reused for dust suppression & plantation.

vi) Raw material along with estimated quantity, likely source marketing. area of

final products, mode of transport of raw material and Finished product.

The dressed saleable ore will be loaded into trucks /tippers of 10 tonnes capacity for

further dispatch to desired destination. Precaution will be taken to cover the material

by tarpaulin during transportation.

vii) Resource optimization / recycling and reuse envisaged in the project, if any,

should be briefly outlined.

No

viii) Availability of water its source, Energy / power requirement and source should

be given.

The water requirement of the project is estimated to 80 KLD of the water is

required for drinking/domestic purpose/ dust suppression. The rain water collected

in the mining pit during monsoon shall be optimally utilize for dust suppression and

plantation. The power requirement will be met from MSEB grid.

Page 12: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

9

xi) Quantity of waste to be generated (liquid and solid) and scheme for their

Management/disposal.

The waste generated will be backfilled in the worked out pits concurrently.

Year Area to be backfilled (m2)

Mineral Wastes (tonnes)

1 5136 18692

2 8453 28750

3 10169 28830

4 9334 28746

5 7204 29844

Total 40296 134862

x) Schematic representation of the feasibility drawing which give information of

EIA purpose.

The EIA will include an assessment of the potential impacts envisaged as an effect

of the project, during the operation of the mine. The assessment will be based on a

consideration of the individual components of the project.

Page 13: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

10

4 SITE ANALYSIS

i) Connectivity: The area is located in jurisdiction of Village Karivane in District

Raigad (Maharashtra). The area can be approached from district headquarters,

Alibag to Wadkhal Naka which is 22 Km. From Wadkhal Naka to Mumbai Goa

National Highway up Mangaon and the distance is 44 km. From Mangaon there is

diversion towards Shriwardhan Tahsil which is 45 Km and connected by tar Road.

ii) Land Use and land Ownership: As per the administrative records the Land use of

the Mine is as given below.

iii) Topography (along with map).

Earlier the Adi - Dharwali - Karivane Plateau is explored. Geologically by Directorate

of Geology and Mining, Maharashtra Government.

Physiographic: The Lease area is divided in the two blocks. Both the blocks are

separated by private land

Block 01: The Block 01 is an aerial extent of 51.15 ha. The area is the part of the

karivane Plateau which is explored by the Directorate of Geology and Mining, Nagpur

in earlier time. The area is having a gentle slope towards East direction. The

maximum elevation is 204 m and lowest is 154m.

Block 2: The aerial extent of the Block is 26.22 Ha. The area is located at the south

of the Block No 01.The maximum elevation is 194m and lowest elevation is 132m.

The area is having gentle slope towards South direction.

iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies

(including area under CRZ), shortest distances from the periphery of the

project to periphery of the forest, national park, wild life sanctuary, eco

sensitive areas, water bodies (distance from the HFL of the river), CRZ. In case

of notified industrial area, a copy of the Gazette notification should be given.

The core zone i.e., applied area is a private land. The buffer zone area is mostly

occupied by Arabian sea on the western side while the other part is occupied by

agricultural waste land. The area under consideration is away from the CRZ.

water bodies and habitations. A key plan showing landuse and shortest distance

Survey No. Lease Area Ha. Ownership/ occupancy

58,61,62,63,64,,65,66,50,51,52,53 77.37 Ha Private Land

Page 14: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

11

from forest and other features is enclosed as Map 3. A brief summary of the

features in 10 Km buffer zone is tabulated below;

v) Existing Infrastructure: At present there is no infrastructure available except

the approach road.

vi) Soil classification: The soil of the lease area is found to be Lateritic soil.

Climatic data from secondary sources. The climate of the area is categorized as

tropical monsoon. Typical coastal climate is experienced in the area. The monsoon

prevails from June to September and the average Rainfall varies from 2500 to

3000 mm. The seasonal variation of temperature and moisture prevailing in the

area is mainly responsible for the process of Bauxitization/Lateritization.

Social Infrastructure : There are school, post office, gram panchayat, hospitals,

communication facilities well developed in the area.

Transport : The transport facilities in the tehsil are well developed and wide

spread.

Sr.

No. Description Detail

1 Reserves Forest Not within 10 Km

2 Nearest National Highway Not within 10 Km 3 Nearest State Highway SH-100, Within Lease area (Block 1)

4 Nearest Railway Station Mangaon 86 Km

5 Nearest Airport Pune 180 Km

6 Nearest Major city Shriwardhan 15 Km 7 District Head Quarter Alibaug, 120 Km

8 Nearest River / Dam Savitri river 1.5 Km south of lease

9 National Park, Wild Life Sanctuary,

Eco Sensitive area

Not within 10 Km

10 Interstate Boundary Not within 10 Km

11 Archaeological Monument Not within 10 Km

12 Historical and places of worship 8.35 Km Harihareshwar

13 Places of tourist attraction

8.35 Km Harihareshwar

15Km Shriwardhan

14 Inland, coastal, marine or underground

waters

Arabian sea 8.0 Km

Page 15: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

12

5. PLANNING BRIEF

i) Planning Concept (type of Industries, facilities, transportation etc) Town

and country planning/ Development authority Classification.

The mining will be carried out as per the approved Mining Plan. During Mining

Plan period, the mining operation will be done by development of fully

mechanized opencast method. The statutory provisions for the development of

mine shall be followed to ensure safe mining practices and conservation of

mineral. During the course of mining protection and conservation of natural

resources and protection of environment will be ensured.

ii) Population Projection.

The mine will provide direct employment to nearly 110 workers. The indirect

employment opportunities will be automatically created with the click of

Manganese mine in this region.

iii) Land use planning (breakup along with green belt etc.).

The landuse for the Mining Lease will be strictly followed as per the approved

Mining Plan.

iv) Assessment of Infrastructure Demand (physical & social).

The proposed mining will require roads for the transport of the mineral besides

it will require manpower to operate the proposed mine.

v) Amenities/Facilities.

These include community washrooms, drinking water facilities like public stand

posts.

Page 16: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

13

6. PROPOSED INFRASTRUCTURE

i) Industrial area (processing area).

The Chemical Composition of the Bauxite available in the area that is acceptable to

Aluminum manufacturing, calcined alumina Industries. Lower grade Bauxite will

be used for blending and for Cement Industries also. ROM will be directly fed to

the Mobile Screening & Crushing Plant within the lead distance of 0.5km (one side

distance). Plant operation will be within lease boundary. No beneficiation will be

carried out.

ii) Residential Area (Non processing Area).

None

iii) Green Belt.

It is proposed to undertake plantation of local tree species within the lease also.

iv) Social Infrastructure.

Connectivity (Traffic and Transportation Road/Rail/Metro/Water ways etc.)is

well established

v) Drinking Water management (Source & Supply of water)

Drinking water for the workers will be met from the tankers by nearby villages.

vi) Sewerage System.

None proposed

vii) Industrial Waste Management.

Not required

viii) Solid Waste Management.

The intercalated waste of approximately 20% of ROM will be temporarily stacked

and subsequently utilized for backfilling in worked out pits.

ix) Power Requirement & Supply / Source:

Through State Electricity Board.

Page 17: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

14

7. REHABILITATION AND RESETTLEMENT (R & R) PLAN

i) Policy to be adopted (central/state) in respect of the project affected

person including home oustees, land oustees and landless laborers (a

brief outline to be given.)

Not envisaged as the project lies on private land and there is no habitation on the

proposed mining lease area.

8. PROJECT SCHEDULE & COST ESTIMATES

i) The capital budget for environmental protection measure is estimated to be Rs.

27 Lakhs and Rs. 23.50 Lakhs as recurring cost Environment Management Plan

is given in Annexure-II.

ii) Likely date of start of construction and likely date of completion (Time

schedule for the project to be given.)

The mining operations shall be carried out after obtaining all statutory

permissions and shall be carried out as per approved Mining Plan.

iii) Estimated project cost along with analysis in terms of economic viability

of the project.

The cost analysis in terms of economic viability of the project is presented at

Annexure III.

Page 18: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

15

9. ANALYSIS OF PROPOSAL FINAL RECOMMENDATIONS

i) Financial and social benefits with special emphasis on the benefit to the

local people including tribal population, if any, in the area.

In compliance with the environmental procedure the environmental clearance

application is made. Necessary scientific studies will be undertaken as per the

guidelines set by the Ministry of Environment and Forests (MoEF) and

prescribed Terms of Reference. The suggestions/recommendations of all the

experts, competent authorities, and government officials are being sought for the

impacts of the proposed project. Views and guidance of the local residents,

community based organizations, social organizations are extremely important in

order to devise a full proof Environment Management Plan for the proposed

mining project and also mitigate the damages caused due to the project.

Allocation of necessary funds, manpower and machinery will be made to for the

protection and conservation of all the components of environment. It is ensured

that all mandatory clearances will be sought from respective competent

authorities before operating the proposed Manganese Mine.

Page 19: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

16

Annexure I

Mine Boundary Pillar Location Statement ( As Per DGPS)

Lease Area ( 77.37 HA)

Page 20: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

17

Annexure II

ENVIRONMENT MANAGEMENT PLAN

1.1 For Water Environment

There is no water regime near to this mine. The water regime is Savitri River

which is far away to have any impact. Surface water is in the form of seasonal

rain fall. It takes normal course and flows out of the area along natural slope. No

impact on surface or ground water is expected as no chemical processing is

involved.

1.2 For Air Environment

The proposed mining operations are mechanized and shall be done through

deployment of mining machineries. The dust from the haul roads and drilling is

expected to pollute the air to some extent. However, considering the production

and nature of proposed mining operations particulate matter level will not be

more than the permissible limit.

However, on the haulage road water will be sprinkled to minimize the raising of

dust in the area.

Further, for minimizing dust generation during drilling & blasting and loading

following measures are proposed:

Drilling will be done by compressed air operated 115 mm diameter drill

machine which will be equipped with wet drilling.

Proper care in regard to quantity of explosives will be taken.

Adequate water spraying on the haul roads will be done to suppress dust.

The trucks used for transportation will not be overloaded and will be

covered with tarpaulin.

Development of green belt / plantation all along roads, back filled area

and Peripheral areas will be done to arrest dust.

Dust masks will be provided to persons employed in dusty areas.

Regular & periodic maintenance of deployed machineries will be carried

out to reduce smoke emission

1.3 For Noise Environment :

Noise Level is likely to increase due to movement of machineries, drilling, etc.

The measures will be taken to maintain the noise levels within limits. Periodical

Page 21: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

18

maintenance of equipment will be carried out. Moreover, the building of green

belt that would be continued along lease boundary, dumping yards, haulage

roads will help in restricting noise level.

1.4 For reducing ground vibrations :

Ground vibrations caused by blasting will be monitored in order to know their

degree and to build safe guards. The ground vibrations would be mainly at the

point of blasting and further away the vibrations will decrease and becomes

imperceptible.

To reduce the ground vibrations multi-row blasting will be adopted and charge

per delay to be kept within limit. Blasting shall be carried out by using NONEL

detonators, which controls air blast and ground vibration effectively.

Blasting will be done preferably in the afternoon. This will minimize vibration

due to blasting and check noise pollution. Ground Vibration monitoring will be

done regularly.

1.5 Stabilization of Overburden Dumps :

The Overburden is in the form of Intercalated Clay which is considered as 20 %

of the Total ROM handling. The intercalated waste will be concurrently filled in

the mined out area.

1.6 For Socio -Economic Environment

The proposed mining activity is expected to have a positive impact on the socio-

economic profile of the area. The local people shall get opportunities of

employment in the unskilled semiskilled category. The overall standard of living

in the area is expected to improve due to coming Karivane Bauxite Mining

Project.

Budget for Environmental Protection (Rs. Lakhs)

Sr. no. Particulars Capital Cost Recurring Cost

1 Pollution Control 18.00 8.50

2 Pollution Monitoring -- 5.00

3 Occupational Health 3.00 2.50

4 Reclamation & Rehabilitation 4.00 4.50

Page 22: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

19

5 Other 2.00 3.00

Total 27.00 23.50

Page 23: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

20

Annexure III

ESTIMATED PROJECT CAPITAL COST & PRODUCTION COST

Project Capital Cost

The total project cost for Karivane Bauxite Mining Project has been estimated at

Rs. 3.90 crores. The break-up of the total estimated capital cost for the project is

presented in following table:

All figures in Rs. Crores

Sr.

No.

Investment Head Estimated Capital

Investment

(In Rs. Corore)

1 Land 2.08

2 Buildings & Structures 0.10

3 Additional Exploration 0.50

4 Departmental Plant & Machinery 0.40

5 Office Vehicles 0.01

6 Office Furniture & Fixtures 0.01

7 Quality Control & Environment Protection

Equipment

0.30

8 Consultancy Charges 0.50

Total 3.90

The basis of estimates for different investment heads are presented below:

Land : The area is Private Non-Forest and Revenue Waste Land. The cost of the

land is estimated to be Rs. 2.08 Crores

Buildings & Structures : This cost includes cost of office & other service

buildings. The cost is on the basis of standard structures that are likely to be

constructed. The prevailing rates have been taken. The cost estimated under this

head is Rs. 0.10 Crores.

Additional Exploration : Additional drilling and trenching is proposed within

the Mining Lease for further detailing about the geology and reserves with an

estimated cost of Rs. 0.50 Crores.

Page 24: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

21

Departmental Plant & Machinery : This includes opencast consisting of drills/

excavators along with accessories, etc. Further, certain machineries like DG Sets

etc may be required to be procured by the proponent.

The capital cost for departmental machinery has been estimated at Rs. 0.40

Crores.

Office Furniture, Fixtures and Vehicles : The cost of the Furniture & Fixtures,

Vehicles and Office Equipment has been estimated from the available

information. The total capital cost estimated under these heads is Rs. 0.02 Crores

Quality Control & Environment Protection Cost : This includes expenses

towards pollution control due to mining activites. The cost towards this head has

been estimated at Rs. 0.30 Crores.

Consultancy Charges : This includes the fees to be paid to technical consultants

for preparation of Mining Plan, Environmental Impact Assessment /

Environmental Management Plan, Project Report etc. It is estimated that

Company has to incur Rs. 0.50 Crores towards payment of Consultancy Charges.

Thus, the basic Project Cost has been estimated as Rs. 3.90 Crores.

Page 25: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

22

Map 1: Cadastral Plan

Page 26: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

23

Map 2: Surface Plan

Page 27: MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGEenvironmentclearance.nic.in/writereaddata/Online/TOR/11... · 2017-05-11 · PRE FEASIBILITY REPORT Submitted to MINISTRY OF ENVIRONMENT,

Pre Feasibility Report : Karivane Bauxite Mine

24

Map 3 : Key Plan

RavtaleUmbershet Kavadoli

Mandivali Shevre

MaharwadiNayane

Maharwadi

Gauliwadi

Panhli Budrukh

Ambavli

KharewadiSakhri

Ranavli

Gudegarh

BaslewadiUmbroliKante

Shipole

KataiwadiKinjalwadi

ShipolewadiVeshvi

KoliwadiBankot

Killawadi

Velas

BaldawadiKeril

Borjwadi

Malgaonwadi

DevhareKuduk Budrukh

Veral

Kalkavne

Dhamni

BorkhatGothe

AdiwadiKarivane

Adi

KolmandleKellchakonde

Godapkonde

Vadi

Vadi

BagmandleBenkolwadiDevgarh

Maral

Nivle

Dharavli

JangamvadiVadi

Vadi

Bhamghar

Jale

SAVITRI RIVER

Bharja River

Kuravde

Hajimushi

Kalinje Saigaon

NigdikodeNavabuddhadi

NigdiNigdi Kati

Galsure Kati

BhakarvadiGalsure

Bapvankandhane

Ranavli

Jasavli

Bhattichamal

Srivardhan

Vadi

Vadghar

Pangloli Vadi Kelte Ghum

Rudravat

KondhePanve

Thakroli

SangvadPangaldi

Toradi

Ambavne

Kinjalghar

Nigadi

Shingvan

Sanavri

Telieadi

Bhagawadi

Ambavde

Vave

SakhariJavele

Vadshet

Sakhravne

Kole

TalavadeKumbale

Konzari

Hareshwar

Vadi

Toradi

73°5' 73°10'

18°0'

18°5' 18°5'

18°0'

73°5' 73°10'

Arati

Kherdi

R.F

R.F

R.F

R.F R.F

R.F

R.F

R.FR.F

R.FR.F

R.F

STREAMS

RIVER / NALA

ROAD

HABITATION

BLOCK BOUNDARY

FOREST BOUNDARY

INDEX

0 1 2 3 4 5Metres 1000Km.

KEY MAP

SRUSHTI SEVA PRIVATE LIMITED

M/S ALTAGE STONE CRUSHING INDUSTRIESKARIVANE BAUXITE ORE MINERAL BLOCK

N

SEA