mike hirst 17.10.2018 e.on energy distribution microgrid

23
E.ON Energy distribution Microgrid in southern Sweden Control, operation, management and power quality within a 100% converter, zero-inertia microgrid 17.10.2018 Mike Hirst

Upload: others

Post on 24-Jan-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

E.ON Energy distribution Microgrid in southern Sweden

Control, operation, management and power quality within a 100% converter, zero-inertia microgrid

17.10.2018 Mike Hirst

Page 2: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

E.ON

~38,2 BEuro in revenues

>22 M customers

~ 43.000 employees

E.ON Fortum

Vattenfall Övriga

Global E.ON Energidistribution

(Sweden) 685 primary substations & 44.460 secondary substations

~ 8.656 km HV-grid & ~128.208 km MV-Grid

~ 1,2 BEuro in network investment

Page 3: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Background – changes to the grid structure in Europe/US European grid

Historically electricity was delivered from central power plants

With LES we are trying to achieve Local balance

The Grid: In rural areas grids can be over-dimensioned and are expensive to re-invest in. In other parts with lots of renewables or growing demand there can be bottlenecks to deliver enough power Production: Renewables in general and small scale (PV) are growing and getting more competitive together with energy storage technologies Customers: Customers demand green electricity and are also interested in becoming self-sufficient

New challenges in the energy market

Page 4: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

EU’s ”Winter package”

In the Winter package it is stated that:

If this becomes reality, it would likely mean that Local Communities will be created to:

1. Maximize self consumption

2. Minimize the cost of energy

4

Page 5: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

E.ON LES Project objectives The objective of this LES Project is mainly: • To build and demonstrate capability (technical and

commercial)

• Understand the business of LES, cost drivers, barriers, possibilities etc.

• Develop business cases and business models as well as identifying potential customers

The vision is to develop new, demanded solutions on the energy market and bring E.ON closer to the customer

5

Page 6: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

6

Simris – Simrishamn’s Municipality

Page 7: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Existing circuit at Simris

7

Page 8: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

8

Development of microgrid system at Simris

Page 9: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

LES Simris – Microgrid components

9 Red = New Blue = existing

02.05.2017

Battery system Back-up generator

The microgrid was inaugurated in October 2017

9

Page 10: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Control structure for battery PCS

Courtesy of BDF Digital / TDE Macno

Droop Z

Voltage being

controlled

Current controller

Voltage source

Page 11: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Battery PCS summary

• Standard 3-limb bridge hardware • Control approach enables the functions that we require:

• Operation in grid-connected and islanded mode • Power sharing with other power electronics and conventional synchronous generation • Seamless transition to between modes without high speed communication • Fault clearance and recovery

• Estimated 10% increase in cost compared to basic power electronicss interface • Partially attributable to low ac voltage to allow fully circular capability for all battery

voltages • Would not currently be compliant with all National Grid (UK TSO) draft requirements for

Grid-Forming inverters • Parallel development activities • Meets all design intents, but in different way to that envisaged

• Additional tests planned to demonstrate transient power sharing

11

Page 12: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Fault testing setup (customers not connected for this test)

12

Page 13: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

13

Voltage and current during 3ph fault, 63A fuse – Battery and solar

Fault cleared and voltage restored within 50ms

±2% within 150ms

Page 14: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Results – Frequency and power of first islanding tests Dec 2017

14

Page 15: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Island Voltage vs Nordic system 12 April

Island operation

Simris Voltage

Nordic grid Voltage

15

Page 16: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Total Harmonic Distorsion – THD 13th April (specification 8% max)

Reduction in THD on the Grid when WTG and PV systems removed.

No significant increase in THD when islanded

Island operation

16

Page 17: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

THD –varies inversely with wind power when islanded

17

Page 18: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Simris frequency (Hz)

Grid frequency (Hz)

Island operation

Frequency compared to Nordic system 11th April

Detailed on next slide

18

Page 19: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Renewables curtailed due to high SOC reported (battery issue). 350kW increase in battery power over 15s

Curtailment released. 750kW decrease in battery power over 45 seconds

120mHz drop. Recovery over 75 seconds

120mHz increase. Recovery over 100 seconds

Battery power (kW)

Simris frequency (Hz)

Frequency compared to Nordic system 11th April

19

Page 20: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Changes to 1 or 2 inverter parameters can seriously affect stability!

20

Page 21: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Timeline

2017 2018 2019

Construction

DSR development

Installation DSR

Test period

Evaluation

Today

Commisioning

Additional 1600kWh battery integration

21

Page 22: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Summary

• Novel battery and power electronics systems have allowed the integration of a microgrid system with operation on 100% converters (zero inertia):

• 20yr old Enercon wind turbine • 6yr old Solar generation

• Power quality well within statutory limits (voltage, frequency, THD etc.) • Security of supply maintained througout transitions and during island operation • Fault current behaviour has been tested and is acceptable • A zero-inertia (no classical inertia) system is capable of handling big load steps • Additional battery with power electronics will be added by end 2018

22

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement n°731289

Page 23: Mike Hirst 17.10.2018 E.ON Energy distribution Microgrid

Thank you for your attention

If you want to follow the system live: les.eon.se For more information, please visit

www.eon.se/simris

[email protected]