Project 2013Microsoft Project for
Professionals5 Simple & Practical Steps to Mastering Task
Context in under 30 Minutes
Jakub MarciniakSolution ConsultantDeltaBahn LLC
![Page 2: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/2.jpg)
Agenda
![Page 3: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/3.jpg)
1. Open the project saved last time
• Open the project that was created and saved from the previous part of the series Task Basics
OR
• Create a new project from the Commercial Construction Template and follow the instructions choosing different tasks
![Page 4: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/4.jpg)
2. Create a summary task
Task tab:
Select the three tasks Prepare and submit project schedule, Prepare and submit schedule of values and Resource Allocation
![Page 5: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/5.jpg)
2. Indent and Outdent tasksSelect the next task that does not belong to the summary task:
Task tab: Task tab:Indent task Outdent task
![Page 6: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/6.jpg)
3. Add a milestone task
Task tab:
Name it:
Note: Milestone tasks have a default Duration of 0 days. The are shown in the Gantt Chart as a diamond shape.
![Page 7: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/7.jpg)
4a. Create a recurring task
Task tab:
Select the task Submit monthly request for payment
Configure the details for the recurring task:
![Page 8: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/8.jpg)
Project identified that some occurrences will take place in non-working times.
Confirm with Yes:
4b. Create a recurring task
![Page 9: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/9.jpg)
5a. Adjust the recurring task
View tab:
In the Task form (at the bottom) right-click and select Predecessors & Successors:
![Page 10: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/10.jpg)
5b. Adjust the recurring task
In the predecessors pane choose the task Receive notice to proceed and sign contract and click OK.
![Page 11: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/11.jpg)
5c. Adjust the recurring task
Look up the ID of the first occurrence of the recurring task, in this case number 11.
Click in the Predecessors column of the task Submit shop drawings andorder long lead items – steel and type in 11.
![Page 12: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/12.jpg)
6a. Create Lag time
View tab:
In the Task form (at the bottom) right-click and select Predecessors & Successors:
Scroll to the summary task Foundations and select the task Cure concrete elevator walls.
![Page 13: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/13.jpg)
6b. Create Lag time
Increase the lag to 2 days and click OK:
Observe the changes in the Outline pane:
![Page 14: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/14.jpg)
7a. Create lead timeTask tab:
Increase the duration to 3 days:
![Page 15: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/15.jpg)
7b. Create lead time
Decrease the lag to -2 days and click OK:
Note that in the Gantt Chart the tasks are now overlapping and the Predecessor column reflects the changes:
![Page 16: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/16.jpg)
8a. Elapsed time
Right-click on the task Cure elevator wall concrete and click Insert Task:
Enter “4ed” for elapsed days:
![Page 17: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/17.jpg)
9a. Determine critical tasksScroll down to the summary task Site Grading and Utilities
View tab:
![Page 18: Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering Task Context in under 30 Minutes](https://reader036.vdocuments.site/reader036/viewer/2022062823/5876fa711a28abf3398b61b9/html5/thumbnails/18.jpg)
9b. Determine critical tasks
Select the task Perform final site grading. This task is critical and has no slack:
Select the task Install storm drainage. Hover over the thin black line after the task bar in the Gantt Chart: