microsoft project association

63
Celeris Celeris Systems Systems Microsoft Project Association March 7, 2007 March 7, 2007

Upload: edolie

Post on 19-Jan-2016

45 views

Category:

Documents


0 download

DESCRIPTION

Microsoft Project Association. March 7, 2007. About Me. Jim Aksel, PMP Director of Project Management Celeris Systems, Inc http://www.celeris-systems.com [email protected] Telephone: 714-813-4025. You get Credit!. You may claim 1 hour of CE (or PDUs) PMI References:. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Microsoft Project Association

Celeris Celeris SystemsSystems

Microsoft Project AssociationMarch 7, 2007March 7, 2007

Page 2: Microsoft Project Association

Celeris Celeris SystemsSystems

About Me

Jim Aksel, PMP

Director of Project Management

Celeris Systems, Inc

http://www.celeris-systems.com

[email protected]

Telephone: 714-813-4025

Page 3: Microsoft Project Association

Celeris Celeris SystemsSystems

You get Credit!

• You may claim 1 hour of CE (or PDUs)• PMI References:

Page 4: Microsoft Project Association

Celeris Celeris SystemsSystems

Backward Compatibility to 2003

Page 5: Microsoft Project Association

Celeris Celeris SystemsSystems

Task Types

Resource Issues & Leveling

Custom Sorting

Conclusion

11

22

33

44 EVMS in Project

Page 6: Microsoft Project Association

Celeris Celeris SystemsSystems

Sorting

Custom Sorts

EVMS

Tasks

LevelingResources

Page 7: Microsoft Project Association

Celeris Celeris SystemsSystems

Fixed UnitsEffort Driven

Fixed UnitsEffort Driven

Fixed DurationEffort Driven

Fixed DurationEffort Driven

Fixed DurationNot Effort Driven

Fixed DurationNot Effort Driven

Fixed UnitsNot Effort Driven

Fixed UnitsNot Effort Driven

Fixed WorkFixed Work

TitleTitleTASKS

Page 8: Microsoft Project Association

Celeris Celeris SystemsSystems

Task Type Definitions

• Fixed Units– The allocations of resource units is held constant

• Fixed Work– Total of all work hours assigned to a task is held

constant

• Fixed Duration– Task Duration is held constant

Page 9: Microsoft Project Association

Celeris Celeris SystemsSystems

Effort Driven

• Total task work remains at its current value, regardless of how many resources are assigned to the task.

• When new resources are assigned, remaining work is distributed amongst all assigned resources, proportionately.

Page 10: Microsoft Project Association

Celeris Celeris SystemsSystems

Basic Task

Page 11: Microsoft Project Association

Celeris Celeris SystemsSystems

Basic Task Work Hours Spread

Page 12: Microsoft Project Association

Celeris Celeris SystemsSystems

Added Resources

Additional resources just increase total work with no change to duration

Page 13: Microsoft Project Association

Celeris Celeris SystemsSystems

Adding Resources After %Complete

Status Date:

15 FEB 2007

On Schedule

Page 14: Microsoft Project Association

Celeris Celeris SystemsSystems

Progress Shown

Status Date:

15 FEB 2007

On Schedule

Page 15: Microsoft Project Association

Celeris Celeris SystemsSystems

New Resources Create Remaining Work

Status Date:

15 FEB 2007

On Schedule

Page 16: Microsoft Project Association

Celeris Celeris SystemsSystems

Adding Effort Driven Labor

Adding Resources reduces duration while keeping total work and units constant

No Work No Work ChangeChange

Added to Basic Task, after making it Effort Driven

Page 17: Microsoft Project Association

Celeris Celeris SystemsSystems

Effort Driven Labor Added after %Complete

Adding Effort Driven Labor keeps finish date and work constant, creates split

Status Date:

15 FEB 2007

On Schedule

Page 18: Microsoft Project Association

Celeris Celeris SystemsSystems

Adding Effort Driven Labor creates splits

Status Date:

15 FEB 2007

On Schedule

Page 19: Microsoft Project Association

Celeris Celeris SystemsSystems

Effort Driven

•Add ResourcesTotal Work ConstantDuration Changes

•Add Work•Changes Duration

•New resourcesAdd work after Status Date

Not Effort Driven

•Duration fixed•Adding Resourcesadds remaining work

•Increasing Workincreases Duration

•New resources add work after Status Date

Fixed UnitsTasks

Page 20: Microsoft Project Association

Celeris Celeris SystemsSystems

Fixed Duration TasksNot Effort Driven behaves as before

Adding resources divides remaining work among all resources

Page 21: Microsoft Project Association

Celeris Celeris SystemsSystems

Fixed Duration w/%Complete

Additional Resources share the remaining work

Status Date:

15 FEB 2007

On Schedule

Page 22: Microsoft Project Association

Celeris Celeris SystemsSystems

Fixed Work Task• Always effort driven

Additional Work alters duration while respecting finish date

Page 23: Microsoft Project Association

Celeris Celeris SystemsSystems

You ChangeYou Change Units Units ED Duration Duration ED Work

Units Duration Duration Work Work Duration

Work Duration Duration Units Units Duration

Duration Work Work Work Work Units

Task Type Fixed:Task Type Fixed:

What Project Recalculates

ED: Effort Driven

Page 24: Microsoft Project Association

Celeris Celeris SystemsSystems

Sorting

Custom Sorts

EVMS

Tasks

Leveling

Resources

Page 25: Microsoft Project Association

Celeris Celeris SystemsSystems

Resources

• Individual names• Skill set grouping

Page 26: Microsoft Project Association

Celeris Celeris SystemsSystems

Named Person

•Unique Calendars•Retains Grouping•Skill Specific

Skill Set List

•Department Wide•Easier to Assign•Interchangeable

Resource Types

Page 27: Microsoft Project Association

Celeris Celeris SystemsSystems

Named Person

•Wage/Privacy•Harder to swap•Skill Specific

Skill Set List

•Department Wide

•Homogeneous•Calendaring•Exact Costs TBD

Resource Types

Page 28: Microsoft Project Association

Celeris Celeris SystemsSystems

Sorting

Custom Sorts

EVMS

Tasks

Leveling

Resources

Page 29: Microsoft Project Association

Celeris Celeris SystemsSystems

Page 30: Microsoft Project Association

Celeris Celeris SystemsSystems

Leveling Order

• Standard   Project looks at predecessor, slack (a task with more total slack time is delayed first), dates (a task with a later start date is delayed first), priorities, and constraints 

• Priority, Standard   Project looks first at priorities and then at predecessors, slack, dates, and constraints to determine whether and how tasks should be leveled

Page 31: Microsoft Project Association

Celeris Celeris SystemsSystems

Leveling Parameters:• Day by Day   Level resources when there is at least one day

more work scheduled for a resource than can be completed within the resource's normal availability for that day.

• Week by Week   Level resources when there is at least one week more work scheduled for a resource than can be completed within the resource's normal availability for that week.

• Month by Month   Level resources when there is at least one month more work scheduled for a resource than can be completed within the resource's normal availability for that month. This is the default setting.

Page 32: Microsoft Project Association

Celeris Celeris SystemsSystems

Leveling Example:

• Ringo assigned to two 8 hour tasks in 1 day.• Leveling:

– Day By Day: Problem– Week By Week: No Problem, work <40– Month By Month: No Problem, work<160

Page 33: Microsoft Project Association

Celeris Celeris SystemsSystems

Other Leveling Settings• Level only within available slack  

– Finish Dates are respected.• Leveling can adjust individual assignments on a

task  – Adjusts when a resource works on a task independent

of the other resources working on the same task. • Leveling can create splits in remaining work

– Any remaining work can be split for leveling. Unchecked will not delay a task with an Actual Start Date.

Page 34: Microsoft Project Association

Celeris Celeris SystemsSystems

General Guidance

• IMHO– Project does a pretty good job of leveling

since it takes a methodical approach– However, it does level in resource order

Page 35: Microsoft Project Association

Celeris Celeris SystemsSystems

Sorting

Custom Sorts

EVMS

Tasks

LevelingResources

Page 36: Microsoft Project Association

Celeris Celeris SystemsSystems

Standard Sorting

Obvious

Just Like Excel

Page 37: Microsoft Project Association

Celeris Celeris SystemsSystems

Sorting

Custom Sorts

EVMSTasks

Leveling

Resources

Page 38: Microsoft Project Association

Celeris Celeris SystemsSystems

Custom Grouping (Sorting)

Page 39: Microsoft Project Association

Celeris Celeris SystemsSystems

Custom Grouping Dialog

Page 40: Microsoft Project Association

Celeris Celeris SystemsSystems

Custom Grouping

Page 41: Microsoft Project Association

Celeris Celeris SystemsSystems

More Powerful Options

Page 42: Microsoft Project Association

Celeris Celeris SystemsSystems

Some Grouping Ideas

• Place custom text field in Resource Usage View– Group by CLIN, Job Number, other accounting

information– Assign Control Account Managers– Supplier ID’s

• WBS Field– Sort by defined code (such as first three levels)

Page 43: Microsoft Project Association

Celeris Celeris SystemsSystems

Sorting

Custom Sorts

EVMS

Tasks

Leveling

Resources

EVMS is my personal opinion

Page 44: Microsoft Project Association

Celeris Celeris SystemsSystems

EVMS in MS Project

BCWS = Budgeted CostCost of Work Scheduled

BCWP = Budgeted CostCost of Work Performed

ACWP = Actual CostCost of Work Performed

Page 45: Microsoft Project Association

Celeris Celeris SystemsSystems

EVMS Comments

• BCWS & BCWP only register in the Baseline Date Period

• If you start/finish on different dates you must enter an Actual Date in the [Actual Start] or [Actual Finish] columns

Page 46: Microsoft Project Association

Celeris Celeris SystemsSystems

MS Project uses %Complete Method

• Think about it – Milestones, Incremental, 80/20, Formula, Apportionment are all subsets of %Complete

• The trick is accurate definition of %Complete

Page 47: Microsoft Project Association

Celeris Celeris SystemsSystems

Example: Concert

• 6 Roadies take 2 days to setup• Fab Four sing some songs for 1 day• 3 Roadies tear down for 1 day

Page 48: Microsoft Project Association

Celeris Celeris SystemsSystems

Resources

• Singers make $500/hr• Roadies make $25/hr• Let’s assume everyone is paid cash at the

end of each phase (setup, sing, teardown)

Page 49: Microsoft Project Association

Celeris Celeris SystemsSystems

Baseline Schedule and Costs

• We have a $19K EAC and 4 Days

Page 50: Microsoft Project Association

Celeris Celeris SystemsSystems

%Complete Example

• After Setup is complete,

we claim 50% EV = $9,500• We pay the roadies $2400

Page 51: Microsoft Project Association

Celeris Celeris SystemsSystems

End of Day 3

• We claim 75% Complete

0.75 x $19,000 = $14,250

Page 52: Microsoft Project Association

Celeris Celeris SystemsSystems

% Complete Earned Value Parameters

Item Mon Tues Wed Thur

BCWS $ 1,200.00 $ 1,200.00 $ 16,000.00 $ 600.00

ACWP $ - $ 2,400.00 $ 16,000.00 $ 600.00

cBCWS $ 1,200.00 $ 2,400.00 $ 18,400.00 $ 19,000.00

cBCWP $ - $ 9,500.00 $ 14,250.00 $ 19,000.00

cACWP $ - $ 2,400.00 $ 18,400.00 $ 19,000.00

Page 53: Microsoft Project Association

Celeris Celeris SystemsSystems

%Complete EV

This is a duration weighted method

%Complete = durationprojectEntire

DurationCompletetasksi

i ii

__

*%1

Page 54: Microsoft Project Association

Celeris Celeris SystemsSystems

%Work Complete

• This is an Effort weighted method

TotalWork

WorkteWorkCompleteWorkComple

tasksi

iii

1

*%%

Page 55: Microsoft Project Association

Celeris Celeris SystemsSystems

%Work Complete

• At the end of the 2nd day, 63% of the labor is complete

• EV= 0.63 x $19,000 = $ 12,000

Page 56: Microsoft Project Association

Celeris Celeris SystemsSystems

%Work Complete

• End of Day 3 we are 84% Labor Complete

0.84 x $19,000 = $16,000

Page 57: Microsoft Project Association

Celeris Celeris SystemsSystems

Physical%Complete

• Allows you more flexibility– EV Method Physical%Complete– Each Task Physical%Complete

Page 58: Microsoft Project Association

Celeris Celeris SystemsSystems

Physical % Complete EV for Tasks

Page 59: Microsoft Project Association

Celeris Celeris SystemsSystems

Physical % Complete EV

stBaselineCo

BCWSCompletePhysicalCompletePhysical

tasksi

i i

1*%

%

Page 60: Microsoft Project Association

Celeris Celeris SystemsSystems

Physcial%Complete Day 2

• At the end of Setup we are 13% Complete

0.13 x $19,000 = $2400

Note: Project displays only 2 significant digitsNote: Project displays only 2 significant digits

Page 61: Microsoft Project Association

Celeris Celeris SystemsSystems

Physical % Complete Day 3

• At end of “Hey Jude…” we are 97% Complete

0.97 x $19,000 = $18,400

Page 62: Microsoft Project Association

Celeris Celeris SystemsSystems

Which one does your boss expect?

Page 63: Microsoft Project Association

Celeris Celeris SystemsSystems

www.celeris-systems.com800-951-EVMS800-951-EVMS