  • Id EDT Nombre de tarea DasCorridos

    Duracin Comienzo Fin

    0 Proyecto : HPX Sinergy 1 Process. / PLANTA ORAFTI CHILE S.A. 45 26 das? lun 10/02/14 mi 26/03/14

    1 1 INICIO DE OBRAS -0 0 das lun 10/02/14 lun 10/02/14

    2 2 INSTALACION DE FAENAS 37 21 das? lun 10/02/14 mar 18/03/14

    3 2.1 Movilizacin 3 2 das lun 10/02/14 mi 12/02/14

    4 2.2 Instalacin de Faena 6 3 das jue 13/02/14 mar 18/02/14

    5 2.3 Desmobilicacion 2 1 da? lun 17/03/14 mar 18/03/14

    6 3 Suministro de Materiales 9 5 das jue 13/02/14 vie 21/02/14

    7 3.1 Suministro de Caerias 9 5 das jue 13/02/14 vie 21/02/14

    8 3.2 Suministro de Fitting 9 5 das jue 13/02/14 vie 21/02/14

    9 3.3 Sumistro de Equipos 9 5 das jue 13/02/14 vie 21/02/14

    10 4 Montaje Equipos 23 13 das lun 17/02/14 mar 11/03/14

    11 4.1 Montaje Equipos Nuevos Exterior Edificio 19 13 8 das lun 17/02/14 sb 01/03/14

    12 4.1.1 Estanque 50 m3 (Cantidad 2) 5 3 das lun 17/02/14 vie 21/02/14

    13 4.1.2 Bonbas (Cantidad 3) 6 3 das jue 20/02/14 mar 25/02/14

    14 4.1.3 Intercambiador de calor 5 3 das mar 25/02/14 sb 01/03/14

    15 4.2 Equipos Reubicacion edificio 14 a Exterior edificio 19 20 11 das jue 20/02/14 mar 11/03/14

    16 4.2.1 Desmontaje de Intercambiador de calor a trasladar 3 2 das jue 20/02/14 sb 22/02/14

    17 4.2.2 Montaje Intercambiador de calor Reubicar 5 3 das mar 04/03/14 sb 08/03/14

    18 4.2.3 Desmontaje Estanque de 1 m3 trasladar 4 2 das vie 21/02/14 mar 25/02/14

    19 4.2.4 Montaje estanque de 1 m3 5 3 das lun 03/03/14 vie 07/03/14

    20 4.2.5 Desmonataje Bomba 3 2 das mar 25/02/14 vie 28/02/14

    21 4.2.6 Montaje Bomba 6 3 das jue 06/03/14 mar 11/03/14

    22 4.3 Montaje de Equipos Edificio 15 10 6 das mar 25/02/14 vie 07/03/14

    23 4.3.1 Estanque 10 m3 (Montaje Primer Nivel) 7 4 das mar 25/02/14 mar 04/03/14

    24 4.3.2 Bomba a Reubicar (Cantidad 1 ) 3 2 das jue 27/02/14 sb 01/03/14

    25 4.3.3 Intercambiador de calor Nuevo 5 3 das lun 03/03/14 vie 07/03/14

    26 4.4 Montaje de Equipos Edificio 19 6 3 das jue 06/03/14 mar 11/03/14

    27 4.4.1 Bonba Montar dentro edificio 19 6 3 das jue 06/03/14 mar 11/03/14

    28 5 Montaje Caeria HPX Sinergy 1 Process 34 19 das jue 13/02/14 mar 18/03/14

    29 5.1 Proceso de Montaje 34 19 das jue 13/02/14 mar 18/03/14

    30 5.1.1 Caeria D 150 mm 14 8 das mar 18/02/14 mar 04/03/14

    31 5.1.2 Caeria D 100 mm 23 13 das vie 21/02/14 sb 15/03/14

    32 5.1.3 Caeria D 80 mm 34 19 das jue 13/02/14 mar 18/03/14

    33 5.1.4 Caeria D 70 mm 20 12 das lun 24/02/14 sb 15/03/14

    34 5.1.5 Caeria D 50 mm 16 9 das vie 28/02/14 sb 15/03/14

    35 5.1.6 Caeria D 40 mm 11 6 das vie 07/03/14 mar 18/03/14

    36 5.1.7 Caeria D 32 mm 9 5 das lun 10/03/14 mar 18/03/14

    37 5.1.8 Caeria D 25 mm 7 4 das mar 11/03/14 mar 18/03/14

    38 5.1.9 Caeria D 15 mm 7 4 das mar 11/03/14 mar 18/03/14

    39 5.2 Inspecion y Pruebas 23 13 das vie 21/02/14 sb 15/03/14

    40 5.2.1 Inspecion visual Soldadura y Tintas Penetrantes 23 13 das vie 21/02/14 sb 15/03/14

    41 5.2.2 Pruebas Hidraulica 13 8 das lun 03/03/14 sb 15/03/14

    42 6 Aislacion y Recubrimiento 28 16 das jue 27/02/14 mi 26/03/14

    43 6.1 Aislacion Equipos 17 10 das jue 27/02/14 sb 15/03/14

    44 6.1.1 Aislacion estanque 50 m3 17 10 das jue 27/02/14 sb 15/03/14

    45 6.1.2 Aislacion estanque 10 m3 13 7 das vie 28/02/14 mi 12/03/14

    46 6.2 Aislacion Caeria 28 16 das jue 27/02/14 mi 26/03/14

    47 6.2.1 Caeria D 150 mm 14 8 das vie 07/03/14 vie 21/03/14

    48 6.2.2 Caeria D 100 mm 16 9 das mar 04/03/14 mi 19/03/14

    49 6.2.3 Caeria D 80 mm 23 13 das jue 27/02/14 vie 21/03/14

    50 6.2.4 Caeria D 70 mm 20 11 das vie 07/03/14 mi 26/03/14

    51 6.2.5 Caeria D 50 mm 16 9 das mar 11/03/14 mi 26/03/14

    52 6.2.6 Caeria D 40 mm 10 6 das lun 17/03/14 mi 26/03/14

    53 6.2.7 Caeria D 32 mm 9 5 das jue 13/03/14 vie 21/03/14

    54 6.2.8 ASEO Y ENTREGA A MANDANTE 9 5 das lun 17/03/14 mar 25/03/14

    080910111213141516171819202122232425262728010203040506070809101112131415161718192021222324252627210 feb '14 17 feb '14 24 feb '14 03 mar '14 10 mar '14 17 mar '14 24 mar '14

    Montaje Piping y Equipos Proyecto : HPX Sinergy 1 Process.

    ORAFTI CHILE S. A.

    22-02-2014

    Pgina 1