MICHIGAN STATE UNIVERSITY - INFRASTRUCTURE PLANNING AND FACILITIES FACILITIES DATA REPORT 1 April 2022 BUILDING DATA LIST COMPLEX BUILDING ARCHITECT BLDG FUNC COST $ COST / SQ FT AREA SF YEAR BUILT 0128 1407 S HARRISON 0128 1407 S HARRISON ORIGINAL CONSTRUCTION 1973 SUPPORT 56,695 $1,587,019 $28.00 WARREN-HOLMES 1800 1855 PLACE COMPLEX 1801 1855 PLACE-BUILDING 1801 ORIGINAL CONSTRUCTION 2017 HOUSING 148,446 $25,347,696 $171.00 NEUMANN/SMITH 1802 1855 PLACE-BUILDING 1802 ORIGINAL CONSTRUCTION 2017 HOUSING 46,205 $8,007,296 $173.00 NEUMANN/SMITH 1803 1855 PLACE-BUILDING 1803 ORIGINAL CONSTRUCTION 2017 HOUSING 38,731 $6,777,750 $175.00 NEUMANN/SMITH 1804 1855 PLACE-BUILDING 1804 ORIGINAL CONSTRUCTION 2017 HOUSING 39,058 $6,874,208 $176.00 NEUMANN/SMITH 1805 1855 PLACE-BUILDING 1805 ORIGINAL CONSTRUCTION 2017 HOUSING 50,083 $6,874,208 $137.00 NEUMANN/SMITH 1806 1855 PLACE-BUILDING 1806 ORIGINAL CONSTRUCTION 2017 HOUSING 26,659 $4,691,984 $176.00 NEUMANN/SMITH 1807 1855 PLACE-BUILDING 1807 ORIGINAL CONSTRUCTION 2017 HOUSING 26,206 $4,612,256 $176.00 NEUMANN/SMITH 1808 1855 PLACE-BUILDING 1808 ORIGINAL CONSTRUCTION 2016 HOUSING 56,869 $10,008,944 $176.00 NEUMANN/SMITH FACILITIES INFORMATION SERVICES 1

Upload: others

Post on 02-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

MICHIGAN STATE UNIVERSITY - INFRASTRUCTURE PLANNING AND FACILITIES

FACILITIES DATA REPORT

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0128 1407 S HARRISON

0128 1407 S HARRISON

ORIGINAL CONSTRUCTION 1973SUPPORT 56,695 $1,587,019 $28.00 WARREN-HOLMES

1800 1855 PLACE COMPLEX

1801 1855 PLACE-BUILDING 1801

ORIGINAL CONSTRUCTION 2017HOUSING 148,446 $25,347,696 $171.00 NEUMANN/SMITH

1802 1855 PLACE-BUILDING 1802

ORIGINAL CONSTRUCTION 2017HOUSING 46,205 $8,007,296 $173.00 NEUMANN/SMITH

1803 1855 PLACE-BUILDING 1803

ORIGINAL CONSTRUCTION 2017HOUSING 38,731 $6,777,750 $175.00 NEUMANN/SMITH

1804 1855 PLACE-BUILDING 1804

ORIGINAL CONSTRUCTION 2017HOUSING 39,058 $6,874,208 $176.00 NEUMANN/SMITH

1805 1855 PLACE-BUILDING 1805

ORIGINAL CONSTRUCTION 2017HOUSING 50,083 $6,874,208 $137.00 NEUMANN/SMITH

1806 1855 PLACE-BUILDING 1806

ORIGINAL CONSTRUCTION 2017HOUSING 26,659 $4,691,984 $176.00 NEUMANN/SMITH

1807 1855 PLACE-BUILDING 1807

ORIGINAL CONSTRUCTION 2017HOUSING 26,206 $4,612,256 $176.00 NEUMANN/SMITH

1808 1855 PLACE-BUILDING 1808

ORIGINAL CONSTRUCTION 2016HOUSING 56,869 $10,008,944 $176.00 NEUMANN/SMITH

FACILITIES INFORMATION SERVICES 1

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1800 1855 PLACE COMPLEX

1809 1855 PLACE-BUILDING 1809

ORIGINAL CONSTRUCTION 2016HOUSING 56,864 $10,008,240 $176.00 NEUMANN/SMITH

1810 1855 PLACE-BUILDING 1810

ORIGINAL CONSTRUCTION 2016HOUSING 56,865 $10,008,240 $176.00 NEUMANN/SMITH

COMPLEX TOTALS $93,210,822545,986

0165 ABRAMS PLANETARIUM

0165 ABRAMS PLANETARIUM

ORIGINAL CONSTRUCTION 1963ACADEMIC 17,465 $297,957 $17.00 CALDER

0402 AG EXPO EXHIBITORS COMPLEX

0402 AG EXPO EXHIB-STORAGE 1 EAST

ORIGINAL CONSTRUCTION 1988FARMS 2,572 $21,903 $9.00 LAND MGMT

0402A AG EXPO EXHIB-WICK 1-SOUTH MAROON

ORIGINAL CONSTRUCTION 1995FARMS 4,275 $102,600 $24.00 LAND MGMT

0402C AG EXPO EXHIB-MORTON-PROP SHOP

ORIGINAL CONSTRUCTION 2016FARMS 991 $0 $0.00

0402D AG EXPO EXHIB-STORAGE 2-WEST

ORIGINAL CONSTRUCTION 1998FARMS 2,490 $65,530 $26.00 PHYSICAL PLANT

0402I AG EXPO EXHIB-WICK 2-NORTH WHITE

ORIGINAL CONSTRUCTION 2009OTHER 1,408 $40,832 $29.00 LANDMANAGEMENT

COMPLEX TOTALS $230,86511,736

FACILITIES INFORMATION SERVICES 2

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0091 AGRICULTURE ENGINEERING COMPLEX

0091 FARRALL HALL

ORIGINAL CONSTRUCTION 1948ACADEMIC 72,985 $681,542 $9.00 MUNSON

1999ACADEMIC 3,634 $937,582 $258.00 PROGRESSIVEARCH

ADD 1 - ADDITION 1

76,619 $1,619,124

0091A FARRALL-PROTOTYPE ASSEMBLY

ORIGINAL CONSTRUCTION 1999ACADEMIC 5,009 $190,000 $38.00 PHYSICAL PLANT

COMPLEX TOTALS $1,809,12481,628

0401 AKERS GOLF COURSE COMPLEX

0401A AKERS GOLF-CART SHELTER-WEST

ORIGINAL CONSTRUCTION 1979ATHLETICS 2,151 $42,537 $20.00 PHYSICAL PLANT

1988ATHLETICS 1,229 $56,100 $46.00 PHYSICAL PLANTADD 1 - ADDITION 1

3,380 $98,637

0401B AKERS GOLF-MAINTENANCE-EAST

ORIGINAL CONSTRUCTION 1967ATHLETICS 3,192 $22,250 $7.00 PHYSICAL PLANT

1976ATHLETICS 793 $12,750 $16.00 PHYSICAL PLANTADD 1 - ADDITION 1

3,985 $35,000

0401C AKERS GOLF-MAINTENANCE-WEST

ORIGINAL CONSTRUCTION 1956ATHLETICS 4,812 $28,300 $6.00 PHYSICAL PLANT

0401E AKERS GOLF-MANAGERS HSE-WEST

ORIGINAL CONSTRUCTION 1957ATHLETICS 2,630 $120,441 $46.00

0401J AKERS GOLF-RESTROOM 1-EAST

ORIGINAL CONSTRUCTION 1979ATHLETICS 298 $16,870 $57.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 3

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0401 AKERS GOLF COURSE COMPLEX

0401L AKERS GOLF-SNACK BAR-WEST

ORIGINAL CONSTRUCTION 1987ATHLETICS 241 $43,850 $182.00 PHYSICAL PLANT

0401M AKERS GOLF-SOIL STRG-EAST

ORIGINAL CONSTRUCTION 1988ACADEMIC 2,400 $22,421 $9.00 PHYSICAL PLANT

1992ACADEMIC 1,600 $13,265 $8.00 WING CONSTADD 1 - ADDITION 1

1998ACADEMIC 3,569 $15,789 $4.00ADD 2 - ADDITION 2

7,569 $51,475

0401N AKERS GOLF-STARTER-EAST

ORIGINAL CONSTRUCTION 1989ATHLETICS 61 $27,340 $448.00 PHYSICAL PLANT

0401P AKERS GOLF-DRIVING RANGE-WEST

ORIGINAL CONSTRUCTION 1990ATHLETICS 282 $23,500 $83.00 PHYSICAL PLANT

0401Q AKERS GOLF-SNACK BAR-EAST

ORIGINAL CONSTRUCTION 1993ATHLETICS 337 $27,705 $82.00 PHYSICAL PLANT

0401S AKERS GOLF-SHELTER 5-EAST

ORIGINAL CONSTRUCTION 1960ATHLETICS 144 $6,500 $45.00

0401T AKERS GOLF-STARTER 1-EAST

ORIGINAL CONSTRUCTION 1996ATHLETICS 4,259 $131,801 $31.00 PHYSICAL PLANT

0401U AKERS GOLF-CART-WEST

ORIGINAL CONSTRUCTION 2001ATHLETICS 3,660 $74,000 $20.00 PHYSICAL PLANT

0401V AKERS GOLF-DRIVING RANGE ENCL

ORIGINAL CONSTRUCTION 2009ATHLETICS 6,693 $472,809 $71.00 MAYOTTE JACOBS

0401W AKERS GOLF-EQUIPMENT STRG-WEST

ORIGINAL CONSTRUCTION 2011ATHLETICS 2,579 $55,000 $21.00

FACILITIES INFORMATION SERVICES 4

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0401 AKERS GOLF COURSE COMPLEX

0401X AKERS GOLF-CART SHELTER-WEST

ORIGINAL CONSTRUCTION 1995ATHLETICS 164 $0 $0.00

0401Y AKERS GOLF-INTERCOLLEGIATE GOLF

ORIGINAL CONSTRUCTION 2015ATHLETICS 15,533 $4,522,000 $291.00 TMP

0401Z AKERS GOLF-RESTROOM 2-EAST

ORIGINAL CONSTRUCTION 2014ATHLETICS 203 $75,570 $373.00 ROMTEC

COMPLEX TOTALS $5,810,79856,830

0326 AKERS HALL

0326 AKERS HALL

ORIGINAL CONSTRUCTION 1964HOUSING 385,797 $4,780,121 $12.00 CALDER

0030 ALUMNI CHAPEL

0030 ALUMNI CHAPEL

ORIGINAL CONSTRUCTION 1952SUPPORT 8,678 $230,545 $27.00 CALDER

0133 ANGELL UNIV SERVICES

0133 ANGELL UNIV SERVICES

ORIGINAL CONSTRUCTION 1988SUPPORT 75,441 $3,641,879 $48.00 MARGERUM

1998SUPPORT 753 $76,460 $102.00 PHYSICAL PLANTADD 1 - ADDITION 1 GAS STORAGE

2001SUPPORT 6,352 $380,496 $60.00 FTC & HADD 2 - ADDITION 2 STORAGE

82,546 $4,098,835

COMPLEX TOTALS $4,098,83582,546

FACILITIES INFORMATION SERVICES 5

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0132 ANTHONY HALL COMPLEX

0132 ANTHONY HALL

ORIGINAL CONSTRUCTION 1955ACADEMIC 226,275 $3,870,380 $17.00 MUNSON

1964ACADEMIC 895 $9,477 $11.00 PHYSICAL PLANTADD 1 - ADDITION 1

1997ACADEMIC 92,584 $8,812,379 $95.00 BEI ASSOCIATESADD 2 - ADDITION 2

319,754 $12,692,236

0132A ANTHONY-COOLING TOWER

ORIGINAL CONSTRUCTION 19970 $0 $0.00 BEI ASSOCIATES

COMPLEX TOTALS $12,692,236319,754

0031 AUDITORIUM

0031 AUDITORIUM

ORIGINAL CONSTRUCTION 1940ACADEMIC 161,113 $1,025,000 $6.00 MUNSON

0182 BAKER HALL

0182 BAKER HALL

ORIGINAL CONSTRUCTION 1967ACADEMIC 60,298 $1,647,464 $27.00 EBERLE SMITH

0517 BEAL GARDEN-GAZEBO

0517 BEAL GARDEN-GAZEBO

ORIGINAL CONSTRUCTION 1989SUPPORT 110 $1,703 $15.00

0518 BEAL GARDEN-SHED

0518 BEAL GARDEN-SHED

ORIGINAL CONSTRUCTION 1960SUPPORT 315 $6,590 $21.00

0012 BEAUMONT TOWER

0012 BEAUMONT TOWER

FACILITIES INFORMATION SERVICES 6

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0012 BEAUMONT TOWER

0012 BEAUMONT TOWER

ORIGINAL CONSTRUCTION 1928ACADEMIC 2,536 $110,437 $44.00 DONALDSON-MEIER

0471 BEEF CATTLE RESEARCH CENTER COMPLEX

0471A BEEF CATTLE RESEARCH-MAIN

ORIGINAL CONSTRUCTION 1963FARMS 15,378 $230,277 $15.00 FRANK AND STEIN

1968FARMS 3,943 $9,500 $2.00ADD 1 - ADDITION 1 ISOLATION BARN

1972FARMS 1,007 $9,060 $9.00ADD 3 - ADDITION 3 FEEDWAY

2006FARMS 34,881 $0 $0.00 FARMSADD 4 - ADDITION 4 MAIN BLDG

55,209 $248,837

0471E BEEF CATTLE RESEARCH-GLASS SILOS

ORIGINAL CONSTRUCTION 19710 $0 $0.00

0471H BEEF CATTLE RESEARCH-BUNKER SILO

ORIGINAL CONSTRUCTION 19630 $0 $0.00

0471I BEEF CATTLE RESEARCH-ANIMAL SHLTR

ORIGINAL CONSTRUCTION 1981FARMS 14,490 $147,247 $10.00 PHYSICAL PLANT

0471K BEEF CATTLE RESEARCH-HAY STRG

ORIGINAL CONSTRUCTION 1990FARMS 10,468 $64,161 $6.00 WHITEFORDASSOC

0471N BEEF CATTLE RESEARCH-HANDLING

ORIGINAL CONSTRUCTION 1996FARMS 1,635 $686,452 $420.00 CAPITALCONSULTANTS

COMPLEX TOTALS $1,146,69781,802

0480 BEEF CATTLE-STUDENT HOUSING

0480 BEEF CATTLE-STUDENT HOUSING

FACILITIES INFORMATION SERVICES 7

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0480 BEEF CATTLE-STUDENT HOUSING

0480 BEEF CATTLE-STUDENT HOUSING

ORIGINAL CONSTRUCTION 1998FARMS 1,000 $84,350 $84.00 PHYSICAL PLANT

0002 BERKEY HALL

0002 BERKEY HALL

ORIGINAL CONSTRUCTION 1947ACADEMIC 152,169 $1,177,019 $8.00 MUNSON

0079 BESSEY HALL

0079 BESSEY HALL

ORIGINAL CONSTRUCTION 1961ACADEMIC 137,398 $2,201,200 $16.00 CALDER

1994ACADEMIC 13,265 $3,039,255 $229.00 MCNAMEE,PORTER,SEELY

ADD 1 - ADDITION 1

150,663 $5,240,455

COMPLEX TOTALS $5,240,455150,663

0233 BIO ENGINEERING

0233 BIO ENGINEERING

ORIGINAL CONSTRUCTION 2015ACADEMIC 131,197 $52,229,589 $398.00 INTEGRATEDDESIGN

0168 BIOCHEMISTRY

0168 BIOCHEMISTRY

ORIGINAL CONSTRUCTION 1964ACADEMIC 157,744 $4,235,641 $27.00 HARLEY-ELLINGTON

0160 BIOMEDICAL PHYSICAL SCIENCES

0160 BIOMEDICAL PHYSICAL SCIENCES

ORIGINAL CONSTRUCTION 2001ACADEMIC 377,230 $78,164,009 $207.00 SMITH HINCHMANGRYLL

0452 BOTANY FIELD LAB COMPLEX

0452 BOTANY FIELD LAB

FACILITIES INFORMATION SERVICES 8

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0452 BOTANY FIELD LAB COMPLEX

0452 BOTANY FIELD LAB

ORIGINAL CONSTRUCTION 1969FARMS 12,442 $57,205 $5.00 PHYSICAL PLANT

0452A BOTANY FIELD LAB-PESTICIDE STRG

ORIGINAL CONSTRUCTION 2001FARMS 2,560 $80,000 $31.00 PHYSICAL PLANT

2006FARMS 960 $30,000 $31.00 DESIGN & BUILDADD 1 - ADDITION 1

3,520 $110,000

COMPLEX TOTALS $167,20515,962

0443 BOTANY FIELD RESEARCH COMPLEX

0443B BOTANY QUONSET STORAGE 1

ORIGINAL CONSTRUCTION 1949FARMS 2,157 $16,800 $8.00 KUTCHINS

0477 BOX FARM COMPLEX

0477A BOX FARM-HOUSE

ORIGINAL CONSTRUCTION 1982FARMS 2,878 $197,823 $69.00

0477B BOX FARM-GARAGE

ORIGINAL CONSTRUCTION 1982FARMS 625 $8,922 $14.00

0477C BOX FARM-BARN

ORIGINAL CONSTRUCTION 1982FARMS 1,424 $21,808 $15.00

COMPLEX TOTALS $228,5534,927

0069 BRESLIN

0069 BRESLIN

FACILITIES INFORMATION SERVICES 9

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0069 BRESLIN

0069 BRESLIN

ORIGINAL CONSTRUCTION 1989ACADEMIC 243,612 $37,475,716 $154.00 GIFFELS/HOYEMBASSO

2001ACADEMIC 29,915 $5,494,374 $184.00 IDS, INC.ADD 1 - ADDITION 1 BERKOWITZ

2017ACADEMIC 55,502 $34,353,276 $619.00 ROSSETTIADD 2 - ADDITION 2

2015ACADEMIC 899 $50,000 $56.00 IDSADD 3 - ADDITION 3 CANOPIES

329,928 $77,373,366

COMPLEX TOTALS $77,373,366329,928

0228 BROAD ART MUSEUM

0228 BROAD ART MUSEUM

ORIGINAL CONSTRUCTION 2012ACADEMIC 46,237 $28,936,136 $626.00 ZAHA HADIDARCHITECT

0300 BRODY COMPLEX

0310 BUTTERFIELD HALL

ORIGINAL CONSTRUCTION 1954HOUSING 99,743 $1,537,421 $15.00 CALDER

1962HOUSING 690 $26,138 $38.00 CALDERADD 1 - ADDITION 1

2014HOUSING 3,842 $914,396 $238.00 DESIGN PLUSADD 2 - ADDITION 2

104,275 $2,477,955

0311 RATHER HALL

ORIGINAL CONSTRUCTION 1954HOUSING 112,327 $1,572,656 $14.00 CALDER

2013HOUSING 5,082 $1,209,278 $238.00 SHW GROUPADD 2 - ADDITION 2 - PENTHOUSE

117,409 $2,781,934

0312 BRYAN HALL

ORIGINAL CONSTRUCTION 1954HOUSING 112,607 $1,652,730 $15.00 CALDER

FACILITIES INFORMATION SERVICES 10

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0300 BRODY COMPLEX

0312 BRYAN HALL

2013HOUSING 5,230 $1,244,502 $238.00 SHW GROUPADD 1 - ADDITION NO. 1

117,837 $2,897,232

0313 BRODY HALL

ORIGINAL CONSTRUCTION 1954HOUSING 99,252 $1,619,099 $16.00 CALDER

1955HOUSING 32,962 $1,479,636 $45.00 CALDERADD 1 - ADDITION 1

2011HOUSING 33,832 $8,052,254 $238.00 DESIGN PLUSADD 3 - ADDITION 3

166,046 $11,150,989

0314 EMMONS HALL

ORIGINAL CONSTRUCTION 1955HOUSING 109,591 $1,475,787 $13.00 CALDER

2011HOUSING 3,487 $490,994 $141.00 DESIGN PLUSADD 1 - ADDITION 1

113,078 $1,966,781

0315 BAILEY HALL

ORIGINAL CONSTRUCTION 1955HOUSING 110,247 $1,509,607 $14.00 CALDER

2012HOUSING 5,133 $1,221,654 $238.00 SHW GROUPADD 1 - ADDITION NO. 1 PENTHOUSE

115,380 $2,731,261

0315A BAILEY-GREENHOUSE

ORIGINAL CONSTRUCTION 2012HOUSING 2,145 $82,021 $38.00 PHYSICAL PLANT

0316 ARMSTRONG HALL

ORIGINAL CONSTRUCTION 1955HOUSING 112,927 $1,586,470 $14.00 CALDER

2013HOUSING 5,188 $1,234,744 $238.00 SHW GROUPADD 1 - ADDITION NO. 1

118,115 $2,821,214

FACILITIES INFORMATION SERVICES 11

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0300 BRODY COMPLEX

COMPLEX TOTALS $26,909,387854,285

0080 BUSINESS COLLEGE

0080 BUSINESS COLLEGE

ORIGINAL CONSTRUCTION 1961ACADEMIC 58,199 $1,381,866 $24.00 CALDER

1993ACADEMIC 125,114 $14,400,000 $115.00 HEPYADD 1 - ADDITION 1 ELI BROAD

2019ACADEMIC 104,593 $48,245,371 $461.00 FTC&HADD 2 - ADDITION 2- GRADUATEPAVILION

287,906 $64,027,237

COMPLEX TOTALS $64,027,237287,906

0617 CANDLEWOOD SUITES

0617 CANDLEWOOD SUITES

ORIGINAL CONSTRUCTION 2001OTHER 63,675 $4,500,000 $71.00 DORCHEN/MARTINASSOC

0321 CASE HALL

0321 CASE HALL

ORIGINAL CONSTRUCTION 1961HOUSING 284,312 $3,862,270 $14.00 SARVIS

2008HOUSING 2,006 $416,120 $207.00 FTCHADD 2 - ADDITION 2 - LOADING DOCK

2012HOUSING 16,189 $14,402,008 $890.00 SMITH GROUPADD 3 - ADDITION 3

302,507 $18,680,398

COMPLEX TOTALS $18,680,398302,507

FACILITIES INFORMATION SERVICES 12

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0181A CENTER INTEGRATIVE PLANT SYS-LAB

0181A CENTER INTEGRATIVE PLANT SYS-LAB

ORIGINAL CONSTRUCTION 1967ACADEMIC 37,530 $537,936 $14.00 KINGSCOTT

1969ACADEMIC 38,776 $1,337,533 $34.00 KINGSCOTTADD 1 - ADDITION 1 HEADHOUSE

2002ACADEMIC 13,108 $791,650 $60.00 PHYSICAL PLANTADD 2 - ADDITION 2POLYGREENHOUSE

2004ACADEMIC 8,150 $115,470 $14.00 PHYSICAL PLANTADD 3 - ADDITION 3POLYGREENHOUSE

97,564 $2,782,589

COMPLEX TOTALS $2,782,58997,564

0204 CENTRAL SCHOOL COMPLEX

0204 CENTRAL SCHOOL

ORIGINAL CONSTRUCTION 1916ACADEMIC 22,225 $92,827 $4.00 BOWD

1988ACADEMIC 2,014 $151,041 $75.00 WBDCADD 1 - ADDITION 1

24,239 $243,868

0204A CENTRAL SCHOOL-SHED

ORIGINAL CONSTRUCTION 1987OTHER 387 $3,500 $9.00 CAMPUS PARKPLANNING

COMPLEX TOTALS $247,36824,626

0060 CENTRAL SERVICES

0060 CENTRAL SERVICES

ORIGINAL CONSTRUCTION 1948SUPPORT 49,022 $504,839 $10.00 MUNSON

1952SUPPORT 9,598 $171,000 $18.00 MUNSONADD 1 - ADDITION 1

1956SUPPORT 11,415 $129,644 $11.00 MUNSONADD 2 - ADDITION 2

FACILITIES INFORMATION SERVICES 13

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0060 CENTRAL SERVICES

0060 CENTRAL SERVICES

70,035 $805,483

COMPLEX TOTALS $805,48370,035

0475 CHEMICAL WASTE FACILITY COMPLEX

0475A CHEMICAL WASTE FACILITY 1

ORIGINAL CONSTRUCTION 1981SUPPORT 1,537 $95,843 $62.00 PHYSICAL PLANT

2003SUPPORT 557 $65,000 $117.00 LEDY DESIGNGROUP

ADD 1 - ADDITION NO 1

2,094 $160,843

0475B CHEMICAL WASTE FACILITY 2

ORIGINAL CONSTRUCTION 1972SUPPORT 1,506 $44,637 $30.00 PHYSICAL PLANT

1989SUPPORT 3,120 $70,000 $22.00 PHYSICAL PLANTADD 1 - ADDITION 1

2013SUPPORT 480 $0 $0.00 IPFADD 2 - ADDITION 2 GARAGE

5,106 $114,637

0475C CHEMICAL WASTE CONT STRG

ORIGINAL CONSTRUCTION 1984SUPPORT 901 $33,411 $37.00 ARCHCONSORTIUM

2013SUPPORT 211 $37,330 $177.00 PHYSICAL PLANTADD 1 - ADDITION NO. 1-CONNECTORWING

1,112 $70,741

COMPLEX TOTALS $346,2218,312

0163 CHEMISTRY

0163 CHEMISTRY

FACILITIES INFORMATION SERVICES 14

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0163 CHEMISTRY

0163 CHEMISTRY

ORIGINAL CONSTRUCTION 1963ACADEMIC 282,368 $5,811,392 $21.00 CALDER

1997ACADEMIC 2,893 $272,000 $94.00 ORIONADD 1 - ADDITION 1 SUBSTATION

2008ACADEMIC 32,034 $16,007,470 $500.00 FTC & HADD 2 - ADDITION 2

317,295 $22,090,862

COMPLEX TOTALS $22,090,862317,295

0612 CHILDREN'S GARDEN COMPLEX

0612 CHILDREN'S GARDEN-SUPPORT STRUCT

ORIGINAL CONSTRUCTION 2001ACADEMIC 1,515 $21,630 $14.00 PHYSICAL PLANT

2009ACADEMIC 243 $25,000 $103.00 PHYSICAL PLANTADD 1 - ADDITION 1 COVERED PATIO

1,758 $46,630

0612A CHILDREN'S GARDEN-GARDEN HOUSE

ORIGINAL CONSTRUCTION 1992OTHER 246 $3,379 $14.00 PHYSICAL PLANT

0612B CHILDREN'S GARDEN-RESTROOM

ORIGINAL CONSTRUCTION 2015ACADEMIC 304 $237,669 $781.00 WTA ARCHITECTS

COMPLEX TOTALS $287,6782,308

0019 CHITTENDEN HALL

0019 CHITTENDEN HALL

ORIGINAL CONSTRUCTION 1901ACADEMIC 16,809 $15,000 $1.00 GEORGE LOHMAN

FACILITIES INFORMATION SERVICES 15

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0202 CLINICAL CENTER-ANIMAL

0202 CLINICAL CENTER-ANIMAL

ORIGINAL CONSTRUCTION 1976ACADEMIC 43,941 $2,170,582 $49.00 CALDER

2014ACADEMIC 1,367 $619,720 $453.00 PETER BASSOADD 1 - ADDITION 1

45,308 $2,790,302

COMPLEX TOTALS $2,790,30245,308

0200 CLINICAL CENTER-CLINIC

0200 CLINICAL CENTER-CLINIC

ORIGINAL CONSTRUCTION 1976ACADEMIC 182,756 $8,593,874 $47.00 CALDER

1985ACADEMIC 4,987 $2,200,000 $441.00 TORKE/MASLOWSKI

ADD 1 - ADDITION 1 M.R.C.

1988ACADEMIC 8,586 $4,450,000 $518.00 THRESHOLD/GEADD 2 - ADDITION 2 M.R.C.

2003ACADEMIC 18,333 $5,030,131 $274.00 H & H SYSTEMS &DES

ADD 3 - ADDITION 3RADIOPHARMACEUTICAL

214,662 $20,274,005

COMPLEX TOTALS $20,274,005214,662

0201 CLINICAL CENTER-OFFICE/LAB

0201 CLINICAL CENTER-OFFICE/LAB

ORIGINAL CONSTRUCTION 1976ACADEMIC 77,530 $3,415,544 $44.00 CALDER

0592 COMM STRG 1 SPARTAN VILLAGE

0592 COMM STRG 1 SPARTAN VILLAGE

ORIGINAL CONSTRUCTION 2001SUPPORT 119 $15,000 $126.00 LEDY DESIGNGROUP

FACILITIES INFORMATION SERVICES 16

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0593 COMM STRG 2 SPARTAN VILLAGE

0593 COMM STRG 2 SPARTAN VILLAGE

ORIGINAL CONSTRUCTION 2001SUPPORT 59 $15,000 $254.00 LEDY DESIGNGROUP

0613 COMM STRG-SOUTH CAMPUS

0613 COMM STRG-SOUTH CAMPUS

ORIGINAL CONSTRUCTION 2001SUPPORT 319 $58,000 $182.00 PHYSICAL PLANT

0610 COMM STRG-UNIV VILLAGE

0610 COMM STRG-UNIV VILLAGE

ORIGINAL CONSTRUCTION 2000SUPPORT 341 $55,000 $161.00 PHYSICAL PLANT

0084 COMMUNICATION ARTS COMPLEX

0084 COMMUNICATION ARTS

ORIGINAL CONSTRUCTION 1981ACADEMIC 248,215 $17,760,432 $72.00 HARLEY-ELLINGTON

0084A COMMUNICATION ARTS - MITN STORAGE

ORIGINAL CONSTRUCTION 1990ACADEMIC 240 $48,723 $203.00 GILLETTASSOCIATION

0084B COMMUNICATION ARTS - COOLING TOWER

ORIGINAL CONSTRUCTION 1981ACADEMIC 0 $0 $0.00 HARLEY-ELLINGTON

0084C COMMUNICATION ARTS - UPLINK SHELTER

ORIGINAL CONSTRUCTION 2014ACADEMIC 51 $0 $0.00

COMPLEX TOTALS $17,809,155248,506

0615 COMPOSTING FACILITY SOUTH CAMPUS

0615 COMPOSTING FACILITY SOUTH CAMPUS

ORIGINAL CONSTRUCTION 2002FARMS 13,598 $79,591 $6.00 FTC & H

2006FARMS 27,957 $545,000 $19.00ADD 1 - ADDITION NO. 1 - LEAN TO

FACILITIES INFORMATION SERVICES 17

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0615 COMPOSTING FACILITY SOUTH CAMPUS

0615 COMPOSTING FACILITY SOUTH CAMPUS

41,555 $624,591

COMPLEX TOTALS $624,59141,555

0035 COMPUTER CENTER

0035 COMPUTER CENTER

ORIGINAL CONSTRUCTION 1948ACADEMIC 78,933 $1,058,644 $13.00 MUNSON

0328 CONRAD HALL

0328 CONRAD HALL

ORIGINAL CONSTRUCTION 1964ACADEMIC 23,096 $455,510 $20.00 CALDER

0020 COOK-SEEVERS HALL

0020 COOK-SEEVERS HALL

ORIGINAL CONSTRUCTION 1889ACADEMIC 11,534 $7,500 $1.00 S. JOHNSON

2018ACADEMIC 3,061 $2,961,079 $967.00 HOPKINSBURNSDESIGN

ADD 1 - ADDITION NO. 1

14,595 $2,968,579

COMPLEX TOTALS $2,968,57914,595

0009 COWLES HOUSE

0009 COWLES HOUSE

ORIGINAL CONSTRUCTION 1857SUPPORT 5,405 $0 $0.00 J. J. SCOTT

1950SUPPORT 10,540 $112,577 $11.00 CALDERADD 1 - ADDITION 1

2000SUPPORT 965 $105,628 $109.00 PHYSICAL PLANTADD 2 - ADDITION 2 - PORCHENCLOSURE

FACILITIES INFORMATION SERVICES 18

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0009 COWLES HOUSE

0009 COWLES HOUSE

2020SUPPORT 1,267 $4,075,384 $3,217.00 HOPKINSBURNSDESIGN

ADD 3 - ADDITION 3 - EXPANDGARAGE

18,177 $4,293,589

COMPLEX TOTALS $4,293,58918,177

0614 CREW MEN & WOMEN BOATHOUSE COMPLEX

0614A CREW WOMEN'S BOATHOUSE

ORIGINAL CONSTRUCTION 20028,821 $261,000 $30.00 FREEMAN & SMITH

0614B CREW MEN'S BOATHOUSE

ORIGINAL CONSTRUCTION 20024,951 $152,250 $31.00 FREEMAN SMITH

COMPLEX TOTALS $413,25013,772

0442 CROP SCIENCE COMPLEX

0213 CROP SCIENCE-FIELD LAB

ORIGINAL CONSTRUCTION 1954FARMS 12,393 $67,640 $5.00 MUNSON

1996FARMS 37,470 $2,339,020 $62.00 SIMS-VARNERADD 1 - CROP SCI FIELD LAB

2015FARMS 3,246 $118,037 $36.00 ORASKOADD 2 - GREENHOUSE

53,109 $2,524,697

0442E CROP SCIENCE-STRG 1

ORIGINAL CONSTRUCTION 1985FARMS 16,266 $104,100 $6.00 PHYSICAL PLANT

0442F CROP SCIENCE-PESTICIDE/HERBICIDE

ORIGINAL CONSTRUCTION 1992FARMS 3,222 $138,000 $43.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 19

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0442 CROP SCIENCE COMPLEX

0442G CROP SCIENCE-RESEARCH

ORIGINAL CONSTRUCTION 1992FARMS 1,406 $60,678 $43.00 PHYSICAL PLANT

0442J CROP SCIENCE-FERTILIZER STORAGE

ORIGINAL CONSTRUCTION 2011FARMS 2,414 $78,000 $32.00

0442K CROP SCIENCE-STRG 2

ORIGINAL CONSTRUCTION 2015FARMS 14,121 $199,840 $14.00 TAILORED

COMPLEX TOTALS $3,105,31590,538

0469 DAIRY CATTLE TEACHING & RES COMPLEX

0469A DAIRY RESEARCH-HEIFER BARN 1

ORIGINAL CONSTRUCTION 1961FARMS 7,272 $39,233 $5.00 J.W. OLDS

0469F DAIRY RESEARCH-FOREMAN'S HSE

ORIGINAL CONSTRUCTION 1961FARMS 3,852 $232,332 $60.00 J.W. OLDS

0469H DAIRY RESEARCH-MAIN BARN

ORIGINAL CONSTRUCTION 1961FARMS 24,819 $148,991 $6.00 J W OLDS

1970FARMS 3,781 $78,400 $21.00 PHYSICAL PLANTADD 1 - ADDITION 1 MILKING PARLOR

1984FARMS 21,461 $590,843 $28.00 PHYSICAL PLANTADD 2 - ADDITION 2 DAIRY BARN

1996FARMS 3,717 $362,741 $98.00 CAPITALCONSULTANTS

ADD 3 - ADDITION 3 INTENSIVEMETABOLIS

53,778 $1,180,975

0469L DAIRY RESEARCH-SWITCH GEAR

ORIGINAL CONSTRUCTION 1983FARMS 64 $4,837 $76.00 PHYSICAL PLANT

0469O DAIRY RESEARCH-SOUTH HAY BARN

ORIGINAL CONSTRUCTION 1987FARMS 13,420 $89,700 $7.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 20

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0469 DAIRY CATTLE TEACHING & RES COMPLEX

0469P DAIRY RESEARCH-HEIFER BARN 2

ORIGINAL CONSTRUCTION 1988FARMS 10,503 $272,850 $26.00 PHYSICAL PLANT

0469Q DAIRY RESEARCH-CONCRETE SILOS

ORIGINAL CONSTRUCTION 1979FARMS 0 $0 $0.00

COMPLEX TOTALS $1,819,92788,889

0469T DAIRY RESEARCH - HOOP HOUSE

0469T DAIRY RESEARCH - HOOP HOUSE

ORIGINAL CONSTRUCTION 2022FARMS 0 $0 $0.00 LANDMANAGEMENT

0244 DATA CENTER

0244 DATA CENTER

ORIGINAL CONSTRUCTION 2017SUPPORT 25,505 $24,497,008 $960.00 CH2M HILL ENG INC

0224 DEMMER SHOOTING SPORTS EDUC COMPLEX

0224 DEMMER SPORTS EDUCATION

ORIGINAL CONSTRUCTION 2009ATHLETICS 25,776 $3,500,000 $136.00 DESIGN BUILD

0224A DEMMER SPORTS EDUCATION-STRG

ORIGINAL CONSTRUCTION 2009ATHLETICS 1,082 $50,000 $46.00 DESIGN BUILD

COMPLEX TOTALS $3,550,00026,858

0057 DEMONSTRATION HALL

0057 DEMONSTRATION HALL

ORIGINAL CONSTRUCTION 1928ACADEMIC 90,353 $355,000 $4.00 BOWD-MUNSON

FACILITIES INFORMATION SERVICES 21

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0057 DEMONSTRATION HALL

0057 DEMONSTRATION HALL

1948ACADEMIC 5,855 $0 $0.00ADD 1 - ADDITION NO. 1

96,208 $355,000

COMPLEX TOTALS $355,00096,208

0601 DOBIE TOWER TV & FM TRANSMITTING

0601 DOBIE TOWER TV/FM TRANS

ORIGINAL CONSTRUCTION 1954ACADEMIC 2,214 $28,447 $13.00 MUNSON

1973ACADEMIC 358 $18,630 $52.00 PHYSICAL PLANTADD 1 - ADDITION 1

1993ACADEMIC 599 $119,640 $200.00 FISHBECKADD 2 - ADDITION 2

3,171 $166,717

0601A DOBIE TOWER TV/FM TRANS-TOWER

ORIGINAL CONSTRUCTION 20120 $1,041,263 $0.00 KPFF CONSULTINGENG

COMPLEX TOTALS $1,207,9803,171

0077 DUFFY DAUGHTERY-SAAC COMPLEX

0077 DUFFY DAUGHERTY-SAAC

ORIGINAL CONSTRUCTION 1980ATHLETICS 14,189 $1,429,925 $101.00 WAKELY-KUSHNERASSOC

1985ATHLETICS 98,539 $2,807,141 $28.00 SIMS-VARNER &ASSOC

ADD 1 - ADDITION 1 FOOTBALLPRACTICE

1997ATHLETICS 21,094 $4,597,172 $218.00 GHAFARI ASSOCADD 2 - ADDITION 2

1998ATHLETICS 40,201 $5,669,343 $141.00 GHAFARI ASSOCADD 3 - ADDITION 3 STUDENT A.A.C

2008ATHLETICS 33,223 $8,961,769 $270.00 INTEGRATEDDESIGN

ADD 4 - ADDITION 4 SKANDALARIS

FACILITIES INFORMATION SERVICES 22

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0077 DUFFY DAUGHTERY-SAAC COMPLEX

0077 DUFFY DAUGHERTY-SAAC

2010ATHLETICS 190 $45,000 $237.00 INTEGRATEDDESIGN

ADD 5 - ADDITION 5

2015ATHLETICS 1,915 $715,306 $374.00 INTEGRATEDDESIGN

ADD 6 - ADDITION 6

2021ATHLETICS 1,355 $3,976,412 $2,934.00 GRANGERADD 7 - ADDITION 7

210,706 $28,202,068

0077A DUFFY DAUGHERTY-FILM TOWER

ORIGINAL CONSTRUCTION 2013ATHLETICS 610 $185,792 $305.00 FTC&H

COMPLEX TOTALS $28,387,860211,316

0470 ENDOCRINE RESEARCH CENTER COMPLEX

0470C ENDOCRINE RES-SURGERY

ORIGINAL CONSTRUCTION 1962FARMS 4,078 $22,687 $6.00 SUP ARCHITECT

0470D ENDOCRINE RES-SWINE

ORIGINAL CONSTRUCTION 1997FARMS 4,449 $400,000 $90.00 CAPITALCONSULTANTS

0470E MSU POLLINATOR PERFORMANCE CENTER

ORIGINAL CONSTRUCTION 2007FARMS 6,363 $700,000 $110.00 WEDEVENBROS/HAMILTN

2010FARMS 6,752 $198,000 $29.00 STEDFASTCONSTRUCTIO

ADD 1 - ADDITION 1

13,115 $898,000

0470G ENDOCRINE RES-ADREC

ORIGINAL CONSTRUCTION 2010FARMS 7,007 $696,260 $99.00 WILCOXPROFESSIONAL

0470H ENDOCRINE RES-ADREC CONTAINER

ORIGINAL CONSTRUCTION 2014FARMS 320 $250,000 $781.00

FACILITIES INFORMATION SERVICES 23

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0470 ENDOCRINE RESEARCH CENTER COMPLEX

COMPLEX TOTALS $2,266,94728,969

0081 ENGINEERING

0081 ENGINEERING

ORIGINAL CONSTRUCTION 1962ACADEMIC 177,895 $3,096,882 $17.00 GIFFELS-ROSSETTI

1962ACADEMIC 22,442 $391,282 $17.00 GIFFELS-ROSSETTIADD 1 - ADDITION 1

1989ACADEMIC 139,495 $12,700,000 $91.00 ALBERT KAHNASSOC

ADD 2 - ADDITION 2

1996ACADEMIC 85,252 $12,567,085 $147.00 ALBERT KAHNASSOC

ADD 3 - ADDITION 3

2008ACADEMIC 643 $529,122 $823.00 DLZADD 4 - ADDITION 4 - VESTIBULE

2016ACADEMIC 8,739 $3,030,508 $347.00 PETER BASSOADD 5 - ADDITION 5

434,466 $32,314,879

COMPLEX TOTALS $32,314,879434,466

0206 ENGINEERING RES JOLLY RD COMPLEX

0206 ENG RESEARCH-JOLLY RD

ORIGINAL CONSTRUCTION 1979ACADEMIC 10,215 $260,000 $25.00 DESIGN & BUILD

0206A ENG RESEARCH-JOLLY RD-CONC LAB

ORIGINAL CONSTRUCTION 2002ACADEMIC 11,710 $1,670,878 $143.00 HOBBS & BLACK

2007ACADEMIC 1,990 $363,532 $183.00 FTC & HADD 1 - ADDITION 1 FURNACEENCLOSURE

13,700 $2,034,410

0206B ENG RESEARCH-JOLLY RD-STRG

ORIGINAL CONSTRUCTION 2011FARMS 2,222 $51,000 $23.00

FACILITIES INFORMATION SERVICES 24

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0206 ENGINEERING RES JOLLY RD COMPLEX

COMPLEX TOTALS $2,345,41026,137

0203 ENGINEERING RESEARCH COMPLEX

0203A ENG RESEARCH COMPLEX

ORIGINAL CONSTRUCTION 1986ACADEMIC 81,802 $4,010,000 $49.00 PHYSICAL PLANT

2004ACADEMIC 8,364 $1,744,126 $209.00 FTC & HADD 1 - ADDITION 1 NMR

2007ACADEMIC 29,543 $5,407,011 $183.00 DLZADD 2 - ADDITION 2 ENERGY &AUTOMOT

2010ACADEMIC 2,847 $746,520 $262.00 DICLEMENTESIEGEL

ADD 3 - ADDITION 3 OFFICE ADDITION

2018ACADEMIC 5,494 $3,960,894 $721.00 C2AEADD 4 - ADDITION 4 FRAUNHOFERCENTER

128,050 $15,868,551

COMPLEX TOTALS $15,868,551128,050

0474 ENTOMOLOGY FIELD & RESEARCH COMPLEX

0474 ENTOMOLOGY FIELD RESEARCH-MAIN

ORIGINAL CONSTRUCTION 1966FARMS 8,034 $46,176 $6.00 PHYSICAL PLANT

0130 ENTOMOLOGY STORAGE

0130 ENTOMOLOGY STORAGE

ORIGINAL CONSTRUCTION 1965FARMS 648 $1,133 $2.00 PHYSICAL PLANT

0639 ENVIRO HEALTH AND SAFETY-RAD STRG

0639 ENVIRO HEALTH AND SAFETY-RAD STRG

ORIGINAL CONSTRUCTION 2012SUPPORT 1,647 $110,000 $67.00 LANDMANAGEMENT

FACILITIES INFORMATION SERVICES 25

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0144 ERICKSON HALL

0144 ERICKSON HALL

ORIGINAL CONSTRUCTION 1957ACADEMIC 209,364 $3,563,610 $17.00 CALDER

1974ACADEMIC 2,515 $770,000 $306.00 CALDERADD 2 - ADDITION 2

2006ACADEMIC 7,015 $1,587,193 $226.00 DESIGN PLUSADD 3 - ADDITION 3

2009ACADEMIC 355 $72,450 $204.00 DESIGN PLUSADD 4 - ADDITION 4

219,249 $5,993,253

COMPLEX TOTALS $5,993,253219,249

0015 EUSTACE-COLE HALL

0015 EUSTACE-COLE HALL

ORIGINAL CONSTRUCTION 1888ACADEMIC 9,864 $7,000 $1.00 WM. D. APPLEYARD

1998ACADEMIC 1,568 $1,339,353 $854.00 ARCHITECTS FOURADD 1 - ADDITION 1

11,432 $1,346,353

COMPLEX TOTALS $1,346,35311,432

0218 EXECUTIVE DEVELOPMENT

0218 EXECUTIVE DEVELOPMENT

ORIGINAL CONSTRUCTION 2001ACADEMIC 98,257 $21,250,000 $216.00 KEYSTONE DESIGN

0706 FACULTY APARTMENT SUBSTATION

0706 FACULTY APARTMENT SUBSTATION

ORIGINAL CONSTRUCTION 1985OTHER 1,094 $267,844 $245.00 PHYSICAL PLANT

2000OTHER 321 $49,000 $153.00 PHYSICAL PLANTADD 1 - ADDITION 1

FACILITIES INFORMATION SERVICES 26

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0706 FACULTY APARTMENT SUBSTATION

0706 FACULTY APARTMENT SUBSTATION

1,415 $316,844

COMPLEX TOTALS $316,8441,415

0327 FEE HALL

0327 FEE HALL

ORIGINAL CONSTRUCTION 1964ACADEMIC 386,485 $4,780,121 $12.00 CALDER

1972ACADEMIC 1,631 $50,000 $31.00 PHYSICAL PLANTADD 1 - ADDITION 1

388,116 $4,830,121

COMPLEX TOTALS $4,830,121388,116

0131 FIRE STATION

0131 FIRE STATION

ORIGINAL CONSTRUCTION 1955SUPPORT 8,334 $110,010 $13.00 MUNSON

1981SUPPORT 1,098 $121,632 $111.00 PHYSICAL PLANTADD 1 - ADDITION 1

9,432 $231,642

COMPLEX TOTALS $231,6429,432

0207 FOOD PROCESSING INNOVATION CENTER

0207 FOOD PROCESSING INNOVATION CENTER

ORIGINAL CONSTRUCTION 1971ACADEMIC 6,479 $426,000 $66.00 GRANGERCONSTRUCTION

FACILITIES INFORMATION SERVICES 27

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0207 FOOD PROCESSING INNOVATION CENTER

0207 FOOD PROCESSING INNOVATION CENTER

2018ACADEMIC 2,916 $2,734,066 $938.00 DAN VOSCONSTRUCTION

ADD 2 - ADDITION NO. 2

9,395 $3,160,066

COMPLEX TOTALS $3,160,0669,395

0186 FOOD SAFETY TOXICOLOGY

0186 FOOD SAFETY TOXICOLOGY

ORIGINAL CONSTRUCTION 1997ACADEMIC 115,133 $19,166,215 $166.00 HARLEYELLINGTON

0179 FOOD SCIENCE

0179 FOOD SCIENCE

ORIGINAL CONSTRUCTION 1966ACADEMIC 115,530 $3,442,532 $30.00 KAHN

2004ACADEMIC 4,571 $12,788,671 $2,798.00 PETER BASSOADD 1 - ADDITION 1 PENTHOUSE

120,101 $16,231,203

COMPLEX TOTALS $16,231,203120,101

0171 FOOD STORES

0171 FOOD STORES

ORIGINAL CONSTRUCTION 1964SUPPORT 81,230 $1,063,800 $13.00 MANSON,KANE,JACKSON

2006SUPPORT 12,227 $3,131,412 $256.00 DESIGN PLUSADD 1 - ADDITION 1 RELOCATEBAKERY

93,457 $4,195,212

FACILITIES INFORMATION SERVICES 28

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0171 FOOD STORES

COMPLEX TOTALS $4,195,21293,457

0164 FRIB COMPLEX

0164 FRIB

ORIGINAL CONSTRUCTION 1963ACADEMIC 31,263 $1,200,000 $38.00 KENNETH BLACKASSOC

1968ACADEMIC 17,225 $496,450 $29.00 KENNETH BLACKASSOC

ADD 1 - ADDITION 1

1978ACADEMIC 5,056 $318,076 $63.00 HOLMES ANDBLACK

ADD 2 - ADDITION 2 WEST HIGH BAY

1979ACADEMIC 0 $79,500 $0.00 PHYSICAL PLANTADD 3 - ADDITION 3

1982ACADEMIC 33,497 $5,150,000 $154.00 COMMONWEALTHASSOC

ADD 4 - ADDITION 4

1985ACADEMIC 0 $126,538 $0.00 N.S.C.L.ADD 5 - ADDITION 5

1988ACADEMIC 6,445 $1,544,700 $240.00 HEPYADD 6 - ADDITION 6

1996ACADEMIC 6,770 $1,028,295 $152.00 HEPYADD 7 - ADDITION 7 EAST HIGH BAY

1999ACADEMIC 6,624 $1,549,561 $234.00 HARLEYELLINGTON

ADD 8 - ADDITION 8 CRYOGENICEXPANSION

2003ACADEMIC 13,389 $2,955,560 $221.00 HARLEY ELLISADD 9 - ADDITION 9 OFFICE

2004ACADEMIC 14,811 $2,206,830 $149.00 HARLEY ELLISADD 10 - ADDITION 10 ASSEMBLY

2009ACADEMIC 26,802 $6,682,500 $249.00 HARLEY ELLISADD 11 - ADDITION 11 OFFICE

2009ACADEMIC 13,066 $2,628,800 $201.00 HARLEY ELLISADD 12 - ADDITION 12 LOW ENERGYRES

2011ACADEMIC 33,189 $8,132,170 $245.00 URSCORPORATION

ADD 14 - ADDITION 14 OFFICE

2011ACADEMIC 16,348 $2,675,035 $164.00 URSCORPORATION

ADD 15 - ADDITION 15 HIGH BAY

2016ACADEMIC 63,883 $23,753,826 $372.00 SMITH GROUPADD 16 - ADDITION 16 OFFICE

2015ACADEMIC 36,652 $15,500,000 $423.00 SMITH GROUPADD 17 - ADDITION 17 RADIO FREQHIGHBAY

2020ACADEMIC 22,219 $21,560,246 $970.00 BARTON MALOWADD 18 - ADDITION 18 HIGH RESSPECTROM

2019ACADEMIC 15,628 $10,300,123 $659.00 BARTON MALOWADD 19 - ADDITION 19 CRYOGENICASSEMBLY

FACILITIES INFORMATION SERVICES 29

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0164 FRIB COMPLEX

0164 FRIB

362,867 $107,888,210

COMPLEX TOTALS $107,888,210362,867

0522 GAS METER STATION

0522 GAS METER STATION

ORIGINAL CONSTRUCTION 1985SUPPORT 139 $180,087 $1,296.00 PHYSICAL PLANT

0176 GEOGRAPHY

0176 GEOGRAPHY

ORIGINAL CONSTRUCTION 1965ACADEMIC 31,221 $795,230 $25.00 CALDER

0028 GILTNER HALL

0028 GILTNER HALL

ORIGINAL CONSTRUCTION 1913ACADEMIC 13,440 $33,000 $2.00 BOWD

1931ACADEMIC 26,172 $110,165 $4.00 BOWD-MUNSONADD 1 - ADDITION 1 (ANATOMY & RES)

1938ACADEMIC 26,559 $120,938 $5.00 BOWD-MUNSONADD 2 - ADDITION 2 (NORTH WING OFVET)

1940ACADEMIC 13,938 $59,874 $4.00 BOWD-MUNSONADD 3 - ADDITION 3 (SOUTH WING OFVET)

1952ACADEMIC 170,824 $2,287,483 $13.00 MUNSONADD 5 - ADDITION 5 (VET & ANATOMY)

1968ACADEMIC 1,068 $118,168 $111.00 CALDERADD 6 - ADDITION 6 (TRANSFORMERROOM)

1994ACADEMIC 1,355 $387,589 $286.00 ORIONENGINEERING

ADD 7 - ADDITION 7 (ELECSUBSTATION)

253,356 $3,117,217

COMPLEX TOTALS $3,117,217253,356

FACILITIES INFORMATION SERVICES 30

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0476 HANCOCK TURFGRASS FIELD LAB COMPLEX

0476 HANCOCK TURFGRASS-FIELD LAB

ORIGINAL CONSTRUCTION 1980FARMS 7,530 $106,504 $14.00 PHYSICAL PLANT

0476B HANCOCK TURFGRASS-PESTICIDE STRG

ORIGINAL CONSTRUCTION 1985FARMS 326 $1,830 $6.00

0476C HANCOCK TURFGRASS-PUMP HSE

ORIGINAL CONSTRUCTION 1985FARMS 39 $593 $15.00

0476D HANCOCK TURFGRASS-COLD STRG

ORIGINAL CONSTRUCTION 1996FARMS 6,027 $113,434 $19.00 PHYSICAL PLANT

COMPLEX TOTALS $222,36113,922

0067 HANNAH ADMINISTRATION

0067 HANNAH ADMINISTRATION

ORIGINAL CONSTRUCTION 1968SUPPORT 170,216 $5,215,167 $31.00 CALDER

0332 HOLDEN HALL

0332 HOLDEN HALL

ORIGINAL CONSTRUCTION 1967HOUSING 357,199 $5,993,441 $17.00 CALDER

0330 HOLMES HALL

0330 HOLMES HALL

ORIGINAL CONSTRUCTION 1965HOUSING 399,755 $5,524,798 $14.00 CALDER

0456 HORSE RESEARCH CENTER COMPLEX

0456B HORSE RESEARCH-WEST HORSE BARN

ORIGINAL CONSTRUCTION 1946FARMS 13,484 $20,466 $2.00

0456D HORSE RESEARCH-STALLION BARN

FACILITIES INFORMATION SERVICES 31

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0456 HORSE RESEARCH CENTER COMPLEX

0456D HORSE RESEARCH-STALLION BARN

ORIGINAL CONSTRUCTION 1946FARMS 919 $13,630 $15.00

0456F HORSE RESEARCH-GARAGE IMPLEMNT SHED

ORIGINAL CONSTRUCTION 1946FARMS 867 $12,375 $14.00

0456I HORSE RESEARCH-WOODS HORSE BARN

ORIGINAL CONSTRUCTION 1983FARMS 1,259 $50,815 $40.00

0456L HORSE RESEARCH-TEACH RESEARCH BARN

ORIGINAL CONSTRUCTION 1984FARMS 3,871 $139,271 $36.00

0456M HORSE RESEARCH-STRG/EXERCISE

ORIGINAL CONSTRUCTION 1990FARMS 8,028 $74,693 $9.00 TAILORED BLDGSYS

0456N HORSE RESEARCH-ARENA

ORIGINAL CONSTRUCTION 1995FARMS 18,559 $540,000 $29.00 HOBBS & BLACK

0456O HORSE RESEARCH-BARN

ORIGINAL CONSTRUCTION 1995FARMS 10,570 $214,000 $20.00 HOBBS & BLACK

COMPLEX TOTALS $1,065,25057,557

0407 HORTICULTURE RESEARCH CENTR COMPLEX

0407A HORTICULTURE RES-HOUSE/OFFICE

ORIGINAL CONSTRUCTION 1966FARMS 3,002 $53,449 $18.00 MAYOTTE-WEBB

0407B HORTICULTURE RES-GARAGE

ORIGINAL CONSTRUCTION 1966FARMS 6,592 $111,279 $17.00 MAYOTTE-WEBB

0407C HORTICULTURE RES-EQUIP STRG

ORIGINAL CONSTRUCTION 1966FARMS 6,156 $21,950 $4.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 32

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0407 HORTICULTURE RESEARCH CENTR COMPLEX

0407D HORTICULTURE RES-STORAGE SHED

ORIGINAL CONSTRUCTION 1975FARMS 1,689 $26,021 $15.00

0407F HORTICULTURE RES-WINERY

ORIGINAL CONSTRUCTION 1989FARMS 4,275 $195,735 $46.00 MJK ARCH

0407G HORTICULTURE RES-LATH HSE

ORIGINAL CONSTRUCTION 1988FARMS 0 $2,500 $0.00 HORT RES CTR

0407H HORTICULTURE RES-PEST STOR & RES

ORIGINAL CONSTRUCTION 1997FARMS 3,434 $249,690 $73.00 PHYSICAL PLANT

0407I HORTICULTURE RES-GREENHOUSE

ORIGINAL CONSTRUCTION 1997FARMS 30,167 $384,892 $13.00 FTC & H

0407J HORTICULTURE RES-PROCESS SHELTER

ORIGINAL CONSTRUCTION 2007FARMS 976 $11,921 $12.00 WEDEVEN BROSHAMILTN

0407K HORTICULTURE RES-FERT STRG UNIT

ORIGINAL CONSTRUCTION 2015FARMS 130 $0 $0.00

0407L HORTICULTURE RES-IRRIGATION WELL

ORIGINAL CONSTRUCTION 2018FARMS 85 $9,700 $115.00 LANDMANAGEMENT

COMPLEX TOTALS $1,067,13756,506

0331 HUBBARD HALL

0331 HUBBARD HALL

ORIGINAL CONSTRUCTION 1966HOUSING 351,373 $5,785,328 $16.00 CALDER

0005 HUMAN ECOLOGY

0005 HUMAN ECOLOGY

FACILITIES INFORMATION SERVICES 33

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0005 HUMAN ECOLOGY

0005 HUMAN ECOLOGY

ORIGINAL CONSTRUCTION 1924ACADEMIC 67,373 $400,000 $6.00 BOWD

1937ACADEMIC 8,411 $16,177 $2.00 BOWD-MUNSONADD 1 - ADDITION 1

1980ACADEMIC 1,889 $171,521 $91.00 PHYSICAL PLANTADD 2 - ADDITION 2

1990ACADEMIC 786 $207,892 $264.00 CLARK TROMBLYADD 3 - ADDITION 3 - ELECTSUBSTATION

78,459 $795,590

COMPLEX TOTALS $795,59078,459

0051 IM SPORTS-CIRCLE

0051 IM SPORTS-CIRCLE

ORIGINAL CONSTRUCTION 1916ATHLETICS 72,965 $229,000 $3.00 BOWD

1958ATHLETICS 90,539 $2,305,076 $25.00 CALDERADD 1 - ADDITION 1

163,504 $2,534,076

COMPLEX TOTALS $2,534,076163,504

0643 IM SPORTS-CIRCLE-SUBSTATION

0643 IM SPORTS-CIRCLE-SUBSTATION

ORIGINAL CONSTRUCTION 2013SUPPORT 1,408 $622,000 $442.00 FTC&H

0175 IM SPORTS-EAST

0175 IM SPORTS-EAST

ORIGINAL CONSTRUCTION 1988ATHLETICS 75,237 $5,243,237 $70.00 CALDER

FACILITIES INFORMATION SERVICES 34

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0151 IM SPORTS-WEST COMPLEX

0151 IM SPORTS-WEST

ORIGINAL CONSTRUCTION 1958ATHLETICS 230,288 $3,212,508 $14.00 SARVIS

2005ATHLETICS 5,284 $3,737,122 $707.00 TMP ASSOCIATESADD 1 - ADDITION 1 COURTYARD

235,572 $6,949,630

COMPLEX TOTALS $6,949,630235,572

0481 INLAND LAKES STORAGE NO. 1

0481 INLAND LAKES STORAGE NO. 1

ORIGINAL CONSTRUCTION 2020FARMS 6,000 $180,000 $30.00

0129 INSECTORY (ENTOMOLOGY)

0129 INSECTORY (ENTOMOLOGY)

ORIGINAL CONSTRUCTION 1932FARMS 204 $200 $1.00

0247 INTERDISCIPLINARY SCIENCE & TECH

0247 INTERDISCIPLINARY SCIENCE & TECH

ORIGINAL CONSTRUCTION 2019ACADEMIC 166,808 $81,934,425 $491.00 SMITH GROUP JJR

0169 INTERNATIONAL CENTER

0169 INTERNATIONAL CENTER

ORIGINAL CONSTRUCTION 1964ACADEMIC 94,447 $1,201,000 $13.00 CALDER

1980ACADEMIC 17,063 $1,146,943 $67.00 CALDERADD 1 - ADDITION 1

2003ACADEMIC 22,014 $5,852,691 $266.00 CALDERADD 2 - ADDITION 2 DELIA KOO

133,524 $8,200,634

FACILITIES INFORMATION SERVICES 35

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0169 INTERNATIONAL CENTER

COMPLEX TOTALS $8,200,634133,524

0167 IPF

0167 IPF

ORIGINAL CONSTRUCTION 1963SUPPORT 95,249 $779,331 $8.00 PHYSICAL PLANT

1969SUPPORT 1,764 $43,931 $25.00 PHYSICAL PLANTADD 1 - ADDITION 1

1994SUPPORT 206 $68,088 $331.00 PHYSICAL PLANTADD 2 - ADDITION 2- ENCLOSE DOCK

97,219 $891,350

COMPLEX TOTALS $891,35097,219

0209 IPF - STORAGE NO. 1

0209 IPF - STORAGE NO. 1

ORIGINAL CONSTRUCTION 1993SUPPORT 9,013 $139,747 $16.00 PHYSICAL PLANT

2007SUPPORT 22,406 $574,233 $26.00 BERNATH-COAKLEY

ADD 1 - ADDITION 1

2017SUPPORT 4,691 $178,258 $38.00 IPFADD 2 - ADDITION 2

36,110 $892,238

COMPLEX TOTALS $892,23836,110

0210 IPF - STORAGE NO. 2

0210 IPF - STORAGE NO. 2

ORIGINAL CONSTRUCTION 1994SUPPORT 10,231 $151,636 $15.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 36

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0210 IPF - STORAGE NO. 2

0210 IPF - STORAGE NO. 2

1998SUPPORT 11,844 $133,770 $11.00 PHYSICAL PLANTADD 1 - ADDITION 1

22,075 $285,406

COMPLEX TOTALS $285,40622,075

0234 IPF - STORAGE NO. 3

0234 IPF - STORAGE NO. 3

ORIGINAL CONSTRUCTION 2012SUPPORT 7,360 $208,797 $28.00 PHYSICAL PLANT

0430A IPF - STORAGE NO. 6

0430A IPF - STORAGE NO. 6

ORIGINAL CONSTRUCTION 1938FARMS 9,215 $59,290 $6.00 AG ENGR

0056 JENISON FIELDHOUSE

0056 JENISON FIELDHOUSE

ORIGINAL CONSTRUCTION 1940ATHLETICS 200,066 $1,025,000 $5.00 MUNSON

1975ATHLETICS 967 $0 $0.00 PHYSICAL PLANTADD 1 - ADDITION 1

2002ATHLETICS 6,770 $6,606,309 $976.00 ROSSETTI &ASSOC.

ADD 2 - ADDITION 2 LOCKER ROOM

207,803 $7,631,309

COMPLEX TOTALS $7,631,309207,803

0029 KEDZIE HALL

0029 KEDZIE HALL

ORIGINAL CONSTRUCTION 1927ACADEMIC 87,946 $113,800 $1.00 MALCOMSON +HIGGENB.

FACILITIES INFORMATION SERVICES 37

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0029 KEDZIE HALL

0029 KEDZIE HALL

1966ACADEMIC 69,373 $2,035,768 $29.00 HARLEY-ELLINGTON

ADD 1 - ADDITION 1 (SOUTH)

2004ACADEMIC 2,064 $155,000 $75.00 DICLEMENTESIEGEL

ADD 2 - ADDITION 2 ENCLOSECHILLER

159,383 $2,304,568

COMPLEX TOTALS $2,304,568159,383

0055 KELLOGG CENTER

0055 KELLOGG CENTER

ORIGINAL CONSTRUCTION 1951SUPPORT 138,523 $1,768,052 $13.00 SARVIS

1955SUPPORT 3,169 $124,170 $39.00 SARVISADD 1 - ADDITION 1

1955SUPPORT 17,099 $289,260 $17.00 SARVISADD 2 - ADDITION 2

1959SUPPORT 21,403 $331,650 $15.00 SARVISADD 3 - ADDITION 3

1988SUPPORT 51,978 $3,320,759 $64.00 CALDERADD 4 - ADDITION 4

232,172 $5,833,891

COMPLEX TOTALS $5,833,891232,172

0150 KRESGE ART CENTER COMPLEX

0150 KRESGE ART

ORIGINAL CONSTRUCTION 1958ACADEMIC 82,056 $1,480,160 $18.00 CALDER

1966ACADEMIC 14,109 $320,720 $23.00 CALDERADD 1 - ADDITION 1

1973ACADEMIC 815 $40,000 $49.00 CALDERADD 2 - ADDITION 2 KILN & FOUNDRYROOM

96,980 $1,840,880

FACILITIES INFORMATION SERVICES 38

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0150 KRESGE ART CENTER COMPLEX

0150A KRESGE ART-SCULPTURE STUDIO

ORIGINAL CONSTRUCTION 1966ACADEMIC 7,695 $164,665 $21.00 CALDER

COMPLEX TOTALS $2,005,545104,675

0158 LANDSCAPE SERVICES

0158 LANDSCAPE SERVICES

ORIGINAL CONSTRUCTION 1959SUPPORT 19,502 $87,757 $5.00 CAMPBELL ENG

1965SUPPORT 12,811 $77,745 $6.00 PHYSICAL PLANTADD 1 - ADDITION 1

2014SUPPORT 133 $0 $0.00 BERNATHCOAKLEY

ADD 2 - ADDITION 2 - EAST ENTRANCE

32,446 $165,502

COMPLEX TOTALS $165,50232,446

0406 LANDSCAPE SERVICES NURSERY COMPLEX

0406A LANDSCAPE SRVCS NURSERY-HEADHOUSE

ORIGINAL CONSTRUCTION 1964SUPPORT 1,320 $8,971 $7.00 PHYSICAL PLANT

1964SUPPORT 2,191 $14,133 $6.00 PHYSICAL PLANTADD 1 - ADDITION 1 GREENHOUSE

3,511 $23,104

0406C LANDSCAPE SRVCS NURSERY-ROOT CELLAR

ORIGINAL CONSTRUCTION 1964SUPPORT 393 $2,541 $6.00 PHYSICAL PLANT

0406E LANDSCAPE SRVCS NURSERY-HOOP HSE

ORIGINAL CONSTRUCTION 1964SUPPORT 2,346 $21,865 $9.00 PHYSICAL PLANT

0406G LANDSCAPE SRVCS NURSERY-BARN 1

FACILITIES INFORMATION SERVICES 39

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0406 LANDSCAPE SERVICES NURSERY COMPLEX

0406G LANDSCAPE SRVCS NURSERY-BARN 1

ORIGINAL CONSTRUCTION 2007SUPPORT 3,399 $46,240 $14.00 AUSTIN &ASSOCIATES

0406H LANDSCAPE SRVCS NURSERY-BARN 2

ORIGINAL CONSTRUCTION 2007SUPPORT 3,399 $46,240 $14.00 AUSTIN &ASSOCIATES

COMPLEX TOTALS $139,99013,048

0525 LANDSCAPE SRVCS-SALT STRG 1

0525 LANDSCAPE SRVCS-SALT STRG 1

ORIGINAL CONSTRUCTION 1978SUPPORT 625 $19,400 $31.00 PHYSICAL PLANT

0536 LANDSCAPE SRVCS-SALT STRG 2

0536 LANDSCAPE SRVCS-SALT STRG 2

ORIGINAL CONSTRUCTION 1995SUPPORT 1,140 $66,900 $59.00 PHYSICAL PLANT

0655 LANDSCAPE SRVCS-SALT STRG 3

0655 LANDSCAPE SRVCS-SALT STRG 3

ORIGINAL CONSTRUCTION 2020SUPPORT 4,616 $262,244 $57.00

0611 LANDSCAPE SRVCS-STRG 2

0611 LANDSCAPE SRVCS-STRG 2

ORIGINAL CONSTRUCTION 2000SUPPORT 162 $7,450 $46.00 PHYSICAL PLANT

0447 LARGE ANIMAL CLINICAL RES COMPLEX

0447B LARGE ANIMAL RES-HAY BARN

ORIGINAL CONSTRUCTION 1984FARMS 3,833 $52,754 $14.00 ARCH. CONSORT.

0049 LIBRARY

0049 LIBRARY

FACILITIES INFORMATION SERVICES 40

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0049 LIBRARY

0049 LIBRARY

ORIGINAL CONSTRUCTION 1955ACADEMIC 286,504 $3,712,865 $13.00 CALDER

1964ACADEMIC 2,623 $375,000 $143.00 PHYSICAL PLANTADD 1 - ADDITION 1

1967ACADEMIC 147,962 $3,547,524 $24.00 CALDERADD 2 - ADDITION 2

1995ACADEMIC 20,175 $4,200,000 $208.00 CALDERADD 3 - ADDITION 3

2014ACADEMIC 1,650 $1,524,507 $924.00 DICLEMENTESIEGEL

ADD 4 - ADDITION 4 - SUBSTATION

458,914 $13,359,896

COMPLEX TOTALS $13,359,896458,914

0183 LIFE SCIENCE

0183 LIFE SCIENCE

ORIGINAL CONSTRUCTION 1971ACADEMIC 180,617 $7,797,177 $43.00 CALDER

2012ACADEMIC 47,854 $10,973,302 $229.00 TMPADD 1 - ADDITION 1 - BOTT NURSINGEDUC

228,471 $18,770,479

COMPLEX TOTALS $18,770,479228,471

0068 LINEN SERVICES

0068 LINEN SERVICES

ORIGINAL CONSTRUCTION 1968SUPPORT 72,412 $1,221,130 $17.00 MAYOTTE-WEBB

0014 LINTON HALL

0014 LINTON HALL

ORIGINAL CONSTRUCTION 1881ACADEMIC 18,451 $22,000 $1.00 MARSH-ARNOLD

FACILITIES INFORMATION SERVICES 41

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0014 LINTON HALL

0014 LINTON HALL

1947ACADEMIC 19,878 $368,550 $19.00 MUNSONADD 1 - ADDITION 1

1989ACADEMIC 622 $269,428 $433.00 CLARK TROMBLYRANDER

ADD 2 - ADDITION 2 - ELECTSUBSTATION

1996ACADEMIC 888 $348,741 $393.00 FTC&HADD 3 - ADDITION 3 - HANDICAPACCESS

39,839 $1,008,719

COMPLEX TOTALS $1,008,71939,839

0154 MANLY MILES

0154 MANLY MILES

ORIGINAL CONSTRUCTION 1959ACADEMIC 58,519 $749,325 $13.00 SARVIS

0016 MARSHALL-ADAMS HALL

0016 MARSHALL-ADAMS HALL

ORIGINAL CONSTRUCTION 1902ACADEMIC 20,189 $27,000 $1.00 BOWD

0302 MASON ABBOT HALL

0302 MASON ABBOT HALL

ORIGINAL CONSTRUCTION 1938HOUSING 189,167 $1,050,000 $6.00 BOWD-MUNSON

0607 MASON RESEARCH FARM COMPLEX

0607B MASON RESEARCH FARM-STRG

ORIGINAL CONSTRUCTION 1984FARMS 5,193 $14,400 $3.00

0607C MASON RESEARCH FARM-LAB

ORIGINAL CONSTRUCTION 1997FARMS 3,923 $120,000 $31.00

FACILITIES INFORMATION SERVICES 42

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0607 MASON RESEARCH FARM COMPLEX

COMPLEX TOTALS $134,4009,116

0324 MCDONEL HALL

0324 MCDONEL HALL

ORIGINAL CONSTRUCTION 1963HOUSING 348,498 $4,020,925 $12.00 CALDER

0629 METEOROLOGICAL TOWER

0629 METEOROLOGICAL TOWER

ORIGINAL CONSTRUCTION 20130 $137,492 $0.00 PHYSICAL PLANT

0940 MICH BIOTECH INSTITUTE

0940 MICH BIOTECH INSTITUTE

ORIGINAL CONSTRUCTION 1987ACADEMIC 131,797 $16,682,345 $127.00 HEPY

0940B MICH BIOTECH INSTITUTE-PROCESSING

0940B MICH BIOTECH INSTITUTE-PROCESSING

ORIGINAL CONSTRUCTION 2012ACADEMIC 208 $0 $0.00

0940A MICH BIOTECH INSTITUTE-STORAGE

0940A MICH BIOTECH INSTITUTE-STORAGE

ORIGINAL CONSTRUCTION 1989OTHER 135 $0 $0.00

0022 MORRILL HALL OF AGRICULTURE

0022 MORRILL HALL OF AGRICULTURE

ORIGINAL CONSTRUCTION 1909ACADEMIC 97,896 $182,000 $2.00 BOWD

1991ACADEMIC 325 $113,493 $350.00 PHYSICAL PLANTADD 1 - ADDITION 1

1999ACADEMIC 35,759 $3,971,878 $111.00 ARCHITECTS FOURADD 2 - ADDITION 2 - ANNEX

133,980 $4,267,371

FACILITIES INFORMATION SERVICES 43

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0022 MORRILL HALL OF AGRICULTURE

COMPLEX TOTALS $4,267,371133,980

0083 MSU COLLEGE OF LAW

0083 MSU COLLEGE OF LAW

ORIGINAL CONSTRUCTION 1997ACADEMIC 185,633 $20,345,284 $110.00 SSOE

2015ACADEMIC 925 $332,572 $360.00 WIGEN TINCKNELLADD 1 - ADDITION 1 - NORTHENTRANCE

186,558 $20,677,856

COMPLEX TOTALS $20,677,856186,558

0638 MSU COMMUNITY MUSIC SCHOOL

0638 MSU COMMUNITY MUSIC SCHOOL

ORIGINAL CONSTRUCTION 1975ACADEMIC 10,429 $0 $0.00 VAN VIENENPOSTEMA

1998ACADEMIC 10,413 $0 $0.00 MAYOTTE JACOBADD 1 - ADDITION NO. 1

20,842 $0

COMPLEX TOTALS $020,842

0606 MSU FEDERAL CREDIT UNION COMPLEX

0606 MSU FCU

ORIGINAL CONSTRUCTION 197023,136 $510,723 $22.00 MAYOTTE-WEBB

198529,606 $1,883,644 $64.00 FREDERICK &VARWIG

ADD 1 - ADDITION NO. 1

19997,306 $578,518 $79.00 DANIELS &ZERMACK

ADD 2 - ADDITION NO. 2

FACILITIES INFORMATION SERVICES 44

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0606 MSU FEDERAL CREDIT UNION COMPLEX

0606 MSU FCU

60,048 $2,972,885

COMPLEX TOTALS $2,972,88560,048

0245 MSU SCENE SHOP TEACHING LAB

0245 MSU SCENE SHOP TEACHING LAB

ORIGINAL CONSTRUCTION 2016ACADEMIC 9,888 $1,251,054 $127.00 BERNATH-COAKLEY

0223 MSU SURPLUS AND RECYCLING COMPLEX

0223 MSU SURPLUS AND RECYCLING

ORIGINAL CONSTRUCTION 2009SUPPORT 73,194 $7,555,424 $103.00 FTCH

0641 MUNN FIELD OBSERVATION TOWER

0641 MUNN FIELD OBSERVATION TOWER

ORIGINAL CONSTRUCTION 2014ATHLETICS 233 $75,625 $324.00 FTC&H

0059 MUNN ICE ARENA

0059 MUNN ICE ARENA

ORIGINAL CONSTRUCTION 1974ATHLETICS 106,644 $3,581,700 $34.00 DAVERMANASSOCIATES

1999ATHLETICS 14,012 $3,306,057 $236.00 ROSSETTIASSOCIATES

ADD 1 - ADDITION 1 - VIP SUITES

2014ATHLETICS 2,536 $1,863,181 $735.00 ROSSETTIASSOCIATES

ADD 2 - ADDITION 2 - CHILLERENCLOSURE

123,192 $8,750,938

COMPLEX TOTALS $8,750,938123,192

FACILITIES INFORMATION SERVICES 45

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0013 MUSEUM

0013 MUSEUM

ORIGINAL CONSTRUCTION 1924ACADEMIC 52,067 $460,000 $9.00 BOWD-MUNSON

1957ACADEMIC 2,931 $264,624 $90.00 CALDERADD 1 - ADDITION 1

54,998 $724,624

COMPLEX TOTALS $724,62454,998

0011 MUSIC

0011 MUSIC

ORIGINAL CONSTRUCTION 1940ACADEMIC 34,852 $227,288 $7.00 CALDER

1956ACADEMIC 21,965 $568,970 $26.00 CALDERADD 1 - ADDITION 1

2013ACADEMIC 1,222 $298,363 $244.00 ORIONADD 2 - ADDITION 2 ELECTRICALSUBSTATN

2020ACADEMIC 41,643 $29,879,199 $718.00 TMPADD 3 - ADDITION 3

99,682 $30,973,820

COMPLEX TOTALS $30,973,82099,682

0021 MUSIC PRACTICE

0021 MUSIC PRACTICE

ORIGINAL CONSTRUCTION 1968ACADEMIC 35,964 $1,283,626 $36.00 CALDER

0180 NATURAL RESOURCES

0180 NATURAL RESOURCES

ORIGINAL CONSTRUCTION 1966ACADEMIC 149,972 $3,405,054 $23.00 KAHN

FACILITIES INFORMATION SERVICES 46

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0024 NATURAL SCIENCE

0024 NATURAL SCIENCE

ORIGINAL CONSTRUCTION 1948ACADEMIC 191,977 $2,687,675 $14.00 MUNSON

2007ACADEMIC 1,336 $624,872 $468.00 ORIONENGINEERING CO

ADD 1 - ADDITION 1 ELECTSUBSTATION

193,313 $3,312,547

COMPLEX TOTALS $3,312,547193,313

0516 NORTH CAMPUS SUBSTATION

0516 NORTH CAMPUS SUBSTATION

ORIGINAL CONSTRUCTION 1921SUPPORT 2,112 $409,000 $194.00 BOWD

1967SUPPORT 5,841 $320,000 $55.00 PHYSICAL PLANTADD 3 - NORTH CAMPUS SUB-STATION

7,953 $729,000

COMPLEX TOTALS $729,0007,953

0196 OBSERVATORY

0196 OBSERVATORY

ORIGINAL CONSTRUCTION 1969ACADEMIC 7,014 $545,400 $78.00 BLACK

1028 OFFICE COMPLEX - ANNEX

1028 OFFICE COMPLEX - ANNEX

ORIGINAL CONSTRUCTION 1996OTHER 13,084 $974,962 $75.00

1027 OFFICE COMPLEX - MAIN BUILDING

1027 OFFICE COMPLEX - MAIN BUILDING

ORIGINAL CONSTRUCTION 1983OTHER 64,159 $3,540,656 $55.00

FACILITIES INFORMATION SERVICES 47

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0017 OLD BOTANY

0017 OLD BOTANY

ORIGINAL CONSTRUCTION 1892ACADEMIC 7,473 $7,227 $1.00 BOWD

1908ACADEMIC 6,578 $8,244 $1.00 BOWDADD 1 - ADDITION 1

14,051 $15,471

COMPLEX TOTALS $15,47114,051

0519 OLD COLLEGE FIELD COMPLEX

0519G OLD COLLEGE FIELD-RESTROOM

ORIGINAL CONSTRUCTION 2009ATHLETICS 859 $553,249 $644.00 HAMILTONANDERSON

2009ATHLETICS 1,887 $572,751 $303.00 HAMILTONANDERSON

ADD 1 - ADDITION 1

2011ATHLETICS 1,486 $183,475 $123.00 FTC&HADD 2 - ADDITION 2 - CONCESSION

4,232 $1,309,475

0519H OLD COLLEGE FIELD-BATTING

ORIGINAL CONSTRUCTION 2007ATHLETICS 9,872 $922,454 $93.00 FTC & H

0519K OLD COLLEGE FIELD-DEMARTIN STADIUM

ORIGINAL CONSTRUCTION 2008ATHLETICS 415 $782,890 $1,885.00 HAMILTONANDERSON

0519L OLD COLLEGE FIELD-MCLANE STADIUM

ORIGINAL CONSTRUCTION 2009ATHLETICS 2,608 $2,920,662 $1,120.00 HAMILTONANDERSON

0519M OLD COLLEGE FIELD-SECCHIA STADIUM

ORIGINAL CONSTRUCTION 2010ATHLETICS 2,006 $1,348,342 $672.00 PHYSICAL PLANT

0519N OLD COLLEGE FIELD-SOFTBALL DUGT 1

ORIGINAL CONSTRUCTION 2009ATHLETICS 360 $87,500 $243.00 PHYSICAL PLANT

0519O OLD COLLEGE FIELD-SOFTBALL DUGT 2

FACILITIES INFORMATION SERVICES 48

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0519 OLD COLLEGE FIELD COMPLEX

0519O OLD COLLEGE FIELD-SOFTBALL DUGT 2

ORIGINAL CONSTRUCTION 2009ATHLETICS 360 $87,500 $243.00 PHYSICAL PLANT

0519P OLD COLLEGE FIELD-BASEBALL DUGT 1

ORIGINAL CONSTRUCTION 2002ATHLETICS 560 $34,103 $61.00 PHYSICAL PLANT

0519Q OLD COLLEGE FIELD-BASEBALL DUGT 2

ORIGINAL CONSTRUCTION 2002ATHLETICS 560 $34,103 $61.00 PHYSICAL PLANT

0519R OLD COLLEGE FIELD-TICKET

ORIGINAL CONSTRUCTION 2013ATHLETICS 821 $258,713 $315.00 SMITHGROUP

COMPLEX TOTALS $7,785,74221,794

0025 OLD HORTICULTURE

0025 OLD HORTICULTURE

ORIGINAL CONSTRUCTION 1924ACADEMIC 42,426 $383,000 $9.00 BOWD-MUNSON

1963ACADEMIC 1,444 $29,540 $20.00 PHYSICAL PLANTADD 1 - ADDITION 1

1991ACADEMIC 605 $159,000 $263.00 FREEMAN/SMITHADD 2 - ADDITION 2

44,475 $571,540

COMPLEX TOTALS $571,54044,475

0047 OLDS HALL

0047 OLDS HALL

ORIGINAL CONSTRUCTION 1916ACADEMIC 73,319 $202,000 $3.00 BOWD

FACILITIES INFORMATION SERVICES 49

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0003 OLIN HEALTH CENTER COMPLEX

0003 OLIN HEALTH CENTER

ORIGINAL CONSTRUCTION 1939ACADEMIC 38,404 $250,000 $7.00 CALDER

1956SUPPORT 61,660 $1,318,900 $21.00 CALDERADD 1 - ADDITION 1

1969SUPPORT 5,350 $343,062 $64.00 CALDERADD 2 - ADDITION 2

105,414 $1,911,962

0003B OLIN-ELEC SUBSTATION

ORIGINAL CONSTRUCTION 1992SUPPORT 1,357 $527,389 $389.00 FTC&H

0003C OLIN-COOLING TOWER 2

ORIGINAL CONSTRUCTION 2014SUPPORT 0 $85,860 $0.00 DICLEMENTESIEGEL

COMPLEX TOTALS $2,525,211106,771

0320 OWEN GRADUATE HALL

0320 OWEN GRADUATE HALL

ORIGINAL CONSTRUCTION 1961HOUSING 162,385 $2,347,266 $14.00 CALDER

1965HOUSING 130,032 $2,266,047 $17.00 CALDERADD 1 - ADDITION 1

2009HOUSING 482 $49,387 $102.00 SMITH GROUPADD 2 - ADDITION 2 COVER LOADINGDOCK

292,899 $4,662,700

COMPLEX TOTALS $4,662,700292,899

0089 OYER SPEECH AND HEARING

0089 OYER SPEECH AND HEARING

ORIGINAL CONSTRUCTION 1968ACADEMIC 19,896 $649,811 $33.00 HARLEY-ELLINGTON

FACILITIES INFORMATION SERVICES 50

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0177 PACKAGING

0177 PACKAGING

ORIGINAL CONSTRUCTION 1964ACADEMIC 20,781 $418,852 $20.00 CALDER

1987ACADEMIC 29,681 $3,056,000 $103.00 CALDERADD 1 - ADDITION 1

50,462 $3,474,852

COMPLEX TOTALS $3,474,85250,462

0652 PARKING BOOTH 1-LOT 100

0652 PARKING BOOTH 1-LOT 100

ORIGINAL CONSTRUCTION 2017PARKING 44 $0 $0.00

0511 PARKING BOOTH 1-LOT 39

0511 PARKING BOOTH 1-LOT 39

ORIGINAL CONSTRUCTION 1983PARKING 44 $1,265 $29.00 PHYSICAL PLANT

0534A PARKING BOOTH 1-LOT 62 (NEW)

0534A PARKING BOOTH 1-LOT 62 (NEW)

ORIGINAL CONSTRUCTION 2008PARKING 40 $27,000 $675.00 PHYSICAL PLANT

0597 PARKING BOOTH 2-LOT 100

0597 PARKING BOOTH 2-LOT 100

ORIGINAL CONSTRUCTION 1997PARKING 44 $2,575 $59.00 DESIGN PLUS

0574 PARKING BOOTH 2-LOT 39

0574 PARKING BOOTH 2-LOT 39

ORIGINAL CONSTRUCTION 1997PARKING 44 $2,300 $52.00 FTC & H

0534B PARKING BOOTH 2-LOT 62 (NEW)

0534B PARKING BOOTH 2-LOT 62 (NEW)

FACILITIES INFORMATION SERVICES 51

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0534B PARKING BOOTH 2-LOT 62 (NEW)

0534B PARKING BOOTH 2-LOT 62 (NEW)

ORIGINAL CONSTRUCTION 2008PARKING 40 $27,000 $675.00 PHYSICAL PLAN T

0576 PARKING BOOTH 2-RAMP 3 (EAST)

0576 PARKING BOOTH 2-RAMP 3 (EAST)

ORIGINAL CONSTRUCTION 1997PARKING 44 $2,800 $64.00 WALKER PARKINGCONS

0575 PARKING BOOTH-RAMP 3 (WEST)

0575 PARKING BOOTH-RAMP 3 (WEST)

ORIGINAL CONSTRUCTION 1997PARKING 44 $2,800 $64.00 WALKER PARKINGCONS

0219 PARKING RAMP 1-SHAW LANE

0219 PARKING RAMP 1-SHAW LANE

ORIGINAL CONSTRUCTION 2002PARKING 426,114 $19,367,462 $45.00 SHG, INC.

0185 PARKING RAMP 2-AUDITORIUM RD

0185 PARKING RAMP 2-AUDITORIUM RD

ORIGINAL CONSTRUCTION 1967PARKING 177,223 $1,185,850 $7.00 BLACK

0111 PARKING RAMP 3-WHARTON

0111 PARKING RAMP 3-WHARTON

ORIGINAL CONSTRUCTION 1983PARKING 324,798 $2,262,479 $7.00 CARL WALKER

1997PARKING 41,132 $5,602,165 $136.00 WALKER PARKINGCONS

ADD 1 - ADDITION 1

365,930 $7,864,644

COMPLEX TOTALS $7,864,644365,930

0155 PARKING RAMP 4-KELLOGG

0155 PARKING RAMP 4-KELLOGG

FACILITIES INFORMATION SERVICES 52

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0155 PARKING RAMP 4-KELLOGG

0155 PARKING RAMP 4-KELLOGG

ORIGINAL CONSTRUCTION 1989PARKING 297,502 $7,476,471 $25.00 CALDER

0216 PARKING RAMP 5-COMM ARTS

0216 PARKING RAMP 5-COMM ARTS

ORIGINAL CONSTRUCTION 2001PARKING 322,171 $10,176,717 $32.00 HARLEYELLINGTON

0222 PARKING RAMP 6-GRAND RIVER

0222 PARKING RAMP 6-GRAND RIVER

ORIGINAL CONSTRUCTION 2006PARKING 276,390 $14,097,032 $51.00 FTC & H

0246 PARKING RAMP 7-HARRISON RD

0246 PARKING RAMP 7-HARRISON RD

ORIGINAL CONSTRUCTION 2016PARKING 269,155 $9,758,257 $36.00 NEWMANN/SMITH

0524 PATHOLOGICAL INCINERATOR

0524 PATHOLOGICAL INCINERATOR

ORIGINAL CONSTRUCTION 1975SUPPORT 1,972 $179,200 $91.00 PHYSICAL PLANT

0524A PATHOLOGICAL INCINERATOR - STORAGE

0524A PATHOLOGICAL INCINERATOR - STORAGE

ORIGINAL CONSTRUCTION 2018SUPPORT 923 $90,000 $98.00

0212 PAVILION AG LIVESTOCK ED COMPLEX

0212 PAVILION AG LIVESTOCK

ORIGINAL CONSTRUCTION 1996ACADEMIC 204,594 $13,043,863 $64.00 HOBBS & BLACK

0212A PAVILION AG LIVESTOCK-HORSE BARN

ORIGINAL CONSTRUCTION 2000FARMS 24,633 $219,282 $9.00 PHYSICAL PLANT

0439A PAVILION AG LIVESTOCK-STORAGE

ORIGINAL CONSTRUCTION 1949FARMS 3,258 $23,649 $7.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 53

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0212 PAVILION AG LIVESTOCK ED COMPLEX

COMPLEX TOTALS $13,286,794232,485

0086 PLANT AND SOIL SCIENCE

0086 PLANT AND SOIL SCIENCE

ORIGINAL CONSTRUCTION 1986ACADEMIC 274,996 $22,535,561 $82.00 HOYEM-BASSO

2012ACADEMIC 89,682 $33,880,776 $378.00 SMITH GROUPADD 1 - ADDITION 1 MOLECULARPLANT SCI

364,678 $56,416,337

COMPLEX TOTALS $56,416,337364,678

0178 PLANT BIOLOGY

0178 PLANT BIOLOGY

ORIGINAL CONSTRUCTION 1966ACADEMIC 62,709 $2,147,756 $34.00 BLACK

1968ACADEMIC 55,202 $2,405,000 $44.00 BLACKADD 1 - ADDITION 1

1968ACADEMIC 31,394 $1,025,445 $33.00 BLACKADD 2 - ADDITION 2 BOTANY

1985ACADEMIC 40,211 $5,791,716 $144.00 HOYEM-BASSOADD 3 - ADDITION 3

189,516 $11,369,917

COMPLEX TOTALS $11,369,917189,516

0098C PLANT SCIENCE GREENHOUSE-EAST

0098C PLANT SCIENCE GREENHOUSE-EAST

ORIGINAL CONSTRUCTION 1966ACADEMIC 18,717 $502,361 $27.00 BLACK

FACILITIES INFORMATION SERVICES 54

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0098C PLANT SCIENCE GREENHOUSE-EAST

0098C PLANT SCIENCE GREENHOUSE-EAST

1980ACADEMIC 2,016 $159,733 $79.00 MAYOTTE,CROUSE, DHA

ADD 1 - GREENHOUSE (EAST RANGE)

1998ACADEMIC 3,054 $632,954 $207.00 PHYSICAL PLANTADD 2 - TRANSGENIC GREENHOUSE

23,787 $1,295,048

COMPLEX TOTALS $1,295,04823,787

0094 PLANT SCIENCE GREENHOUSE-SUPPORT

0094 PLANT SCIENCE GREENHOUSE-SUPPORT

ORIGINAL CONSTRUCTION 1984ACADEMIC 4,059 $10,050 $2.00 ARCH. CONSORT.

0093 PLANT SCIENCE GREENHOUSE-WEST

0093 PLANT SCIENCE GREENHOUSE-WEST

ORIGINAL CONSTRUCTION 1942ACADEMIC 8,190 $87,495 $11.00 PHYSICAL PLANT

1949ACADEMIC 60,945 $331,943 $5.00 PHYSICAL PLANTADD 1 - ADDITION 1 - PLANT SCIGRNHSE

1956ACADEMIC 1,730 $10,768 $6.00 PHYSICAL PLANTADD 2 - ADDITION 2 - GRNHSE WRANGE

1958ACADEMIC 5,819 $18,891 $3.00 PHYSICAL PLANTADD 3 - ADDITION 3 - GRNHSE WRANGE

1962ACADEMIC 1,596 $63,901 $40.00 PHYSICAL PLANTADD 4 - ADDITION 4 - GRNHSE WRANGE

1981ACADEMIC 4,266 $274,966 $64.00 KILGOREADD 6 - ADDITION 6 - GRNHSE WRANGE

82,546 $787,964

COMPLEX TOTALS $787,96482,546

0473 POULTRY TEACHING & RES COMPLEX

0473A POULTRY-SERVICE

FACILITIES INFORMATION SERVICES 55

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0473 POULTRY TEACHING & RES COMPLEX

0473A POULTRY-SERVICE

ORIGINAL CONSTRUCTION 1965FARMS 4,000 $21,760 $5.00 FRANK AND STEIN

0473B POULTRY-LAB

ORIGINAL CONSTRUCTION 1965FARMS 4,700 $31,216 $7.00 FRANK AND STEIN

0473C POULTRY-CHICK BROOD

ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN

0473D POULTRY-CHICK REAR

ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN

0473E POULTRY-CHICK CAGE

ORIGINAL CONSTRUCTION 1965FARMS 6,101 $33,077 $5.00 FRANK AND STEIN

0473H POULTRY-CHICK PROG

ORIGINAL CONSTRUCTION 1965FARMS 5,948 $33,077 $6.00 FRANK AND STEIN

0473I POULTRY-CHICK BREED

ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN

0473J POULTRY-TURKEY BREED

ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN

0473K POULTRY-MINK

ORIGINAL CONSTRUCTION 1957FARMS 4,276 $19,584 $5.00 PHYSICAL PLANT

0473M POULTRY-FOREMAN HSE

ORIGINAL CONSTRUCTION 1965FARMS 2,943 $93,181 $32.00

0473N POULTRY-MINK SHED 1

ORIGINAL CONSTRUCTION 1965FARMS 1,120 $24,234 $22.00 AG ENGRG

0473O POULTRY-MINK SHED 2

ORIGINAL CONSTRUCTION 1965FARMS 1,120 $24,234 $22.00 AG ENGRG

FACILITIES INFORMATION SERVICES 56

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0473 POULTRY TEACHING & RES COMPLEX

0473P POULTRY-MINK SHED 3

ORIGINAL CONSTRUCTION 1965FARMS 1,120 $24,234 $22.00 AG ENGRG

0473Q POULTRY-N STRG SHED

ORIGINAL CONSTRUCTION 1965FARMS 588 $2,053 $3.00 AG ENGRG

0473R POULTRY-S STRG SHED

ORIGINAL CONSTRUCTION 1965FARMS 715 $10,687 $15.00

0473S POULTRY-FREEZER STG

ORIGINAL CONSTRUCTION 1965FARMS 251 $2,400 $10.00

0473T POULTRY-TURKEY RESEARCH

ORIGINAL CONSTRUCTION 1996FARMS 5,124 $557,286 $109.00 CAPITALCONSULTANTS

0473U POULTRY-LAYING HEN RESEARCH

ORIGINAL CONSTRUCTION 2012FARMS 17,967 $1,375,000 $77.00 HENNING

COMPLEX TOTALS $2,384,33179,769

0027 PSYCHOLOGY

0027 PSYCHOLOGY

ORIGINAL CONSTRUCTION 1949ACADEMIC 97,947 $1,540,511 $16.00 CALDER

1955ACADEMIC 503 $6,500 $13.00 PHYSICAL PLANTADD 1 - ADDITION 1

1973ACADEMIC 1,384 $61,785 $45.00 PHYSICAL PLANTADD 2 - ADDITION 2

1976ACADEMIC 13,483 $650,500 $48.00 SEDGEWICK-SELLER

ADD 3 - ADDITION 3

113,317 $2,259,296

FACILITIES INFORMATION SERVICES 57

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0027 PSYCHOLOGY

COMPLEX TOTALS $2,259,296113,317

0087 PUBLIC SAFETY

0087 PUBLIC SAFETY

ORIGINAL CONSTRUCTION 1975SUPPORT 26,130 $1,140,022 $44.00 MANSON,JACKSON,KANE

1992SUPPORT 9,963 $920,797 $92.00 PHYSICAL PLANTADD 2 - ADDITION 2

36,093 $2,060,819

COMPLEX TOTALS $2,060,81936,093

0595 PUMP STATION 1-FARM LANE

0595 PUMP STATION 1-FARM LANE

ORIGINAL CONSTRUCTION 2009SUPPORT 935 $100,000 $107.00 URS

0596 PUMP STATION 2-FARM LANE

0596 PUMP STATION 2-FARM LANE

ORIGINAL CONSTRUCTION 2009SUPPORT 935 $100,000 $107.00 URS

0450 PUREBRED BEEF CATTLE TEACH COMPLEX

0450A PUREBRED BEEF-MAIN

ORIGINAL CONSTRUCTION 1930FARMS 11,116 $54,307 $5.00 MUNSON

1953FARMS 9,120 $63,388 $7.00 PHYSICAL PLANTADD 1 - ADDITION 1

20,236 $117,695

0450B PUREBRED BEEF-SHEEP BARN

ORIGINAL CONSTRUCTION 1953FARMS 2,046 $5,000 $2.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 58

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0450 PUREBRED BEEF CATTLE TEACH COMPLEX

0450C PUREBRED BEEF-LOOSE HOUSING

ORIGINAL CONSTRUCTION 1954FARMS 7,368 $23,100 $3.00 PHYSICAL PLANT

0450D PUREBRED BEEF-SCALE HOUSE

ORIGINAL CONSTRUCTION 1954FARMS 1,295 $2,920 $2.00 PHYSICAL PLANT

0450E PUREBRED BEEF-HAY SHED

ORIGINAL CONSTRUCTION 1954FARMS 640 $1,475 $2.00 PHYSICAL PLANT

COMPLEX TOTALS $150,19031,585

0577 RADIO EQUIPMENT SHELTER COMPLEX

0577 RADIO EQUIPMENT SHELTER

ORIGINAL CONSTRUCTION 1999OTHER 327 $110,480 $338.00 MILLER BUILDINGSYS

0577A RADIO EQUIPMENT SHELTER - TOWER

ORIGINAL CONSTRUCTION 1999OTHER 0 $150,435 $0.00

COMPLEX TOTALS $260,915327

0600 RADIO FACILITY COMPLEX

0600A RADIO FACILITY-RADIO TRANSM WKAR

ORIGINAL CONSTRUCTION 1948ACADEMIC 2,934 $24,187 $8.00 PHYSICAL PLANT

0600B RADIO FACILITY-RADIO TOWER WKAR

ORIGINAL CONSTRUCTION 19700 $0 $0.00

0600C RADIO FACILITY-DIR TOWER WKAR

ORIGINAL CONSTRUCTION 19700 $0 $0.00

FACILITIES INFORMATION SERVICES 59

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0600 RADIO FACILITY COMPLEX

COMPLEX TOTALS $24,1872,934

0214 RADIOLOGY COMPLEX

0214 RADIOLOGY

ORIGINAL CONSTRUCTION 1998ACADEMIC 64,773 $6,701,829 $103.00 REDSTONE-TISCOARCH

0214A RADIOLOGY-GREENHOUSE

ORIGINAL CONSTRUCTION 2006ACADEMIC 1,499 $78,783 $53.00 PHYSICAL PLANT

0214B RADIOLOGY-STORAGE SHED

ORIGINAL CONSTRUCTION 2000ACADEMIC 198 $7,480 $38.00 PHYSICAL PLANT

COMPLEX TOTALS $6,788,09266,470

0189 REGIONAL CHILLED WATER PLANT

0189 REGIONAL CHILLED WATER PLANT

ORIGINAL CONSTRUCTION 1971SUPPORT 5,977 $559,100 $94.00 CALDER

1976SUPPORT 5,355 $590,000 $110.00 CALDERADD 1 - ADDITION 1

1985SUPPORT 4,803 $781,000 $163.00 HOYEM-BASSOADD 2 - ADDITION 2

1991SUPPORT 5,041 $408,570 $81.00 HEPYADD 3 - ADDITION 3

1993SUPPORT 5,023 $1,512,000 $301.00 HEPYADD 4 - ADDITION 4

26,199 $3,850,670

COMPLEX TOTALS $3,850,67026,199

FACILITIES INFORMATION SERVICES 60

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0205 RENTAL STORAGE FACILITY B

0205 RENTAL STORAGE FACILITY B

ORIGINAL CONSTRUCTION 1987SUPPORT 25,792 $215,000 $8.00 PHYSICAL PLANT

0325 RHS SERVICES

0325 RHS SERVICES

ORIGINAL CONSTRUCTION 1962SUPPORT 12,080 $107,500 $9.00 MANSON,JACKSON,KANE

0515 RIVER INTAKE STATION

0515 RIVER INTAKE STATION

ORIGINAL CONSTRUCTION 1940SUPPORT 910 $6,375 $7.00 BOWD-MUNSON

0616 RIVER TERRACE HOUSE

0616 RIVER TERRACE HOUSE

ORIGINAL CONSTRUCTION 1941HOUSING 4,744 $27,500 $6.00

1994HOUSING 267 $3,500 $13.00ADD 1 - ADDITION 1 COVERED WALK

5,011 $31,000

COMPLEX TOTALS $31,0005,011

0052 RIVER WATER RESEARCH COMPLEX

0052A RIVER WATER RESEARCH - LAB

ORIGINAL CONSTRUCTION 1953ACADEMIC 2,702 $21,640 $8.00 PHYSICAL PLANT

1972ACADEMIC 901 $34,777 $39.00 PHYSICAL PLANTADD 1 - ADDITION 1 (ENVIROMENTALENG)

3,603 $56,417

0052B RIVER WATER RESEARCH - STORAGE

ORIGINAL CONSTRUCTION 1998ACADEMIC 2,808 $48,260 $17.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 61

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0052 RIVER WATER RESEARCH COMPLEX

COMPLEX TOTALS $104,6776,411

0317 SHAW HALL

0317 SHAW HALL

ORIGINAL CONSTRUCTION 1950HOUSING 275,821 $3,482,153 $13.00 CALDER

2013HOUSING 1,377 $356,643 $259.00 NEUMANN/SMITHADD 1 - ADDITION 1 LOADING DOCK

277,198 $3,838,796

COMPLEX TOTALS $3,838,796277,198

0449 SHEEP BARN

0449 SHEEP BARN

1992FARMS 7,328 $61,000 $8.00ADD 1 - ANGLE BARN

2016FARMS 6,400 $325,000 $51.00 STEDFASTADD 2 - SHEEP LAMBING RESEARCH

13,728 $386,000

COMPLEX TOTALS $386,00013,728

0468 SHEEP RESEARCH & TEACHING COMPLEX

0468A SHEEP RESEARCH-BARN

ORIGINAL CONSTRUCTION 1961FARMS 6,693 $46,219 $7.00 PHYSICAL PLANT

0468B SHEEP RESEARCH-OPEN SHED

ORIGINAL CONSTRUCTION 1961FARMS 2,473 $3,600 $1.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 62

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0468 SHEEP RESEARCH & TEACHING COMPLEX

COMPLEX TOTALS $49,8199,166

0537 SHOOTING RANGE COMPLEX

0537A SHOOTING RANGE-STRG 1

ORIGINAL CONSTRUCTION 1965SUPPORT 146 $3,500 $24.00

0537B SHOOTING RANGE-STRG 2

ORIGINAL CONSTRUCTION 1995SUPPORT 796 $20,000 $25.00

0537C SHOOTING RANGE-PAVILION

ORIGINAL CONSTRUCTION 1995SUPPORT 344 $10,000 $29.00

0537D SHOOTING RANGE-CANINE

ORIGINAL CONSTRUCTION 1997SUPPORT 840 $27,000 $32.00

0537E SHOOTING RANGE-TRAINING 1

ORIGINAL CONSTRUCTION 2011SUPPORT 2,712 $105,000 $39.00 DESIGN-BUILD

2015SUPPORT 454 $41,079 $90.00 DESIGN-BUILDADD 1 - ADDITION 1

3,166 $146,079

0537F SHOOTING RANGE-TRAINING 2

ORIGINAL CONSTRUCTION 2012SUPPORT 576 $14,189 $25.00

COMPLEX TOTALS $220,7685,868

0537G SHOOTING RANGE-OPERATIONS CENTER

0537G SHOOTING RANGE-OPERATIONS CENTER

ORIGINAL CONSTRUCTION 2015FARMS 5,200 $286,728 $55.00

FACILITIES INFORMATION SERVICES 63

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0300 SNYDER PHILLIPS HALL

0300 SNYDER PHILLIPS HALL

ORIGINAL CONSTRUCTION 1947HOUSING 204,733 $2,192,578 $11.00 MUNSON

2007HOUSING 96,647 $27,061,160 $280.00 EINHORN YAFFEEPRESC

ADD 1 - ADDITION 1

301,380 $29,253,738

COMPLEX TOTALS $29,253,738301,380

0625 SOUTH CAMPUS ANAEROBIC DIGESTER

0625 S CAMPUS & RES ANAEROBIC DIGS-CNTRL

ORIGINAL CONSTRUCTION 2010FARMS 1,671 $77,848 $47.00 LANDMANAGEMENT

0625A RESEARCH ANAEROBIC DIGESTER

ORIGINAL CONSTRUCTION 20100 $0 $0.00 LANDMANAGEMENT

0625B RESEARCH ANAEROBIC DIG-REC PITS N&S

ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT

0625C S CAMPUS ANAEROBIC DIG-REC PITS N&S

ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT

0625D S CAMPUS ANAEROBIC DIG-MIX TANK

ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT

0625E S CAMPUS ANAEROBIC DIG-MECH EQ

ORIGINAL CONSTRUCTION 2013FARMS 236 $0 $0.00 LANDMANAGEMENT

0625F S CAMPUS & RES ANAEROBIC DIGS- DHT

ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT

0625G S CAMPUS ANAEROBIC DIG-HELIOS DIG

ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT

FACILITIES INFORMATION SERVICES 64

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0625 SOUTH CAMPUS ANAEROBIC DIGESTER

0625H S CAMPUS ANAEROBIC DIG-ELEC EQ

ORIGINAL CONSTRUCTION 2013FARMS 283 $0 $0.00

0625J S CAMPUS ANAEROBIC DIG-WASH

ORIGINAL CONSTRUCTION 2013FARMS 88 $0 $0.00

0625K RESEARCH ANAEROBIC DIG-RES SHED

ORIGINAL CONSTRUCTION 2013FARMS 48 $0 $0.00

0625L RESEARCH ANAEROBIC DIG-LG RES POND

ORIGINAL CONSTRUCTION 2013FARMS 0 $0 $0.00

0625N S CAMPUS & RES ANAEROBIC DIGS-PIT

ORIGINAL CONSTRUCTION 2013FARMS 0 $0 $0.00

0625P S CAMPUS & RES ANAEROBIC DIGS-STORG

ORIGINAL CONSTRUCTION 2013FARMS 159 $0 $0.00

COMPLEX TOTALS $77,8482,485

0217 SPARTAN CHILD DEVELOPMENT CNTR CX

0217 SPARTAN CHILD DEVELOPMENT

ORIGINAL CONSTRUCTION 2002SUPPORT 16,076 $1,513,332 $94.00 TOWER PINKSTERTITUS

0217A SPARTAN CHILD DEV - STORAGE SHED

ORIGINAL CONSTRUCTION 2002SUPPORT 132 $1,200 $9.00

COMPLEX TOTALS $1,514,53216,208

FACILITIES INFORMATION SERVICES 65

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0058 SPARTAN STADIUM COMPLEX

0058 SPARTAN STADIUM

ORIGINAL CONSTRUCTION 1923ATHLETICS 0 $160,000 $0.00 BOWD

1948ATHLETICS 83,877 $1,432,574 $17.00 MUNSONADD 1 - ADDITION 1 (27,250 SEATS)

1956ATHLETICS 9,004 $397,347 $44.00 MUNSONADD 2 - ADDITION 2 (9,000 SEATS)

1957ATHLETICS 93,015 $1,805,317 $19.00 MUNSONADD 3 - ADDITION 3 (16,000 SEATS)

2006ATHLETICS 235,951 $45,532,099 $193.00 HNTBADD 4 - ADDITION 4

2014ATHLETICS 47,257 $18,362,298 $389.00 INTEGRATEDDESIGN

ADD 5 - ADDITION 5 NORTH ENDZONE

2017ATHLETICS 21,382 $10,319,152 $483.00 INTEGRATEDDESIGN

ADD 6 - ADDITION 6 SOUTH ENDZONE

490,486 $78,008,787

0058A SPARTAN STADIUM-TRACK STRG

ORIGINAL CONSTRUCTION 2002ATHLETICS 1,248 $80,000 $64.00 O'BOYLE,COWELL,BLALO

0058B SPARTAN STADIUM-PRESSBOX

ORIGINAL CONSTRUCTION 2002ATHLETICS 200 $19,500 $98.00 O'BOYLE,COWELL,BLALO

0058C SPARTAN STADIUM-SCOREBOARD 1

ORIGINAL CONSTRUCTION 2012ATHLETICS 9,405 $3,225,098 $343.00

0058D SPARTAN STADIUM-SCOREBOARD 2

ORIGINAL CONSTRUCTION 2012ATHLETICS 3,962 $3,225,098 $814.00

0058E SPARTAN STADIUM-SCOREBOARD 3

ORIGINAL CONSTRUCTION 2012ATHLETICS 3,962 $3,225,098 $814.00

COMPLEX TOTALS $87,783,581509,263

0533 SPARTAN VILLAGE - PICNIC SHELTER

0533 SPARTAN VILLAGE - PICNIC SHELTER

FACILITIES INFORMATION SERVICES 66

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0533 SPARTAN VILLAGE - PICNIC SHELTER

0533 SPARTAN VILLAGE - PICNIC SHELTER

ORIGINAL CONSTRUCTION 1995SUPPORT 664 $28,500 $43.00

1400 SPARTAN VILLAGE APTS COMPLEX

1429 SPARTAN VILLAGE 1429

ORIGINAL CONSTRUCTION 1958HOUSING 8,546 $82,450 $10.00 MANSON CARVER

1430 SPARTAN VILLAGE 1430

ORIGINAL CONSTRUCTION 1958HOUSING 7,014 $82,450 $12.00 MANSON CARVER

1431 SPARTAN VILLAGE 1431

ORIGINAL CONSTRUCTION 1958HOUSING 6,756 $82,450 $12.00 MANSON CARVER

1432 SPARTAN VILLAGE 1432

ORIGINAL CONSTRUCTION 1958HOUSING 6,941 $82,450 $12.00 MANSON CARVER

1433 SPARTAN VILLAGE 1433

ORIGINAL CONSTRUCTION 1958HOUSING 8,637 $82,450 $10.00 MANSON CARVER

1434 SPARTAN VILLAGE 1434

ORIGINAL CONSTRUCTION 1958HOUSING 9,556 $82,450 $9.00 MANSON CARVER

1435 SPARTAN VILLAGE 1435

ORIGINAL CONSTRUCTION 1958HOUSING 11,227 $82,450 $7.00 MANSON CARVER

1436 SPARTAN VILLAGE 1436

ORIGINAL CONSTRUCTION 1958HOUSING 9,357 $82,450 $9.00 MANSON CARVER

1439 SPARTAN VILLAGE-LAUNDRY 1439

ORIGINAL CONSTRUCTION 1958HOUSING 10,834 $49,406 $5.00 MANSON CARVER

1440 SPARTAN VILLAGE 1440

ORIGINAL CONSTRUCTION 1958HOUSING 10,391 $82,450 $8.00 MANSON CARVER

1441 SPARTAN VILLAGE 1441

FACILITIES INFORMATION SERVICES 67

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1441 SPARTAN VILLAGE 1441

ORIGINAL CONSTRUCTION 1958HOUSING 6,434 $82,450 $13.00 MANSON CARVER

1442 SPARTAN VILLAGE 1442

ORIGINAL CONSTRUCTION 1958HOUSING 9,323 $82,450 $9.00 MANSON CARVER

1443 SPARTAN VILLAGE 1443

ORIGINAL CONSTRUCTION 1958HOUSING 10,006 $82,450 $8.00 MANSON CARVER

1444 SPARTAN VILLAGE 1444

ORIGINAL CONSTRUCTION 1958HOUSING 9,771 $82,450 $8.00 MANSON CARVER

1445 SPARTAN VILLAGE 1445

ORIGINAL CONSTRUCTION 1958HOUSING 9,323 $82,450 $9.00 MANSON CARVER

1446 SPARTAN VILLAGE 1446

ORIGINAL CONSTRUCTION 1958HOUSING 6,307 $82,450 $13.00 MANSON CARVER

1447 SPARTAN VILLAGE 1447

ORIGINAL CONSTRUCTION 1958HOUSING 9,621 $82,450 $9.00 MANSON CARVER

1448 SPARTAN VILLAGE 1448

ORIGINAL CONSTRUCTION 1958HOUSING 9,154 $82,450 $9.00 MANSON CARVER

1449 SPARTAN VILLAGE 1449

ORIGINAL CONSTRUCTION 1958HOUSING 6,312 $82,450 $13.00 MANSON CARVER

1450 SPARTAN VILLAGE 1450

ORIGINAL CONSTRUCTION 1958HOUSING 8,853 $82,450 $9.00 MANSON CARVER

1451 SPARTAN VILLAGE 1451

ORIGINAL CONSTRUCTION 1958HOUSING 9,329 $82,450 $9.00 MANSON CARVER

1452 SPARTAN VILLAGE 1452

ORIGINAL CONSTRUCTION 1958HOUSING 6,468 $82,450 $13.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 68

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1521 SPARTAN VILLAGE-LAUNDRY SHOP 1521

ORIGINAL CONSTRUCTION 1957SUPPORT 4,629 $55,465 $12.00 MANSON CARVER

1523 SPARTAN VILLAGE 1523

ORIGINAL CONSTRUCTION 1958HOUSING 7,378 $82,450 $11.00 MANSON CARVER

1524 SPARTAN VILLAGE 1524

ORIGINAL CONSTRUCTION 1958HOUSING 9,006 $82,450 $9.00 MANSON CARVER

1525 SPARTAN VILLAGE 1525

ORIGINAL CONSTRUCTION 1958HOUSING 6,452 $82,450 $13.00 MANSON CARVER

1535 SPARTAN VILLAGE 1535

ORIGINAL CONSTRUCTION 1958HOUSING 7,120 $82,450 $12.00 MANSON CARVER

1536 SPARTAN VILLAGE 1536

ORIGINAL CONSTRUCTION 1958HOUSING 10,961 $82,450 $8.00 MANSON CARVER

1537 SPARTAN VILLAGE 1537

ORIGINAL CONSTRUCTION 1958HOUSING 6,517 $82,450 $13.00 MANSON CARVER

1538 SPARTAN VILLAGE 1538

ORIGINAL CONSTRUCTION 1958HOUSING 7,122 $82,450 $12.00 MANSON CARVER

1539 SPARTAN VILLAGE 1539

ORIGINAL CONSTRUCTION 1958HOUSING 8,669 $82,450 $10.00 MANSON CARVER

1540 SPARTAN VILLAGE 1540

ORIGINAL CONSTRUCTION 1958HOUSING 10,987 $82,450 $8.00 MANSON CARVER

1541 SPARTAN VILLAGE 1541

ORIGINAL CONSTRUCTION 1958HOUSING 9,497 $82,450 $9.00 MANSON CARVER

1542 SPARTAN VILLAGE 1542

ORIGINAL CONSTRUCTION 1958HOUSING 7,242 $82,450 $11.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 69

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1543 SPARTAN VILLAGE 1543

ORIGINAL CONSTRUCTION 1958HOUSING 7,127 $82,450 $12.00 MANSON CARVER

1544 SPARTAN VILLAGE 1544

ORIGINAL CONSTRUCTION 1958HOUSING 8,637 $82,450 $10.00 MANSON CARVER

1545 SPARTAN VILLAGE 1545

ORIGINAL CONSTRUCTION 1958HOUSING 6,323 $82,450 $13.00 MANSON CARVER

1546 SPARTAN VILLAGE 1546

ORIGINAL CONSTRUCTION 1958HOUSING 8,664 $82,494 $10.00 MANSON CARVER

1547 SPARTAN VILLAGE 1547

ORIGINAL CONSTRUCTION 1958HOUSING 7,126 $82,450 $12.00 MANSON CARVER

1548 SPARTAN VILLAGE 1548

ORIGINAL CONSTRUCTION 1958HOUSING 8,653 $82,450 $10.00 MANSON CARVER

1549 SPARTAN VILLAGE 1549

ORIGINAL CONSTRUCTION 1958HOUSING 7,224 $82,450 $11.00 MANSON CARVER

1550 SPARTAN VILLAGE 1550

ORIGINAL CONSTRUCTION 1958HOUSING 7,178 $82,450 $11.00 MANSON CARVER

1551 SPARTAN VILLAGE 1551

ORIGINAL CONSTRUCTION 1958HOUSING 9,150 $82,450 $9.00 MANSON CARVER

1565 SPARTAN VILLAGE 1565

ORIGINAL CONSTRUCTION 1958HOUSING 8,792 $82,450 $9.00 MANSON CARVER

1566 SPARTAN VILLAGE 1566

ORIGINAL CONSTRUCTION 1958HOUSING 9,061 $82,450 $9.00 MANSON CARVER

1567 SPARTAN VILLAGE 1567

ORIGINAL CONSTRUCTION 1958HOUSING 6,815 $82,450 $12.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 70

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1568 SPARTAN VILLAGE 1568

ORIGINAL CONSTRUCTION 1958HOUSING 7,056 $82,450 $12.00 MANSON CARVER

1569 SPARTAN VILLAGE 1569

ORIGINAL CONSTRUCTION 1958HOUSING 10,869 $82,450 $8.00 MANSON CARVER

1570 SPARTAN VILLAGE 1570

ORIGINAL CONSTRUCTION 1958HOUSING 6,589 $82,450 $13.00 MANSON CARVER

1571 SPARTAN VILLAGE 1571

ORIGINAL CONSTRUCTION 1958HOUSING 10,913 $82,450 $8.00 MANSON CARVER

1572 SPARTAN VILLAGE 1572

ORIGINAL CONSTRUCTION 1958HOUSING 7,246 $82,450 $11.00 MANSON CARVER

1573 SPARTAN VILLAGE 1573

ORIGINAL CONSTRUCTION 1958HOUSING 8,700 $82,450 $9.00 MANSON CARVER

1574 SPARTAN VILLAGE 1574

ORIGINAL CONSTRUCTION 1958HOUSING 7,116 $82,450 $12.00 MANSON CARVER

1575 SPARTAN VILLAGE 1575

ORIGINAL CONSTRUCTION 1966HOUSING 11,727 $82,450 $7.00 MANSON CARVER

1576 SPARTAN VILLAGE 1576

ORIGINAL CONSTRUCTION 1966HOUSING 7,909 $82,450 $10.00 MANSON CARVER

1577 SPARTAN VILLAGE 1577

ORIGINAL CONSTRUCTION 1966HOUSING 6,433 $82,450 $13.00 MANSON CARVER

1578 SPARTAN VILLAGE 1578

ORIGINAL CONSTRUCTION 1966HOUSING 9,115 $82,450 $9.00 MANSON CARVER

1579 SPARTAN VILLAGE 1579

ORIGINAL CONSTRUCTION 1966HOUSING 9,251 $82,450 $9.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 71

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1612 SPARTAN VILLAGE 1612

ORIGINAL CONSTRUCTION 1958HOUSING 10,928 $82,450 $8.00 MANSON CARVER

1613 SPARTAN VILLAGE 1613

ORIGINAL CONSTRUCTION 1958HOUSING 9,344 $82,450 $9.00 MANSON CARVER

1614 SPARTAN VILLAGE 1614

ORIGINAL CONSTRUCTION 1958HOUSING 8,725 $82,450 $9.00 MANSON CARVER

1615 SPARTAN VILLAGE 1615

ORIGINAL CONSTRUCTION 1958HOUSING 6,560 $82,450 $13.00 MANSON CARVER

1616 SPARTAN VILLAGE 1616

ORIGINAL CONSTRUCTION 1958HOUSING 11,204 $82,450 $7.00 MANSON CARVER

1617 SPARTAN VILLAGE 1617

ORIGINAL CONSTRUCTION 1958HOUSING 9,509 $82,450 $9.00 MANSON CARVER

1618 SPARTAN VILLAGE 1618

ORIGINAL CONSTRUCTION 1958HOUSING 10,919 $82,450 $8.00 MANSON CARVER

1619 SPARTAN VILLAGE 1619

ORIGINAL CONSTRUCTION 1958HOUSING 9,610 $82,450 $9.00 MANSON CARVER

1620 SPARTAN VILLAGE 1620

ORIGINAL CONSTRUCTION 1958HOUSING 6,312 $82,450 $13.00 MANSON CARVER

1621 SPARTAN VILLAGE 1621

ORIGINAL CONSTRUCTION 1958HOUSING 7,196 $82,450 $11.00 MANSON CARVER

1622 SPARTAN VILLAGE 1622

ORIGINAL CONSTRUCTION 1958HOUSING 7,150 $82,450 $12.00 MANSON CARVER

1623 SPARTAN VILLAGE 1623

ORIGINAL CONSTRUCTION 1958HOUSING 8,230 $82,450 $10.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 72

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1624 SPARTAN VILLAGE 1624

ORIGINAL CONSTRUCTION 1958HOUSING 7,426 $82,450 $11.00 MANSON CARVER

1625 SPARTAN VILLAGE 1625

ORIGINAL CONSTRUCTION 1958HOUSING 9,951 $82,450 $8.00 MANSON CARVER

1626 SPARTAN VILLAGE 1626

ORIGINAL CONSTRUCTION 1958HOUSING 7,553 $82,450 $11.00 MANSON CARVER

1627 SPARTAN VILLAGE 1627

ORIGINAL CONSTRUCTION 1958HOUSING 9,346 $82,450 $9.00 MANSON CARVER

1628 SPARTAN VILLAGE 1628

ORIGINAL CONSTRUCTION 1958HOUSING 7,135 $82,494 $12.00 MANSON CARVER

1629 SPARTAN VILLAGE 1629

ORIGINAL CONSTRUCTION 1958HOUSING 8,390 $82,450 $10.00 MANSON CARVER

1630 SPARTAN VILLAGE 1630

ORIGINAL CONSTRUCTION 1958HOUSING 7,132 $82,450 $12.00 MANSON CARVER

1631 SPARTAN VILLAGE 1631

ORIGINAL CONSTRUCTION 1958HOUSING 6,999 $82,450 $12.00 MANSON CARVER

1632 SPARTAN VILLAGE 1632

ORIGINAL CONSTRUCTION 1958HOUSING 8,865 $82,450 $9.00 MANSON CARVER

1633 SPARTAN VILLAGE 1633

ORIGINAL CONSTRUCTION 1966HOUSING 10,549 $82,450 $8.00 MANSON CARVER

1634 SPARTAN VILLAGE 1634

ORIGINAL CONSTRUCTION 1958HOUSING 8,832 $82,494 $9.00 MANSON CARVER

1635 SPARTAN VILLAGE 1635

ORIGINAL CONSTRUCTION 1958HOUSING 9,297 $82,450 $9.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 73

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

1636 SPARTAN VILLAGE 1636

ORIGINAL CONSTRUCTION 1958HOUSING 7,923 $82,450 $10.00 MANSON CARVER

1637 SPARTAN VILLAGE 1637

ORIGINAL CONSTRUCTION 1958HOUSING 7,102 $82,450 $12.00 MANSON CARVER

1638 SPARTAN VILLAGE 1638

ORIGINAL CONSTRUCTION 1958HOUSING 7,082 $82,450 $12.00 MANSON CARVER

1639 SPARTAN VILLAGE 1639

ORIGINAL CONSTRUCTION 1958HOUSING 8,850 $82,450 $9.00 MANSON CARVER

1640 SPARTAN VILLAGE 1640

ORIGINAL CONSTRUCTION 1958HOUSING 7,086 $82,450 $12.00 MANSON CARVER

1641 SPARTAN VILLAGE 1641

ORIGINAL CONSTRUCTION 1958HOUSING 7,066 $82,450 $12.00 MANSON CARVER

1642 SPARTAN VILLAGE 1642

ORIGINAL CONSTRUCTION 1958HOUSING 10,989 $82,450 $8.00 MANSON CARVER

1643 SPARTAN VILLAGE 1643

ORIGINAL CONSTRUCTION 1958HOUSING 10,905 $82,450 $8.00 MANSON CARVER

1644 SPARTAN VILLAGE 1644

ORIGINAL CONSTRUCTION 1958HOUSING 6,970 $82,450 $12.00 MANSON CARVER

1645 SPARTAN VILLAGE 1645

ORIGINAL CONSTRUCTION 1958HOUSING 11,068 $82,450 $7.00 MANSON CARVER

1646 SPARTAN VILLAGE 1646

ORIGINAL CONSTRUCTION 1958HOUSING 6,948 $82,450 $12.00 MANSON CARVER

1647 SPARTAN VILLAGE 1647

ORIGINAL CONSTRUCTION 1966HOUSING 10,433 $82,450 $8.00 MANSON CARVER

FACILITIES INFORMATION SERVICES 74

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1400 SPARTAN VILLAGE APTS COMPLEX

COMPLEX TOTALS $7,690,403792,998

0194 SPARTAN VILLAGE COMMUNITY CNTR

0194 SPARTAN VILLAGE COMMUNITY CNTR

ORIGINAL CONSTRUCTION 1962SUPPORT 5,818 $514,360 $88.00 MANSON,JACKSON, KAN

1964SUPPORT 8,548 $755,480 $88.00 MANSON,JACKSON, KAN

ADD 1 - ADDITION 1 FOURCLASSROOMS

1966SUPPORT 9,262 $815,056 $88.00 MANSON,JACKSON, KAN

ADD 2 - ADDITION 2 FOURCLASSROOMS

1979SUPPORT 1,707 $150,304 $88.00ADD 3 - ADDITION 3 MULTI PURPOSEROOM

1981SUPPORT 2,935 $258,368 $88.00 MANSON,JACKSON,KANE

ADD 4 - ADDITION 4 COMMUNITYCNTR

1992SUPPORT 17,429 $1,399,376 $80.00ADD 5 - ADDITION 5 GYM

45,699 $3,892,944

COMPLEX TOTALS $3,892,94445,699

0061 STEM TEACHING & LEARNING FACILITY

0061 STEM TEACHING & LEARNING FACILITY

ORIGINAL CONSTRUCTION 1948ACADEMIC 30,234 $506,000 $17.00 ERICKSON

1958ACADEMIC 9,225 $677,900 $73.00 COMMONWEALTHADD 1 - ADDITION 1

2021ACADEMIC 152,749 $90,495,217 $592.00 INTEGRATEDDESIGN

ADD 2 - ADDITION 2 - STEM

192,208 $91,679,117

COMPLEX TOTALS $91,679,117192,208

FACILITIES INFORMATION SERVICES 75

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0142 STUDENT SERVICES

0142 STUDENT SERVICES

ORIGINAL CONSTRUCTION 1957SUPPORT 121,938 $2,141,011 $18.00 CALDER

0440 SWINE RESEARCH CENTER COMPLEX

0440A SWINE RESEARCH-BARN/ELEVATOR STRG

ORIGINAL CONSTRUCTION 1951FARMS 7,524 $34,099 $5.00 PHYSICAL PLANT

1954FARMS 4,850 $59,363 $12.00 PHYSICAL PLANTADD 1 - ADDITION 1

1961FARMS 1,196 $7,035 $6.00 PHYSICAL PLANTADD 2 - ADDITION 2

13,570 $100,497

0440B SWINE RESEARCH-GARAGE

ORIGINAL CONSTRUCTION 1955FARMS 362 $5,452 $15.00

0440E SWINE RESEARCH-GESTATION

ORIGINAL CONSTRUCTION 1961FARMS 5,277 $21,500 $4.00 PHYSICAL PLANT

0440F SWINE RESEARCH-AG POLLUTION CNTRL

ORIGINAL CONSTRUCTION 1970FARMS 1,531 $108,190 $71.00 FRANK AND STEIN

0440G SWINE RESEARCH-FINISHING BARN

ORIGINAL CONSTRUCTION 1970FARMS 6,150 $27,230 $4.00 FRANK AND STEIN

0440L SWINE RESEARCH-HSE 1

ORIGINAL CONSTRUCTION 1984FARMS 677 $26,414 $39.00 PHYSICAL PLANT

COMPLEX TOTALS $289,28327,567

0479 SWINE TEACHING & RESEARCH COMPLEX

0479 SWINE TEACH AND RESEARCH

ORIGINAL CONSTRUCTION 1997FARMS 36,822 $2,060,686 $56.00 CAPITALCONSULTANTS

FACILITIES INFORMATION SERVICES 76

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0479 SWINE TEACHING & RESEARCH COMPLEX

0479A SWINE TEACH AND RESEARCH-COMPOST

ORIGINAL CONSTRUCTION 1997FARMS 4,001 $48,000 $12.00 CAPITALCONSULTANTS

0479B SWINE TEACH AND RESEARCH-MANURE 1

ORIGINAL CONSTRUCTION 1997FARMS 304 $5,000 $16.00 CAPITALCONSULTANTS

0479C SWINE TEACH AND RESEARCH-MANURE 2

ORIGINAL CONSTRUCTION 1997FARMS 307 $5,000 $16.00 CAPITALCONSULTANTS

0479D SWINE TEACH AND RESEARCH-SLURRY

ORIGINAL CONSTRUCTION 1997FARMS 0 $175,000 $0.00 CAPITALCONSULTANTS

0479E SWINE TEACH AND RESEARCH-STRG 3

ORIGINAL CONSTRUCTION 1998FARMS 2,629 $65,532 $25.00 MORTONBUILDINGS

0479F SWINE TEACH AND RESEARCH-OZONATION

ORIGINAL CONSTRUCTION 1999FARMS 254 $103,855 $409.00 PHYSICAL PLANT

0479G SWINE TEACH AND RESEARCH-MANURE 3

ORIGINAL CONSTRUCTION 2006FARMS 369 $6,500 $18.00 FARMS

COMPLEX TOTALS $2,469,57344,686

0065 TB SIMON POWER PLANT COMPLEX

0065 TB SIMON POWER PLANT

ORIGINAL CONSTRUCTION 1965SUPPORT 118,444 $8,462,386 $71.00 BENJ,WOODHS,GUENTHER

1974SUPPORT 46,216 $8,900,200 $193.00 COMMONWEALTHADD 1 - ADDITION 1 UNIT 3

1981SUPPORT 10,277 $5,387,000 $524.00 COMMONWEALTHADD 2 - ADDITION 2 BAGHOUSE

1993SUPPORT 86,088 $57,776,300 $671.00 BLACK ANDVEATCH

ADD 3 - ADDITION 3 UNIT 4

1998SUPPORT 1,705 $445,032 $261.00 FTC&HADD 4 - ADDITION 4 OFFICE

FACILITIES INFORMATION SERVICES 77

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0065 TB SIMON POWER PLANT COMPLEX

0065 TB SIMON POWER PLANT

2006SUPPORT 30,771 $32,204,360 $1,047.00 CUMMINS &BARNARD

ADD 5 - ADDITION 5 UNITS 5 & 6

293,501 $113,175,278

0065C TB SIMON POWER PLANT-SUBSTATION

ORIGINAL CONSTRUCTION 1965SUPPORT 1,129 $19,953 $18.00 BENJ,WOODHS,GUENTHER

1993SUPPORT 1,541 $472,189 $306.00 BLACK & VEATCHADD 1 - ADDITION 1

2,670 $492,142

0065D TB SIMON POWER PLANT-COOLING 1

ORIGINAL CONSTRUCTION 1965SUPPORT 0 $175,758 $0.00 BENJ,WOODHS,GUENTHER

0065I TB SIMON POWER PLANT-SIDE FILTER

ORIGINAL CONSTRUCTION 1976SUPPORT 403 $27,500 $68.00 COMMONWEALTH

0065K TB SIMON POWER PLANT-COOLING 2

ORIGINAL CONSTRUCTION 19930 $3,223,700 $0.00 BLACK ANDVEATCH

0065L TB SIMON POWER PLANT-COOLING 3

ORIGINAL CONSTRUCTION 20060 $683,865 $0.00 CUMMINS &BARNARD

0065N TB SIMON POWER PLANT-COAL STRG

ORIGINAL CONSTRUCTION 2009SUPPORT 18,504 $600,483 $32.00 BLACK & VEATCH

0065P TB SIMON POWER PLANT-ELEC CNTRL

ORIGINAL CONSTRUCTION 2009SUPPORT 685 $643,523 $940.00 BLACK & VEATCH

0065Q TB SIMON POWER PLANT-AIR CMPRSS

ORIGINAL CONSTRUCTION 2009SUPPORT 129 $108,095 $838.00 BLACK & VEATCH

0065R TB SIMON POWER PLANT-GAS CMPRSS

ORIGINAL CONSTRUCTION 2006SUPPORT 155 $0 $0.00 CUMMINS &BARNARD

FACILITIES INFORMATION SERVICES 78

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0065 TB SIMON POWER PLANT COMPLEX

0065T TB SIMON POWER PLANT-SWITCH HSE

ORIGINAL CONSTRUCTION 2016SUPPORT 2,734 $2,607,520 $954.00 BLACK & VEATCH

0065U TB SIMON POWER PLANT-UREA PUMP

ORIGINAL CONSTRUCTION 1993SUPPORT 240 $0 $0.00 BLACK & VEATCH

0065V TB SIMON POWER PLANT-TRANSFER TWR

ORIGINAL CONSTRUCTION 1965SUPPORT 5,536 $0 $0.00 BENJ,WOODHS<GUENTHER

0065W TB SIMON POWER PLANT-RICE

ORIGINAL CONSTRUCTION 2022SUPPORT 11,178 $0 $0.00 BLACK & VEATCH

COMPLEX TOTALS $121,737,864335,735

0065Y TB SIMON POWER PLANT-ELECTRIC HOUSE

0065Y TB SIMON POWER PLANT-ELECTRIC HOUSE

ORIGINAL CONSTRUCTION 2022SUPPORT 0 $0 $0.00

0538 TENNIS COURT-RESTROOM AND STRG

0538 TENNIS COURT-RESTROOM AND STRG

ORIGINAL CONSTRUCTION 1996ATHLETICS 480 $77,400 $161.00 FUNCTIONS

0208 TENNIS FACILITY COMPLEX

0208 TENNIS FACILITY

ORIGINAL CONSTRUCTION 1985ATHLETICS 67,091 $1,711,894 $26.00 ANSELMO & ASSOC

0445A THAYER HOUSE

0445A THAYER HOUSE

ORIGINAL CONSTRUCTION 1952FARMS 3,090 $39,032 $13.00

FACILITIES INFORMATION SERVICES 79

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0225 TRANSPORTATION SERVICES COMPLEX

0225A TRANSPORTATION-FUEL AND CAR WASH

ORIGINAL CONSTRUCTION 2013SUPPORT 5,814 $2,101,572 $361.00 FTC&H

1057 TRAUMATIC BRAIN INJURY RESEARCH

1057 TRAUMATIC BRAIN INJURY RESEARCH

ORIGINAL CONSTRUCTION 2018ACADEMIC 1,375 $399,067 $290.00 BERGMANNASSOCIATES

0472 TREE RESEARCH CENTER COMPLEX

0472A TREE RESEARCH-SHOP/OFFICE

ORIGINAL CONSTRUCTION 1964FARMS 2,209 $31,890 $14.00 PHYSICAL PLANT

0472D TREE RESEARCH-HEADHOUSE

ORIGINAL CONSTRUCTION 1975FARMS 1,210 $7,740 $6.00 FORESTRY DEPT

1975FARMS 2,407 $16,180 $7.00 FORESTRY DEPTADD 1 - ADDITION 1 GREENHOUSE(NORTH)

1975FARMS 2,407 $16,180 $7.00 FORESTRY DEPTADD 2 - ADDITION 2 GREENHOUSE(SOUTH)

6,024 $40,100

0472G TREE RESEARCH-STRG 1

ORIGINAL CONSTRUCTION 1979FARMS 818 $9,724 $12.00 PHYSICAL PLANT

0472H TREE RESEARCH-RESIDENCE

ORIGINAL CONSTRUCTION 1978FARMS 1,739 $58,858 $34.00

1986FARMS 343 $18,968 $55.00 PHYSICAL PLANTADD 1 - ADDITION 1

2,082 $77,826

0472I TREE RESEARCH-SHADE HSE

ORIGINAL CONSTRUCTION 19900 $0 $0.00

0472J TREE RESEARCH-STRG 2

ORIGINAL CONSTRUCTION 1996FARMS 5,251 $41,468 $8.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 80

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0472 TREE RESEARCH CENTER COMPLEX

COMPLEX TOTALS $201,00816,384

0006 UNION

0006 UNION

ORIGINAL CONSTRUCTION 1924SUPPORT 81,725 $443,149 $5.00 POND AND POND

1936SUPPORT 29,568 $85,120 $3.00 BOWD-MUNSONADD 1 - ADDITION 1

1949SUPPORT 86,897 $2,362,125 $27.00 CALDERADD 2 - ADDITION 2

1980SUPPORT 2,190 $670,000 $306.00 MAYOTTE,CROUSE,DHAEN

ADD 3 - ADDITION 3

1997SUPPORT 8,151 $2,732,270 $335.00 RALPH CALDERASSOC

ADD 4 - ADDITION 4

208,531 $6,292,664

COMPLEX TOTALS $6,292,664208,531

0453 UNIVERSITY FARMS SERVICE COMPLEX

0453D UFSC-COMMUNITY STRG

ORIGINAL CONSTRUCTION 1961FARMS 11,040 $85,027 $8.00 MOVED

0453E UFSC-S EQUIPMENT STRG BARN 1

ORIGINAL CONSTRUCTION 1984FARMS 4,988 $11,675 $2.00 MORTON

0453F UFSC-S EQUIPMENT STRG BARN 2

ORIGINAL CONSTRUCTION 1984FARMS 4,920 $11,675 $2.00 MORTON

0453G UFSC-4-H

ORIGINAL CONSTRUCTION 1986FARMS 14,374 $118,000 $8.00 PHYSICAL PLANT

0453H UFSC-MAINTENANCE

FACILITIES INFORMATION SERVICES 81

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0453 UNIVERSITY FARMS SERVICE COMPLEX

0453H UFSC-MAINTENANCE

ORIGINAL CONSTRUCTION 1989FARMS 11,698 $341,754 $29.00 PHYSICAL PLANT

0453I UFSC-NORTH MORTON

ORIGINAL CONSTRUCTION 1990FARMS 10,408 $97,485 $9.00 TAYLOR BLDG

0453J UFSC-MATERIALS & PESITCIDE STRG

ORIGINAL CONSTRUCTION 1990FARMS 4,894 $39,990 $8.00 MORTONBUILDINGS

0453K UFSC-EQUIP STRG

ORIGINAL CONSTRUCTION 1996FARMS 10,278 $87,700 $9.00 PHYSICAL PLANT

COMPLEX TOTALS $793,30672,600

0088 UNIVERSITY SERVICES

0088 UNIVERSITY SERVICES

ORIGINAL CONSTRUCTION 1969SUPPORT 5,510 $141,537 $26.00 MAYOTTE-WEBB

1700 UNIVERSITY VILLAGE APTS COMPLEX

1701 UNIVERSITY VILLAGE - 1701

ORIGINAL CONSTRUCTION 2007HOUSING 17,860 $1,922,469 $108.00 THE CHRISTMANCO

1702 UNIVERSITY VILLAGE - 1702

ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO

1703 UNIVERSITY VILLAGE - 1703

ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO

1704 UNIVERSITY VILLAGE - 1704

ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO

1705 UNIV VILLAGE COMMUNITY CNTR

FACILITIES INFORMATION SERVICES 82

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

1700 UNIVERSITY VILLAGE APTS COMPLEX

1705 UNIV VILLAGE COMMUNITY CNTR

ORIGINAL CONSTRUCTION 2007HOUSING 2,640 $282,480 $107.00 THE CHRISTMANCO

1706 UNIVERSITY VILLAGE - 1706

ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO

1707 UNIVERSITY VILLAGE - 1707

ORIGINAL CONSTRUCTION 2007HOUSING 11,902 $1,283,893 $108.00 THE CHRISTMANCO

1708 UNIVERSITY VILLAGE - 1708

ORIGINAL CONSTRUCTION 2007HOUSING 17,969 $1,922,469 $107.00 THE CHRISTMANCO

1709 UNIVERSITY VILLAGE - 1709

ORIGINAL CONSTRUCTION 2007HOUSING 17,967 $1,922,469 $107.00 THE CHRISTMANCO

COMPLEX TOTALS $12,469,352116,334

0082 URBAN PLANNING LANDSCAPE ARCH-IMC

0082 URBAN PLANNING LANDSCAPE ARCH-IMC

ORIGINAL CONSTRUCTION 1966ACADEMIC 30,972 $386,084 $12.00 CALDER

1966ACADEMIC 16,041 $232,227 $14.00 CALDERADD 1 - ADDITION 1 INSTRUCTIONALMEDIA

47,013 $618,311

COMPLEX TOTALS $618,31147,013

0319 VAN HOOSEN HALL

0319 VAN HOOSEN HALL

ORIGINAL CONSTRUCTION 1957HOUSING 32,834 $447,781 $14.00 MANSON ANDCARVER

FACILITIES INFORMATION SERVICES 83

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0215 VETERINARY DIAGNOSTIC LAB COMPLEX

0215 VETERINARY DIAGNOSTIC LABORATORY

ORIGINAL CONSTRUCTION 2003FARMS 158,471 $35,455,000 $224.00 HARLEY ELLIS, INC.

0215A VETERINARY DIAGNOSTIC LAB-CONTAIN 1

ORIGINAL CONSTRUCTION 2002ACADEMIC 6,422 $191,296 $30.00 HARLEY ELLIS

0215B VETERINARY DIAGNOSTIC LAB-CONTAIN 2

ORIGINAL CONSTRUCTION 2002ACADEMIC 8,327 $248,684 $30.00 HARLEY ELLIS

0215C VETERINARY DIAGNOSTIC LAB-CONTAIN 3

ORIGINAL CONSTRUCTION 2002ACADEMIC 8,327 $248,684 $30.00 HARLEY ELLIS

0215D VETERINARY DIAGNOSTIC LAB-CONTAIN 4

ORIGINAL CONSTRUCTION 2002ACADEMIC 6,422 $191,296 $30.00 HARLEY ELLIS

0215E VETERINARY DIAGNOSTIC LAB-DNR

ORIGINAL CONSTRUCTION 2002ACADEMIC 3,035 $288,300 $95.00 HARLEY ELLIS

0215F VETERINARY DIAGNOSTIC LAB-CREMTRY 1

ORIGINAL CONSTRUCTION 2007FARMS 332 $73,003 $220.00 PHYSICAL PLANT

0215G VETERINARY DIAGNOSTIC LAB-BSL3 2

ORIGINAL CONSTRUCTION 2012ACADEMIC 655 $681,720 $1,041.00 PHYSICAL PLANT

0221 VETERINARY DIAGNOSTIC LAB-BSL3 1

ORIGINAL CONSTRUCTION 2002ACADEMIC 672 $30,800 $46.00 PHYSICAL PLANT

COMPLEX TOTALS $37,408,783192,663

0170 VETERINARY MEDICAL CENTER COMPLEX

0170 VETERINARY MEDICAL CENTER

ORIGINAL CONSTRUCTION 1965ACADEMIC 181,077 $3,818,616 $21.00 HARLEY-ELLINGTON

FACILITIES INFORMATION SERVICES 84

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0170 VETERINARY MEDICAL CENTER COMPLEX

0170 VETERINARY MEDICAL CENTER

1991ACADEMIC 159,547 $28,234,643 $177.00 GBKBADD 1 - ADDITION 1

2005ACADEMIC 39,162 $8,675,581 $222.00 DUCE SIMMONSASSOC

ADD 2 - ADDITION 2 ONCOLOGY

2007ACADEMIC 3,654 $1,102,647 $302.00 TOWER PINKSTERTITUS

ADD 3 - ADDITION 3 SECOND FLOOR FBLDG

2007ACADEMIC 217 $234,380 $1,082.00 DESIGN PLUSADD 4 - ADDITION 4 SMALL ANIMALENTRAN

383,657 $42,065,867

0170A VETERINARY MEDICAL CENTER-EQUINE

ORIGINAL CONSTRUCTION 1989ACADEMIC 10,524 $640,000 $61.00 GBKB

2001ACADEMIC 23,782 $1,771,379 $74.00 FTCHADD 1 - ADDITION 1 EQUINEPERFORM CNTR

34,306 $2,411,379

0170B VETERINARY MEDICAL CENTER-PEGASUS

ORIGINAL CONSTRUCTION 2005ACADEMIC 8,818 $2,468,374 $280.00 DUCE SIMMONSASSOC

COMPLEX TOTALS $46,945,620426,781

0446 VETERINARY RESEARCH CENTER COMPLEX

0211 UNIV RESEARCH CONTAINMENT

ORIGINAL CONSTRUCTION 1993ACADEMIC 67,274 $6,556,167 $97.00 HEPY

1995ACADEMIC 22,033 $2,002,239 $91.00 HEPYADD 1 - ANIMAL INFEC DISEASE-ADDN1

89,307 $8,558,406

0446A VET RESEARCH-LARGE ANIMAL

ORIGINAL CONSTRUCTION 1958FARMS 4,225 $45,633 $11.00 PHYSICAL PLANT

0446B VET RESEARCH-ROUND ROOF

ORIGINAL CONSTRUCTION 1949FARMS 11,536 $69,324 $6.00 MUNSON

FACILITIES INFORMATION SERVICES 85

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0446 VETERINARY RESEARCH CENTER COMPLEX

0446C VET RESEARCH-MANAGER'S HOUSE

ORIGINAL CONSTRUCTION 1949FARMS 2,587 $168,209 $65.00

0446D VET RESEARCH-WOODEN

ORIGINAL CONSTRUCTION 1949FARMS 988 $7,800 $8.00 PHYSICAL PLANT

0446E VET RESEARCH-OFFICE

ORIGINAL CONSTRUCTION 1951FARMS 6,264 $50,552 $8.00 MUNSON

0446F VET RESEARCH-GERM FREE BARN

ORIGINAL CONSTRUCTION 1960FARMS 2,880 $47,000 $16.00 PHYSICAL PLANT

0446G VET RESEARCH-WEST

ORIGINAL CONSTRUCTION 1961FARMS 7,254 $89,645 $12.00 PHYSICAL PLANT

0446I VET RESEARCH-GARAGE 2

ORIGINAL CONSTRUCTION 1965FARMS 572 $8,860 $15.00

0446J VET RESEARCH-SMALL ANIMAL

ORIGINAL CONSTRUCTION 1966FARMS 10,329 $171,848 $17.00 HARLEY-ELLINGTON

0446K VET RESEARCH-POLE BARN

ORIGINAL CONSTRUCTION 1970FARMS 830 $5,000 $6.00 PHYSICAL PLANT

0446L VET RESEARCH-STORAGE BARN

ORIGINAL CONSTRUCTION 1975FARMS 4,444 $9,000 $2.00 PHYSICAL PLANT

0446N VET RESEARCH-BOVINE RESP DISEASE

ORIGINAL CONSTRUCTION 1985FARMS 243 $3,312 $14.00 PHYSICAL PLANT

0446O VET RESEARCH-ANIMAL SHELTER 2

ORIGINAL CONSTRUCTION 1988FARMS 1,784 $24,041 $13.00 MORTON BLD

FACILITIES INFORMATION SERVICES 86

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0446 VETERINARY RESEARCH CENTER COMPLEX

COMPLEX TOTALS $9,258,630143,243

0220 VISITOR CENTER

0220 VISITOR CENTER

ORIGINAL CONSTRUCTION 2001SUPPORT 255 $128,000 $502.00 CP &P

0458 WATER QUALITY MANAGEMENT COMPLEX

0458A WATER QUALITY MGMT-GARAGE

ORIGINAL CONSTRUCTION 1975OTHER 1,176 $21,640 $18.00 PHYSICAL PLANT

0458B WATER QUALITY MGMT-PUMP HSE

ORIGINAL CONSTRUCTION 1973OTHER 964 $200,000 $207.00 JOHNSON-ANDERSON,INC

0458C WATER QUALITY MGMT-PUMP HSE SHED

ORIGINAL CONSTRUCTION 1973OTHER 97 $850 $9.00

0458D WATER QUALITY MGMT-BEE BIO

ORIGINAL CONSTRUCTION 1997OTHER 2,560 $72,968 $29.00 PHYSICAL PLANT

COMPLEX TOTALS $295,4584,797

0096 WATER RESERVOIR

0096 WATER RESERVOIR

ORIGINAL CONSTRUCTION 1951SUPPORT 4,225 $225,560 $53.00 ERICKSON

1973SUPPORT 897 $25,344 $28.00 PHYSICAL PLANTADD 1 - ADDITION 1

1987SUPPORT 2,900 $410,000 $141.00 WOLF/WINEMANADD 2 - ADDITION 2

1988SUPPORT 1,193 $42,000 $35.00 PHYSICAL PLANTADD 3 - ADDITION 3

FACILITIES INFORMATION SERVICES 87

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0096 WATER RESERVOIR

0096 WATER RESERVOIR

9,215 $702,904

COMPLEX TOTALS $702,9049,215

0250 WATER TREATMENT PLANT

0250 WATER TREATMENT PLANT

ORIGINAL CONSTRUCTION 2020SUPPORT 12,551 $8,460,231 $674.00 FTC&H

0250A WATER TREATMENT PLANT - TOWER

ORIGINAL CONSTRUCTION 2020SUPPORT 2,124 $2,655,685 $1,250.00 FTC&H

COMPLEX TOTALS $11,115,91614,675

0566 WELL HOUSE 1-IRRIGATION

0566 WELL HOUSE 1-IRRIGATION

ORIGINAL CONSTRUCTION 2008SUPPORT 120 $25,160 $210.00 STS/AECOM

0550 WELL HOUSE 15

0550 WELL HOUSE 15

ORIGINAL CONSTRUCTION 1956SUPPORT 124 $1,898 $15.00 PHYSICAL PLANT

0551 WELL HOUSE 16

0551 WELL HOUSE 16

ORIGINAL CONSTRUCTION 1956SUPPORT 348 $5,503 $16.00 PHYSICAL PLANT

1994SUPPORT 227 $13,284 $58.00 PHYSICAL PLANTADD 1 - ADDITION NO. 1

575 $18,787

FACILITIES INFORMATION SERVICES 88

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0551 WELL HOUSE 16

COMPLEX TOTALS $18,787575

0570 WELL HOUSE 17

0570 WELL HOUSE 17

ORIGINAL CONSTRUCTION 1957SUPPORT 120 $1,967 $16.00 PHYSICAL PLANT

0553 WELL HOUSE 18

0553 WELL HOUSE 18

ORIGINAL CONSTRUCTION 1963SUPPORT 125 $2,430 $19.00 PHYSICAL PLANT

0554 WELL HOUSE 19

0554 WELL HOUSE 19

ORIGINAL CONSTRUCTION 1962SUPPORT 120 $2,242 $19.00 PHYSICAL PLANT

0567 WELL HOUSE 2-IRRIGATION

0567 WELL HOUSE 2-IRRIGATION

ORIGINAL CONSTRUCTION 2008SUPPORT 96 $25,160 $263.00 STS/AECOM

0555 WELL HOUSE 21

0555 WELL HOUSE 21

ORIGINAL CONSTRUCTION 1965SUPPORT 130 $2,625 $20.00 PHYSICAL PLANT

0556 WELL HOUSE 22

0556 WELL HOUSE 22

ORIGINAL CONSTRUCTION 1967SUPPORT 140 $4,703 $34.00 PHYSICAL PLANT

0557 WELL HOUSE 23

0557 WELL HOUSE 23

ORIGINAL CONSTRUCTION 1966SUPPORT 140 $2,931 $21.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 89

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0558 WELL HOUSE 24

0558 WELL HOUSE 24

ORIGINAL CONSTRUCTION 1967SUPPORT 140 $3,048 $22.00 PHYSICAL PLANT

0559 WELL HOUSE 25

0559 WELL HOUSE 25

ORIGINAL CONSTRUCTION 1968SUPPORT 140 $3,251 $23.00 PHYSICAL PLANT

0560 WELL HOUSE 26

0560 WELL HOUSE 26

ORIGINAL CONSTRUCTION 1969SUPPORT 140 $3,562 $25.00 PHYSICAL PLANT

0561 WELL HOUSE 27

0561 WELL HOUSE 27

ORIGINAL CONSTRUCTION 1970SUPPORT 140 $3,770 $27.00 PHYSICAL PLANT

0562 WELL HOUSE 28

0562 WELL HOUSE 28

ORIGINAL CONSTRUCTION 1970SUPPORT 140 $3,770 $27.00 PHYSICAL PLANT

0563 WELL HOUSE 29

0563 WELL HOUSE 29

ORIGINAL CONSTRUCTION 1986SUPPORT 192 $13,196 $69.00 PHYSICAL PLANT

0568 WELL HOUSE 3-IRRIGATION

0568 WELL HOUSE 3-IRRIGATION

ORIGINAL CONSTRUCTION 2008SUPPORT 180 $25,160 $140.00 STS/AECOM

0564 WELL HOUSE 30

0564 WELL HOUSE 30

ORIGINAL CONSTRUCTION 1988SUPPORT 192 $13,807 $72.00 PHYSICAL PLANT

FACILITIES INFORMATION SERVICES 90

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0565 WELL HOUSE 31

0565 WELL HOUSE 31

ORIGINAL CONSTRUCTION 2007SUPPORT 234 $45,000 $192.00 FTC & H

0651 WELL HOUSE 33

0651 WELL HOUSE 33

ORIGINAL CONSTRUCTION 2019SUPPORT 207 $177,720 $859.00 FTC&H

0569 WELL HOUSE 4-IRRIGATION

0569 WELL HOUSE 4-IRRIGATION

ORIGINAL CONSTRUCTION 2012SUPPORT 27 $20,000 $744.00

0599 WELL HOUSE 5-IRRIGATION

0599 WELL HOUSE 5-IRRIGATION

ORIGINAL CONSTRUCTION 2012SUPPORT 34 $20,000 $586.00

0078 WELLS HALL

0078 WELLS HALL

ORIGINAL CONSTRUCTION 1967ACADEMIC 205,863 $4,659,834 $23.00 HARLEY-ELLINGTON

1970ACADEMIC 23,181 $826,500 $36.00 HARLEY-ELLINGTON

ADD 1 - ADDITION 1

2012ACADEMIC 86,841 $23,502,119 $271.00 INTEGRATEDDESIGN

ADD 2 - ADDITION 2

315,885 $28,988,453

COMPLEX TOTALS $28,988,453315,885

0301 WEST CIRCLE COMPLEX

0304 CAMPBELL HALL

ORIGINAL CONSTRUCTION 1939HOUSING 80,384 $474,628 $6.00 MALCOMSON,CALDER

1969HOUSING 759 $32,000 $42.00 CALDERADD 1 - ADDITION 1

FACILITIES INFORMATION SERVICES 91

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0301 WEST CIRCLE COMPLEX

0304 CAMPBELL HALL

81,143 $506,628

0305 LANDON HALL

ORIGINAL CONSTRUCTION 1947HOUSING 81,299 $1,346,256 $17.00 CALDER

1969HOUSING 744 $37,000 $50.00 CALDERADD 1 - ADDITION 1

2014HOUSING 2,467 $2,047,067 $830.00 SMITHGROUPADD 2 - ADDITION 2-LOADINGDOCK/DINING

84,510 $3,430,323

0306 YAKELEY GILCHRIST HALL

ORIGINAL CONSTRUCTION 1948HOUSING 134,442 $2,023,239 $15.00 CALDER

0308 WILLIAMS HALL

ORIGINAL CONSTRUCTION 1937HOUSING 67,415 $500,000 $7.00 CALDER

0309 MARY MAYO HALL

ORIGINAL CONSTRUCTION 1931HOUSING 64,319 $425,000 $7.00 MALCOMSON,TROUT,HIGG

COMPLEX TOTALS $6,885,190431,829

0085 WHARTON

0085 WHARTON

ORIGINAL CONSTRUCTION 1982ACADEMIC 158,453 $16,583,483 $105.00 HARLEYELLINGTON

2009ACADEMIC 22,542 $6,909,300 $307.00 TMPADD 1 - ADDITION 1 ADMIN OFFICE

2009ACADEMIC 6,509 $6,715,975 $1,032.00 TMPADD 2 - ADDITION 2 COVER LOADINGDOCK

187,504 $30,208,758

FACILITIES INFORMATION SERVICES 92

1 April 2022BUILDING DATA LIST

COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT

0085 WHARTON

COMPLEX TOTALS $30,208,758187,504

0603 WILDLIFE ECOLOGY

0603 WILDLIFE ECOLOGY

ORIGINAL CONSTRUCTION 1970FARMS 507 $8,100 $16.00 PHYSICAL PLANT

0008 WILLS HOUSE

0008 WILLS HOUSE

ORIGINAL CONSTRUCTION 1927ACADEMIC 7,878 $37,500 $5.00 BOWD-MUNSON

0322 WILSON HALL

0322 WILSON HALL

ORIGINAL CONSTRUCTION 1962HOUSING 343,928 $4,583,085 $13.00 CALDER

0323 WONDERS HALL

0323 WONDERS HALL

ORIGINAL CONSTRUCTION 1963HOUSING 343,543 $4,429,982 $13.00 CALDER