FACILITIES DATA REPORT
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0128 1407 S HARRISON
0128 1407 S HARRISON
ORIGINAL CONSTRUCTION 1973SUPPORT 56,695 $1,587,019 $28.00 WARREN-HOLMES
1800 1855 PLACE COMPLEX
1801 1855 PLACE-BUILDING 1801
ORIGINAL CONSTRUCTION 2017HOUSING 148,446 $25,347,696 $171.00 NEUMANN/SMITH
1802 1855 PLACE-BUILDING 1802
ORIGINAL CONSTRUCTION 2017HOUSING 46,205 $8,007,296 $173.00 NEUMANN/SMITH
1803 1855 PLACE-BUILDING 1803
ORIGINAL CONSTRUCTION 2017HOUSING 38,731 $6,777,750 $175.00 NEUMANN/SMITH
1804 1855 PLACE-BUILDING 1804
ORIGINAL CONSTRUCTION 2017HOUSING 39,058 $6,874,208 $176.00 NEUMANN/SMITH
1805 1855 PLACE-BUILDING 1805
ORIGINAL CONSTRUCTION 2017HOUSING 50,083 $6,874,208 $137.00 NEUMANN/SMITH
1806 1855 PLACE-BUILDING 1806
ORIGINAL CONSTRUCTION 2017HOUSING 26,659 $4,691,984 $176.00 NEUMANN/SMITH
1807 1855 PLACE-BUILDING 1807
ORIGINAL CONSTRUCTION 2017HOUSING 26,206 $4,612,256 $176.00 NEUMANN/SMITH
1808 1855 PLACE-BUILDING 1808
ORIGINAL CONSTRUCTION 2016HOUSING 56,869 $10,008,944 $176.00 NEUMANN/SMITH
FACILITIES INFORMATION SERVICES 1
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1800 1855 PLACE COMPLEX
1809 1855 PLACE-BUILDING 1809
ORIGINAL CONSTRUCTION 2016HOUSING 56,864 $10,008,240 $176.00 NEUMANN/SMITH
1810 1855 PLACE-BUILDING 1810
ORIGINAL CONSTRUCTION 2016HOUSING 56,865 $10,008,240 $176.00 NEUMANN/SMITH
COMPLEX TOTALS $93,210,822545,986
0165 ABRAMS PLANETARIUM
0165 ABRAMS PLANETARIUM
ORIGINAL CONSTRUCTION 1963ACADEMIC 17,465 $297,957 $17.00 CALDER
0402 AG EXPO EXHIBITORS COMPLEX
0402 AG EXPO EXHIB-STORAGE 1 EAST
ORIGINAL CONSTRUCTION 1988FARMS 2,572 $21,903 $9.00 LAND MGMT
0402A AG EXPO EXHIB-WICK 1-SOUTH MAROON
ORIGINAL CONSTRUCTION 1995FARMS 4,275 $102,600 $24.00 LAND MGMT
0402C AG EXPO EXHIB-MORTON-PROP SHOP
ORIGINAL CONSTRUCTION 2016FARMS 991 $0 $0.00
0402D AG EXPO EXHIB-STORAGE 2-WEST
ORIGINAL CONSTRUCTION 1998FARMS 2,490 $65,530 $26.00 PHYSICAL PLANT
0402I AG EXPO EXHIB-WICK 2-NORTH WHITE
ORIGINAL CONSTRUCTION 2009OTHER 1,408 $40,832 $29.00 LANDMANAGEMENT
COMPLEX TOTALS $230,86511,736
FACILITIES INFORMATION SERVICES 2
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0091 AGRICULTURE ENGINEERING COMPLEX
0091 FARRALL HALL
ORIGINAL CONSTRUCTION 1948ACADEMIC 72,985 $681,542 $9.00 MUNSON
1999ACADEMIC 3,634 $937,582 $258.00 PROGRESSIVEARCH
ADD 1 - ADDITION 1
76,619 $1,619,124
0091A FARRALL-PROTOTYPE ASSEMBLY
ORIGINAL CONSTRUCTION 1999ACADEMIC 5,009 $190,000 $38.00 PHYSICAL PLANT
COMPLEX TOTALS $1,809,12481,628
0401 AKERS GOLF COURSE COMPLEX
0401A AKERS GOLF-CART SHELTER-WEST
ORIGINAL CONSTRUCTION 1979ATHLETICS 2,151 $42,537 $20.00 PHYSICAL PLANT
1988ATHLETICS 1,229 $56,100 $46.00 PHYSICAL PLANTADD 1 - ADDITION 1
3,380 $98,637
0401B AKERS GOLF-MAINTENANCE-EAST
ORIGINAL CONSTRUCTION 1967ATHLETICS 3,192 $22,250 $7.00 PHYSICAL PLANT
1976ATHLETICS 793 $12,750 $16.00 PHYSICAL PLANTADD 1 - ADDITION 1
3,985 $35,000
0401C AKERS GOLF-MAINTENANCE-WEST
ORIGINAL CONSTRUCTION 1956ATHLETICS 4,812 $28,300 $6.00 PHYSICAL PLANT
0401E AKERS GOLF-MANAGERS HSE-WEST
ORIGINAL CONSTRUCTION 1957ATHLETICS 2,630 $120,441 $46.00
0401J AKERS GOLF-RESTROOM 1-EAST
ORIGINAL CONSTRUCTION 1979ATHLETICS 298 $16,870 $57.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 3
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0401 AKERS GOLF COURSE COMPLEX
0401L AKERS GOLF-SNACK BAR-WEST
ORIGINAL CONSTRUCTION 1987ATHLETICS 241 $43,850 $182.00 PHYSICAL PLANT
0401M AKERS GOLF-SOIL STRG-EAST
ORIGINAL CONSTRUCTION 1988ACADEMIC 2,400 $22,421 $9.00 PHYSICAL PLANT
1992ACADEMIC 1,600 $13,265 $8.00 WING CONSTADD 1 - ADDITION 1
1998ACADEMIC 3,569 $15,789 $4.00ADD 2 - ADDITION 2
7,569 $51,475
0401N AKERS GOLF-STARTER-EAST
ORIGINAL CONSTRUCTION 1989ATHLETICS 61 $27,340 $448.00 PHYSICAL PLANT
0401P AKERS GOLF-DRIVING RANGE-WEST
ORIGINAL CONSTRUCTION 1990ATHLETICS 282 $23,500 $83.00 PHYSICAL PLANT
0401Q AKERS GOLF-SNACK BAR-EAST
ORIGINAL CONSTRUCTION 1993ATHLETICS 337 $27,705 $82.00 PHYSICAL PLANT
0401S AKERS GOLF-SHELTER 5-EAST
ORIGINAL CONSTRUCTION 1960ATHLETICS 144 $6,500 $45.00
0401T AKERS GOLF-STARTER 1-EAST
ORIGINAL CONSTRUCTION 1996ATHLETICS 4,259 $131,801 $31.00 PHYSICAL PLANT
0401U AKERS GOLF-CART-WEST
ORIGINAL CONSTRUCTION 2001ATHLETICS 3,660 $74,000 $20.00 PHYSICAL PLANT
0401V AKERS GOLF-DRIVING RANGE ENCL
ORIGINAL CONSTRUCTION 2009ATHLETICS 6,693 $472,809 $71.00 MAYOTTE JACOBS
0401W AKERS GOLF-EQUIPMENT STRG-WEST
ORIGINAL CONSTRUCTION 2011ATHLETICS 2,579 $55,000 $21.00
FACILITIES INFORMATION SERVICES 4
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0401 AKERS GOLF COURSE COMPLEX
0401X AKERS GOLF-CART SHELTER-WEST
ORIGINAL CONSTRUCTION 1995ATHLETICS 164 $0 $0.00
0401Y AKERS GOLF-INTERCOLLEGIATE GOLF
ORIGINAL CONSTRUCTION 2015ATHLETICS 15,533 $4,522,000 $291.00 TMP
0401Z AKERS GOLF-RESTROOM 2-EAST
ORIGINAL CONSTRUCTION 2014ATHLETICS 203 $75,570 $373.00 ROMTEC
COMPLEX TOTALS $5,810,79856,830
0326 AKERS HALL
0326 AKERS HALL
ORIGINAL CONSTRUCTION 1964HOUSING 385,797 $4,780,121 $12.00 CALDER
0030 ALUMNI CHAPEL
0030 ALUMNI CHAPEL
ORIGINAL CONSTRUCTION 1952SUPPORT 8,678 $230,545 $27.00 CALDER
0133 ANGELL UNIV SERVICES
0133 ANGELL UNIV SERVICES
ORIGINAL CONSTRUCTION 1988SUPPORT 75,441 $3,641,879 $48.00 MARGERUM
1998SUPPORT 753 $76,460 $102.00 PHYSICAL PLANTADD 1 - ADDITION 1 GAS STORAGE
2001SUPPORT 6,352 $380,496 $60.00 FTC & HADD 2 - ADDITION 2 STORAGE
82,546 $4,098,835
COMPLEX TOTALS $4,098,83582,546
FACILITIES INFORMATION SERVICES 5
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0132 ANTHONY HALL COMPLEX
0132 ANTHONY HALL
ORIGINAL CONSTRUCTION 1955ACADEMIC 226,275 $3,870,380 $17.00 MUNSON
1964ACADEMIC 895 $9,477 $11.00 PHYSICAL PLANTADD 1 - ADDITION 1
1997ACADEMIC 92,584 $8,812,379 $95.00 BEI ASSOCIATESADD 2 - ADDITION 2
319,754 $12,692,236
0132A ANTHONY-COOLING TOWER
ORIGINAL CONSTRUCTION 19970 $0 $0.00 BEI ASSOCIATES
COMPLEX TOTALS $12,692,236319,754
0031 AUDITORIUM
0031 AUDITORIUM
ORIGINAL CONSTRUCTION 1940ACADEMIC 161,113 $1,025,000 $6.00 MUNSON
0182 BAKER HALL
0182 BAKER HALL
ORIGINAL CONSTRUCTION 1967ACADEMIC 60,298 $1,647,464 $27.00 EBERLE SMITH
0517 BEAL GARDEN-GAZEBO
0517 BEAL GARDEN-GAZEBO
ORIGINAL CONSTRUCTION 1989SUPPORT 110 $1,703 $15.00
0518 BEAL GARDEN-SHED
0518 BEAL GARDEN-SHED
ORIGINAL CONSTRUCTION 1960SUPPORT 315 $6,590 $21.00
0012 BEAUMONT TOWER
0012 BEAUMONT TOWER
FACILITIES INFORMATION SERVICES 6
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0012 BEAUMONT TOWER
0012 BEAUMONT TOWER
ORIGINAL CONSTRUCTION 1928ACADEMIC 2,536 $110,437 $44.00 DONALDSON-MEIER
0471 BEEF CATTLE RESEARCH CENTER COMPLEX
0471A BEEF CATTLE RESEARCH-MAIN
ORIGINAL CONSTRUCTION 1963FARMS 15,378 $230,277 $15.00 FRANK AND STEIN
1968FARMS 3,943 $9,500 $2.00ADD 1 - ADDITION 1 ISOLATION BARN
1972FARMS 1,007 $9,060 $9.00ADD 3 - ADDITION 3 FEEDWAY
2006FARMS 34,881 $0 $0.00 FARMSADD 4 - ADDITION 4 MAIN BLDG
55,209 $248,837
0471E BEEF CATTLE RESEARCH-GLASS SILOS
ORIGINAL CONSTRUCTION 19710 $0 $0.00
0471H BEEF CATTLE RESEARCH-BUNKER SILO
ORIGINAL CONSTRUCTION 19630 $0 $0.00
0471I BEEF CATTLE RESEARCH-ANIMAL SHLTR
ORIGINAL CONSTRUCTION 1981FARMS 14,490 $147,247 $10.00 PHYSICAL PLANT
0471K BEEF CATTLE RESEARCH-HAY STRG
ORIGINAL CONSTRUCTION 1990FARMS 10,468 $64,161 $6.00 WHITEFORDASSOC
0471N BEEF CATTLE RESEARCH-HANDLING
ORIGINAL CONSTRUCTION 1996FARMS 1,635 $686,452 $420.00 CAPITALCONSULTANTS
COMPLEX TOTALS $1,146,69781,802
0480 BEEF CATTLE-STUDENT HOUSING
0480 BEEF CATTLE-STUDENT HOUSING
FACILITIES INFORMATION SERVICES 7
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0480 BEEF CATTLE-STUDENT HOUSING
0480 BEEF CATTLE-STUDENT HOUSING
ORIGINAL CONSTRUCTION 1998FARMS 1,000 $84,350 $84.00 PHYSICAL PLANT
0002 BERKEY HALL
0002 BERKEY HALL
ORIGINAL CONSTRUCTION 1947ACADEMIC 152,169 $1,177,019 $8.00 MUNSON
0079 BESSEY HALL
0079 BESSEY HALL
ORIGINAL CONSTRUCTION 1961ACADEMIC 137,398 $2,201,200 $16.00 CALDER
1994ACADEMIC 13,265 $3,039,255 $229.00 MCNAMEE,PORTER,SEELY
ADD 1 - ADDITION 1
150,663 $5,240,455
COMPLEX TOTALS $5,240,455150,663
0233 BIO ENGINEERING
0233 BIO ENGINEERING
ORIGINAL CONSTRUCTION 2015ACADEMIC 131,197 $52,229,589 $398.00 INTEGRATEDDESIGN
0168 BIOCHEMISTRY
0168 BIOCHEMISTRY
ORIGINAL CONSTRUCTION 1964ACADEMIC 157,744 $4,235,641 $27.00 HARLEY-ELLINGTON
0160 BIOMEDICAL PHYSICAL SCIENCES
0160 BIOMEDICAL PHYSICAL SCIENCES
ORIGINAL CONSTRUCTION 2001ACADEMIC 377,230 $78,164,009 $207.00 SMITH HINCHMANGRYLL
0452 BOTANY FIELD LAB COMPLEX
0452 BOTANY FIELD LAB
FACILITIES INFORMATION SERVICES 8
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0452 BOTANY FIELD LAB COMPLEX
0452 BOTANY FIELD LAB
ORIGINAL CONSTRUCTION 1969FARMS 12,442 $57,205 $5.00 PHYSICAL PLANT
0452A BOTANY FIELD LAB-PESTICIDE STRG
ORIGINAL CONSTRUCTION 2001FARMS 2,560 $80,000 $31.00 PHYSICAL PLANT
2006FARMS 960 $30,000 $31.00 DESIGN & BUILDADD 1 - ADDITION 1
3,520 $110,000
COMPLEX TOTALS $167,20515,962
0443 BOTANY FIELD RESEARCH COMPLEX
0443B BOTANY QUONSET STORAGE 1
ORIGINAL CONSTRUCTION 1949FARMS 2,157 $16,800 $8.00 KUTCHINS
0477 BOX FARM COMPLEX
0477A BOX FARM-HOUSE
ORIGINAL CONSTRUCTION 1982FARMS 2,878 $197,823 $69.00
0477B BOX FARM-GARAGE
ORIGINAL CONSTRUCTION 1982FARMS 625 $8,922 $14.00
0477C BOX FARM-BARN
ORIGINAL CONSTRUCTION 1982FARMS 1,424 $21,808 $15.00
COMPLEX TOTALS $228,5534,927
0069 BRESLIN
0069 BRESLIN
FACILITIES INFORMATION SERVICES 9
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0069 BRESLIN
0069 BRESLIN
ORIGINAL CONSTRUCTION 1989ACADEMIC 243,612 $37,475,716 $154.00 GIFFELS/HOYEMBASSO
2001ACADEMIC 29,915 $5,494,374 $184.00 IDS, INC.ADD 1 - ADDITION 1 BERKOWITZ
2017ACADEMIC 55,502 $34,353,276 $619.00 ROSSETTIADD 2 - ADDITION 2
2015ACADEMIC 899 $50,000 $56.00 IDSADD 3 - ADDITION 3 CANOPIES
329,928 $77,373,366
COMPLEX TOTALS $77,373,366329,928
0228 BROAD ART MUSEUM
0228 BROAD ART MUSEUM
ORIGINAL CONSTRUCTION 2012ACADEMIC 46,237 $28,936,136 $626.00 ZAHA HADIDARCHITECT
0300 BRODY COMPLEX
0310 BUTTERFIELD HALL
ORIGINAL CONSTRUCTION 1954HOUSING 99,743 $1,537,421 $15.00 CALDER
1962HOUSING 690 $26,138 $38.00 CALDERADD 1 - ADDITION 1
2014HOUSING 3,842 $914,396 $238.00 DESIGN PLUSADD 2 - ADDITION 2
104,275 $2,477,955
0311 RATHER HALL
ORIGINAL CONSTRUCTION 1954HOUSING 112,327 $1,572,656 $14.00 CALDER
2013HOUSING 5,082 $1,209,278 $238.00 SHW GROUPADD 2 - ADDITION 2 - PENTHOUSE
117,409 $2,781,934
0312 BRYAN HALL
ORIGINAL CONSTRUCTION 1954HOUSING 112,607 $1,652,730 $15.00 CALDER
FACILITIES INFORMATION SERVICES 10
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0300 BRODY COMPLEX
0312 BRYAN HALL
2013HOUSING 5,230 $1,244,502 $238.00 SHW GROUPADD 1 - ADDITION NO. 1
117,837 $2,897,232
0313 BRODY HALL
ORIGINAL CONSTRUCTION 1954HOUSING 99,252 $1,619,099 $16.00 CALDER
1955HOUSING 32,962 $1,479,636 $45.00 CALDERADD 1 - ADDITION 1
2011HOUSING 33,832 $8,052,254 $238.00 DESIGN PLUSADD 3 - ADDITION 3
166,046 $11,150,989
0314 EMMONS HALL
ORIGINAL CONSTRUCTION 1955HOUSING 109,591 $1,475,787 $13.00 CALDER
2011HOUSING 3,487 $490,994 $141.00 DESIGN PLUSADD 1 - ADDITION 1
113,078 $1,966,781
0315 BAILEY HALL
ORIGINAL CONSTRUCTION 1955HOUSING 110,247 $1,509,607 $14.00 CALDER
2012HOUSING 5,133 $1,221,654 $238.00 SHW GROUPADD 1 - ADDITION NO. 1 PENTHOUSE
115,380 $2,731,261
0315A BAILEY-GREENHOUSE
ORIGINAL CONSTRUCTION 2012HOUSING 2,145 $82,021 $38.00 PHYSICAL PLANT
0316 ARMSTRONG HALL
ORIGINAL CONSTRUCTION 1955HOUSING 112,927 $1,586,470 $14.00 CALDER
2013HOUSING 5,188 $1,234,744 $238.00 SHW GROUPADD 1 - ADDITION NO. 1
118,115 $2,821,214
FACILITIES INFORMATION SERVICES 11
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0300 BRODY COMPLEX
COMPLEX TOTALS $26,909,387854,285
0080 BUSINESS COLLEGE
0080 BUSINESS COLLEGE
ORIGINAL CONSTRUCTION 1961ACADEMIC 58,199 $1,381,866 $24.00 CALDER
1993ACADEMIC 125,114 $14,400,000 $115.00 HEPYADD 1 - ADDITION 1 ELI BROAD
2019ACADEMIC 104,593 $48,245,371 $461.00 FTC&HADD 2 - ADDITION 2- GRADUATEPAVILION
287,906 $64,027,237
COMPLEX TOTALS $64,027,237287,906
0617 CANDLEWOOD SUITES
0617 CANDLEWOOD SUITES
ORIGINAL CONSTRUCTION 2001OTHER 63,675 $4,500,000 $71.00 DORCHEN/MARTINASSOC
0321 CASE HALL
0321 CASE HALL
ORIGINAL CONSTRUCTION 1961HOUSING 284,312 $3,862,270 $14.00 SARVIS
2008HOUSING 2,006 $416,120 $207.00 FTCHADD 2 - ADDITION 2 - LOADING DOCK
2012HOUSING 16,189 $14,402,008 $890.00 SMITH GROUPADD 3 - ADDITION 3
302,507 $18,680,398
COMPLEX TOTALS $18,680,398302,507
FACILITIES INFORMATION SERVICES 12
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0181A CENTER INTEGRATIVE PLANT SYS-LAB
0181A CENTER INTEGRATIVE PLANT SYS-LAB
ORIGINAL CONSTRUCTION 1967ACADEMIC 37,530 $537,936 $14.00 KINGSCOTT
1969ACADEMIC 38,776 $1,337,533 $34.00 KINGSCOTTADD 1 - ADDITION 1 HEADHOUSE
2002ACADEMIC 13,108 $791,650 $60.00 PHYSICAL PLANTADD 2 - ADDITION 2POLYGREENHOUSE
2004ACADEMIC 8,150 $115,470 $14.00 PHYSICAL PLANTADD 3 - ADDITION 3POLYGREENHOUSE
97,564 $2,782,589
COMPLEX TOTALS $2,782,58997,564
0204 CENTRAL SCHOOL COMPLEX
0204 CENTRAL SCHOOL
ORIGINAL CONSTRUCTION 1916ACADEMIC 22,225 $92,827 $4.00 BOWD
1988ACADEMIC 2,014 $151,041 $75.00 WBDCADD 1 - ADDITION 1
24,239 $243,868
0204A CENTRAL SCHOOL-SHED
ORIGINAL CONSTRUCTION 1987OTHER 387 $3,500 $9.00 CAMPUS PARKPLANNING
COMPLEX TOTALS $247,36824,626
0060 CENTRAL SERVICES
0060 CENTRAL SERVICES
ORIGINAL CONSTRUCTION 1948SUPPORT 49,022 $504,839 $10.00 MUNSON
1952SUPPORT 9,598 $171,000 $18.00 MUNSONADD 1 - ADDITION 1
1956SUPPORT 11,415 $129,644 $11.00 MUNSONADD 2 - ADDITION 2
FACILITIES INFORMATION SERVICES 13
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0060 CENTRAL SERVICES
0060 CENTRAL SERVICES
70,035 $805,483
COMPLEX TOTALS $805,48370,035
0475 CHEMICAL WASTE FACILITY COMPLEX
0475A CHEMICAL WASTE FACILITY 1
ORIGINAL CONSTRUCTION 1981SUPPORT 1,537 $95,843 $62.00 PHYSICAL PLANT
2003SUPPORT 557 $65,000 $117.00 LEDY DESIGNGROUP
ADD 1 - ADDITION NO 1
2,094 $160,843
0475B CHEMICAL WASTE FACILITY 2
ORIGINAL CONSTRUCTION 1972SUPPORT 1,506 $44,637 $30.00 PHYSICAL PLANT
1989SUPPORT 3,120 $70,000 $22.00 PHYSICAL PLANTADD 1 - ADDITION 1
2013SUPPORT 480 $0 $0.00 IPFADD 2 - ADDITION 2 GARAGE
5,106 $114,637
0475C CHEMICAL WASTE CONT STRG
ORIGINAL CONSTRUCTION 1984SUPPORT 901 $33,411 $37.00 ARCHCONSORTIUM
2013SUPPORT 211 $37,330 $177.00 PHYSICAL PLANTADD 1 - ADDITION NO. 1-CONNECTORWING
1,112 $70,741
COMPLEX TOTALS $346,2218,312
0163 CHEMISTRY
0163 CHEMISTRY
FACILITIES INFORMATION SERVICES 14
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0163 CHEMISTRY
0163 CHEMISTRY
ORIGINAL CONSTRUCTION 1963ACADEMIC 282,368 $5,811,392 $21.00 CALDER
1997ACADEMIC 2,893 $272,000 $94.00 ORIONADD 1 - ADDITION 1 SUBSTATION
2008ACADEMIC 32,034 $16,007,470 $500.00 FTC & HADD 2 - ADDITION 2
317,295 $22,090,862
COMPLEX TOTALS $22,090,862317,295
0612 CHILDREN'S GARDEN COMPLEX
0612 CHILDREN'S GARDEN-SUPPORT STRUCT
ORIGINAL CONSTRUCTION 2001ACADEMIC 1,515 $21,630 $14.00 PHYSICAL PLANT
2009ACADEMIC 243 $25,000 $103.00 PHYSICAL PLANTADD 1 - ADDITION 1 COVERED PATIO
1,758 $46,630
0612A CHILDREN'S GARDEN-GARDEN HOUSE
ORIGINAL CONSTRUCTION 1992OTHER 246 $3,379 $14.00 PHYSICAL PLANT
0612B CHILDREN'S GARDEN-RESTROOM
ORIGINAL CONSTRUCTION 2015ACADEMIC 304 $237,669 $781.00 WTA ARCHITECTS
COMPLEX TOTALS $287,6782,308
0019 CHITTENDEN HALL
0019 CHITTENDEN HALL
ORIGINAL CONSTRUCTION 1901ACADEMIC 16,809 $15,000 $1.00 GEORGE LOHMAN
FACILITIES INFORMATION SERVICES 15
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0202 CLINICAL CENTER-ANIMAL
0202 CLINICAL CENTER-ANIMAL
ORIGINAL CONSTRUCTION 1976ACADEMIC 43,941 $2,170,582 $49.00 CALDER
2014ACADEMIC 1,367 $619,720 $453.00 PETER BASSOADD 1 - ADDITION 1
45,308 $2,790,302
COMPLEX TOTALS $2,790,30245,308
0200 CLINICAL CENTER-CLINIC
0200 CLINICAL CENTER-CLINIC
ORIGINAL CONSTRUCTION 1976ACADEMIC 182,756 $8,593,874 $47.00 CALDER
1985ACADEMIC 4,987 $2,200,000 $441.00 TORKE/MASLOWSKI
ADD 1 - ADDITION 1 M.R.C.
1988ACADEMIC 8,586 $4,450,000 $518.00 THRESHOLD/GEADD 2 - ADDITION 2 M.R.C.
2003ACADEMIC 18,333 $5,030,131 $274.00 H & H SYSTEMS &DES
ADD 3 - ADDITION 3RADIOPHARMACEUTICAL
214,662 $20,274,005
COMPLEX TOTALS $20,274,005214,662
0201 CLINICAL CENTER-OFFICE/LAB
0201 CLINICAL CENTER-OFFICE/LAB
ORIGINAL CONSTRUCTION 1976ACADEMIC 77,530 $3,415,544 $44.00 CALDER
0592 COMM STRG 1 SPARTAN VILLAGE
0592 COMM STRG 1 SPARTAN VILLAGE
ORIGINAL CONSTRUCTION 2001SUPPORT 119 $15,000 $126.00 LEDY DESIGNGROUP
FACILITIES INFORMATION SERVICES 16
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0593 COMM STRG 2 SPARTAN VILLAGE
0593 COMM STRG 2 SPARTAN VILLAGE
ORIGINAL CONSTRUCTION 2001SUPPORT 59 $15,000 $254.00 LEDY DESIGNGROUP
0613 COMM STRG-SOUTH CAMPUS
0613 COMM STRG-SOUTH CAMPUS
ORIGINAL CONSTRUCTION 2001SUPPORT 319 $58,000 $182.00 PHYSICAL PLANT
0610 COMM STRG-UNIV VILLAGE
0610 COMM STRG-UNIV VILLAGE
ORIGINAL CONSTRUCTION 2000SUPPORT 341 $55,000 $161.00 PHYSICAL PLANT
0084 COMMUNICATION ARTS COMPLEX
0084 COMMUNICATION ARTS
ORIGINAL CONSTRUCTION 1981ACADEMIC 248,215 $17,760,432 $72.00 HARLEY-ELLINGTON
0084A COMMUNICATION ARTS - MITN STORAGE
ORIGINAL CONSTRUCTION 1990ACADEMIC 240 $48,723 $203.00 GILLETTASSOCIATION
0084B COMMUNICATION ARTS - COOLING TOWER
ORIGINAL CONSTRUCTION 1981ACADEMIC 0 $0 $0.00 HARLEY-ELLINGTON
0084C COMMUNICATION ARTS - UPLINK SHELTER
ORIGINAL CONSTRUCTION 2014ACADEMIC 51 $0 $0.00
COMPLEX TOTALS $17,809,155248,506
0615 COMPOSTING FACILITY SOUTH CAMPUS
0615 COMPOSTING FACILITY SOUTH CAMPUS
ORIGINAL CONSTRUCTION 2002FARMS 13,598 $79,591 $6.00 FTC & H
2006FARMS 27,957 $545,000 $19.00ADD 1 - ADDITION NO. 1 - LEAN TO
FACILITIES INFORMATION SERVICES 17
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0615 COMPOSTING FACILITY SOUTH CAMPUS
0615 COMPOSTING FACILITY SOUTH CAMPUS
41,555 $624,591
COMPLEX TOTALS $624,59141,555
0035 COMPUTER CENTER
0035 COMPUTER CENTER
ORIGINAL CONSTRUCTION 1948ACADEMIC 78,933 $1,058,644 $13.00 MUNSON
0328 CONRAD HALL
0328 CONRAD HALL
ORIGINAL CONSTRUCTION 1964ACADEMIC 23,096 $455,510 $20.00 CALDER
0020 COOK-SEEVERS HALL
0020 COOK-SEEVERS HALL
ORIGINAL CONSTRUCTION 1889ACADEMIC 11,534 $7,500 $1.00 S. JOHNSON
2018ACADEMIC 3,061 $2,961,079 $967.00 HOPKINSBURNSDESIGN
ADD 1 - ADDITION NO. 1
14,595 $2,968,579
COMPLEX TOTALS $2,968,57914,595
0009 COWLES HOUSE
0009 COWLES HOUSE
ORIGINAL CONSTRUCTION 1857SUPPORT 5,405 $0 $0.00 J. J. SCOTT
1950SUPPORT 10,540 $112,577 $11.00 CALDERADD 1 - ADDITION 1
2000SUPPORT 965 $105,628 $109.00 PHYSICAL PLANTADD 2 - ADDITION 2 - PORCHENCLOSURE
FACILITIES INFORMATION SERVICES 18
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0009 COWLES HOUSE
0009 COWLES HOUSE
2020SUPPORT 1,267 $4,075,384 $3,217.00 HOPKINSBURNSDESIGN
ADD 3 - ADDITION 3 - EXPANDGARAGE
18,177 $4,293,589
COMPLEX TOTALS $4,293,58918,177
0614 CREW MEN & WOMEN BOATHOUSE COMPLEX
0614A CREW WOMEN'S BOATHOUSE
ORIGINAL CONSTRUCTION 20028,821 $261,000 $30.00 FREEMAN & SMITH
0614B CREW MEN'S BOATHOUSE
ORIGINAL CONSTRUCTION 20024,951 $152,250 $31.00 FREEMAN SMITH
COMPLEX TOTALS $413,25013,772
0442 CROP SCIENCE COMPLEX
0213 CROP SCIENCE-FIELD LAB
ORIGINAL CONSTRUCTION 1954FARMS 12,393 $67,640 $5.00 MUNSON
1996FARMS 37,470 $2,339,020 $62.00 SIMS-VARNERADD 1 - CROP SCI FIELD LAB
2015FARMS 3,246 $118,037 $36.00 ORASKOADD 2 - GREENHOUSE
53,109 $2,524,697
0442E CROP SCIENCE-STRG 1
ORIGINAL CONSTRUCTION 1985FARMS 16,266 $104,100 $6.00 PHYSICAL PLANT
0442F CROP SCIENCE-PESTICIDE/HERBICIDE
ORIGINAL CONSTRUCTION 1992FARMS 3,222 $138,000 $43.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 19
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0442 CROP SCIENCE COMPLEX
0442G CROP SCIENCE-RESEARCH
ORIGINAL CONSTRUCTION 1992FARMS 1,406 $60,678 $43.00 PHYSICAL PLANT
0442J CROP SCIENCE-FERTILIZER STORAGE
ORIGINAL CONSTRUCTION 2011FARMS 2,414 $78,000 $32.00
0442K CROP SCIENCE-STRG 2
ORIGINAL CONSTRUCTION 2015FARMS 14,121 $199,840 $14.00 TAILORED
COMPLEX TOTALS $3,105,31590,538
0469 DAIRY CATTLE TEACHING & RES COMPLEX
0469A DAIRY RESEARCH-HEIFER BARN 1
ORIGINAL CONSTRUCTION 1961FARMS 7,272 $39,233 $5.00 J.W. OLDS
0469F DAIRY RESEARCH-FOREMAN'S HSE
ORIGINAL CONSTRUCTION 1961FARMS 3,852 $232,332 $60.00 J.W. OLDS
0469H DAIRY RESEARCH-MAIN BARN
ORIGINAL CONSTRUCTION 1961FARMS 24,819 $148,991 $6.00 J W OLDS
1970FARMS 3,781 $78,400 $21.00 PHYSICAL PLANTADD 1 - ADDITION 1 MILKING PARLOR
1984FARMS 21,461 $590,843 $28.00 PHYSICAL PLANTADD 2 - ADDITION 2 DAIRY BARN
1996FARMS 3,717 $362,741 $98.00 CAPITALCONSULTANTS
ADD 3 - ADDITION 3 INTENSIVEMETABOLIS
53,778 $1,180,975
0469L DAIRY RESEARCH-SWITCH GEAR
ORIGINAL CONSTRUCTION 1983FARMS 64 $4,837 $76.00 PHYSICAL PLANT
0469O DAIRY RESEARCH-SOUTH HAY BARN
ORIGINAL CONSTRUCTION 1987FARMS 13,420 $89,700 $7.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 20
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0469 DAIRY CATTLE TEACHING & RES COMPLEX
0469P DAIRY RESEARCH-HEIFER BARN 2
ORIGINAL CONSTRUCTION 1988FARMS 10,503 $272,850 $26.00 PHYSICAL PLANT
0469Q DAIRY RESEARCH-CONCRETE SILOS
ORIGINAL CONSTRUCTION 1979FARMS 0 $0 $0.00
COMPLEX TOTALS $1,819,92788,889
0469T DAIRY RESEARCH - HOOP HOUSE
0469T DAIRY RESEARCH - HOOP HOUSE
ORIGINAL CONSTRUCTION 2022FARMS 0 $0 $0.00 LANDMANAGEMENT
0244 DATA CENTER
0244 DATA CENTER
ORIGINAL CONSTRUCTION 2017SUPPORT 25,505 $24,497,008 $960.00 CH2M HILL ENG INC
0224 DEMMER SHOOTING SPORTS EDUC COMPLEX
0224 DEMMER SPORTS EDUCATION
ORIGINAL CONSTRUCTION 2009ATHLETICS 25,776 $3,500,000 $136.00 DESIGN BUILD
0224A DEMMER SPORTS EDUCATION-STRG
ORIGINAL CONSTRUCTION 2009ATHLETICS 1,082 $50,000 $46.00 DESIGN BUILD
COMPLEX TOTALS $3,550,00026,858
0057 DEMONSTRATION HALL
0057 DEMONSTRATION HALL
ORIGINAL CONSTRUCTION 1928ACADEMIC 90,353 $355,000 $4.00 BOWD-MUNSON
FACILITIES INFORMATION SERVICES 21
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0057 DEMONSTRATION HALL
0057 DEMONSTRATION HALL
1948ACADEMIC 5,855 $0 $0.00ADD 1 - ADDITION NO. 1
96,208 $355,000
COMPLEX TOTALS $355,00096,208
0601 DOBIE TOWER TV & FM TRANSMITTING
0601 DOBIE TOWER TV/FM TRANS
ORIGINAL CONSTRUCTION 1954ACADEMIC 2,214 $28,447 $13.00 MUNSON
1973ACADEMIC 358 $18,630 $52.00 PHYSICAL PLANTADD 1 - ADDITION 1
1993ACADEMIC 599 $119,640 $200.00 FISHBECKADD 2 - ADDITION 2
3,171 $166,717
0601A DOBIE TOWER TV/FM TRANS-TOWER
ORIGINAL CONSTRUCTION 20120 $1,041,263 $0.00 KPFF CONSULTINGENG
COMPLEX TOTALS $1,207,9803,171
0077 DUFFY DAUGHTERY-SAAC COMPLEX
0077 DUFFY DAUGHERTY-SAAC
ORIGINAL CONSTRUCTION 1980ATHLETICS 14,189 $1,429,925 $101.00 WAKELY-KUSHNERASSOC
1985ATHLETICS 98,539 $2,807,141 $28.00 SIMS-VARNER &ASSOC
ADD 1 - ADDITION 1 FOOTBALLPRACTICE
1997ATHLETICS 21,094 $4,597,172 $218.00 GHAFARI ASSOCADD 2 - ADDITION 2
1998ATHLETICS 40,201 $5,669,343 $141.00 GHAFARI ASSOCADD 3 - ADDITION 3 STUDENT A.A.C
2008ATHLETICS 33,223 $8,961,769 $270.00 INTEGRATEDDESIGN
ADD 4 - ADDITION 4 SKANDALARIS
FACILITIES INFORMATION SERVICES 22
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0077 DUFFY DAUGHTERY-SAAC COMPLEX
0077 DUFFY DAUGHERTY-SAAC
2010ATHLETICS 190 $45,000 $237.00 INTEGRATEDDESIGN
ADD 5 - ADDITION 5
2015ATHLETICS 1,915 $715,306 $374.00 INTEGRATEDDESIGN
ADD 6 - ADDITION 6
2021ATHLETICS 1,355 $3,976,412 $2,934.00 GRANGERADD 7 - ADDITION 7
210,706 $28,202,068
0077A DUFFY DAUGHERTY-FILM TOWER
ORIGINAL CONSTRUCTION 2013ATHLETICS 610 $185,792 $305.00 FTC&H
COMPLEX TOTALS $28,387,860211,316
0470 ENDOCRINE RESEARCH CENTER COMPLEX
0470C ENDOCRINE RES-SURGERY
ORIGINAL CONSTRUCTION 1962FARMS 4,078 $22,687 $6.00 SUP ARCHITECT
0470D ENDOCRINE RES-SWINE
ORIGINAL CONSTRUCTION 1997FARMS 4,449 $400,000 $90.00 CAPITALCONSULTANTS
0470E MSU POLLINATOR PERFORMANCE CENTER
ORIGINAL CONSTRUCTION 2007FARMS 6,363 $700,000 $110.00 WEDEVENBROS/HAMILTN
2010FARMS 6,752 $198,000 $29.00 STEDFASTCONSTRUCTIO
ADD 1 - ADDITION 1
13,115 $898,000
0470G ENDOCRINE RES-ADREC
ORIGINAL CONSTRUCTION 2010FARMS 7,007 $696,260 $99.00 WILCOXPROFESSIONAL
0470H ENDOCRINE RES-ADREC CONTAINER
ORIGINAL CONSTRUCTION 2014FARMS 320 $250,000 $781.00
FACILITIES INFORMATION SERVICES 23
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0470 ENDOCRINE RESEARCH CENTER COMPLEX
COMPLEX TOTALS $2,266,94728,969
0081 ENGINEERING
0081 ENGINEERING
ORIGINAL CONSTRUCTION 1962ACADEMIC 177,895 $3,096,882 $17.00 GIFFELS-ROSSETTI
1962ACADEMIC 22,442 $391,282 $17.00 GIFFELS-ROSSETTIADD 1 - ADDITION 1
1989ACADEMIC 139,495 $12,700,000 $91.00 ALBERT KAHNASSOC
ADD 2 - ADDITION 2
1996ACADEMIC 85,252 $12,567,085 $147.00 ALBERT KAHNASSOC
ADD 3 - ADDITION 3
2008ACADEMIC 643 $529,122 $823.00 DLZADD 4 - ADDITION 4 - VESTIBULE
2016ACADEMIC 8,739 $3,030,508 $347.00 PETER BASSOADD 5 - ADDITION 5
434,466 $32,314,879
COMPLEX TOTALS $32,314,879434,466
0206 ENGINEERING RES JOLLY RD COMPLEX
0206 ENG RESEARCH-JOLLY RD
ORIGINAL CONSTRUCTION 1979ACADEMIC 10,215 $260,000 $25.00 DESIGN & BUILD
0206A ENG RESEARCH-JOLLY RD-CONC LAB
ORIGINAL CONSTRUCTION 2002ACADEMIC 11,710 $1,670,878 $143.00 HOBBS & BLACK
2007ACADEMIC 1,990 $363,532 $183.00 FTC & HADD 1 - ADDITION 1 FURNACEENCLOSURE
13,700 $2,034,410
0206B ENG RESEARCH-JOLLY RD-STRG
ORIGINAL CONSTRUCTION 2011FARMS 2,222 $51,000 $23.00
FACILITIES INFORMATION SERVICES 24
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0206 ENGINEERING RES JOLLY RD COMPLEX
COMPLEX TOTALS $2,345,41026,137
0203 ENGINEERING RESEARCH COMPLEX
0203A ENG RESEARCH COMPLEX
ORIGINAL CONSTRUCTION 1986ACADEMIC 81,802 $4,010,000 $49.00 PHYSICAL PLANT
2004ACADEMIC 8,364 $1,744,126 $209.00 FTC & HADD 1 - ADDITION 1 NMR
2007ACADEMIC 29,543 $5,407,011 $183.00 DLZADD 2 - ADDITION 2 ENERGY &AUTOMOT
2010ACADEMIC 2,847 $746,520 $262.00 DICLEMENTESIEGEL
ADD 3 - ADDITION 3 OFFICE ADDITION
2018ACADEMIC 5,494 $3,960,894 $721.00 C2AEADD 4 - ADDITION 4 FRAUNHOFERCENTER
128,050 $15,868,551
COMPLEX TOTALS $15,868,551128,050
0474 ENTOMOLOGY FIELD & RESEARCH COMPLEX
0474 ENTOMOLOGY FIELD RESEARCH-MAIN
ORIGINAL CONSTRUCTION 1966FARMS 8,034 $46,176 $6.00 PHYSICAL PLANT
0130 ENTOMOLOGY STORAGE
0130 ENTOMOLOGY STORAGE
ORIGINAL CONSTRUCTION 1965FARMS 648 $1,133 $2.00 PHYSICAL PLANT
0639 ENVIRO HEALTH AND SAFETY-RAD STRG
0639 ENVIRO HEALTH AND SAFETY-RAD STRG
ORIGINAL CONSTRUCTION 2012SUPPORT 1,647 $110,000 $67.00 LANDMANAGEMENT
FACILITIES INFORMATION SERVICES 25
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0144 ERICKSON HALL
0144 ERICKSON HALL
ORIGINAL CONSTRUCTION 1957ACADEMIC 209,364 $3,563,610 $17.00 CALDER
1974ACADEMIC 2,515 $770,000 $306.00 CALDERADD 2 - ADDITION 2
2006ACADEMIC 7,015 $1,587,193 $226.00 DESIGN PLUSADD 3 - ADDITION 3
2009ACADEMIC 355 $72,450 $204.00 DESIGN PLUSADD 4 - ADDITION 4
219,249 $5,993,253
COMPLEX TOTALS $5,993,253219,249
0015 EUSTACE-COLE HALL
0015 EUSTACE-COLE HALL
ORIGINAL CONSTRUCTION 1888ACADEMIC 9,864 $7,000 $1.00 WM. D. APPLEYARD
1998ACADEMIC 1,568 $1,339,353 $854.00 ARCHITECTS FOURADD 1 - ADDITION 1
11,432 $1,346,353
COMPLEX TOTALS $1,346,35311,432
0218 EXECUTIVE DEVELOPMENT
0218 EXECUTIVE DEVELOPMENT
ORIGINAL CONSTRUCTION 2001ACADEMIC 98,257 $21,250,000 $216.00 KEYSTONE DESIGN
0706 FACULTY APARTMENT SUBSTATION
0706 FACULTY APARTMENT SUBSTATION
ORIGINAL CONSTRUCTION 1985OTHER 1,094 $267,844 $245.00 PHYSICAL PLANT
2000OTHER 321 $49,000 $153.00 PHYSICAL PLANTADD 1 - ADDITION 1
FACILITIES INFORMATION SERVICES 26
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0706 FACULTY APARTMENT SUBSTATION
0706 FACULTY APARTMENT SUBSTATION
1,415 $316,844
COMPLEX TOTALS $316,8441,415
0327 FEE HALL
0327 FEE HALL
ORIGINAL CONSTRUCTION 1964ACADEMIC 386,485 $4,780,121 $12.00 CALDER
1972ACADEMIC 1,631 $50,000 $31.00 PHYSICAL PLANTADD 1 - ADDITION 1
388,116 $4,830,121
COMPLEX TOTALS $4,830,121388,116
0131 FIRE STATION
0131 FIRE STATION
ORIGINAL CONSTRUCTION 1955SUPPORT 8,334 $110,010 $13.00 MUNSON
1981SUPPORT 1,098 $121,632 $111.00 PHYSICAL PLANTADD 1 - ADDITION 1
9,432 $231,642
COMPLEX TOTALS $231,6429,432
0207 FOOD PROCESSING INNOVATION CENTER
0207 FOOD PROCESSING INNOVATION CENTER
ORIGINAL CONSTRUCTION 1971ACADEMIC 6,479 $426,000 $66.00 GRANGERCONSTRUCTION
FACILITIES INFORMATION SERVICES 27
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0207 FOOD PROCESSING INNOVATION CENTER
0207 FOOD PROCESSING INNOVATION CENTER
2018ACADEMIC 2,916 $2,734,066 $938.00 DAN VOSCONSTRUCTION
ADD 2 - ADDITION NO. 2
9,395 $3,160,066
COMPLEX TOTALS $3,160,0669,395
0186 FOOD SAFETY TOXICOLOGY
0186 FOOD SAFETY TOXICOLOGY
ORIGINAL CONSTRUCTION 1997ACADEMIC 115,133 $19,166,215 $166.00 HARLEYELLINGTON
0179 FOOD SCIENCE
0179 FOOD SCIENCE
ORIGINAL CONSTRUCTION 1966ACADEMIC 115,530 $3,442,532 $30.00 KAHN
2004ACADEMIC 4,571 $12,788,671 $2,798.00 PETER BASSOADD 1 - ADDITION 1 PENTHOUSE
120,101 $16,231,203
COMPLEX TOTALS $16,231,203120,101
0171 FOOD STORES
0171 FOOD STORES
ORIGINAL CONSTRUCTION 1964SUPPORT 81,230 $1,063,800 $13.00 MANSON,KANE,JACKSON
2006SUPPORT 12,227 $3,131,412 $256.00 DESIGN PLUSADD 1 - ADDITION 1 RELOCATEBAKERY
93,457 $4,195,212
FACILITIES INFORMATION SERVICES 28
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0171 FOOD STORES
COMPLEX TOTALS $4,195,21293,457
0164 FRIB COMPLEX
0164 FRIB
ORIGINAL CONSTRUCTION 1963ACADEMIC 31,263 $1,200,000 $38.00 KENNETH BLACKASSOC
1968ACADEMIC 17,225 $496,450 $29.00 KENNETH BLACKASSOC
ADD 1 - ADDITION 1
1978ACADEMIC 5,056 $318,076 $63.00 HOLMES ANDBLACK
ADD 2 - ADDITION 2 WEST HIGH BAY
1979ACADEMIC 0 $79,500 $0.00 PHYSICAL PLANTADD 3 - ADDITION 3
1982ACADEMIC 33,497 $5,150,000 $154.00 COMMONWEALTHASSOC
ADD 4 - ADDITION 4
1985ACADEMIC 0 $126,538 $0.00 N.S.C.L.ADD 5 - ADDITION 5
1988ACADEMIC 6,445 $1,544,700 $240.00 HEPYADD 6 - ADDITION 6
1996ACADEMIC 6,770 $1,028,295 $152.00 HEPYADD 7 - ADDITION 7 EAST HIGH BAY
1999ACADEMIC 6,624 $1,549,561 $234.00 HARLEYELLINGTON
ADD 8 - ADDITION 8 CRYOGENICEXPANSION
2003ACADEMIC 13,389 $2,955,560 $221.00 HARLEY ELLISADD 9 - ADDITION 9 OFFICE
2004ACADEMIC 14,811 $2,206,830 $149.00 HARLEY ELLISADD 10 - ADDITION 10 ASSEMBLY
2009ACADEMIC 26,802 $6,682,500 $249.00 HARLEY ELLISADD 11 - ADDITION 11 OFFICE
2009ACADEMIC 13,066 $2,628,800 $201.00 HARLEY ELLISADD 12 - ADDITION 12 LOW ENERGYRES
2011ACADEMIC 33,189 $8,132,170 $245.00 URSCORPORATION
ADD 14 - ADDITION 14 OFFICE
2011ACADEMIC 16,348 $2,675,035 $164.00 URSCORPORATION
ADD 15 - ADDITION 15 HIGH BAY
2016ACADEMIC 63,883 $23,753,826 $372.00 SMITH GROUPADD 16 - ADDITION 16 OFFICE
2015ACADEMIC 36,652 $15,500,000 $423.00 SMITH GROUPADD 17 - ADDITION 17 RADIO FREQHIGHBAY
2020ACADEMIC 22,219 $21,560,246 $970.00 BARTON MALOWADD 18 - ADDITION 18 HIGH RESSPECTROM
2019ACADEMIC 15,628 $10,300,123 $659.00 BARTON MALOWADD 19 - ADDITION 19 CRYOGENICASSEMBLY
FACILITIES INFORMATION SERVICES 29
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0164 FRIB COMPLEX
0164 FRIB
362,867 $107,888,210
COMPLEX TOTALS $107,888,210362,867
0522 GAS METER STATION
0522 GAS METER STATION
ORIGINAL CONSTRUCTION 1985SUPPORT 139 $180,087 $1,296.00 PHYSICAL PLANT
0176 GEOGRAPHY
0176 GEOGRAPHY
ORIGINAL CONSTRUCTION 1965ACADEMIC 31,221 $795,230 $25.00 CALDER
0028 GILTNER HALL
0028 GILTNER HALL
ORIGINAL CONSTRUCTION 1913ACADEMIC 13,440 $33,000 $2.00 BOWD
1931ACADEMIC 26,172 $110,165 $4.00 BOWD-MUNSONADD 1 - ADDITION 1 (ANATOMY & RES)
1938ACADEMIC 26,559 $120,938 $5.00 BOWD-MUNSONADD 2 - ADDITION 2 (NORTH WING OFVET)
1940ACADEMIC 13,938 $59,874 $4.00 BOWD-MUNSONADD 3 - ADDITION 3 (SOUTH WING OFVET)
1952ACADEMIC 170,824 $2,287,483 $13.00 MUNSONADD 5 - ADDITION 5 (VET & ANATOMY)
1968ACADEMIC 1,068 $118,168 $111.00 CALDERADD 6 - ADDITION 6 (TRANSFORMERROOM)
1994ACADEMIC 1,355 $387,589 $286.00 ORIONENGINEERING
ADD 7 - ADDITION 7 (ELECSUBSTATION)
253,356 $3,117,217
COMPLEX TOTALS $3,117,217253,356
FACILITIES INFORMATION SERVICES 30
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0476 HANCOCK TURFGRASS FIELD LAB COMPLEX
0476 HANCOCK TURFGRASS-FIELD LAB
ORIGINAL CONSTRUCTION 1980FARMS 7,530 $106,504 $14.00 PHYSICAL PLANT
0476B HANCOCK TURFGRASS-PESTICIDE STRG
ORIGINAL CONSTRUCTION 1985FARMS 326 $1,830 $6.00
0476C HANCOCK TURFGRASS-PUMP HSE
ORIGINAL CONSTRUCTION 1985FARMS 39 $593 $15.00
0476D HANCOCK TURFGRASS-COLD STRG
ORIGINAL CONSTRUCTION 1996FARMS 6,027 $113,434 $19.00 PHYSICAL PLANT
COMPLEX TOTALS $222,36113,922
0067 HANNAH ADMINISTRATION
0067 HANNAH ADMINISTRATION
ORIGINAL CONSTRUCTION 1968SUPPORT 170,216 $5,215,167 $31.00 CALDER
0332 HOLDEN HALL
0332 HOLDEN HALL
ORIGINAL CONSTRUCTION 1967HOUSING 357,199 $5,993,441 $17.00 CALDER
0330 HOLMES HALL
0330 HOLMES HALL
ORIGINAL CONSTRUCTION 1965HOUSING 399,755 $5,524,798 $14.00 CALDER
0456 HORSE RESEARCH CENTER COMPLEX
0456B HORSE RESEARCH-WEST HORSE BARN
ORIGINAL CONSTRUCTION 1946FARMS 13,484 $20,466 $2.00
0456D HORSE RESEARCH-STALLION BARN
FACILITIES INFORMATION SERVICES 31
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0456 HORSE RESEARCH CENTER COMPLEX
0456D HORSE RESEARCH-STALLION BARN
ORIGINAL CONSTRUCTION 1946FARMS 919 $13,630 $15.00
0456F HORSE RESEARCH-GARAGE IMPLEMNT SHED
ORIGINAL CONSTRUCTION 1946FARMS 867 $12,375 $14.00
0456I HORSE RESEARCH-WOODS HORSE BARN
ORIGINAL CONSTRUCTION 1983FARMS 1,259 $50,815 $40.00
0456L HORSE RESEARCH-TEACH RESEARCH BARN
ORIGINAL CONSTRUCTION 1984FARMS 3,871 $139,271 $36.00
0456M HORSE RESEARCH-STRG/EXERCISE
ORIGINAL CONSTRUCTION 1990FARMS 8,028 $74,693 $9.00 TAILORED BLDGSYS
0456N HORSE RESEARCH-ARENA
ORIGINAL CONSTRUCTION 1995FARMS 18,559 $540,000 $29.00 HOBBS & BLACK
0456O HORSE RESEARCH-BARN
ORIGINAL CONSTRUCTION 1995FARMS 10,570 $214,000 $20.00 HOBBS & BLACK
COMPLEX TOTALS $1,065,25057,557
0407 HORTICULTURE RESEARCH CENTR COMPLEX
0407A HORTICULTURE RES-HOUSE/OFFICE
ORIGINAL CONSTRUCTION 1966FARMS 3,002 $53,449 $18.00 MAYOTTE-WEBB
0407B HORTICULTURE RES-GARAGE
ORIGINAL CONSTRUCTION 1966FARMS 6,592 $111,279 $17.00 MAYOTTE-WEBB
0407C HORTICULTURE RES-EQUIP STRG
ORIGINAL CONSTRUCTION 1966FARMS 6,156 $21,950 $4.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 32
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0407 HORTICULTURE RESEARCH CENTR COMPLEX
0407D HORTICULTURE RES-STORAGE SHED
ORIGINAL CONSTRUCTION 1975FARMS 1,689 $26,021 $15.00
0407F HORTICULTURE RES-WINERY
ORIGINAL CONSTRUCTION 1989FARMS 4,275 $195,735 $46.00 MJK ARCH
0407G HORTICULTURE RES-LATH HSE
ORIGINAL CONSTRUCTION 1988FARMS 0 $2,500 $0.00 HORT RES CTR
0407H HORTICULTURE RES-PEST STOR & RES
ORIGINAL CONSTRUCTION 1997FARMS 3,434 $249,690 $73.00 PHYSICAL PLANT
0407I HORTICULTURE RES-GREENHOUSE
ORIGINAL CONSTRUCTION 1997FARMS 30,167 $384,892 $13.00 FTC & H
0407J HORTICULTURE RES-PROCESS SHELTER
ORIGINAL CONSTRUCTION 2007FARMS 976 $11,921 $12.00 WEDEVEN BROSHAMILTN
0407K HORTICULTURE RES-FERT STRG UNIT
ORIGINAL CONSTRUCTION 2015FARMS 130 $0 $0.00
0407L HORTICULTURE RES-IRRIGATION WELL
ORIGINAL CONSTRUCTION 2018FARMS 85 $9,700 $115.00 LANDMANAGEMENT
COMPLEX TOTALS $1,067,13756,506
0331 HUBBARD HALL
0331 HUBBARD HALL
ORIGINAL CONSTRUCTION 1966HOUSING 351,373 $5,785,328 $16.00 CALDER
0005 HUMAN ECOLOGY
0005 HUMAN ECOLOGY
FACILITIES INFORMATION SERVICES 33
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0005 HUMAN ECOLOGY
0005 HUMAN ECOLOGY
ORIGINAL CONSTRUCTION 1924ACADEMIC 67,373 $400,000 $6.00 BOWD
1937ACADEMIC 8,411 $16,177 $2.00 BOWD-MUNSONADD 1 - ADDITION 1
1980ACADEMIC 1,889 $171,521 $91.00 PHYSICAL PLANTADD 2 - ADDITION 2
1990ACADEMIC 786 $207,892 $264.00 CLARK TROMBLYADD 3 - ADDITION 3 - ELECTSUBSTATION
78,459 $795,590
COMPLEX TOTALS $795,59078,459
0051 IM SPORTS-CIRCLE
0051 IM SPORTS-CIRCLE
ORIGINAL CONSTRUCTION 1916ATHLETICS 72,965 $229,000 $3.00 BOWD
1958ATHLETICS 90,539 $2,305,076 $25.00 CALDERADD 1 - ADDITION 1
163,504 $2,534,076
COMPLEX TOTALS $2,534,076163,504
0643 IM SPORTS-CIRCLE-SUBSTATION
0643 IM SPORTS-CIRCLE-SUBSTATION
ORIGINAL CONSTRUCTION 2013SUPPORT 1,408 $622,000 $442.00 FTC&H
0175 IM SPORTS-EAST
0175 IM SPORTS-EAST
ORIGINAL CONSTRUCTION 1988ATHLETICS 75,237 $5,243,237 $70.00 CALDER
FACILITIES INFORMATION SERVICES 34
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0151 IM SPORTS-WEST COMPLEX
0151 IM SPORTS-WEST
ORIGINAL CONSTRUCTION 1958ATHLETICS 230,288 $3,212,508 $14.00 SARVIS
2005ATHLETICS 5,284 $3,737,122 $707.00 TMP ASSOCIATESADD 1 - ADDITION 1 COURTYARD
235,572 $6,949,630
COMPLEX TOTALS $6,949,630235,572
0481 INLAND LAKES STORAGE NO. 1
0481 INLAND LAKES STORAGE NO. 1
ORIGINAL CONSTRUCTION 2020FARMS 6,000 $180,000 $30.00
0129 INSECTORY (ENTOMOLOGY)
0129 INSECTORY (ENTOMOLOGY)
ORIGINAL CONSTRUCTION 1932FARMS 204 $200 $1.00
0247 INTERDISCIPLINARY SCIENCE & TECH
0247 INTERDISCIPLINARY SCIENCE & TECH
ORIGINAL CONSTRUCTION 2019ACADEMIC 166,808 $81,934,425 $491.00 SMITH GROUP JJR
0169 INTERNATIONAL CENTER
0169 INTERNATIONAL CENTER
ORIGINAL CONSTRUCTION 1964ACADEMIC 94,447 $1,201,000 $13.00 CALDER
1980ACADEMIC 17,063 $1,146,943 $67.00 CALDERADD 1 - ADDITION 1
2003ACADEMIC 22,014 $5,852,691 $266.00 CALDERADD 2 - ADDITION 2 DELIA KOO
133,524 $8,200,634
FACILITIES INFORMATION SERVICES 35
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0169 INTERNATIONAL CENTER
COMPLEX TOTALS $8,200,634133,524
0167 IPF
0167 IPF
ORIGINAL CONSTRUCTION 1963SUPPORT 95,249 $779,331 $8.00 PHYSICAL PLANT
1969SUPPORT 1,764 $43,931 $25.00 PHYSICAL PLANTADD 1 - ADDITION 1
1994SUPPORT 206 $68,088 $331.00 PHYSICAL PLANTADD 2 - ADDITION 2- ENCLOSE DOCK
97,219 $891,350
COMPLEX TOTALS $891,35097,219
0209 IPF - STORAGE NO. 1
0209 IPF - STORAGE NO. 1
ORIGINAL CONSTRUCTION 1993SUPPORT 9,013 $139,747 $16.00 PHYSICAL PLANT
2007SUPPORT 22,406 $574,233 $26.00 BERNATH-COAKLEY
ADD 1 - ADDITION 1
2017SUPPORT 4,691 $178,258 $38.00 IPFADD 2 - ADDITION 2
36,110 $892,238
COMPLEX TOTALS $892,23836,110
0210 IPF - STORAGE NO. 2
0210 IPF - STORAGE NO. 2
ORIGINAL CONSTRUCTION 1994SUPPORT 10,231 $151,636 $15.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 36
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0210 IPF - STORAGE NO. 2
0210 IPF - STORAGE NO. 2
1998SUPPORT 11,844 $133,770 $11.00 PHYSICAL PLANTADD 1 - ADDITION 1
22,075 $285,406
COMPLEX TOTALS $285,40622,075
0234 IPF - STORAGE NO. 3
0234 IPF - STORAGE NO. 3
ORIGINAL CONSTRUCTION 2012SUPPORT 7,360 $208,797 $28.00 PHYSICAL PLANT
0430A IPF - STORAGE NO. 6
0430A IPF - STORAGE NO. 6
ORIGINAL CONSTRUCTION 1938FARMS 9,215 $59,290 $6.00 AG ENGR
0056 JENISON FIELDHOUSE
0056 JENISON FIELDHOUSE
ORIGINAL CONSTRUCTION 1940ATHLETICS 200,066 $1,025,000 $5.00 MUNSON
1975ATHLETICS 967 $0 $0.00 PHYSICAL PLANTADD 1 - ADDITION 1
2002ATHLETICS 6,770 $6,606,309 $976.00 ROSSETTI &ASSOC.
ADD 2 - ADDITION 2 LOCKER ROOM
207,803 $7,631,309
COMPLEX TOTALS $7,631,309207,803
0029 KEDZIE HALL
0029 KEDZIE HALL
ORIGINAL CONSTRUCTION 1927ACADEMIC 87,946 $113,800 $1.00 MALCOMSON +HIGGENB.
FACILITIES INFORMATION SERVICES 37
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0029 KEDZIE HALL
0029 KEDZIE HALL
1966ACADEMIC 69,373 $2,035,768 $29.00 HARLEY-ELLINGTON
ADD 1 - ADDITION 1 (SOUTH)
2004ACADEMIC 2,064 $155,000 $75.00 DICLEMENTESIEGEL
ADD 2 - ADDITION 2 ENCLOSECHILLER
159,383 $2,304,568
COMPLEX TOTALS $2,304,568159,383
0055 KELLOGG CENTER
0055 KELLOGG CENTER
ORIGINAL CONSTRUCTION 1951SUPPORT 138,523 $1,768,052 $13.00 SARVIS
1955SUPPORT 3,169 $124,170 $39.00 SARVISADD 1 - ADDITION 1
1955SUPPORT 17,099 $289,260 $17.00 SARVISADD 2 - ADDITION 2
1959SUPPORT 21,403 $331,650 $15.00 SARVISADD 3 - ADDITION 3
1988SUPPORT 51,978 $3,320,759 $64.00 CALDERADD 4 - ADDITION 4
232,172 $5,833,891
COMPLEX TOTALS $5,833,891232,172
0150 KRESGE ART CENTER COMPLEX
0150 KRESGE ART
ORIGINAL CONSTRUCTION 1958ACADEMIC 82,056 $1,480,160 $18.00 CALDER
1966ACADEMIC 14,109 $320,720 $23.00 CALDERADD 1 - ADDITION 1
1973ACADEMIC 815 $40,000 $49.00 CALDERADD 2 - ADDITION 2 KILN & FOUNDRYROOM
96,980 $1,840,880
FACILITIES INFORMATION SERVICES 38
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0150 KRESGE ART CENTER COMPLEX
0150A KRESGE ART-SCULPTURE STUDIO
ORIGINAL CONSTRUCTION 1966ACADEMIC 7,695 $164,665 $21.00 CALDER
COMPLEX TOTALS $2,005,545104,675
0158 LANDSCAPE SERVICES
0158 LANDSCAPE SERVICES
ORIGINAL CONSTRUCTION 1959SUPPORT 19,502 $87,757 $5.00 CAMPBELL ENG
1965SUPPORT 12,811 $77,745 $6.00 PHYSICAL PLANTADD 1 - ADDITION 1
2014SUPPORT 133 $0 $0.00 BERNATHCOAKLEY
ADD 2 - ADDITION 2 - EAST ENTRANCE
32,446 $165,502
COMPLEX TOTALS $165,50232,446
0406 LANDSCAPE SERVICES NURSERY COMPLEX
0406A LANDSCAPE SRVCS NURSERY-HEADHOUSE
ORIGINAL CONSTRUCTION 1964SUPPORT 1,320 $8,971 $7.00 PHYSICAL PLANT
1964SUPPORT 2,191 $14,133 $6.00 PHYSICAL PLANTADD 1 - ADDITION 1 GREENHOUSE
3,511 $23,104
0406C LANDSCAPE SRVCS NURSERY-ROOT CELLAR
ORIGINAL CONSTRUCTION 1964SUPPORT 393 $2,541 $6.00 PHYSICAL PLANT
0406E LANDSCAPE SRVCS NURSERY-HOOP HSE
ORIGINAL CONSTRUCTION 1964SUPPORT 2,346 $21,865 $9.00 PHYSICAL PLANT
0406G LANDSCAPE SRVCS NURSERY-BARN 1
FACILITIES INFORMATION SERVICES 39
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0406 LANDSCAPE SERVICES NURSERY COMPLEX
0406G LANDSCAPE SRVCS NURSERY-BARN 1
ORIGINAL CONSTRUCTION 2007SUPPORT 3,399 $46,240 $14.00 AUSTIN &ASSOCIATES
0406H LANDSCAPE SRVCS NURSERY-BARN 2
ORIGINAL CONSTRUCTION 2007SUPPORT 3,399 $46,240 $14.00 AUSTIN &ASSOCIATES
COMPLEX TOTALS $139,99013,048
0525 LANDSCAPE SRVCS-SALT STRG 1
0525 LANDSCAPE SRVCS-SALT STRG 1
ORIGINAL CONSTRUCTION 1978SUPPORT 625 $19,400 $31.00 PHYSICAL PLANT
0536 LANDSCAPE SRVCS-SALT STRG 2
0536 LANDSCAPE SRVCS-SALT STRG 2
ORIGINAL CONSTRUCTION 1995SUPPORT 1,140 $66,900 $59.00 PHYSICAL PLANT
0655 LANDSCAPE SRVCS-SALT STRG 3
0655 LANDSCAPE SRVCS-SALT STRG 3
ORIGINAL CONSTRUCTION 2020SUPPORT 4,616 $262,244 $57.00
0611 LANDSCAPE SRVCS-STRG 2
0611 LANDSCAPE SRVCS-STRG 2
ORIGINAL CONSTRUCTION 2000SUPPORT 162 $7,450 $46.00 PHYSICAL PLANT
0447 LARGE ANIMAL CLINICAL RES COMPLEX
0447B LARGE ANIMAL RES-HAY BARN
ORIGINAL CONSTRUCTION 1984FARMS 3,833 $52,754 $14.00 ARCH. CONSORT.
0049 LIBRARY
0049 LIBRARY
FACILITIES INFORMATION SERVICES 40
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0049 LIBRARY
0049 LIBRARY
ORIGINAL CONSTRUCTION 1955ACADEMIC 286,504 $3,712,865 $13.00 CALDER
1964ACADEMIC 2,623 $375,000 $143.00 PHYSICAL PLANTADD 1 - ADDITION 1
1967ACADEMIC 147,962 $3,547,524 $24.00 CALDERADD 2 - ADDITION 2
1995ACADEMIC 20,175 $4,200,000 $208.00 CALDERADD 3 - ADDITION 3
2014ACADEMIC 1,650 $1,524,507 $924.00 DICLEMENTESIEGEL
ADD 4 - ADDITION 4 - SUBSTATION
458,914 $13,359,896
COMPLEX TOTALS $13,359,896458,914
0183 LIFE SCIENCE
0183 LIFE SCIENCE
ORIGINAL CONSTRUCTION 1971ACADEMIC 180,617 $7,797,177 $43.00 CALDER
2012ACADEMIC 47,854 $10,973,302 $229.00 TMPADD 1 - ADDITION 1 - BOTT NURSINGEDUC
228,471 $18,770,479
COMPLEX TOTALS $18,770,479228,471
0068 LINEN SERVICES
0068 LINEN SERVICES
ORIGINAL CONSTRUCTION 1968SUPPORT 72,412 $1,221,130 $17.00 MAYOTTE-WEBB
0014 LINTON HALL
0014 LINTON HALL
ORIGINAL CONSTRUCTION 1881ACADEMIC 18,451 $22,000 $1.00 MARSH-ARNOLD
FACILITIES INFORMATION SERVICES 41
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0014 LINTON HALL
0014 LINTON HALL
1947ACADEMIC 19,878 $368,550 $19.00 MUNSONADD 1 - ADDITION 1
1989ACADEMIC 622 $269,428 $433.00 CLARK TROMBLYRANDER
ADD 2 - ADDITION 2 - ELECTSUBSTATION
1996ACADEMIC 888 $348,741 $393.00 FTC&HADD 3 - ADDITION 3 - HANDICAPACCESS
39,839 $1,008,719
COMPLEX TOTALS $1,008,71939,839
0154 MANLY MILES
0154 MANLY MILES
ORIGINAL CONSTRUCTION 1959ACADEMIC 58,519 $749,325 $13.00 SARVIS
0016 MARSHALL-ADAMS HALL
0016 MARSHALL-ADAMS HALL
ORIGINAL CONSTRUCTION 1902ACADEMIC 20,189 $27,000 $1.00 BOWD
0302 MASON ABBOT HALL
0302 MASON ABBOT HALL
ORIGINAL CONSTRUCTION 1938HOUSING 189,167 $1,050,000 $6.00 BOWD-MUNSON
0607 MASON RESEARCH FARM COMPLEX
0607B MASON RESEARCH FARM-STRG
ORIGINAL CONSTRUCTION 1984FARMS 5,193 $14,400 $3.00
0607C MASON RESEARCH FARM-LAB
ORIGINAL CONSTRUCTION 1997FARMS 3,923 $120,000 $31.00
FACILITIES INFORMATION SERVICES 42
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0607 MASON RESEARCH FARM COMPLEX
COMPLEX TOTALS $134,4009,116
0324 MCDONEL HALL
0324 MCDONEL HALL
ORIGINAL CONSTRUCTION 1963HOUSING 348,498 $4,020,925 $12.00 CALDER
0629 METEOROLOGICAL TOWER
0629 METEOROLOGICAL TOWER
ORIGINAL CONSTRUCTION 20130 $137,492 $0.00 PHYSICAL PLANT
0940 MICH BIOTECH INSTITUTE
0940 MICH BIOTECH INSTITUTE
ORIGINAL CONSTRUCTION 1987ACADEMIC 131,797 $16,682,345 $127.00 HEPY
0940B MICH BIOTECH INSTITUTE-PROCESSING
0940B MICH BIOTECH INSTITUTE-PROCESSING
ORIGINAL CONSTRUCTION 2012ACADEMIC 208 $0 $0.00
0940A MICH BIOTECH INSTITUTE-STORAGE
0940A MICH BIOTECH INSTITUTE-STORAGE
ORIGINAL CONSTRUCTION 1989OTHER 135 $0 $0.00
0022 MORRILL HALL OF AGRICULTURE
0022 MORRILL HALL OF AGRICULTURE
ORIGINAL CONSTRUCTION 1909ACADEMIC 97,896 $182,000 $2.00 BOWD
1991ACADEMIC 325 $113,493 $350.00 PHYSICAL PLANTADD 1 - ADDITION 1
1999ACADEMIC 35,759 $3,971,878 $111.00 ARCHITECTS FOURADD 2 - ADDITION 2 - ANNEX
133,980 $4,267,371
FACILITIES INFORMATION SERVICES 43
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0022 MORRILL HALL OF AGRICULTURE
COMPLEX TOTALS $4,267,371133,980
0083 MSU COLLEGE OF LAW
0083 MSU COLLEGE OF LAW
ORIGINAL CONSTRUCTION 1997ACADEMIC 185,633 $20,345,284 $110.00 SSOE
2015ACADEMIC 925 $332,572 $360.00 WIGEN TINCKNELLADD 1 - ADDITION 1 - NORTHENTRANCE
186,558 $20,677,856
COMPLEX TOTALS $20,677,856186,558
0638 MSU COMMUNITY MUSIC SCHOOL
0638 MSU COMMUNITY MUSIC SCHOOL
ORIGINAL CONSTRUCTION 1975ACADEMIC 10,429 $0 $0.00 VAN VIENENPOSTEMA
1998ACADEMIC 10,413 $0 $0.00 MAYOTTE JACOBADD 1 - ADDITION NO. 1
20,842 $0
COMPLEX TOTALS $020,842
0606 MSU FEDERAL CREDIT UNION COMPLEX
0606 MSU FCU
ORIGINAL CONSTRUCTION 197023,136 $510,723 $22.00 MAYOTTE-WEBB
198529,606 $1,883,644 $64.00 FREDERICK &VARWIG
ADD 1 - ADDITION NO. 1
19997,306 $578,518 $79.00 DANIELS &ZERMACK
ADD 2 - ADDITION NO. 2
FACILITIES INFORMATION SERVICES 44
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0606 MSU FEDERAL CREDIT UNION COMPLEX
0606 MSU FCU
60,048 $2,972,885
COMPLEX TOTALS $2,972,88560,048
0245 MSU SCENE SHOP TEACHING LAB
0245 MSU SCENE SHOP TEACHING LAB
ORIGINAL CONSTRUCTION 2016ACADEMIC 9,888 $1,251,054 $127.00 BERNATH-COAKLEY
0223 MSU SURPLUS AND RECYCLING COMPLEX
0223 MSU SURPLUS AND RECYCLING
ORIGINAL CONSTRUCTION 2009SUPPORT 73,194 $7,555,424 $103.00 FTCH
0641 MUNN FIELD OBSERVATION TOWER
0641 MUNN FIELD OBSERVATION TOWER
ORIGINAL CONSTRUCTION 2014ATHLETICS 233 $75,625 $324.00 FTC&H
0059 MUNN ICE ARENA
0059 MUNN ICE ARENA
ORIGINAL CONSTRUCTION 1974ATHLETICS 106,644 $3,581,700 $34.00 DAVERMANASSOCIATES
1999ATHLETICS 14,012 $3,306,057 $236.00 ROSSETTIASSOCIATES
ADD 1 - ADDITION 1 - VIP SUITES
2014ATHLETICS 2,536 $1,863,181 $735.00 ROSSETTIASSOCIATES
ADD 2 - ADDITION 2 - CHILLERENCLOSURE
123,192 $8,750,938
COMPLEX TOTALS $8,750,938123,192
FACILITIES INFORMATION SERVICES 45
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0013 MUSEUM
0013 MUSEUM
ORIGINAL CONSTRUCTION 1924ACADEMIC 52,067 $460,000 $9.00 BOWD-MUNSON
1957ACADEMIC 2,931 $264,624 $90.00 CALDERADD 1 - ADDITION 1
54,998 $724,624
COMPLEX TOTALS $724,62454,998
0011 MUSIC
0011 MUSIC
ORIGINAL CONSTRUCTION 1940ACADEMIC 34,852 $227,288 $7.00 CALDER
1956ACADEMIC 21,965 $568,970 $26.00 CALDERADD 1 - ADDITION 1
2013ACADEMIC 1,222 $298,363 $244.00 ORIONADD 2 - ADDITION 2 ELECTRICALSUBSTATN
2020ACADEMIC 41,643 $29,879,199 $718.00 TMPADD 3 - ADDITION 3
99,682 $30,973,820
COMPLEX TOTALS $30,973,82099,682
0021 MUSIC PRACTICE
0021 MUSIC PRACTICE
ORIGINAL CONSTRUCTION 1968ACADEMIC 35,964 $1,283,626 $36.00 CALDER
0180 NATURAL RESOURCES
0180 NATURAL RESOURCES
ORIGINAL CONSTRUCTION 1966ACADEMIC 149,972 $3,405,054 $23.00 KAHN
FACILITIES INFORMATION SERVICES 46
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0024 NATURAL SCIENCE
0024 NATURAL SCIENCE
ORIGINAL CONSTRUCTION 1948ACADEMIC 191,977 $2,687,675 $14.00 MUNSON
2007ACADEMIC 1,336 $624,872 $468.00 ORIONENGINEERING CO
ADD 1 - ADDITION 1 ELECTSUBSTATION
193,313 $3,312,547
COMPLEX TOTALS $3,312,547193,313
0516 NORTH CAMPUS SUBSTATION
0516 NORTH CAMPUS SUBSTATION
ORIGINAL CONSTRUCTION 1921SUPPORT 2,112 $409,000 $194.00 BOWD
1967SUPPORT 5,841 $320,000 $55.00 PHYSICAL PLANTADD 3 - NORTH CAMPUS SUB-STATION
7,953 $729,000
COMPLEX TOTALS $729,0007,953
0196 OBSERVATORY
0196 OBSERVATORY
ORIGINAL CONSTRUCTION 1969ACADEMIC 7,014 $545,400 $78.00 BLACK
1028 OFFICE COMPLEX - ANNEX
1028 OFFICE COMPLEX - ANNEX
ORIGINAL CONSTRUCTION 1996OTHER 13,084 $974,962 $75.00
1027 OFFICE COMPLEX - MAIN BUILDING
1027 OFFICE COMPLEX - MAIN BUILDING
ORIGINAL CONSTRUCTION 1983OTHER 64,159 $3,540,656 $55.00
FACILITIES INFORMATION SERVICES 47
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0017 OLD BOTANY
0017 OLD BOTANY
ORIGINAL CONSTRUCTION 1892ACADEMIC 7,473 $7,227 $1.00 BOWD
1908ACADEMIC 6,578 $8,244 $1.00 BOWDADD 1 - ADDITION 1
14,051 $15,471
COMPLEX TOTALS $15,47114,051
0519 OLD COLLEGE FIELD COMPLEX
0519G OLD COLLEGE FIELD-RESTROOM
ORIGINAL CONSTRUCTION 2009ATHLETICS 859 $553,249 $644.00 HAMILTONANDERSON
2009ATHLETICS 1,887 $572,751 $303.00 HAMILTONANDERSON
ADD 1 - ADDITION 1
2011ATHLETICS 1,486 $183,475 $123.00 FTC&HADD 2 - ADDITION 2 - CONCESSION
4,232 $1,309,475
0519H OLD COLLEGE FIELD-BATTING
ORIGINAL CONSTRUCTION 2007ATHLETICS 9,872 $922,454 $93.00 FTC & H
0519K OLD COLLEGE FIELD-DEMARTIN STADIUM
ORIGINAL CONSTRUCTION 2008ATHLETICS 415 $782,890 $1,885.00 HAMILTONANDERSON
0519L OLD COLLEGE FIELD-MCLANE STADIUM
ORIGINAL CONSTRUCTION 2009ATHLETICS 2,608 $2,920,662 $1,120.00 HAMILTONANDERSON
0519M OLD COLLEGE FIELD-SECCHIA STADIUM
ORIGINAL CONSTRUCTION 2010ATHLETICS 2,006 $1,348,342 $672.00 PHYSICAL PLANT
0519N OLD COLLEGE FIELD-SOFTBALL DUGT 1
ORIGINAL CONSTRUCTION 2009ATHLETICS 360 $87,500 $243.00 PHYSICAL PLANT
0519O OLD COLLEGE FIELD-SOFTBALL DUGT 2
FACILITIES INFORMATION SERVICES 48
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0519 OLD COLLEGE FIELD COMPLEX
0519O OLD COLLEGE FIELD-SOFTBALL DUGT 2
ORIGINAL CONSTRUCTION 2009ATHLETICS 360 $87,500 $243.00 PHYSICAL PLANT
0519P OLD COLLEGE FIELD-BASEBALL DUGT 1
ORIGINAL CONSTRUCTION 2002ATHLETICS 560 $34,103 $61.00 PHYSICAL PLANT
0519Q OLD COLLEGE FIELD-BASEBALL DUGT 2
ORIGINAL CONSTRUCTION 2002ATHLETICS 560 $34,103 $61.00 PHYSICAL PLANT
0519R OLD COLLEGE FIELD-TICKET
ORIGINAL CONSTRUCTION 2013ATHLETICS 821 $258,713 $315.00 SMITHGROUP
COMPLEX TOTALS $7,785,74221,794
0025 OLD HORTICULTURE
0025 OLD HORTICULTURE
ORIGINAL CONSTRUCTION 1924ACADEMIC 42,426 $383,000 $9.00 BOWD-MUNSON
1963ACADEMIC 1,444 $29,540 $20.00 PHYSICAL PLANTADD 1 - ADDITION 1
1991ACADEMIC 605 $159,000 $263.00 FREEMAN/SMITHADD 2 - ADDITION 2
44,475 $571,540
COMPLEX TOTALS $571,54044,475
0047 OLDS HALL
0047 OLDS HALL
ORIGINAL CONSTRUCTION 1916ACADEMIC 73,319 $202,000 $3.00 BOWD
FACILITIES INFORMATION SERVICES 49
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0003 OLIN HEALTH CENTER COMPLEX
0003 OLIN HEALTH CENTER
ORIGINAL CONSTRUCTION 1939ACADEMIC 38,404 $250,000 $7.00 CALDER
1956SUPPORT 61,660 $1,318,900 $21.00 CALDERADD 1 - ADDITION 1
1969SUPPORT 5,350 $343,062 $64.00 CALDERADD 2 - ADDITION 2
105,414 $1,911,962
0003B OLIN-ELEC SUBSTATION
ORIGINAL CONSTRUCTION 1992SUPPORT 1,357 $527,389 $389.00 FTC&H
0003C OLIN-COOLING TOWER 2
ORIGINAL CONSTRUCTION 2014SUPPORT 0 $85,860 $0.00 DICLEMENTESIEGEL
COMPLEX TOTALS $2,525,211106,771
0320 OWEN GRADUATE HALL
0320 OWEN GRADUATE HALL
ORIGINAL CONSTRUCTION 1961HOUSING 162,385 $2,347,266 $14.00 CALDER
1965HOUSING 130,032 $2,266,047 $17.00 CALDERADD 1 - ADDITION 1
2009HOUSING 482 $49,387 $102.00 SMITH GROUPADD 2 - ADDITION 2 COVER LOADINGDOCK
292,899 $4,662,700
COMPLEX TOTALS $4,662,700292,899
0089 OYER SPEECH AND HEARING
0089 OYER SPEECH AND HEARING
ORIGINAL CONSTRUCTION 1968ACADEMIC 19,896 $649,811 $33.00 HARLEY-ELLINGTON
FACILITIES INFORMATION SERVICES 50
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0177 PACKAGING
0177 PACKAGING
ORIGINAL CONSTRUCTION 1964ACADEMIC 20,781 $418,852 $20.00 CALDER
1987ACADEMIC 29,681 $3,056,000 $103.00 CALDERADD 1 - ADDITION 1
50,462 $3,474,852
COMPLEX TOTALS $3,474,85250,462
0652 PARKING BOOTH 1-LOT 100
0652 PARKING BOOTH 1-LOT 100
ORIGINAL CONSTRUCTION 2017PARKING 44 $0 $0.00
0511 PARKING BOOTH 1-LOT 39
0511 PARKING BOOTH 1-LOT 39
ORIGINAL CONSTRUCTION 1983PARKING 44 $1,265 $29.00 PHYSICAL PLANT
0534A PARKING BOOTH 1-LOT 62 (NEW)
0534A PARKING BOOTH 1-LOT 62 (NEW)
ORIGINAL CONSTRUCTION 2008PARKING 40 $27,000 $675.00 PHYSICAL PLANT
0597 PARKING BOOTH 2-LOT 100
0597 PARKING BOOTH 2-LOT 100
ORIGINAL CONSTRUCTION 1997PARKING 44 $2,575 $59.00 DESIGN PLUS
0574 PARKING BOOTH 2-LOT 39
0574 PARKING BOOTH 2-LOT 39
ORIGINAL CONSTRUCTION 1997PARKING 44 $2,300 $52.00 FTC & H
0534B PARKING BOOTH 2-LOT 62 (NEW)
0534B PARKING BOOTH 2-LOT 62 (NEW)
FACILITIES INFORMATION SERVICES 51
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0534B PARKING BOOTH 2-LOT 62 (NEW)
0534B PARKING BOOTH 2-LOT 62 (NEW)
ORIGINAL CONSTRUCTION 2008PARKING 40 $27,000 $675.00 PHYSICAL PLAN T
0576 PARKING BOOTH 2-RAMP 3 (EAST)
0576 PARKING BOOTH 2-RAMP 3 (EAST)
ORIGINAL CONSTRUCTION 1997PARKING 44 $2,800 $64.00 WALKER PARKINGCONS
0575 PARKING BOOTH-RAMP 3 (WEST)
0575 PARKING BOOTH-RAMP 3 (WEST)
ORIGINAL CONSTRUCTION 1997PARKING 44 $2,800 $64.00 WALKER PARKINGCONS
0219 PARKING RAMP 1-SHAW LANE
0219 PARKING RAMP 1-SHAW LANE
ORIGINAL CONSTRUCTION 2002PARKING 426,114 $19,367,462 $45.00 SHG, INC.
0185 PARKING RAMP 2-AUDITORIUM RD
0185 PARKING RAMP 2-AUDITORIUM RD
ORIGINAL CONSTRUCTION 1967PARKING 177,223 $1,185,850 $7.00 BLACK
0111 PARKING RAMP 3-WHARTON
0111 PARKING RAMP 3-WHARTON
ORIGINAL CONSTRUCTION 1983PARKING 324,798 $2,262,479 $7.00 CARL WALKER
1997PARKING 41,132 $5,602,165 $136.00 WALKER PARKINGCONS
ADD 1 - ADDITION 1
365,930 $7,864,644
COMPLEX TOTALS $7,864,644365,930
0155 PARKING RAMP 4-KELLOGG
0155 PARKING RAMP 4-KELLOGG
FACILITIES INFORMATION SERVICES 52
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0155 PARKING RAMP 4-KELLOGG
0155 PARKING RAMP 4-KELLOGG
ORIGINAL CONSTRUCTION 1989PARKING 297,502 $7,476,471 $25.00 CALDER
0216 PARKING RAMP 5-COMM ARTS
0216 PARKING RAMP 5-COMM ARTS
ORIGINAL CONSTRUCTION 2001PARKING 322,171 $10,176,717 $32.00 HARLEYELLINGTON
0222 PARKING RAMP 6-GRAND RIVER
0222 PARKING RAMP 6-GRAND RIVER
ORIGINAL CONSTRUCTION 2006PARKING 276,390 $14,097,032 $51.00 FTC & H
0246 PARKING RAMP 7-HARRISON RD
0246 PARKING RAMP 7-HARRISON RD
ORIGINAL CONSTRUCTION 2016PARKING 269,155 $9,758,257 $36.00 NEWMANN/SMITH
0524 PATHOLOGICAL INCINERATOR
0524 PATHOLOGICAL INCINERATOR
ORIGINAL CONSTRUCTION 1975SUPPORT 1,972 $179,200 $91.00 PHYSICAL PLANT
0524A PATHOLOGICAL INCINERATOR - STORAGE
0524A PATHOLOGICAL INCINERATOR - STORAGE
ORIGINAL CONSTRUCTION 2018SUPPORT 923 $90,000 $98.00
0212 PAVILION AG LIVESTOCK ED COMPLEX
0212 PAVILION AG LIVESTOCK
ORIGINAL CONSTRUCTION 1996ACADEMIC 204,594 $13,043,863 $64.00 HOBBS & BLACK
0212A PAVILION AG LIVESTOCK-HORSE BARN
ORIGINAL CONSTRUCTION 2000FARMS 24,633 $219,282 $9.00 PHYSICAL PLANT
0439A PAVILION AG LIVESTOCK-STORAGE
ORIGINAL CONSTRUCTION 1949FARMS 3,258 $23,649 $7.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 53
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0212 PAVILION AG LIVESTOCK ED COMPLEX
COMPLEX TOTALS $13,286,794232,485
0086 PLANT AND SOIL SCIENCE
0086 PLANT AND SOIL SCIENCE
ORIGINAL CONSTRUCTION 1986ACADEMIC 274,996 $22,535,561 $82.00 HOYEM-BASSO
2012ACADEMIC 89,682 $33,880,776 $378.00 SMITH GROUPADD 1 - ADDITION 1 MOLECULARPLANT SCI
364,678 $56,416,337
COMPLEX TOTALS $56,416,337364,678
0178 PLANT BIOLOGY
0178 PLANT BIOLOGY
ORIGINAL CONSTRUCTION 1966ACADEMIC 62,709 $2,147,756 $34.00 BLACK
1968ACADEMIC 55,202 $2,405,000 $44.00 BLACKADD 1 - ADDITION 1
1968ACADEMIC 31,394 $1,025,445 $33.00 BLACKADD 2 - ADDITION 2 BOTANY
1985ACADEMIC 40,211 $5,791,716 $144.00 HOYEM-BASSOADD 3 - ADDITION 3
189,516 $11,369,917
COMPLEX TOTALS $11,369,917189,516
0098C PLANT SCIENCE GREENHOUSE-EAST
0098C PLANT SCIENCE GREENHOUSE-EAST
ORIGINAL CONSTRUCTION 1966ACADEMIC 18,717 $502,361 $27.00 BLACK
FACILITIES INFORMATION SERVICES 54
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0098C PLANT SCIENCE GREENHOUSE-EAST
0098C PLANT SCIENCE GREENHOUSE-EAST
1980ACADEMIC 2,016 $159,733 $79.00 MAYOTTE,CROUSE, DHA
ADD 1 - GREENHOUSE (EAST RANGE)
1998ACADEMIC 3,054 $632,954 $207.00 PHYSICAL PLANTADD 2 - TRANSGENIC GREENHOUSE
23,787 $1,295,048
COMPLEX TOTALS $1,295,04823,787
0094 PLANT SCIENCE GREENHOUSE-SUPPORT
0094 PLANT SCIENCE GREENHOUSE-SUPPORT
ORIGINAL CONSTRUCTION 1984ACADEMIC 4,059 $10,050 $2.00 ARCH. CONSORT.
0093 PLANT SCIENCE GREENHOUSE-WEST
0093 PLANT SCIENCE GREENHOUSE-WEST
ORIGINAL CONSTRUCTION 1942ACADEMIC 8,190 $87,495 $11.00 PHYSICAL PLANT
1949ACADEMIC 60,945 $331,943 $5.00 PHYSICAL PLANTADD 1 - ADDITION 1 - PLANT SCIGRNHSE
1956ACADEMIC 1,730 $10,768 $6.00 PHYSICAL PLANTADD 2 - ADDITION 2 - GRNHSE WRANGE
1958ACADEMIC 5,819 $18,891 $3.00 PHYSICAL PLANTADD 3 - ADDITION 3 - GRNHSE WRANGE
1962ACADEMIC 1,596 $63,901 $40.00 PHYSICAL PLANTADD 4 - ADDITION 4 - GRNHSE WRANGE
1981ACADEMIC 4,266 $274,966 $64.00 KILGOREADD 6 - ADDITION 6 - GRNHSE WRANGE
82,546 $787,964
COMPLEX TOTALS $787,96482,546
0473 POULTRY TEACHING & RES COMPLEX
0473A POULTRY-SERVICE
FACILITIES INFORMATION SERVICES 55
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0473 POULTRY TEACHING & RES COMPLEX
0473A POULTRY-SERVICE
ORIGINAL CONSTRUCTION 1965FARMS 4,000 $21,760 $5.00 FRANK AND STEIN
0473B POULTRY-LAB
ORIGINAL CONSTRUCTION 1965FARMS 4,700 $31,216 $7.00 FRANK AND STEIN
0473C POULTRY-CHICK BROOD
ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN
0473D POULTRY-CHICK REAR
ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN
0473E POULTRY-CHICK CAGE
ORIGINAL CONSTRUCTION 1965FARMS 6,101 $33,077 $5.00 FRANK AND STEIN
0473H POULTRY-CHICK PROG
ORIGINAL CONSTRUCTION 1965FARMS 5,948 $33,077 $6.00 FRANK AND STEIN
0473I POULTRY-CHICK BREED
ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN
0473J POULTRY-TURKEY BREED
ORIGINAL CONSTRUCTION 1965FARMS 5,949 $33,077 $6.00 FRANK AND STEIN
0473K POULTRY-MINK
ORIGINAL CONSTRUCTION 1957FARMS 4,276 $19,584 $5.00 PHYSICAL PLANT
0473M POULTRY-FOREMAN HSE
ORIGINAL CONSTRUCTION 1965FARMS 2,943 $93,181 $32.00
0473N POULTRY-MINK SHED 1
ORIGINAL CONSTRUCTION 1965FARMS 1,120 $24,234 $22.00 AG ENGRG
0473O POULTRY-MINK SHED 2
ORIGINAL CONSTRUCTION 1965FARMS 1,120 $24,234 $22.00 AG ENGRG
FACILITIES INFORMATION SERVICES 56
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0473 POULTRY TEACHING & RES COMPLEX
0473P POULTRY-MINK SHED 3
ORIGINAL CONSTRUCTION 1965FARMS 1,120 $24,234 $22.00 AG ENGRG
0473Q POULTRY-N STRG SHED
ORIGINAL CONSTRUCTION 1965FARMS 588 $2,053 $3.00 AG ENGRG
0473R POULTRY-S STRG SHED
ORIGINAL CONSTRUCTION 1965FARMS 715 $10,687 $15.00
0473S POULTRY-FREEZER STG
ORIGINAL CONSTRUCTION 1965FARMS 251 $2,400 $10.00
0473T POULTRY-TURKEY RESEARCH
ORIGINAL CONSTRUCTION 1996FARMS 5,124 $557,286 $109.00 CAPITALCONSULTANTS
0473U POULTRY-LAYING HEN RESEARCH
ORIGINAL CONSTRUCTION 2012FARMS 17,967 $1,375,000 $77.00 HENNING
COMPLEX TOTALS $2,384,33179,769
0027 PSYCHOLOGY
0027 PSYCHOLOGY
ORIGINAL CONSTRUCTION 1949ACADEMIC 97,947 $1,540,511 $16.00 CALDER
1955ACADEMIC 503 $6,500 $13.00 PHYSICAL PLANTADD 1 - ADDITION 1
1973ACADEMIC 1,384 $61,785 $45.00 PHYSICAL PLANTADD 2 - ADDITION 2
1976ACADEMIC 13,483 $650,500 $48.00 SEDGEWICK-SELLER
ADD 3 - ADDITION 3
113,317 $2,259,296
FACILITIES INFORMATION SERVICES 57
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0027 PSYCHOLOGY
COMPLEX TOTALS $2,259,296113,317
0087 PUBLIC SAFETY
0087 PUBLIC SAFETY
ORIGINAL CONSTRUCTION 1975SUPPORT 26,130 $1,140,022 $44.00 MANSON,JACKSON,KANE
1992SUPPORT 9,963 $920,797 $92.00 PHYSICAL PLANTADD 2 - ADDITION 2
36,093 $2,060,819
COMPLEX TOTALS $2,060,81936,093
0595 PUMP STATION 1-FARM LANE
0595 PUMP STATION 1-FARM LANE
ORIGINAL CONSTRUCTION 2009SUPPORT 935 $100,000 $107.00 URS
0596 PUMP STATION 2-FARM LANE
0596 PUMP STATION 2-FARM LANE
ORIGINAL CONSTRUCTION 2009SUPPORT 935 $100,000 $107.00 URS
0450 PUREBRED BEEF CATTLE TEACH COMPLEX
0450A PUREBRED BEEF-MAIN
ORIGINAL CONSTRUCTION 1930FARMS 11,116 $54,307 $5.00 MUNSON
1953FARMS 9,120 $63,388 $7.00 PHYSICAL PLANTADD 1 - ADDITION 1
20,236 $117,695
0450B PUREBRED BEEF-SHEEP BARN
ORIGINAL CONSTRUCTION 1953FARMS 2,046 $5,000 $2.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 58
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0450 PUREBRED BEEF CATTLE TEACH COMPLEX
0450C PUREBRED BEEF-LOOSE HOUSING
ORIGINAL CONSTRUCTION 1954FARMS 7,368 $23,100 $3.00 PHYSICAL PLANT
0450D PUREBRED BEEF-SCALE HOUSE
ORIGINAL CONSTRUCTION 1954FARMS 1,295 $2,920 $2.00 PHYSICAL PLANT
0450E PUREBRED BEEF-HAY SHED
ORIGINAL CONSTRUCTION 1954FARMS 640 $1,475 $2.00 PHYSICAL PLANT
COMPLEX TOTALS $150,19031,585
0577 RADIO EQUIPMENT SHELTER COMPLEX
0577 RADIO EQUIPMENT SHELTER
ORIGINAL CONSTRUCTION 1999OTHER 327 $110,480 $338.00 MILLER BUILDINGSYS
0577A RADIO EQUIPMENT SHELTER - TOWER
ORIGINAL CONSTRUCTION 1999OTHER 0 $150,435 $0.00
COMPLEX TOTALS $260,915327
0600 RADIO FACILITY COMPLEX
0600A RADIO FACILITY-RADIO TRANSM WKAR
ORIGINAL CONSTRUCTION 1948ACADEMIC 2,934 $24,187 $8.00 PHYSICAL PLANT
0600B RADIO FACILITY-RADIO TOWER WKAR
ORIGINAL CONSTRUCTION 19700 $0 $0.00
0600C RADIO FACILITY-DIR TOWER WKAR
ORIGINAL CONSTRUCTION 19700 $0 $0.00
FACILITIES INFORMATION SERVICES 59
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0600 RADIO FACILITY COMPLEX
COMPLEX TOTALS $24,1872,934
0214 RADIOLOGY COMPLEX
0214 RADIOLOGY
ORIGINAL CONSTRUCTION 1998ACADEMIC 64,773 $6,701,829 $103.00 REDSTONE-TISCOARCH
0214A RADIOLOGY-GREENHOUSE
ORIGINAL CONSTRUCTION 2006ACADEMIC 1,499 $78,783 $53.00 PHYSICAL PLANT
0214B RADIOLOGY-STORAGE SHED
ORIGINAL CONSTRUCTION 2000ACADEMIC 198 $7,480 $38.00 PHYSICAL PLANT
COMPLEX TOTALS $6,788,09266,470
0189 REGIONAL CHILLED WATER PLANT
0189 REGIONAL CHILLED WATER PLANT
ORIGINAL CONSTRUCTION 1971SUPPORT 5,977 $559,100 $94.00 CALDER
1976SUPPORT 5,355 $590,000 $110.00 CALDERADD 1 - ADDITION 1
1985SUPPORT 4,803 $781,000 $163.00 HOYEM-BASSOADD 2 - ADDITION 2
1991SUPPORT 5,041 $408,570 $81.00 HEPYADD 3 - ADDITION 3
1993SUPPORT 5,023 $1,512,000 $301.00 HEPYADD 4 - ADDITION 4
26,199 $3,850,670
COMPLEX TOTALS $3,850,67026,199
FACILITIES INFORMATION SERVICES 60
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0205 RENTAL STORAGE FACILITY B
0205 RENTAL STORAGE FACILITY B
ORIGINAL CONSTRUCTION 1987SUPPORT 25,792 $215,000 $8.00 PHYSICAL PLANT
0325 RHS SERVICES
0325 RHS SERVICES
ORIGINAL CONSTRUCTION 1962SUPPORT 12,080 $107,500 $9.00 MANSON,JACKSON,KANE
0515 RIVER INTAKE STATION
0515 RIVER INTAKE STATION
ORIGINAL CONSTRUCTION 1940SUPPORT 910 $6,375 $7.00 BOWD-MUNSON
0616 RIVER TERRACE HOUSE
0616 RIVER TERRACE HOUSE
ORIGINAL CONSTRUCTION 1941HOUSING 4,744 $27,500 $6.00
1994HOUSING 267 $3,500 $13.00ADD 1 - ADDITION 1 COVERED WALK
5,011 $31,000
COMPLEX TOTALS $31,0005,011
0052 RIVER WATER RESEARCH COMPLEX
0052A RIVER WATER RESEARCH - LAB
ORIGINAL CONSTRUCTION 1953ACADEMIC 2,702 $21,640 $8.00 PHYSICAL PLANT
1972ACADEMIC 901 $34,777 $39.00 PHYSICAL PLANTADD 1 - ADDITION 1 (ENVIROMENTALENG)
3,603 $56,417
0052B RIVER WATER RESEARCH - STORAGE
ORIGINAL CONSTRUCTION 1998ACADEMIC 2,808 $48,260 $17.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 61
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0052 RIVER WATER RESEARCH COMPLEX
COMPLEX TOTALS $104,6776,411
0317 SHAW HALL
0317 SHAW HALL
ORIGINAL CONSTRUCTION 1950HOUSING 275,821 $3,482,153 $13.00 CALDER
2013HOUSING 1,377 $356,643 $259.00 NEUMANN/SMITHADD 1 - ADDITION 1 LOADING DOCK
277,198 $3,838,796
COMPLEX TOTALS $3,838,796277,198
0449 SHEEP BARN
0449 SHEEP BARN
1992FARMS 7,328 $61,000 $8.00ADD 1 - ANGLE BARN
2016FARMS 6,400 $325,000 $51.00 STEDFASTADD 2 - SHEEP LAMBING RESEARCH
13,728 $386,000
COMPLEX TOTALS $386,00013,728
0468 SHEEP RESEARCH & TEACHING COMPLEX
0468A SHEEP RESEARCH-BARN
ORIGINAL CONSTRUCTION 1961FARMS 6,693 $46,219 $7.00 PHYSICAL PLANT
0468B SHEEP RESEARCH-OPEN SHED
ORIGINAL CONSTRUCTION 1961FARMS 2,473 $3,600 $1.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 62
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0468 SHEEP RESEARCH & TEACHING COMPLEX
COMPLEX TOTALS $49,8199,166
0537 SHOOTING RANGE COMPLEX
0537A SHOOTING RANGE-STRG 1
ORIGINAL CONSTRUCTION 1965SUPPORT 146 $3,500 $24.00
0537B SHOOTING RANGE-STRG 2
ORIGINAL CONSTRUCTION 1995SUPPORT 796 $20,000 $25.00
0537C SHOOTING RANGE-PAVILION
ORIGINAL CONSTRUCTION 1995SUPPORT 344 $10,000 $29.00
0537D SHOOTING RANGE-CANINE
ORIGINAL CONSTRUCTION 1997SUPPORT 840 $27,000 $32.00
0537E SHOOTING RANGE-TRAINING 1
ORIGINAL CONSTRUCTION 2011SUPPORT 2,712 $105,000 $39.00 DESIGN-BUILD
2015SUPPORT 454 $41,079 $90.00 DESIGN-BUILDADD 1 - ADDITION 1
3,166 $146,079
0537F SHOOTING RANGE-TRAINING 2
ORIGINAL CONSTRUCTION 2012SUPPORT 576 $14,189 $25.00
COMPLEX TOTALS $220,7685,868
0537G SHOOTING RANGE-OPERATIONS CENTER
0537G SHOOTING RANGE-OPERATIONS CENTER
ORIGINAL CONSTRUCTION 2015FARMS 5,200 $286,728 $55.00
FACILITIES INFORMATION SERVICES 63
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0300 SNYDER PHILLIPS HALL
0300 SNYDER PHILLIPS HALL
ORIGINAL CONSTRUCTION 1947HOUSING 204,733 $2,192,578 $11.00 MUNSON
2007HOUSING 96,647 $27,061,160 $280.00 EINHORN YAFFEEPRESC
ADD 1 - ADDITION 1
301,380 $29,253,738
COMPLEX TOTALS $29,253,738301,380
0625 SOUTH CAMPUS ANAEROBIC DIGESTER
0625 S CAMPUS & RES ANAEROBIC DIGS-CNTRL
ORIGINAL CONSTRUCTION 2010FARMS 1,671 $77,848 $47.00 LANDMANAGEMENT
0625A RESEARCH ANAEROBIC DIGESTER
ORIGINAL CONSTRUCTION 20100 $0 $0.00 LANDMANAGEMENT
0625B RESEARCH ANAEROBIC DIG-REC PITS N&S
ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT
0625C S CAMPUS ANAEROBIC DIG-REC PITS N&S
ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT
0625D S CAMPUS ANAEROBIC DIG-MIX TANK
ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT
0625E S CAMPUS ANAEROBIC DIG-MECH EQ
ORIGINAL CONSTRUCTION 2013FARMS 236 $0 $0.00 LANDMANAGEMENT
0625F S CAMPUS & RES ANAEROBIC DIGS- DHT
ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT
0625G S CAMPUS ANAEROBIC DIG-HELIOS DIG
ORIGINAL CONSTRUCTION 20130 $0 $0.00 LANDMANAGEMENT
FACILITIES INFORMATION SERVICES 64
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0625 SOUTH CAMPUS ANAEROBIC DIGESTER
0625H S CAMPUS ANAEROBIC DIG-ELEC EQ
ORIGINAL CONSTRUCTION 2013FARMS 283 $0 $0.00
0625J S CAMPUS ANAEROBIC DIG-WASH
ORIGINAL CONSTRUCTION 2013FARMS 88 $0 $0.00
0625K RESEARCH ANAEROBIC DIG-RES SHED
ORIGINAL CONSTRUCTION 2013FARMS 48 $0 $0.00
0625L RESEARCH ANAEROBIC DIG-LG RES POND
ORIGINAL CONSTRUCTION 2013FARMS 0 $0 $0.00
0625N S CAMPUS & RES ANAEROBIC DIGS-PIT
ORIGINAL CONSTRUCTION 2013FARMS 0 $0 $0.00
0625P S CAMPUS & RES ANAEROBIC DIGS-STORG
ORIGINAL CONSTRUCTION 2013FARMS 159 $0 $0.00
COMPLEX TOTALS $77,8482,485
0217 SPARTAN CHILD DEVELOPMENT CNTR CX
0217 SPARTAN CHILD DEVELOPMENT
ORIGINAL CONSTRUCTION 2002SUPPORT 16,076 $1,513,332 $94.00 TOWER PINKSTERTITUS
0217A SPARTAN CHILD DEV - STORAGE SHED
ORIGINAL CONSTRUCTION 2002SUPPORT 132 $1,200 $9.00
COMPLEX TOTALS $1,514,53216,208
FACILITIES INFORMATION SERVICES 65
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0058 SPARTAN STADIUM COMPLEX
0058 SPARTAN STADIUM
ORIGINAL CONSTRUCTION 1923ATHLETICS 0 $160,000 $0.00 BOWD
1948ATHLETICS 83,877 $1,432,574 $17.00 MUNSONADD 1 - ADDITION 1 (27,250 SEATS)
1956ATHLETICS 9,004 $397,347 $44.00 MUNSONADD 2 - ADDITION 2 (9,000 SEATS)
1957ATHLETICS 93,015 $1,805,317 $19.00 MUNSONADD 3 - ADDITION 3 (16,000 SEATS)
2006ATHLETICS 235,951 $45,532,099 $193.00 HNTBADD 4 - ADDITION 4
2014ATHLETICS 47,257 $18,362,298 $389.00 INTEGRATEDDESIGN
ADD 5 - ADDITION 5 NORTH ENDZONE
2017ATHLETICS 21,382 $10,319,152 $483.00 INTEGRATEDDESIGN
ADD 6 - ADDITION 6 SOUTH ENDZONE
490,486 $78,008,787
0058A SPARTAN STADIUM-TRACK STRG
ORIGINAL CONSTRUCTION 2002ATHLETICS 1,248 $80,000 $64.00 O'BOYLE,COWELL,BLALO
0058B SPARTAN STADIUM-PRESSBOX
ORIGINAL CONSTRUCTION 2002ATHLETICS 200 $19,500 $98.00 O'BOYLE,COWELL,BLALO
0058C SPARTAN STADIUM-SCOREBOARD 1
ORIGINAL CONSTRUCTION 2012ATHLETICS 9,405 $3,225,098 $343.00
0058D SPARTAN STADIUM-SCOREBOARD 2
ORIGINAL CONSTRUCTION 2012ATHLETICS 3,962 $3,225,098 $814.00
0058E SPARTAN STADIUM-SCOREBOARD 3
ORIGINAL CONSTRUCTION 2012ATHLETICS 3,962 $3,225,098 $814.00
COMPLEX TOTALS $87,783,581509,263
0533 SPARTAN VILLAGE - PICNIC SHELTER
0533 SPARTAN VILLAGE - PICNIC SHELTER
FACILITIES INFORMATION SERVICES 66
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0533 SPARTAN VILLAGE - PICNIC SHELTER
0533 SPARTAN VILLAGE - PICNIC SHELTER
ORIGINAL CONSTRUCTION 1995SUPPORT 664 $28,500 $43.00
1400 SPARTAN VILLAGE APTS COMPLEX
1429 SPARTAN VILLAGE 1429
ORIGINAL CONSTRUCTION 1958HOUSING 8,546 $82,450 $10.00 MANSON CARVER
1430 SPARTAN VILLAGE 1430
ORIGINAL CONSTRUCTION 1958HOUSING 7,014 $82,450 $12.00 MANSON CARVER
1431 SPARTAN VILLAGE 1431
ORIGINAL CONSTRUCTION 1958HOUSING 6,756 $82,450 $12.00 MANSON CARVER
1432 SPARTAN VILLAGE 1432
ORIGINAL CONSTRUCTION 1958HOUSING 6,941 $82,450 $12.00 MANSON CARVER
1433 SPARTAN VILLAGE 1433
ORIGINAL CONSTRUCTION 1958HOUSING 8,637 $82,450 $10.00 MANSON CARVER
1434 SPARTAN VILLAGE 1434
ORIGINAL CONSTRUCTION 1958HOUSING 9,556 $82,450 $9.00 MANSON CARVER
1435 SPARTAN VILLAGE 1435
ORIGINAL CONSTRUCTION 1958HOUSING 11,227 $82,450 $7.00 MANSON CARVER
1436 SPARTAN VILLAGE 1436
ORIGINAL CONSTRUCTION 1958HOUSING 9,357 $82,450 $9.00 MANSON CARVER
1439 SPARTAN VILLAGE-LAUNDRY 1439
ORIGINAL CONSTRUCTION 1958HOUSING 10,834 $49,406 $5.00 MANSON CARVER
1440 SPARTAN VILLAGE 1440
ORIGINAL CONSTRUCTION 1958HOUSING 10,391 $82,450 $8.00 MANSON CARVER
1441 SPARTAN VILLAGE 1441
FACILITIES INFORMATION SERVICES 67
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1441 SPARTAN VILLAGE 1441
ORIGINAL CONSTRUCTION 1958HOUSING 6,434 $82,450 $13.00 MANSON CARVER
1442 SPARTAN VILLAGE 1442
ORIGINAL CONSTRUCTION 1958HOUSING 9,323 $82,450 $9.00 MANSON CARVER
1443 SPARTAN VILLAGE 1443
ORIGINAL CONSTRUCTION 1958HOUSING 10,006 $82,450 $8.00 MANSON CARVER
1444 SPARTAN VILLAGE 1444
ORIGINAL CONSTRUCTION 1958HOUSING 9,771 $82,450 $8.00 MANSON CARVER
1445 SPARTAN VILLAGE 1445
ORIGINAL CONSTRUCTION 1958HOUSING 9,323 $82,450 $9.00 MANSON CARVER
1446 SPARTAN VILLAGE 1446
ORIGINAL CONSTRUCTION 1958HOUSING 6,307 $82,450 $13.00 MANSON CARVER
1447 SPARTAN VILLAGE 1447
ORIGINAL CONSTRUCTION 1958HOUSING 9,621 $82,450 $9.00 MANSON CARVER
1448 SPARTAN VILLAGE 1448
ORIGINAL CONSTRUCTION 1958HOUSING 9,154 $82,450 $9.00 MANSON CARVER
1449 SPARTAN VILLAGE 1449
ORIGINAL CONSTRUCTION 1958HOUSING 6,312 $82,450 $13.00 MANSON CARVER
1450 SPARTAN VILLAGE 1450
ORIGINAL CONSTRUCTION 1958HOUSING 8,853 $82,450 $9.00 MANSON CARVER
1451 SPARTAN VILLAGE 1451
ORIGINAL CONSTRUCTION 1958HOUSING 9,329 $82,450 $9.00 MANSON CARVER
1452 SPARTAN VILLAGE 1452
ORIGINAL CONSTRUCTION 1958HOUSING 6,468 $82,450 $13.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 68
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1521 SPARTAN VILLAGE-LAUNDRY SHOP 1521
ORIGINAL CONSTRUCTION 1957SUPPORT 4,629 $55,465 $12.00 MANSON CARVER
1523 SPARTAN VILLAGE 1523
ORIGINAL CONSTRUCTION 1958HOUSING 7,378 $82,450 $11.00 MANSON CARVER
1524 SPARTAN VILLAGE 1524
ORIGINAL CONSTRUCTION 1958HOUSING 9,006 $82,450 $9.00 MANSON CARVER
1525 SPARTAN VILLAGE 1525
ORIGINAL CONSTRUCTION 1958HOUSING 6,452 $82,450 $13.00 MANSON CARVER
1535 SPARTAN VILLAGE 1535
ORIGINAL CONSTRUCTION 1958HOUSING 7,120 $82,450 $12.00 MANSON CARVER
1536 SPARTAN VILLAGE 1536
ORIGINAL CONSTRUCTION 1958HOUSING 10,961 $82,450 $8.00 MANSON CARVER
1537 SPARTAN VILLAGE 1537
ORIGINAL CONSTRUCTION 1958HOUSING 6,517 $82,450 $13.00 MANSON CARVER
1538 SPARTAN VILLAGE 1538
ORIGINAL CONSTRUCTION 1958HOUSING 7,122 $82,450 $12.00 MANSON CARVER
1539 SPARTAN VILLAGE 1539
ORIGINAL CONSTRUCTION 1958HOUSING 8,669 $82,450 $10.00 MANSON CARVER
1540 SPARTAN VILLAGE 1540
ORIGINAL CONSTRUCTION 1958HOUSING 10,987 $82,450 $8.00 MANSON CARVER
1541 SPARTAN VILLAGE 1541
ORIGINAL CONSTRUCTION 1958HOUSING 9,497 $82,450 $9.00 MANSON CARVER
1542 SPARTAN VILLAGE 1542
ORIGINAL CONSTRUCTION 1958HOUSING 7,242 $82,450 $11.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 69
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1543 SPARTAN VILLAGE 1543
ORIGINAL CONSTRUCTION 1958HOUSING 7,127 $82,450 $12.00 MANSON CARVER
1544 SPARTAN VILLAGE 1544
ORIGINAL CONSTRUCTION 1958HOUSING 8,637 $82,450 $10.00 MANSON CARVER
1545 SPARTAN VILLAGE 1545
ORIGINAL CONSTRUCTION 1958HOUSING 6,323 $82,450 $13.00 MANSON CARVER
1546 SPARTAN VILLAGE 1546
ORIGINAL CONSTRUCTION 1958HOUSING 8,664 $82,494 $10.00 MANSON CARVER
1547 SPARTAN VILLAGE 1547
ORIGINAL CONSTRUCTION 1958HOUSING 7,126 $82,450 $12.00 MANSON CARVER
1548 SPARTAN VILLAGE 1548
ORIGINAL CONSTRUCTION 1958HOUSING 8,653 $82,450 $10.00 MANSON CARVER
1549 SPARTAN VILLAGE 1549
ORIGINAL CONSTRUCTION 1958HOUSING 7,224 $82,450 $11.00 MANSON CARVER
1550 SPARTAN VILLAGE 1550
ORIGINAL CONSTRUCTION 1958HOUSING 7,178 $82,450 $11.00 MANSON CARVER
1551 SPARTAN VILLAGE 1551
ORIGINAL CONSTRUCTION 1958HOUSING 9,150 $82,450 $9.00 MANSON CARVER
1565 SPARTAN VILLAGE 1565
ORIGINAL CONSTRUCTION 1958HOUSING 8,792 $82,450 $9.00 MANSON CARVER
1566 SPARTAN VILLAGE 1566
ORIGINAL CONSTRUCTION 1958HOUSING 9,061 $82,450 $9.00 MANSON CARVER
1567 SPARTAN VILLAGE 1567
ORIGINAL CONSTRUCTION 1958HOUSING 6,815 $82,450 $12.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 70
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1568 SPARTAN VILLAGE 1568
ORIGINAL CONSTRUCTION 1958HOUSING 7,056 $82,450 $12.00 MANSON CARVER
1569 SPARTAN VILLAGE 1569
ORIGINAL CONSTRUCTION 1958HOUSING 10,869 $82,450 $8.00 MANSON CARVER
1570 SPARTAN VILLAGE 1570
ORIGINAL CONSTRUCTION 1958HOUSING 6,589 $82,450 $13.00 MANSON CARVER
1571 SPARTAN VILLAGE 1571
ORIGINAL CONSTRUCTION 1958HOUSING 10,913 $82,450 $8.00 MANSON CARVER
1572 SPARTAN VILLAGE 1572
ORIGINAL CONSTRUCTION 1958HOUSING 7,246 $82,450 $11.00 MANSON CARVER
1573 SPARTAN VILLAGE 1573
ORIGINAL CONSTRUCTION 1958HOUSING 8,700 $82,450 $9.00 MANSON CARVER
1574 SPARTAN VILLAGE 1574
ORIGINAL CONSTRUCTION 1958HOUSING 7,116 $82,450 $12.00 MANSON CARVER
1575 SPARTAN VILLAGE 1575
ORIGINAL CONSTRUCTION 1966HOUSING 11,727 $82,450 $7.00 MANSON CARVER
1576 SPARTAN VILLAGE 1576
ORIGINAL CONSTRUCTION 1966HOUSING 7,909 $82,450 $10.00 MANSON CARVER
1577 SPARTAN VILLAGE 1577
ORIGINAL CONSTRUCTION 1966HOUSING 6,433 $82,450 $13.00 MANSON CARVER
1578 SPARTAN VILLAGE 1578
ORIGINAL CONSTRUCTION 1966HOUSING 9,115 $82,450 $9.00 MANSON CARVER
1579 SPARTAN VILLAGE 1579
ORIGINAL CONSTRUCTION 1966HOUSING 9,251 $82,450 $9.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 71
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1612 SPARTAN VILLAGE 1612
ORIGINAL CONSTRUCTION 1958HOUSING 10,928 $82,450 $8.00 MANSON CARVER
1613 SPARTAN VILLAGE 1613
ORIGINAL CONSTRUCTION 1958HOUSING 9,344 $82,450 $9.00 MANSON CARVER
1614 SPARTAN VILLAGE 1614
ORIGINAL CONSTRUCTION 1958HOUSING 8,725 $82,450 $9.00 MANSON CARVER
1615 SPARTAN VILLAGE 1615
ORIGINAL CONSTRUCTION 1958HOUSING 6,560 $82,450 $13.00 MANSON CARVER
1616 SPARTAN VILLAGE 1616
ORIGINAL CONSTRUCTION 1958HOUSING 11,204 $82,450 $7.00 MANSON CARVER
1617 SPARTAN VILLAGE 1617
ORIGINAL CONSTRUCTION 1958HOUSING 9,509 $82,450 $9.00 MANSON CARVER
1618 SPARTAN VILLAGE 1618
ORIGINAL CONSTRUCTION 1958HOUSING 10,919 $82,450 $8.00 MANSON CARVER
1619 SPARTAN VILLAGE 1619
ORIGINAL CONSTRUCTION 1958HOUSING 9,610 $82,450 $9.00 MANSON CARVER
1620 SPARTAN VILLAGE 1620
ORIGINAL CONSTRUCTION 1958HOUSING 6,312 $82,450 $13.00 MANSON CARVER
1621 SPARTAN VILLAGE 1621
ORIGINAL CONSTRUCTION 1958HOUSING 7,196 $82,450 $11.00 MANSON CARVER
1622 SPARTAN VILLAGE 1622
ORIGINAL CONSTRUCTION 1958HOUSING 7,150 $82,450 $12.00 MANSON CARVER
1623 SPARTAN VILLAGE 1623
ORIGINAL CONSTRUCTION 1958HOUSING 8,230 $82,450 $10.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 72
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1624 SPARTAN VILLAGE 1624
ORIGINAL CONSTRUCTION 1958HOUSING 7,426 $82,450 $11.00 MANSON CARVER
1625 SPARTAN VILLAGE 1625
ORIGINAL CONSTRUCTION 1958HOUSING 9,951 $82,450 $8.00 MANSON CARVER
1626 SPARTAN VILLAGE 1626
ORIGINAL CONSTRUCTION 1958HOUSING 7,553 $82,450 $11.00 MANSON CARVER
1627 SPARTAN VILLAGE 1627
ORIGINAL CONSTRUCTION 1958HOUSING 9,346 $82,450 $9.00 MANSON CARVER
1628 SPARTAN VILLAGE 1628
ORIGINAL CONSTRUCTION 1958HOUSING 7,135 $82,494 $12.00 MANSON CARVER
1629 SPARTAN VILLAGE 1629
ORIGINAL CONSTRUCTION 1958HOUSING 8,390 $82,450 $10.00 MANSON CARVER
1630 SPARTAN VILLAGE 1630
ORIGINAL CONSTRUCTION 1958HOUSING 7,132 $82,450 $12.00 MANSON CARVER
1631 SPARTAN VILLAGE 1631
ORIGINAL CONSTRUCTION 1958HOUSING 6,999 $82,450 $12.00 MANSON CARVER
1632 SPARTAN VILLAGE 1632
ORIGINAL CONSTRUCTION 1958HOUSING 8,865 $82,450 $9.00 MANSON CARVER
1633 SPARTAN VILLAGE 1633
ORIGINAL CONSTRUCTION 1966HOUSING 10,549 $82,450 $8.00 MANSON CARVER
1634 SPARTAN VILLAGE 1634
ORIGINAL CONSTRUCTION 1958HOUSING 8,832 $82,494 $9.00 MANSON CARVER
1635 SPARTAN VILLAGE 1635
ORIGINAL CONSTRUCTION 1958HOUSING 9,297 $82,450 $9.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 73
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
1636 SPARTAN VILLAGE 1636
ORIGINAL CONSTRUCTION 1958HOUSING 7,923 $82,450 $10.00 MANSON CARVER
1637 SPARTAN VILLAGE 1637
ORIGINAL CONSTRUCTION 1958HOUSING 7,102 $82,450 $12.00 MANSON CARVER
1638 SPARTAN VILLAGE 1638
ORIGINAL CONSTRUCTION 1958HOUSING 7,082 $82,450 $12.00 MANSON CARVER
1639 SPARTAN VILLAGE 1639
ORIGINAL CONSTRUCTION 1958HOUSING 8,850 $82,450 $9.00 MANSON CARVER
1640 SPARTAN VILLAGE 1640
ORIGINAL CONSTRUCTION 1958HOUSING 7,086 $82,450 $12.00 MANSON CARVER
1641 SPARTAN VILLAGE 1641
ORIGINAL CONSTRUCTION 1958HOUSING 7,066 $82,450 $12.00 MANSON CARVER
1642 SPARTAN VILLAGE 1642
ORIGINAL CONSTRUCTION 1958HOUSING 10,989 $82,450 $8.00 MANSON CARVER
1643 SPARTAN VILLAGE 1643
ORIGINAL CONSTRUCTION 1958HOUSING 10,905 $82,450 $8.00 MANSON CARVER
1644 SPARTAN VILLAGE 1644
ORIGINAL CONSTRUCTION 1958HOUSING 6,970 $82,450 $12.00 MANSON CARVER
1645 SPARTAN VILLAGE 1645
ORIGINAL CONSTRUCTION 1958HOUSING 11,068 $82,450 $7.00 MANSON CARVER
1646 SPARTAN VILLAGE 1646
ORIGINAL CONSTRUCTION 1958HOUSING 6,948 $82,450 $12.00 MANSON CARVER
1647 SPARTAN VILLAGE 1647
ORIGINAL CONSTRUCTION 1966HOUSING 10,433 $82,450 $8.00 MANSON CARVER
FACILITIES INFORMATION SERVICES 74
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1400 SPARTAN VILLAGE APTS COMPLEX
COMPLEX TOTALS $7,690,403792,998
0194 SPARTAN VILLAGE COMMUNITY CNTR
0194 SPARTAN VILLAGE COMMUNITY CNTR
ORIGINAL CONSTRUCTION 1962SUPPORT 5,818 $514,360 $88.00 MANSON,JACKSON, KAN
1964SUPPORT 8,548 $755,480 $88.00 MANSON,JACKSON, KAN
ADD 1 - ADDITION 1 FOURCLASSROOMS
1966SUPPORT 9,262 $815,056 $88.00 MANSON,JACKSON, KAN
ADD 2 - ADDITION 2 FOURCLASSROOMS
1979SUPPORT 1,707 $150,304 $88.00ADD 3 - ADDITION 3 MULTI PURPOSEROOM
1981SUPPORT 2,935 $258,368 $88.00 MANSON,JACKSON,KANE
ADD 4 - ADDITION 4 COMMUNITYCNTR
1992SUPPORT 17,429 $1,399,376 $80.00ADD 5 - ADDITION 5 GYM
45,699 $3,892,944
COMPLEX TOTALS $3,892,94445,699
0061 STEM TEACHING & LEARNING FACILITY
0061 STEM TEACHING & LEARNING FACILITY
ORIGINAL CONSTRUCTION 1948ACADEMIC 30,234 $506,000 $17.00 ERICKSON
1958ACADEMIC 9,225 $677,900 $73.00 COMMONWEALTHADD 1 - ADDITION 1
2021ACADEMIC 152,749 $90,495,217 $592.00 INTEGRATEDDESIGN
ADD 2 - ADDITION 2 - STEM
192,208 $91,679,117
COMPLEX TOTALS $91,679,117192,208
FACILITIES INFORMATION SERVICES 75
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0142 STUDENT SERVICES
0142 STUDENT SERVICES
ORIGINAL CONSTRUCTION 1957SUPPORT 121,938 $2,141,011 $18.00 CALDER
0440 SWINE RESEARCH CENTER COMPLEX
0440A SWINE RESEARCH-BARN/ELEVATOR STRG
ORIGINAL CONSTRUCTION 1951FARMS 7,524 $34,099 $5.00 PHYSICAL PLANT
1954FARMS 4,850 $59,363 $12.00 PHYSICAL PLANTADD 1 - ADDITION 1
1961FARMS 1,196 $7,035 $6.00 PHYSICAL PLANTADD 2 - ADDITION 2
13,570 $100,497
0440B SWINE RESEARCH-GARAGE
ORIGINAL CONSTRUCTION 1955FARMS 362 $5,452 $15.00
0440E SWINE RESEARCH-GESTATION
ORIGINAL CONSTRUCTION 1961FARMS 5,277 $21,500 $4.00 PHYSICAL PLANT
0440F SWINE RESEARCH-AG POLLUTION CNTRL
ORIGINAL CONSTRUCTION 1970FARMS 1,531 $108,190 $71.00 FRANK AND STEIN
0440G SWINE RESEARCH-FINISHING BARN
ORIGINAL CONSTRUCTION 1970FARMS 6,150 $27,230 $4.00 FRANK AND STEIN
0440L SWINE RESEARCH-HSE 1
ORIGINAL CONSTRUCTION 1984FARMS 677 $26,414 $39.00 PHYSICAL PLANT
COMPLEX TOTALS $289,28327,567
0479 SWINE TEACHING & RESEARCH COMPLEX
0479 SWINE TEACH AND RESEARCH
ORIGINAL CONSTRUCTION 1997FARMS 36,822 $2,060,686 $56.00 CAPITALCONSULTANTS
FACILITIES INFORMATION SERVICES 76
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0479 SWINE TEACHING & RESEARCH COMPLEX
0479A SWINE TEACH AND RESEARCH-COMPOST
ORIGINAL CONSTRUCTION 1997FARMS 4,001 $48,000 $12.00 CAPITALCONSULTANTS
0479B SWINE TEACH AND RESEARCH-MANURE 1
ORIGINAL CONSTRUCTION 1997FARMS 304 $5,000 $16.00 CAPITALCONSULTANTS
0479C SWINE TEACH AND RESEARCH-MANURE 2
ORIGINAL CONSTRUCTION 1997FARMS 307 $5,000 $16.00 CAPITALCONSULTANTS
0479D SWINE TEACH AND RESEARCH-SLURRY
ORIGINAL CONSTRUCTION 1997FARMS 0 $175,000 $0.00 CAPITALCONSULTANTS
0479E SWINE TEACH AND RESEARCH-STRG 3
ORIGINAL CONSTRUCTION 1998FARMS 2,629 $65,532 $25.00 MORTONBUILDINGS
0479F SWINE TEACH AND RESEARCH-OZONATION
ORIGINAL CONSTRUCTION 1999FARMS 254 $103,855 $409.00 PHYSICAL PLANT
0479G SWINE TEACH AND RESEARCH-MANURE 3
ORIGINAL CONSTRUCTION 2006FARMS 369 $6,500 $18.00 FARMS
COMPLEX TOTALS $2,469,57344,686
0065 TB SIMON POWER PLANT COMPLEX
0065 TB SIMON POWER PLANT
ORIGINAL CONSTRUCTION 1965SUPPORT 118,444 $8,462,386 $71.00 BENJ,WOODHS,GUENTHER
1974SUPPORT 46,216 $8,900,200 $193.00 COMMONWEALTHADD 1 - ADDITION 1 UNIT 3
1981SUPPORT 10,277 $5,387,000 $524.00 COMMONWEALTHADD 2 - ADDITION 2 BAGHOUSE
1993SUPPORT 86,088 $57,776,300 $671.00 BLACK ANDVEATCH
ADD 3 - ADDITION 3 UNIT 4
1998SUPPORT 1,705 $445,032 $261.00 FTC&HADD 4 - ADDITION 4 OFFICE
FACILITIES INFORMATION SERVICES 77
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0065 TB SIMON POWER PLANT COMPLEX
0065 TB SIMON POWER PLANT
2006SUPPORT 30,771 $32,204,360 $1,047.00 CUMMINS &BARNARD
ADD 5 - ADDITION 5 UNITS 5 & 6
293,501 $113,175,278
0065C TB SIMON POWER PLANT-SUBSTATION
ORIGINAL CONSTRUCTION 1965SUPPORT 1,129 $19,953 $18.00 BENJ,WOODHS,GUENTHER
1993SUPPORT 1,541 $472,189 $306.00 BLACK & VEATCHADD 1 - ADDITION 1
2,670 $492,142
0065D TB SIMON POWER PLANT-COOLING 1
ORIGINAL CONSTRUCTION 1965SUPPORT 0 $175,758 $0.00 BENJ,WOODHS,GUENTHER
0065I TB SIMON POWER PLANT-SIDE FILTER
ORIGINAL CONSTRUCTION 1976SUPPORT 403 $27,500 $68.00 COMMONWEALTH
0065K TB SIMON POWER PLANT-COOLING 2
ORIGINAL CONSTRUCTION 19930 $3,223,700 $0.00 BLACK ANDVEATCH
0065L TB SIMON POWER PLANT-COOLING 3
ORIGINAL CONSTRUCTION 20060 $683,865 $0.00 CUMMINS &BARNARD
0065N TB SIMON POWER PLANT-COAL STRG
ORIGINAL CONSTRUCTION 2009SUPPORT 18,504 $600,483 $32.00 BLACK & VEATCH
0065P TB SIMON POWER PLANT-ELEC CNTRL
ORIGINAL CONSTRUCTION 2009SUPPORT 685 $643,523 $940.00 BLACK & VEATCH
0065Q TB SIMON POWER PLANT-AIR CMPRSS
ORIGINAL CONSTRUCTION 2009SUPPORT 129 $108,095 $838.00 BLACK & VEATCH
0065R TB SIMON POWER PLANT-GAS CMPRSS
ORIGINAL CONSTRUCTION 2006SUPPORT 155 $0 $0.00 CUMMINS &BARNARD
FACILITIES INFORMATION SERVICES 78
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0065 TB SIMON POWER PLANT COMPLEX
0065T TB SIMON POWER PLANT-SWITCH HSE
ORIGINAL CONSTRUCTION 2016SUPPORT 2,734 $2,607,520 $954.00 BLACK & VEATCH
0065U TB SIMON POWER PLANT-UREA PUMP
ORIGINAL CONSTRUCTION 1993SUPPORT 240 $0 $0.00 BLACK & VEATCH
0065V TB SIMON POWER PLANT-TRANSFER TWR
ORIGINAL CONSTRUCTION 1965SUPPORT 5,536 $0 $0.00 BENJ,WOODHS<GUENTHER
0065W TB SIMON POWER PLANT-RICE
ORIGINAL CONSTRUCTION 2022SUPPORT 11,178 $0 $0.00 BLACK & VEATCH
COMPLEX TOTALS $121,737,864335,735
0065Y TB SIMON POWER PLANT-ELECTRIC HOUSE
0065Y TB SIMON POWER PLANT-ELECTRIC HOUSE
ORIGINAL CONSTRUCTION 2022SUPPORT 0 $0 $0.00
0538 TENNIS COURT-RESTROOM AND STRG
0538 TENNIS COURT-RESTROOM AND STRG
ORIGINAL CONSTRUCTION 1996ATHLETICS 480 $77,400 $161.00 FUNCTIONS
0208 TENNIS FACILITY COMPLEX
0208 TENNIS FACILITY
ORIGINAL CONSTRUCTION 1985ATHLETICS 67,091 $1,711,894 $26.00 ANSELMO & ASSOC
0445A THAYER HOUSE
0445A THAYER HOUSE
ORIGINAL CONSTRUCTION 1952FARMS 3,090 $39,032 $13.00
FACILITIES INFORMATION SERVICES 79
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0225 TRANSPORTATION SERVICES COMPLEX
0225A TRANSPORTATION-FUEL AND CAR WASH
ORIGINAL CONSTRUCTION 2013SUPPORT 5,814 $2,101,572 $361.00 FTC&H
1057 TRAUMATIC BRAIN INJURY RESEARCH
1057 TRAUMATIC BRAIN INJURY RESEARCH
ORIGINAL CONSTRUCTION 2018ACADEMIC 1,375 $399,067 $290.00 BERGMANNASSOCIATES
0472 TREE RESEARCH CENTER COMPLEX
0472A TREE RESEARCH-SHOP/OFFICE
ORIGINAL CONSTRUCTION 1964FARMS 2,209 $31,890 $14.00 PHYSICAL PLANT
0472D TREE RESEARCH-HEADHOUSE
ORIGINAL CONSTRUCTION 1975FARMS 1,210 $7,740 $6.00 FORESTRY DEPT
1975FARMS 2,407 $16,180 $7.00 FORESTRY DEPTADD 1 - ADDITION 1 GREENHOUSE(NORTH)
1975FARMS 2,407 $16,180 $7.00 FORESTRY DEPTADD 2 - ADDITION 2 GREENHOUSE(SOUTH)
6,024 $40,100
0472G TREE RESEARCH-STRG 1
ORIGINAL CONSTRUCTION 1979FARMS 818 $9,724 $12.00 PHYSICAL PLANT
0472H TREE RESEARCH-RESIDENCE
ORIGINAL CONSTRUCTION 1978FARMS 1,739 $58,858 $34.00
1986FARMS 343 $18,968 $55.00 PHYSICAL PLANTADD 1 - ADDITION 1
2,082 $77,826
0472I TREE RESEARCH-SHADE HSE
ORIGINAL CONSTRUCTION 19900 $0 $0.00
0472J TREE RESEARCH-STRG 2
ORIGINAL CONSTRUCTION 1996FARMS 5,251 $41,468 $8.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 80
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0472 TREE RESEARCH CENTER COMPLEX
COMPLEX TOTALS $201,00816,384
0006 UNION
0006 UNION
ORIGINAL CONSTRUCTION 1924SUPPORT 81,725 $443,149 $5.00 POND AND POND
1936SUPPORT 29,568 $85,120 $3.00 BOWD-MUNSONADD 1 - ADDITION 1
1949SUPPORT 86,897 $2,362,125 $27.00 CALDERADD 2 - ADDITION 2
1980SUPPORT 2,190 $670,000 $306.00 MAYOTTE,CROUSE,DHAEN
ADD 3 - ADDITION 3
1997SUPPORT 8,151 $2,732,270 $335.00 RALPH CALDERASSOC
ADD 4 - ADDITION 4
208,531 $6,292,664
COMPLEX TOTALS $6,292,664208,531
0453 UNIVERSITY FARMS SERVICE COMPLEX
0453D UFSC-COMMUNITY STRG
ORIGINAL CONSTRUCTION 1961FARMS 11,040 $85,027 $8.00 MOVED
0453E UFSC-S EQUIPMENT STRG BARN 1
ORIGINAL CONSTRUCTION 1984FARMS 4,988 $11,675 $2.00 MORTON
0453F UFSC-S EQUIPMENT STRG BARN 2
ORIGINAL CONSTRUCTION 1984FARMS 4,920 $11,675 $2.00 MORTON
0453G UFSC-4-H
ORIGINAL CONSTRUCTION 1986FARMS 14,374 $118,000 $8.00 PHYSICAL PLANT
0453H UFSC-MAINTENANCE
FACILITIES INFORMATION SERVICES 81
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0453 UNIVERSITY FARMS SERVICE COMPLEX
0453H UFSC-MAINTENANCE
ORIGINAL CONSTRUCTION 1989FARMS 11,698 $341,754 $29.00 PHYSICAL PLANT
0453I UFSC-NORTH MORTON
ORIGINAL CONSTRUCTION 1990FARMS 10,408 $97,485 $9.00 TAYLOR BLDG
0453J UFSC-MATERIALS & PESITCIDE STRG
ORIGINAL CONSTRUCTION 1990FARMS 4,894 $39,990 $8.00 MORTONBUILDINGS
0453K UFSC-EQUIP STRG
ORIGINAL CONSTRUCTION 1996FARMS 10,278 $87,700 $9.00 PHYSICAL PLANT
COMPLEX TOTALS $793,30672,600
0088 UNIVERSITY SERVICES
0088 UNIVERSITY SERVICES
ORIGINAL CONSTRUCTION 1969SUPPORT 5,510 $141,537 $26.00 MAYOTTE-WEBB
1700 UNIVERSITY VILLAGE APTS COMPLEX
1701 UNIVERSITY VILLAGE - 1701
ORIGINAL CONSTRUCTION 2007HOUSING 17,860 $1,922,469 $108.00 THE CHRISTMANCO
1702 UNIVERSITY VILLAGE - 1702
ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO
1703 UNIVERSITY VILLAGE - 1703
ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO
1704 UNIVERSITY VILLAGE - 1704
ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO
1705 UNIV VILLAGE COMMUNITY CNTR
FACILITIES INFORMATION SERVICES 82
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
1700 UNIVERSITY VILLAGE APTS COMPLEX
1705 UNIV VILLAGE COMMUNITY CNTR
ORIGINAL CONSTRUCTION 2007HOUSING 2,640 $282,480 $107.00 THE CHRISTMANCO
1706 UNIVERSITY VILLAGE - 1706
ORIGINAL CONSTRUCTION 2007HOUSING 11,999 $1,283,893 $107.00 THE CHRISTMANCO
1707 UNIVERSITY VILLAGE - 1707
ORIGINAL CONSTRUCTION 2007HOUSING 11,902 $1,283,893 $108.00 THE CHRISTMANCO
1708 UNIVERSITY VILLAGE - 1708
ORIGINAL CONSTRUCTION 2007HOUSING 17,969 $1,922,469 $107.00 THE CHRISTMANCO
1709 UNIVERSITY VILLAGE - 1709
ORIGINAL CONSTRUCTION 2007HOUSING 17,967 $1,922,469 $107.00 THE CHRISTMANCO
COMPLEX TOTALS $12,469,352116,334
0082 URBAN PLANNING LANDSCAPE ARCH-IMC
0082 URBAN PLANNING LANDSCAPE ARCH-IMC
ORIGINAL CONSTRUCTION 1966ACADEMIC 30,972 $386,084 $12.00 CALDER
1966ACADEMIC 16,041 $232,227 $14.00 CALDERADD 1 - ADDITION 1 INSTRUCTIONALMEDIA
47,013 $618,311
COMPLEX TOTALS $618,31147,013
0319 VAN HOOSEN HALL
0319 VAN HOOSEN HALL
ORIGINAL CONSTRUCTION 1957HOUSING 32,834 $447,781 $14.00 MANSON ANDCARVER
FACILITIES INFORMATION SERVICES 83
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0215 VETERINARY DIAGNOSTIC LAB COMPLEX
0215 VETERINARY DIAGNOSTIC LABORATORY
ORIGINAL CONSTRUCTION 2003FARMS 158,471 $35,455,000 $224.00 HARLEY ELLIS, INC.
0215A VETERINARY DIAGNOSTIC LAB-CONTAIN 1
ORIGINAL CONSTRUCTION 2002ACADEMIC 6,422 $191,296 $30.00 HARLEY ELLIS
0215B VETERINARY DIAGNOSTIC LAB-CONTAIN 2
ORIGINAL CONSTRUCTION 2002ACADEMIC 8,327 $248,684 $30.00 HARLEY ELLIS
0215C VETERINARY DIAGNOSTIC LAB-CONTAIN 3
ORIGINAL CONSTRUCTION 2002ACADEMIC 8,327 $248,684 $30.00 HARLEY ELLIS
0215D VETERINARY DIAGNOSTIC LAB-CONTAIN 4
ORIGINAL CONSTRUCTION 2002ACADEMIC 6,422 $191,296 $30.00 HARLEY ELLIS
0215E VETERINARY DIAGNOSTIC LAB-DNR
ORIGINAL CONSTRUCTION 2002ACADEMIC 3,035 $288,300 $95.00 HARLEY ELLIS
0215F VETERINARY DIAGNOSTIC LAB-CREMTRY 1
ORIGINAL CONSTRUCTION 2007FARMS 332 $73,003 $220.00 PHYSICAL PLANT
0215G VETERINARY DIAGNOSTIC LAB-BSL3 2
ORIGINAL CONSTRUCTION 2012ACADEMIC 655 $681,720 $1,041.00 PHYSICAL PLANT
0221 VETERINARY DIAGNOSTIC LAB-BSL3 1
ORIGINAL CONSTRUCTION 2002ACADEMIC 672 $30,800 $46.00 PHYSICAL PLANT
COMPLEX TOTALS $37,408,783192,663
0170 VETERINARY MEDICAL CENTER COMPLEX
0170 VETERINARY MEDICAL CENTER
ORIGINAL CONSTRUCTION 1965ACADEMIC 181,077 $3,818,616 $21.00 HARLEY-ELLINGTON
FACILITIES INFORMATION SERVICES 84
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0170 VETERINARY MEDICAL CENTER COMPLEX
0170 VETERINARY MEDICAL CENTER
1991ACADEMIC 159,547 $28,234,643 $177.00 GBKBADD 1 - ADDITION 1
2005ACADEMIC 39,162 $8,675,581 $222.00 DUCE SIMMONSASSOC
ADD 2 - ADDITION 2 ONCOLOGY
2007ACADEMIC 3,654 $1,102,647 $302.00 TOWER PINKSTERTITUS
ADD 3 - ADDITION 3 SECOND FLOOR FBLDG
2007ACADEMIC 217 $234,380 $1,082.00 DESIGN PLUSADD 4 - ADDITION 4 SMALL ANIMALENTRAN
383,657 $42,065,867
0170A VETERINARY MEDICAL CENTER-EQUINE
ORIGINAL CONSTRUCTION 1989ACADEMIC 10,524 $640,000 $61.00 GBKB
2001ACADEMIC 23,782 $1,771,379 $74.00 FTCHADD 1 - ADDITION 1 EQUINEPERFORM CNTR
34,306 $2,411,379
0170B VETERINARY MEDICAL CENTER-PEGASUS
ORIGINAL CONSTRUCTION 2005ACADEMIC 8,818 $2,468,374 $280.00 DUCE SIMMONSASSOC
COMPLEX TOTALS $46,945,620426,781
0446 VETERINARY RESEARCH CENTER COMPLEX
0211 UNIV RESEARCH CONTAINMENT
ORIGINAL CONSTRUCTION 1993ACADEMIC 67,274 $6,556,167 $97.00 HEPY
1995ACADEMIC 22,033 $2,002,239 $91.00 HEPYADD 1 - ANIMAL INFEC DISEASE-ADDN1
89,307 $8,558,406
0446A VET RESEARCH-LARGE ANIMAL
ORIGINAL CONSTRUCTION 1958FARMS 4,225 $45,633 $11.00 PHYSICAL PLANT
0446B VET RESEARCH-ROUND ROOF
ORIGINAL CONSTRUCTION 1949FARMS 11,536 $69,324 $6.00 MUNSON
FACILITIES INFORMATION SERVICES 85
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0446 VETERINARY RESEARCH CENTER COMPLEX
0446C VET RESEARCH-MANAGER'S HOUSE
ORIGINAL CONSTRUCTION 1949FARMS 2,587 $168,209 $65.00
0446D VET RESEARCH-WOODEN
ORIGINAL CONSTRUCTION 1949FARMS 988 $7,800 $8.00 PHYSICAL PLANT
0446E VET RESEARCH-OFFICE
ORIGINAL CONSTRUCTION 1951FARMS 6,264 $50,552 $8.00 MUNSON
0446F VET RESEARCH-GERM FREE BARN
ORIGINAL CONSTRUCTION 1960FARMS 2,880 $47,000 $16.00 PHYSICAL PLANT
0446G VET RESEARCH-WEST
ORIGINAL CONSTRUCTION 1961FARMS 7,254 $89,645 $12.00 PHYSICAL PLANT
0446I VET RESEARCH-GARAGE 2
ORIGINAL CONSTRUCTION 1965FARMS 572 $8,860 $15.00
0446J VET RESEARCH-SMALL ANIMAL
ORIGINAL CONSTRUCTION 1966FARMS 10,329 $171,848 $17.00 HARLEY-ELLINGTON
0446K VET RESEARCH-POLE BARN
ORIGINAL CONSTRUCTION 1970FARMS 830 $5,000 $6.00 PHYSICAL PLANT
0446L VET RESEARCH-STORAGE BARN
ORIGINAL CONSTRUCTION 1975FARMS 4,444 $9,000 $2.00 PHYSICAL PLANT
0446N VET RESEARCH-BOVINE RESP DISEASE
ORIGINAL CONSTRUCTION 1985FARMS 243 $3,312 $14.00 PHYSICAL PLANT
0446O VET RESEARCH-ANIMAL SHELTER 2
ORIGINAL CONSTRUCTION 1988FARMS 1,784 $24,041 $13.00 MORTON BLD
FACILITIES INFORMATION SERVICES 86
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0446 VETERINARY RESEARCH CENTER COMPLEX
COMPLEX TOTALS $9,258,630143,243
0220 VISITOR CENTER
0220 VISITOR CENTER
ORIGINAL CONSTRUCTION 2001SUPPORT 255 $128,000 $502.00 CP &P
0458 WATER QUALITY MANAGEMENT COMPLEX
0458A WATER QUALITY MGMT-GARAGE
ORIGINAL CONSTRUCTION 1975OTHER 1,176 $21,640 $18.00 PHYSICAL PLANT
0458B WATER QUALITY MGMT-PUMP HSE
ORIGINAL CONSTRUCTION 1973OTHER 964 $200,000 $207.00 JOHNSON-ANDERSON,INC
0458C WATER QUALITY MGMT-PUMP HSE SHED
ORIGINAL CONSTRUCTION 1973OTHER 97 $850 $9.00
0458D WATER QUALITY MGMT-BEE BIO
ORIGINAL CONSTRUCTION 1997OTHER 2,560 $72,968 $29.00 PHYSICAL PLANT
COMPLEX TOTALS $295,4584,797
0096 WATER RESERVOIR
0096 WATER RESERVOIR
ORIGINAL CONSTRUCTION 1951SUPPORT 4,225 $225,560 $53.00 ERICKSON
1973SUPPORT 897 $25,344 $28.00 PHYSICAL PLANTADD 1 - ADDITION 1
1987SUPPORT 2,900 $410,000 $141.00 WOLF/WINEMANADD 2 - ADDITION 2
1988SUPPORT 1,193 $42,000 $35.00 PHYSICAL PLANTADD 3 - ADDITION 3
FACILITIES INFORMATION SERVICES 87
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0096 WATER RESERVOIR
0096 WATER RESERVOIR
9,215 $702,904
COMPLEX TOTALS $702,9049,215
0250 WATER TREATMENT PLANT
0250 WATER TREATMENT PLANT
ORIGINAL CONSTRUCTION 2020SUPPORT 12,551 $8,460,231 $674.00 FTC&H
0250A WATER TREATMENT PLANT - TOWER
ORIGINAL CONSTRUCTION 2020SUPPORT 2,124 $2,655,685 $1,250.00 FTC&H
COMPLEX TOTALS $11,115,91614,675
0566 WELL HOUSE 1-IRRIGATION
0566 WELL HOUSE 1-IRRIGATION
ORIGINAL CONSTRUCTION 2008SUPPORT 120 $25,160 $210.00 STS/AECOM
0550 WELL HOUSE 15
0550 WELL HOUSE 15
ORIGINAL CONSTRUCTION 1956SUPPORT 124 $1,898 $15.00 PHYSICAL PLANT
0551 WELL HOUSE 16
0551 WELL HOUSE 16
ORIGINAL CONSTRUCTION 1956SUPPORT 348 $5,503 $16.00 PHYSICAL PLANT
1994SUPPORT 227 $13,284 $58.00 PHYSICAL PLANTADD 1 - ADDITION NO. 1
575 $18,787
FACILITIES INFORMATION SERVICES 88
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0551 WELL HOUSE 16
COMPLEX TOTALS $18,787575
0570 WELL HOUSE 17
0570 WELL HOUSE 17
ORIGINAL CONSTRUCTION 1957SUPPORT 120 $1,967 $16.00 PHYSICAL PLANT
0553 WELL HOUSE 18
0553 WELL HOUSE 18
ORIGINAL CONSTRUCTION 1963SUPPORT 125 $2,430 $19.00 PHYSICAL PLANT
0554 WELL HOUSE 19
0554 WELL HOUSE 19
ORIGINAL CONSTRUCTION 1962SUPPORT 120 $2,242 $19.00 PHYSICAL PLANT
0567 WELL HOUSE 2-IRRIGATION
0567 WELL HOUSE 2-IRRIGATION
ORIGINAL CONSTRUCTION 2008SUPPORT 96 $25,160 $263.00 STS/AECOM
0555 WELL HOUSE 21
0555 WELL HOUSE 21
ORIGINAL CONSTRUCTION 1965SUPPORT 130 $2,625 $20.00 PHYSICAL PLANT
0556 WELL HOUSE 22
0556 WELL HOUSE 22
ORIGINAL CONSTRUCTION 1967SUPPORT 140 $4,703 $34.00 PHYSICAL PLANT
0557 WELL HOUSE 23
0557 WELL HOUSE 23
ORIGINAL CONSTRUCTION 1966SUPPORT 140 $2,931 $21.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 89
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0558 WELL HOUSE 24
0558 WELL HOUSE 24
ORIGINAL CONSTRUCTION 1967SUPPORT 140 $3,048 $22.00 PHYSICAL PLANT
0559 WELL HOUSE 25
0559 WELL HOUSE 25
ORIGINAL CONSTRUCTION 1968SUPPORT 140 $3,251 $23.00 PHYSICAL PLANT
0560 WELL HOUSE 26
0560 WELL HOUSE 26
ORIGINAL CONSTRUCTION 1969SUPPORT 140 $3,562 $25.00 PHYSICAL PLANT
0561 WELL HOUSE 27
0561 WELL HOUSE 27
ORIGINAL CONSTRUCTION 1970SUPPORT 140 $3,770 $27.00 PHYSICAL PLANT
0562 WELL HOUSE 28
0562 WELL HOUSE 28
ORIGINAL CONSTRUCTION 1970SUPPORT 140 $3,770 $27.00 PHYSICAL PLANT
0563 WELL HOUSE 29
0563 WELL HOUSE 29
ORIGINAL CONSTRUCTION 1986SUPPORT 192 $13,196 $69.00 PHYSICAL PLANT
0568 WELL HOUSE 3-IRRIGATION
0568 WELL HOUSE 3-IRRIGATION
ORIGINAL CONSTRUCTION 2008SUPPORT 180 $25,160 $140.00 STS/AECOM
0564 WELL HOUSE 30
0564 WELL HOUSE 30
ORIGINAL CONSTRUCTION 1988SUPPORT 192 $13,807 $72.00 PHYSICAL PLANT
FACILITIES INFORMATION SERVICES 90
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0565 WELL HOUSE 31
0565 WELL HOUSE 31
ORIGINAL CONSTRUCTION 2007SUPPORT 234 $45,000 $192.00 FTC & H
0651 WELL HOUSE 33
0651 WELL HOUSE 33
ORIGINAL CONSTRUCTION 2019SUPPORT 207 $177,720 $859.00 FTC&H
0569 WELL HOUSE 4-IRRIGATION
0569 WELL HOUSE 4-IRRIGATION
ORIGINAL CONSTRUCTION 2012SUPPORT 27 $20,000 $744.00
0599 WELL HOUSE 5-IRRIGATION
0599 WELL HOUSE 5-IRRIGATION
ORIGINAL CONSTRUCTION 2012SUPPORT 34 $20,000 $586.00
0078 WELLS HALL
0078 WELLS HALL
ORIGINAL CONSTRUCTION 1967ACADEMIC 205,863 $4,659,834 $23.00 HARLEY-ELLINGTON
1970ACADEMIC 23,181 $826,500 $36.00 HARLEY-ELLINGTON
ADD 1 - ADDITION 1
2012ACADEMIC 86,841 $23,502,119 $271.00 INTEGRATEDDESIGN
ADD 2 - ADDITION 2
315,885 $28,988,453
COMPLEX TOTALS $28,988,453315,885
0301 WEST CIRCLE COMPLEX
0304 CAMPBELL HALL
ORIGINAL CONSTRUCTION 1939HOUSING 80,384 $474,628 $6.00 MALCOMSON,CALDER
1969HOUSING 759 $32,000 $42.00 CALDERADD 1 - ADDITION 1
FACILITIES INFORMATION SERVICES 91
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0301 WEST CIRCLE COMPLEX
0304 CAMPBELL HALL
81,143 $506,628
0305 LANDON HALL
ORIGINAL CONSTRUCTION 1947HOUSING 81,299 $1,346,256 $17.00 CALDER
1969HOUSING 744 $37,000 $50.00 CALDERADD 1 - ADDITION 1
2014HOUSING 2,467 $2,047,067 $830.00 SMITHGROUPADD 2 - ADDITION 2-LOADINGDOCK/DINING
84,510 $3,430,323
0306 YAKELEY GILCHRIST HALL
ORIGINAL CONSTRUCTION 1948HOUSING 134,442 $2,023,239 $15.00 CALDER
0308 WILLIAMS HALL
ORIGINAL CONSTRUCTION 1937HOUSING 67,415 $500,000 $7.00 CALDER
0309 MARY MAYO HALL
ORIGINAL CONSTRUCTION 1931HOUSING 64,319 $425,000 $7.00 MALCOMSON,TROUT,HIGG
COMPLEX TOTALS $6,885,190431,829
0085 WHARTON
0085 WHARTON
ORIGINAL CONSTRUCTION 1982ACADEMIC 158,453 $16,583,483 $105.00 HARLEYELLINGTON
2009ACADEMIC 22,542 $6,909,300 $307.00 TMPADD 1 - ADDITION 1 ADMIN OFFICE
2009ACADEMIC 6,509 $6,715,975 $1,032.00 TMPADD 2 - ADDITION 2 COVER LOADINGDOCK
187,504 $30,208,758
FACILITIES INFORMATION SERVICES 92
1 April 2022BUILDING DATA LIST
COMPLEX BUILDING ARCHITECTBLDG FUNC COST $ COST / SQ FTAREA SF YEAR BUILT
0085 WHARTON
COMPLEX TOTALS $30,208,758187,504
0603 WILDLIFE ECOLOGY
0603 WILDLIFE ECOLOGY
ORIGINAL CONSTRUCTION 1970FARMS 507 $8,100 $16.00 PHYSICAL PLANT
0008 WILLS HOUSE
0008 WILLS HOUSE
ORIGINAL CONSTRUCTION 1927ACADEMIC 7,878 $37,500 $5.00 BOWD-MUNSON
0322 WILSON HALL
0322 WILSON HALL
ORIGINAL CONSTRUCTION 1962HOUSING 343,928 $4,583,085 $13.00 CALDER
0323 WONDERS HALL
0323 WONDERS HALL
ORIGINAL CONSTRUCTION 1963HOUSING 343,543 $4,429,982 $13.00 CALDER
FACILITIES INFORMATION SERVICES 93