micce 2010 peb presentation (2) by habibie razak cm4 2
TRANSCRIPT
11
The Use of Pre-Engineered Building System in The Use of Pre-Engineered Building System in Mining Industries; the Implementation of Value Mining Industries; the Implementation of Value Engineering Concept in Optimizing Project Cost Engineering Concept in Optimizing Project Cost (Case Study: Fire Station and Emergency Clinic (Case Study: Fire Station and Emergency Clinic
Project)Project)
11stst MICCE MICCE
Makassar, IndonesiaMakassar, Indonesia
March 2010March 2010
Presented byPresented byIr. Habibie Razak, IPIr. Habibie Razak, IP
Ir. Hajar AswadIr. Hajar Aswad
22
AGENDAAGENDA Value Engineering in Construction Value Engineering in Construction
Project Project
Pre-Engineered Building System, an Pre-Engineered Building System, an Alternative Design to Implement Value Alternative Design to Implement Value Engineering ConceptEngineering Concept
Use of PEB in Use of PEB in Mining Industries, Case Mining Industries, Case Study: Study: Fire Station and Emergency Clinic Fire Station and Emergency Clinic Building Project; the Implementation VE Building Project; the Implementation VE ConceptConcept
Lessons Learned and RecommendationLessons Learned and Recommendation
33
Value Engineering in Construction Value Engineering in Construction ProjectProject
• VE is a systematic evaluation of a project design to obtain VE is a systematic evaluation of a project design to obtain the most value for every dollar of cost. By carefully the most value for every dollar of cost. By carefully investigating costs, availability of materials, construction investigating costs, availability of materials, construction methods, shipping costs or physical limitations, planning methods, shipping costs or physical limitations, planning and organizing, cost/benefit values, and similar cost and organizing, cost/benefit values, and similar cost influencing items, an improvement in the overall cost of a influencing items, an improvement in the overall cost of a project can be realized.project can be realized.
• 4 Fundamentals of VE4 Fundamentals of VE
Function = specific purpose or use intended for somethingFunction = specific purpose or use intended for something
Worth = least cost required to provide the functionWorth = least cost required to provide the function
Cost = total amount of money required to obtain and use Cost = total amount of money required to obtain and use the functionthe function
Value = worth = utilityValue = worth = utility
cost costcost cost
44
Opportunity
for VE by the Contractor
Opportunity for VE by
the Architect or Engineer
Level of
Activity
TimeProject/Phase Start
Project/Phase Finish
Feasibility Study Phase
Design PhaseProcurement Phase
Construction PhaseStart-up
Phase
Operation & Maintenanc
e Phase
Opportunity for Value Engineering:Opportunity for Value Engineering:VE by the Architect or Engineer, VE by ContractorVE by the Architect or Engineer, VE by Contractor
Initiating Processe
s
Planning Processe
s
Controlling Processes
Closing Processe
s
Executing
Processes
55
Methods of Value Engineering used by EngineersMethods of Value Engineering used by Engineers
Design concrete structures with as many Design concrete structures with as many duplicate members as is practical to allow the duplicate members as is practical to allow the reuse of forms without rebuildingreuse of forms without rebuilding
Confine design elements to modular material Confine design elements to modular material sizes where possiblesizes where possible
Simplify the design of the structure wherever Simplify the design of the structure wherever possible possible
Design for the use of cost-saving equipment and Design for the use of cost-saving equipment and methodsmethods
Eliminate unnecessary special construction Eliminate unnecessary special construction requirementsrequirements
Design to reduce the required labor to minimumDesign to reduce the required labor to minimum Specify a quality of workmanship that is Specify a quality of workmanship that is
consistent with the quality of the projectconsistent with the quality of the project
66
Methods of Value Engineering used by Engineers Methods of Value Engineering used by Engineers (Continued)(Continued)
Furnish adequate foundation information Furnish adequate foundation information wherever possiblewherever possible
Refrain from requiring the contractor to assume Refrain from requiring the contractor to assume responsibility for information that should have responsibility for information that should have been furnished by the engineer, or for the been furnished by the engineer, or for the adequacy of the designadequacy of the design
Use local materials when they are satisfactoryUse local materials when they are satisfactory Write simple, straightforward specifications that Write simple, straightforward specifications that
state clearly what is expected of the contractor. state clearly what is expected of the contractor. Use standardized specifications that are familiar Use standardized specifications that are familiar to most contractors whenever possibleto most contractors whenever possible
Hold preconstruction conferences with Hold preconstruction conferences with contractors to eliminate any uncertainties and to contractors to eliminate any uncertainties and to reduce change orders resulting from reduce change orders resulting from misunderstandings to a minimummisunderstandings to a minimum
77
Pre-Engineered Building System, an Pre-Engineered Building System, an Alternative Design to Implement Value Alternative Design to Implement Value
Engineering ConceptEngineering Concept In structural engineering, In structural engineering, pre engineered pre engineered
buildingsbuildings (PEBs) is constructed using a pre- (PEBs) is constructed using a pre-determined inventory of raw materials that can determined inventory of raw materials that can satisfy a wide range of structural and aesthetic satisfy a wide range of structural and aesthetic design requirement.design requirement.
The primary framing structure: build up of I shaped The primary framing structure: build up of I shaped members, often referred as I beams. members, often referred as I beams.
The I beams used are usually formed by welding The I beams used are usually formed by welding together steel plates to form the I section. The I together steel plates to form the I section. The I beams are then bolted together to form the entire beams are then bolted together to form the entire frame of the Pre-Engineered Building. frame of the Pre-Engineered Building.
Some manufactures taper the framing members Some manufactures taper the framing members (varying in web depth) according to the loadings (varying in web depth) according to the loadings with larger depths in the areas of highest stress.with larger depths in the areas of highest stress.
88
Pre-Engineered Building System, an Pre-Engineered Building System, an Alternative Design to Implement Value Alternative Design to Implement Value
Engineering Concept (Continued)Engineering Concept (Continued) Basic Building Parameter of Pre-Engineered Basic Building Parameter of Pre-Engineered
BuildingBuilding
Building WidthBuilding Width
Building LengthBuilding Length
Building HeightBuilding Height
Roof SlopeRoof Slope
End Bay LengthEnd Bay Length
Interior Bay LengthInterior Bay Length
Design LoadsDesign Loads
99
Basic Building Parameter of PEBBasic Building Parameter of PEB
Building WidthBuilding Width
is defined as the distance from outside of eave strut is defined as the distance from outside of eave strut of one sidewall to outside of eave strut of the of one sidewall to outside of eave strut of the opposite sidewall opposite sidewall
Building LengthBuilding Length
the distance between the outside flanges of end-the distance between the outside flanges of end-wall columns in opposite end-walls is the building wall columns in opposite end-walls is the building length. It is a combination of several bay lengthslength. It is a combination of several bay lengths
Building HeightBuilding Height
is the eave height which usually is the distance is the eave height which usually is the distance from the bottom of the main frame column base from the bottom of the main frame column base plate to the top outer point of the eave strut plate to the top outer point of the eave strut
1010
Roof SlopeRoof Slope (x/10): (x/10):This is the angle of the roof with respect to the This is the angle of the roof with respect to the horizontal. The most common roof slopes are 0.5/10 horizontal. The most common roof slopes are 0.5/10 and 1/10. Any practical roof slope is possible.and 1/10. Any practical roof slope is possible.
End bay lengthEnd bay length::The distance from outside of the outer flange of end-The distance from outside of the outer flange of end-wall columns to center line of the first interior frame wall columns to center line of the first interior frame column.column.
Interior bay lengthInterior bay length::The distance between the center lines of two adjacent The distance between the center lines of two adjacent interior main frame columns. The most common bay interior main frame columns. The most common bay lengths are 6 m, 7.5 m and 9 m.lengths are 6 m, 7.5 m and 9 m.
Design LoadsDesign Loads::Usually:Usually:Roof Live Load: 0.57 kN/m2Roof Live Load: 0.57 kN/m2Design Wind Speed: 110 km/hDesign Wind Speed: 110 km/h
Basic Building Parameter of PEBBasic Building Parameter of PEB
1111
Advantages of PEBAdvantages of PEB Structure weightStructure weight
Lighter 30%, primary framing members are Lighter 30%, primary framing members are tapered built up sections with larger depths in the tapered built up sections with larger depths in the areas of highest stressareas of highest stress
DesignDesignQuick and efficient since mainly formed of Quick and efficient since mainly formed of standard sections and connectionsstandard sections and connectionsUsing software analysis for calculation and Using software analysis for calculation and drawingsdrawings
FoundationsFoundationsSimply design, easy to construct and lightweightSimply design, easy to construct and lightweight
Erection simplicityErection simplicityfaster in erection, supported by vendor’s erection faster in erection, supported by vendor’s erection supervisorsupervisor
1212
Advantages of PEB (Continued)Advantages of PEB (Continued)
Seismic resistanceSeismic resistanceThe low weight flexible frames offer higher The low weight flexible frames offer higher resistances to seismic forcesresistances to seismic forces
Overall pricesOverall pricesPrice per square meter may be as much as 30% Price per square meter may be as much as 30% lower than conventional steellower than conventional steel
Sourcing and coordinationSourcing and coordinationSupplied complete with cladding and all Supplied complete with cladding and all accessoriesaccessories
Cost of changeCost of changeLittle or no material is wasted even if a change of Little or no material is wasted even if a change of order is made after fabrication starts order is made after fabrication starts
1313
Applications of Pre-Engineered BuildingsApplications of Pre-Engineered Buildings
IndustrialIndustrial FactoriesFactories WorkshopsWorkshops WarehousesWarehouses Cold storesCold stores Car parking shedsCar parking sheds Slaughter housesSlaughter houses Bulk product storaBulk product stora
gege
Commercial Commercial ShowroomsShowrooms Distribution centerDistribution center
ss
SupermarketsSupermarkets RestaurantsRestaurants OfficesOffices Service stationsService stations Shopping centersShopping centers
Institutional Institutional SchoolsSchools Exhibition hallsExhibition halls HospitalsHospitals TheatersTheaters AuditoriumsAuditoriums Sports hallsSports halls
1414
Applications of Pre-Engineered BuildingsApplications of Pre-Engineered Buildings
Heavy Industrial Heavy Industrial Cement PlantsCement Plants Steel rolling millsSteel rolling mills Sugar millsSugar mills Ceramic factoriesCeramic factories
Aviation & MilitaryAviation & Military Aircraft hangersAircraft hangers Administration BuildAdministration Build
ingsings
Residential barracksResidential barracks Support facilities Support facilities
Recreational Recreational Gymnasiums Gymnasiums Swimming Swimming
pool pool enclosures enclosures
Indoor tennis Indoor tennis courtscourts
Agricultural Agricultural Poultry-Dairy Farms Poultry-Dairy Farms Greenhouses Greenhouses Grain storage Grain storage Animal confinement Animal confinement Pump stations Pump stations
1515
Use of PEB in Fire Station and Use of PEB in Fire Station and Emergency Clinic Building Project; Emergency Clinic Building Project; the Implementation the Implementation of of VE ConceptVE Concept
Project OverviewProject Overview
Project objective is to Project objective is to build a new facility for Fire Station for build a new facility for Fire Station for reliable operation to back up the existing operation reliable operation to back up the existing operation especially to response emergency cases. The new building especially to response emergency cases. The new building will accommodate office staffs, training room, parking of will accommodate office staffs, training room, parking of fire truck equipment, gymnasium and include clinic facilitiesfire truck equipment, gymnasium and include clinic facilities
Project Owner: General Manager EHS PT IncoProject Owner: General Manager EHS PT Inco Scope of works: comprised geotechnical/civil and structural, Scope of works: comprised geotechnical/civil and structural,
mechanical, electrical and instrumentationmechanical, electrical and instrumentation Project team were taken from Central Engineering PT Inco Project team were taken from Central Engineering PT Inco
consist of project manager, project engineer, design consist of project manager, project engineer, design engineer (civil, mechanical, electrical and instrument)engineer (civil, mechanical, electrical and instrument)
1616
Building LayoutBuilding Layout
1717
Key Aspects to Decide using PEB System Key Aspects to Decide using PEB System onon Design PhaseDesign Phase
Budget constraintBudget constraintLess budget allowed by business case that was Less budget allowed by business case that was presented by project sponsorpresented by project sponsor
Time consumptionTime consumptionMore time required to develop design calculation, More time required to develop design calculation, detail drawing and so on by in-house engineering. By detail drawing and so on by in-house engineering. By PEB concept, project engineer only sent the building PEB concept, project engineer only sent the building parameter to vendor (drawing layout and parameter to vendor (drawing layout and specifications)specifications)
Bidding list had also shown the price differences Bidding list had also shown the price differences between conventional steel and pre-engineered between conventional steel and pre-engineered building. It was proven from in-house engineering building. It was proven from in-house engineering designs using conventional steel, the price of PEB is designs using conventional steel, the price of PEB is 30% cheaper 30% cheaper
1818
Comparison between PEB and Conventional Steel Comparison between PEB and Conventional Steel PricePrice
1919
Cross Section of Structures resulted from In-house Cross Section of Structures resulted from In-house
Engineering Design CalculationsEngineering Design Calculations
2020
Vendor Drawing Submission by PEB VendorVendor Drawing Submission by PEB Vendor
2121
Product of Pre-Engineered Building on this Product of Pre-Engineered Building on this ProjectProject
Design ProductDesign Product• Design information such as applicable design Design information such as applicable design
codes, material specifications, design codes, material specifications, design assumptions and load combinations, design assumptions and load combinations, design summary, plan and elevations, frame cross summary, plan and elevations, frame cross section, roof extension details, portal frame section, roof extension details, portal frame details, column reaction, drainage design, and details, column reaction, drainage design, and bracing designbracing design
• Computer design print outsComputer design print outs• Design reference tables and computer Design reference tables and computer
explanationsexplanations• Construction drawingsConstruction drawings
2222
Product of Pre-Engineered Building on this Product of Pre-Engineered Building on this ProjectProject
Construction ProductConstruction Product
The construction product as a process and The construction product as a process and result of delivery and construction stagesresult of delivery and construction stages as as follows:follows:
• PEB PEB ssteel materialsteel materials• Shipment to siteShipment to site• Supervision during erectionSupervision during erection• Punch list and commissioningPunch list and commissioning• Owner’s mOwner’s maintenance manual for PEB aintenance manual for PEB
system provided by system provided by vvendorendor
2323
2424
Lessons Learned and Conclusion taken Lessons Learned and Conclusion taken from Projectfrom Project
PProfessional engineerrofessional engineer must be must be open minded to new ideas, open minded to new ideas, new innovations and technologies. There are always new innovations and technologies. There are always opportunities to try something new on the project that is opportunities to try something new on the project that is possible to give more benefits to the successful of the possible to give more benefits to the successful of the project. PEB system is actually an old technologyproject. PEB system is actually an old technology in low in low rise buildings,rise buildings, unfortunately, currently some of in house unfortunately, currently some of in house civil engineers are only focusing on conventional steel civil engineers are only focusing on conventional steel experiences.experiences.
Value engineering concept is very applicable on design Value engineering concept is very applicable on design phases where the engineers could save more money phases where the engineers could save more money without reducing the utility or function of final products.without reducing the utility or function of final products.
The use of pre-engineered building could benefit both The use of pre-engineered building could benefit both engineers (project engineer) and constructors. Engineer engineers (project engineer) and constructors. Engineer was only doing FEED stage to produce the layout and was only doing FEED stage to produce the layout and specification and then the EPCI work will be performed by specification and then the EPCI work will be performed by the constructor + PEB vendor easily. the constructor + PEB vendor easily.
2525
ReferencesReferences
Fisk, R., Edward (2003). Construction Project Fisk, R., Edward (2003). Construction Project Administration. Prentice Hall Upper Saddle River, Administration. Prentice Hall Upper Saddle River, New Jersey, Columbus, Ohio: 2003New Jersey, Columbus, Ohio: 2003
Zamil Steel Website. Zamil Steel Website. http://zamilsteel.com/peb/en/default.asp?iID=LJJME, http://zamilsteel.com/peb/en/default.asp?iID=LJJME, 20092009
Wikipedia Website. http://en.wikipedia.org/wiki/Pre-Wikipedia Website. http://en.wikipedia.org/wiki/Pre-engineered_building, 2009engineered_building, 2009
Engineering Procedures Manual. PT International Engineering Procedures Manual. PT International Nickel Indonesia, 2006Nickel Indonesia, 2006