Featuring Richard Tucker and Cara Moloney from the Railway Procurement Agency. This presentation is specific to the St. Stephen's Green section of the development of Metro North. For more info on Metro North see www.rpa.ie or www.facebook.com/pages/Dublin/Metro-North/139624076083382?ref=sgm This video was shoot by Fred English for RPA.

TRANSCRIPT

Page 1: Metro north st_stephens_green _presentation_22nov2010

Place title here

Metro North

Page 2: Metro north st_stephens_green _presentation_22nov2010

Metro North● Estuary● Swords● Fosterstown● Airport● Dardistown● Northwood● Ballymun● DCU● Griffith Avenue● Drumcondra● Mater● Parnell Square● O’Connell Bridge● St Stephen’s Green

St Stephen’s Green to Estuary

• 16.5km total length – 11 km in tunnel (City centre to Ballymun and

Airport)– 5.5 km in retained cut, at-grade or elevated

• 14 stops – 9 underground stops from St. Stephen’s

Green to Ballymun and at Airport– 5 surface stops

• Planning Permission Granted – 20 Conditions– Depot relocation permission early 2011– Enabling Works can commence

Page 3: Metro north st_stephens_green _presentation_22nov2010

St. Stephens Green - Faiche Stiofán

Page 4: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green

Page 5: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green

Page 6: Metro north st_stephens_green _presentation_22nov2010

The Works

The works are split into 2 distinct phases

1. Enabling works

2. Main Works

Page 7: Metro north st_stephens_green _presentation_22nov2010

The Aim

The aim for RPA is to design and construct the workswithout materially impacting on the existing businesses

Keeping Dublin Open for Business

Ensuring that City centre remains an attractive destination for shoppers

Page 8: Metro north st_stephens_green _presentation_22nov2010

Keeping the Green Open for Business

• By maintaining pedestrian access to all premises

• By maintaining access for servicing and deliveries

• By maintaining access to all existing car parks

• Getting the message across to the Public

All of this is achieved through

• Careful planning and execution of the works

Page 9: Metro north st_stephens_green _presentation_22nov2010

Keeping the Green an attractive destination

• Noise and dust limits strictly controlled and monitored• High quality, well maintained attractive hoarding• Good lighting and signage will be provided between the

worksites and the shops• Good housekeeping, plant and equipment cleaned and fully

serviced, worksites kept tidy and dust free• By RPA and its contractor working closely with you the

business community throughout the construction period

Page 10: Metro north st_stephens_green _presentation_22nov2010

Enabling Works Spring 2011 to Spring 2012

Heritage Works, Tree Removal and Utility Diversions

Page 11: Metro north st_stephens_green _presentation_22nov2010

Heritage Works

Fusiliers Arch

Will remain in Place during the works with suitable protection measures

Page 12: Metro north st_stephens_green _presentation_22nov2010

Heritage Works

Temporary Relocation of Statues•Robert Emmet •Lord Ardilaun•O’Donovan Rossa Memorial

All will be temporarily moved to the south side of the Green

Page 13: Metro north st_stephens_green _presentation_22nov2010

Heritage Works

Temporary Removal of Island

Page 14: Metro north st_stephens_green _presentation_22nov2010

Tree Removal

Page 15: Metro north st_stephens_green _presentation_22nov2010

Tree Removal

Page 16: Metro north st_stephens_green _presentation_22nov2010

Service Diversions

Page 17: Metro north st_stephens_green _presentation_22nov2010

Phase 1

Page 18: Metro north st_stephens_green _presentation_22nov2010

Phase 2

Page 19: Metro north st_stephens_green _presentation_22nov2010

Phase 3

Page 20: Metro north st_stephens_green _presentation_22nov2010

Phase 4

Page 21: Metro north st_stephens_green _presentation_22nov2010

Phase 5

Page 22: Metro north st_stephens_green _presentation_22nov2010

Phase 6

Page 23: Metro north st_stephens_green _presentation_22nov2010

Phase 7

Page 24: Metro north st_stephens_green _presentation_22nov2010

Phase 8

Page 25: Metro north st_stephens_green _presentation_22nov2010

Phase 9

Page 26: Metro north st_stephens_green _presentation_22nov2010

Phase 10

Page 27: Metro north st_stephens_green _presentation_22nov2010

Local Service Diversions

•Manholes

•Shallow trench excavations

•Short durations

•Works in road way carried out at night

Page 28: Metro north st_stephens_green _presentation_22nov2010

Local Service Diversions

Page 29: Metro north st_stephens_green _presentation_22nov2010

Main Works & Phasing

Page 30: Metro north st_stephens_green _presentation_22nov2010

Main Works Station Construction

• Main works 48 months (excavation and concrete works) 2012 to 2016

• Equipping the Station 12 months

• Testing and commissioning the system 12months

• Main works is carried out in 3 distinct phases to ensure pedestrian access maintained

Page 31: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green

Page 32: Metro north st_stephens_green _presentation_22nov2010

Main Works Phase 1 (14months)

Page 33: Metro north st_stephens_green _presentation_22nov2010

Main Works Phase 2 (13 months)

Page 34: Metro north st_stephens_green _presentation_22nov2010

Main Works Phase 3 ( 21 months)

Page 35: Metro north st_stephens_green _presentation_22nov2010

Pedestrian Access

Page 36: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green West Current Situation

10.5 m - 34ft 6 inches

Page 37: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green West Phase 1 (12 months)

10.5 m - 34ft 6 inches

4.0 m (14ft)

Page 38: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green West Current Situation

10.5 m - 34ft 6 inches

Page 39: Metro north st_stephens_green _presentation_22nov2010

St Stephens Green West Phase 1 (12 months)

3.3 m -11ft

4.0 m (14ft)

Page 40: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green North Current Situation

10.5 m - 34ft 6 inches

Page 41: Metro north st_stephens_green _presentation_22nov2010

St Stephens Green North Phase1 (12 Months)

3.2 m – 10ft 8 inches 3.2 m min 4.0 m (14ft)

Page 42: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green North Current Situation

10.5 m - 34ft 6 inches

Page 43: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green North Phase 2

10.5 m - 34ft 6 inches

4.0 m (14ft)

5.8 m (19ft)

Page 44: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green North Current Situation

10.5 m - 34ft 6 inches

Page 45: Metro north st_stephens_green _presentation_22nov2010

St Stephen’s Green Phase 2 (12 Months)

3.2 m – 10ft 8 inches 3.2 m min

5.8 m (19ft)

Page 46: Metro north st_stephens_green _presentation_22nov2010

Traffic Management & Car Park Access

Page 47: Metro north st_stephens_green _presentation_22nov2010

Main Works Traffic Management

Page 48: Metro north st_stephens_green _presentation_22nov2010
Page 49: Metro north st_stephens_green _presentation_22nov2010
Page 50: Metro north st_stephens_green _presentation_22nov2010
Page 51: Metro north st_stephens_green _presentation_22nov2010
Page 52: Metro north st_stephens_green _presentation_22nov2010

Our Commitment to you

A public information centre will be established

• Communications HQ & media centre for press briefings

• Venue for open forums with local businesses and residents

• 24/7 telephone hotline for queries and complaints

• up to date public information on the works

• marketing campaign for the city “open for business as usual”

Community Liaison Officers will be available for you

Page 53: Metro north st_stephens_green _presentation_22nov2010

How RPA honor's it’s Commitment

RPA will

• Have an ongoing role throughout the works

• Review the contractor’s method of work to ensure compliance

• Ensure you have been consulted about the works

• Audit and monitor the works as they happen

Be available and answerable to you

Page 54: Metro north st_stephens_green _presentation_22nov2010

Contractor’s Commitments

The Contractor

• Will comply with Conditions of Contract the Railway Order & EIS

• Will plan his works in line with best practice

• Will be a good neighbour

• Educate and brief his workforce on an ongoing basis

Will engage with you

Page 55: Metro north st_stephens_green _presentation_22nov2010

Next Steps

November 2010

Provide presentation to affected businesses Parnell Square

November 2010 – March 2011

Meet with individual businesses to discuss impacts and agree appropriate measures