method statements 20 % week 08-09
TRANSCRIPT
-
7/27/2019 Method Statements 20 % Week 08-09
1/10
Method Statements
at all stages
PRODUCTION ORGANISATION & HUMAN RESOURCE MANAGEMENT
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
28th July 2010
-
7/27/2019 Method Statements 20 % Week 08-09
2/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
A method statements is a written explanation of the proposed methods of construction
relating to specific site operations, building elements or stages of work.
It may be presented in a written or tabular format.
Often include details of the like hazards - risk assessment process
It may be categorised into 3 distinct formats: Tender/Construction/Safety
Preparation of method statements forms an essential part of contractors' procedures
Method statements may be drawn up at any stage of a project - the extent of detail is
determined by the purpose and stage being produced
Consideration of methods is essential before programming is carried out
-
7/27/2019 Method Statements 20 % Week 08-09
3/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Depending on the format of the method statement, it can be prepared
by various people
Can be subject, but the main thing is that the job is thought through
carefully and a safe and efficient method of working is determined
Collation of available information
Deciding what is to be included where and what needs detailing
Formulating check list of clauses
Write to construction sequence
-
7/27/2019 Method Statements 20 % Week 08-09
4/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Typical areas to cover:
Significant Preliminary Items
Use of major items of plant
Handling materials
Any assumptions in conjunction with operations of importance
Assumed restrictions in working
Confirming the method of working of the major operations planned
-
7/27/2019 Method Statements 20 % Week 08-09
5/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Advice:
Should not repeat the specification
Should clarify any aspect not clear from elsewhere
May be used as evidence as regards assumed method in a claim orextension of time/delay situation
-
7/27/2019 Method Statements 20 % Week 08-09
6/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Tender Method Statement
Outlines the sequence and method of construction upon which the
estimate is based
Should include major elements of work
Highlight areas where alternative methods are being considered,
including cost assessment
Should be supported by details of labour, plant, outputs and
supervision requirements
Provision should be made for any temporary works requirements
-
7/27/2019 Method Statements 20 % Week 08-09
7/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Construction Method Statement
Explain the contractor's proposed methods and sequence of working
for checking by the client's representative
Calculate activity durations for the programme
Decide on gang composition and resource requirements for individual
activities
Plan activities in detail so that a logical construction sequence is
adopted
Provide an easily understood document which can be communicated to
those who will carry out the work on site
-
7/27/2019 Method Statements 20 % Week 08-09
8/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Safety Method Statement
Demonstrate safe systems of work for hazardous operations
Incorporate method statement into Health & Safety Plan, together with
those of any sub-contractors
Manage any residual risks identified in the risk assessment
Provide practical control measures
Explain how the work is to be supervised and monitored
Show PPE requirements and explain first aid and emergency
arrangements should the worst happen
-
7/27/2019 Method Statements 20 % Week 08-09
9/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Discussion
Pre-stressed Concrete Terracing units ("L" shaped beams) to the 6th floor
lecture theatres.
Formulate a descriptive method statement to cover the parties involved
for the delivery. off-loading and handling of the units prior to fixing.
-
7/27/2019 Method Statements 20 % Week 08-09
10/10
definition | preparation | tender | construction | safety
BSc (Hons)
BUILDING CONSTRUCTION MANAGEMENT
Method Statements
Some Examples